Operations Management Session 8 –  JIT and Lean Operations
Learning Objectives When you complete this chapter you should be able to: Define just-in-time, TPS, and lean operations Define the seven wastes and the 5 Ss Explain JIT partnerships Determine optimal setup time
Learning Objectives When you complete this chapter you should be able to: Define kanban Compute the required number of kanbans Explain the principles of the Toyota Production System
Toyota Motor Corporation Largest vehicle manufacturer in the world with annual sales of over 9 million vehicles Success due to two techniques, JIT and TPS Continual problem solving is central to JIT Eliminating excess inventory makes problems immediately evident
Toyota Motor Corporation Central to TPS is a continuing effort to produce products under ideal conditions Respect for people is fundamental Small building but high levels of production Subassemblies are transferred to the assembly line on a JIT basis High quality and low assembly time per vehicle
Just-In-Time, TPS, and  Lean Operations JIT is a philosophy of continuous and forced problem solving via a focus on throughput and reduced inventory TPS emphasizes continuous improvement, respect for people, and standard work practices Lean production supplies the customer with their exact wants when the customer wants it without waste
Just-In-Time, TPS, and  Lean Operations JIT emphasizes forced problem solving TPS emphasizes employee learning and empowerment in an assembly-line environment Lean operations emphasize understanding the customer
Eliminate Waste Waste is anything that does not add value from the customer point of view Storage, inspection, delay, waiting in queues, and defective products do not add value and are 100% waste
Ohno’s Seven Wastes Overproduction Queues Transportation Inventory Motion Overprocessing Defective products
Eliminate Waste Other resources such as energy, water, and air are often wasted Efficient, ethical, and socially responsible production minimizes inputs, reduces waste Traditional “housekeeping” has been expanded to the 5 Ss
The 5 Ss Sort/segregate  – when in doubt, throw it out Simplify/straighten  – methods analysis tools Shine/sweep  – clean daily Standardize  – remove variations from processes Sustain/self-discipline  – review work and recognize progress
The 5 Ss Sort/segregate  – when in doubt, throw it out Simplify/straighten  – methods analysis tools Shine/sweep  – clean daily Standardize  – remove variations from processes Sustain/self-discipline  – review work and recognize progress Two additional Ss Safety – build in good practices Support/maintenance – reduce variability and unplanned downtime
Remove Variability JIT systems require managers to reduce variability caused by both internal and external factors Variability is any deviation from the optimum process Inventory hides variability Less variability results in less waste
Sources of Variability Incomplete or inaccurate drawings or specifications Poor production processes resulting in incorrect quantities, late, or non-conforming units Unknown customer demands
Sources of Variability Incomplete or inaccurate drawings or specifications Poor production processes resulting in incorrect quantities, late, or non-conforming units Unknown customer demands Both JIT and inventory reduction are effective tools in identifying causes of variability
Improve Throughput The time it takes to move an order from receipt to delivery The time between the arrival of raw materials and the shipping of the finished order is called manufacturing cycle time A pull system increases throughput
Improve Throughput By pulling material in small lots, inventory cushions are removed, exposing problems and emphasizing continual improvement Manufacturing cycle time is reduced Push systems dump orders on the downstream stations regardless of the need
Just-In-Time (JIT) Powerful strategy for improving operations Materials arrive where they  are needed when they are  needed Identifying problems and  driving out waste reduces  costs and variability and  improves throughput Requires a meaningful  buyer-supplier relationship
JIT and Competitive Advantage Figure 16.1
JIT and Competitive Advantage Figure 16.1
JIT Partnerships JIT partnerships exist when a supplier and purchaser work together to remove waste and drive down costs Four goals of JIT partnerships are: Removal of unnecessary activities Removal of in-plant inventory Removal of in-transit inventory Improved quality and reliability
JIT Partnerships Figure 16.2
Concerns of Suppliers Diversification  – ties to only one customer increases risk Scheduling  – don’t believe customers can create a smooth schedule Changes  – short lead times mean engineering or specification changes can create problems Quality  – limited by capital budgets, processes, or technology Lot sizes  – small lot sizes may transfer costs to suppliers
JIT Layout Table 16.1 Reduce waste due to movement JIT Layout Tactics Build work cells for families of products Include a large number operations in a small area Minimize distance Design little space for inventory Improve employee communication Use poka-yoke devices Build flexible or movable equipment Cross-train workers to add flexibility
Distance Reduction Large lots and long production lines with single-purpose machinery are being replaced by smaller flexible cells Often U-shaped for shorter paths and improved communication Often using group technology concepts
Increased Flexibility Cells designed to be rearranged as volume or designs change Applicable in office environments as well as production settings Facilitates both product and process improvement
Impact on Employees Employees are cross trained for flexibility and efficiency Improved communications facilitate the passing on of important information about the process With little or no inventory buffer, getting it right the first time is critical
Reduced Space and Inventory With reduced space, inventory must be in very small lots Units are always moving because there is no storage
Inventory Inventory is at the minimum level necessary to keep operations running Table 16.2 JIT Inventory Tactics Use a pull system to move inventory Reduce lot sizes Develop just-in-time delivery systems with suppliers Deliver directly to point of use Perform to schedule Reduce setup time Use group technology
Reduce Variability Inventory level Figure 16.3 Process downtime Scrap Setup time Late deliveries Quality problems
Reduce Variability Inventory level Scrap Setup time Late deliveries Quality problems Process downtime Figure 16.3
Reduce Lot Sizes Figure 16.4 200  – 100  – Inventory Time Q 2 When average order size = 100 average inventory is 50 Q 1 When average order size = 200 average inventory is 100
Reduce Lot Sizes Ideal situation is to have lot sizes of one pulled from one process to the next Often not feasible Can use EOQ analysis to calculate desired setup time Two key changes necessary Improve material handling Reduce setup time
Lot Size Example D = Annual demand = 400,000 units d = Daily demand = 400,000/250 = 1,600 per day p = Daily production rate = 4,000 units Q = EOQ desired = 400 H = Holding cost = $20 per unit S = Setup cost (to be determined) Setup time = $2.40/($30/hour) = 0.08 hr = 4.8 minutes Q = 2DS H(1 - d/p) Q 2  = 2DS H(1 - d/p) S =  =  = $2.40 (Q 2 )(H)(1 - d/p) 2D (3,200,000)(0.6) 800,000
Reduce Setup Costs High setup costs encourage large lot sizes Reducing setup costs reduces lot size and reduces average inventory Setup time can be reduced through preparation prior to shutdown and changeover
Lower Setup Costs Figure 16.5 Sum of ordering and holding costs Holding cost Setup cost curves (S 1 , S 2 ) T 1 S 1 T 2 S 2 Cost Lot size
Reduce Setup Times Figure 16.6 Use one-touch system to eliminate adjustments (save 10 minutes) Step 4 Step 5 Training operators and standardizing work procedures (save 2 minutes) Initial Setup Time Step 2 Move material closer and improve material handling (save 20 minutes) Step 1 Separate setup into preparation and actual setup, doing as much as possible while the machine/process is operating  (save 30 minutes) Step 3 Standardize and improve tooling (save 15 minutes) 90 min  — 60 min  — 45 min  — 25 min  — 15 min  — 13 min  — — Repeat cycle until subminute setup is achieved Step 6
JIT Scheduling Schedules must be communicated inside and outside the organization Level schedules Process frequent small batches Freezing the schedule helps stability Kanban Signals used in a pull system
JIT Scheduling Table 16.3 Better scheduling improves performance JIT Scheduling Tactics Communicate schedules to suppliers Make level schedules Freeze part of the schedule Perform to schedule Seek one-piece-make and one-piece move Eliminate waste Produce in small lots Use kanbans Make each operation produce a perfect part
Level Schedules Process frequent small batches rather than a few large batches Make and move small lots so the level schedule is economical “ Jelly bean” scheduling Freezing the schedule closest to the due dates can improve performance
Scheduling Small Lots Figure 16.7 A B C A A A B B B B B C JIT Level Material-Use Approach A C A A A B B B B B C C B B B B A A Large-Lot Approach Time
Kanban Kanban is the Japanese word for card The card is an authorization for the next container of material to be produced A sequence of kanbans  pulls material through  the process Many different sorts of  signals are used, but  the system is still called  a kanban
Kanban User removes a standard sized container Signal is seen by the producing department as authorization to replenish Figure 16.8 Part numbers mark location Signal marker on boxes
Kanban Figure 16.9 Purchased Parts Supplier Work cell Raw Material Supplier Kanban Sub-assembly Ship Kanban Kanban Kanban Kanban Finished goods Customer order Final assembly Kanban
More Kanban When the producer and user are not in visual contact, a card can be used When the producer and user are in visual contact, a light or flag or empty spot on the floor may be adequate Since several  components may  be required,  several different  kanban techniques  may be employed
More Kanban Usually each card controls a specific quantity or parts Multiple card systems may be used if there are several components or different lot sizes In an MRP system, the schedule can be thought of as a build authorization and the kanban a type of pull system that initiates actual production
More Kanban Kanban cards provide a direct control and limit on the amount of work-in-process between cells If there is an immediate storage area, a two-card system can be used with one card circulating between the user and storage area and the other between the storage area and the producer
The Number of Kanban Cards or Containers Need to know the lead time needed to produce a container of parts Need to know the amount of safety stock needed Number of kanbans (containers) Demand during  Safety lead time + stock Size of container =
Number of Kanbans Example Daily demand = 500 cakes Production lead time = 2 days (Wait time +  Material handling time +  Processing time) Safety stock = 1/2 day Container size = 250 cakes Demand during lead time = 2 days x 500 cakes = 1,000 Number of kanbans =  = 5 1,000 + 250 250
Advantages of Kanban Allow only limited amount of faulty or delayed material Problems are immediately evident Puts downward pressure on bad aspects of inventory Standardized containers reduce weight, disposal costs, wasted space, and labor
Quality Strong relationship JIT cuts the cost of obtaining good quality because JIT exposes poor quality Because lead times are shorter, quality problems are exposed sooner Better quality means fewer buffers and allows simpler JIT systems to be used
JIT Quality Tactics Table 16.4 Use statistical process control Empower employees Build fail-safe methods (poka-yoke, checklists, etc.) Expose poor quality with small lot JIT Provide immediate feedback
Toyota Production System Continuous improvement Build an organizational culture and value system that stresses improvement of all processes Part of everyone’s job Respect for people People are treated as  knowledge workers Engage mental and  physical capabilities Empower employees
Toyota Production System Standard work practice Work shall be completely specified as to content, sequence, timing, and outcome Internal and external customer-supplier connection are direct Product and service flows must be simple and direct Any improvement must be made in accordance with the scientific method at the lowest possible level of the organization
Lean Operations Different from JIT in that it is externally focused on the customer Starts with understanding what the customer wants Optimize the entire process from the customer’s perspective
Building a Lean Organization Transitioning to a lean system can be difficult Lean systems tend to have the following attributes Use JIT techniques Build systems that help employees produce perfect parts Reduce space requirements
Building a Lean Organization Develop partnerships with suppliers Educate suppliers Eliminate all but value-added activities Develop employees Make jobs challenging Build worker flexibility
JIT in Services The JIT techniques used in manufacturing are used in services Suppliers Layouts Inventory Scheduling

More Related Content

PPTX
JIT and lean operations
PPT
Jit & Lean Operations
PPT
Jit and lean operations
PPT
PPTX
Just in time (jit) and lean production
PPTX
Toyota way
PPTX
Just In Time and Lean Operation Chapter Presentation
PPT
Slide Show Week #9 Chapter 11 Jit
JIT and lean operations
Jit & Lean Operations
Jit and lean operations
Just in time (jit) and lean production
Toyota way
Just In Time and Lean Operation Chapter Presentation
Slide Show Week #9 Chapter 11 Jit

What's hot (20)

PPTX
Just In Time and Lean Management
PPT
Just in-time and lean production
PPT
Just-In-Time
PPTX
How does Kanban work? - ADDVALUE - Nilesh Arora
PPTX
PDF
Just in Time Technique
PPT
6 just in-time and lean thinking
PDF
Lean Management and Kanban System
PPTX
Presentation on Just in Time
PPTX
Just In Time - JIT
PPTX
Just In Time Production (JIT)
PPT
just in time manufacturing
PPT
Jit And Lean
PPTX
JIT and Lean Manufacturing
PPTX
Footwear Manufacturing Industry In Bangladesh
PPTX
Just In Time & Kanban
PPS
PDF
JUST IN TIME PRODUCTION SYSTEM
Just In Time and Lean Management
Just in-time and lean production
Just-In-Time
How does Kanban work? - ADDVALUE - Nilesh Arora
Just in Time Technique
6 just in-time and lean thinking
Lean Management and Kanban System
Presentation on Just in Time
Just In Time - JIT
Just In Time Production (JIT)
just in time manufacturing
Jit And Lean
JIT and Lean Manufacturing
Footwear Manufacturing Industry In Bangladesh
Just In Time & Kanban
JUST IN TIME PRODUCTION SYSTEM
Ad

Viewers also liked (6)

PPT
Chapter 7_OM
PPT
Session 3
PPT
Session 5
PPT
Chapter 7_OM
PPT
Session 7_OM
PPT
Session 6
Chapter 7_OM
Session 3
Session 5
Chapter 7_OM
Session 7_OM
Session 6
Ad

Similar to Session 8 (20)

PPTX
Session 15-16_Lean and TPS and lean.pptx
PPT
16. hr_om11_ch16_GE_ JIT, Lean Operations, and the Toyota Production System.ppt
PPT
just-in-time-by-sashi-prabhu
PPT
37021790 just-in-time-by-sashi-prabhu
PPTX
Mba om 12_japanese manufacturing systems
DOCX
just in time and lean manufacturing
PDF
Introduction to JIT & Lean Operations.pdf
PPTX
10. Lean Manufacturing and Just In Time.pptx
PPT
Just in Time and Lean operation management
PPTX
jit.pptx
PPT
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
PPT
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
PPTX
Lean Operations and Concepts Principles of Operations Management, Tenth Editi...
PPTX
Just In Time
PDF
Heizer om10 ch16
PPT
Just in-time systems
PPTX
Operations Management: Sustainability and Supply Chain Management
PPTX
Just in time
PPT
Chapter.1 just in time
PDF
5a session 5a_jit systems cfvg 2012
Session 15-16_Lean and TPS and lean.pptx
16. hr_om11_ch16_GE_ JIT, Lean Operations, and the Toyota Production System.ppt
just-in-time-by-sashi-prabhu
37021790 just-in-time-by-sashi-prabhu
Mba om 12_japanese manufacturing systems
just in time and lean manufacturing
Introduction to JIT & Lean Operations.pdf
10. Lean Manufacturing and Just In Time.pptx
Just in Time and Lean operation management
jit.pptx
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
Lean Operations and Concepts Principles of Operations Management, Tenth Editi...
Just In Time
Heizer om10 ch16
Just in-time systems
Operations Management: Sustainability and Supply Chain Management
Just in time
Chapter.1 just in time
5a session 5a_jit systems cfvg 2012

More from thangv (12)

PPT
Session 2
PPT
Session 4_OM
PPT
Session 1
PPT
Session 1_OM
PPT
Session 8_OM
PPT
Lesson03_static11
PPT
Lesson06_static11
PPT
Lesson05_Static11
PPT
Lesson04_Static11
PPT
Lesson08_static11
PPT
Lesson02_Static.11
PPT
Lesson01_Static.11
Session 2
Session 4_OM
Session 1
Session 1_OM
Session 8_OM
Lesson03_static11
Lesson06_static11
Lesson05_Static11
Lesson04_Static11
Lesson08_static11
Lesson02_Static.11
Lesson01_Static.11

Recently uploaded (20)

PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
Complications of Minimal Access Surgery at WLH
PPTX
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PDF
VCE English Exam - Section C Student Revision Booklet
PDF
TR - Agricultural Crops Production NC III.pdf
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PDF
Classroom Observation Tools for Teachers
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPTX
Lesson notes of climatology university.
PDF
Insiders guide to clinical Medicine.pdf
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Module 4: Burden of Disease Tutorial Slides S2 2025
Final Presentation General Medicine 03-08-2024.pptx
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
Complications of Minimal Access Surgery at WLH
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
STATICS OF THE RIGID BODIES Hibbelers.pdf
VCE English Exam - Section C Student Revision Booklet
TR - Agricultural Crops Production NC III.pdf
Microbial disease of the cardiovascular and lymphatic systems
2.FourierTransform-ShortQuestionswithAnswers.pdf
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Classroom Observation Tools for Teachers
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
Lesson notes of climatology university.
Insiders guide to clinical Medicine.pdf
Pharmacology of Heart Failure /Pharmacotherapy of CHF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student

Session 8

  • 1. Operations Management Session 8 – JIT and Lean Operations
  • 2. Learning Objectives When you complete this chapter you should be able to: Define just-in-time, TPS, and lean operations Define the seven wastes and the 5 Ss Explain JIT partnerships Determine optimal setup time
  • 3. Learning Objectives When you complete this chapter you should be able to: Define kanban Compute the required number of kanbans Explain the principles of the Toyota Production System
  • 4. Toyota Motor Corporation Largest vehicle manufacturer in the world with annual sales of over 9 million vehicles Success due to two techniques, JIT and TPS Continual problem solving is central to JIT Eliminating excess inventory makes problems immediately evident
  • 5. Toyota Motor Corporation Central to TPS is a continuing effort to produce products under ideal conditions Respect for people is fundamental Small building but high levels of production Subassemblies are transferred to the assembly line on a JIT basis High quality and low assembly time per vehicle
  • 6. Just-In-Time, TPS, and Lean Operations JIT is a philosophy of continuous and forced problem solving via a focus on throughput and reduced inventory TPS emphasizes continuous improvement, respect for people, and standard work practices Lean production supplies the customer with their exact wants when the customer wants it without waste
  • 7. Just-In-Time, TPS, and Lean Operations JIT emphasizes forced problem solving TPS emphasizes employee learning and empowerment in an assembly-line environment Lean operations emphasize understanding the customer
  • 8. Eliminate Waste Waste is anything that does not add value from the customer point of view Storage, inspection, delay, waiting in queues, and defective products do not add value and are 100% waste
  • 9. Ohno’s Seven Wastes Overproduction Queues Transportation Inventory Motion Overprocessing Defective products
  • 10. Eliminate Waste Other resources such as energy, water, and air are often wasted Efficient, ethical, and socially responsible production minimizes inputs, reduces waste Traditional “housekeeping” has been expanded to the 5 Ss
  • 11. The 5 Ss Sort/segregate – when in doubt, throw it out Simplify/straighten – methods analysis tools Shine/sweep – clean daily Standardize – remove variations from processes Sustain/self-discipline – review work and recognize progress
  • 12. The 5 Ss Sort/segregate – when in doubt, throw it out Simplify/straighten – methods analysis tools Shine/sweep – clean daily Standardize – remove variations from processes Sustain/self-discipline – review work and recognize progress Two additional Ss Safety – build in good practices Support/maintenance – reduce variability and unplanned downtime
  • 13. Remove Variability JIT systems require managers to reduce variability caused by both internal and external factors Variability is any deviation from the optimum process Inventory hides variability Less variability results in less waste
  • 14. Sources of Variability Incomplete or inaccurate drawings or specifications Poor production processes resulting in incorrect quantities, late, or non-conforming units Unknown customer demands
  • 15. Sources of Variability Incomplete or inaccurate drawings or specifications Poor production processes resulting in incorrect quantities, late, or non-conforming units Unknown customer demands Both JIT and inventory reduction are effective tools in identifying causes of variability
  • 16. Improve Throughput The time it takes to move an order from receipt to delivery The time between the arrival of raw materials and the shipping of the finished order is called manufacturing cycle time A pull system increases throughput
  • 17. Improve Throughput By pulling material in small lots, inventory cushions are removed, exposing problems and emphasizing continual improvement Manufacturing cycle time is reduced Push systems dump orders on the downstream stations regardless of the need
  • 18. Just-In-Time (JIT) Powerful strategy for improving operations Materials arrive where they are needed when they are needed Identifying problems and driving out waste reduces costs and variability and improves throughput Requires a meaningful buyer-supplier relationship
  • 19. JIT and Competitive Advantage Figure 16.1
  • 20. JIT and Competitive Advantage Figure 16.1
  • 21. JIT Partnerships JIT partnerships exist when a supplier and purchaser work together to remove waste and drive down costs Four goals of JIT partnerships are: Removal of unnecessary activities Removal of in-plant inventory Removal of in-transit inventory Improved quality and reliability
  • 23. Concerns of Suppliers Diversification – ties to only one customer increases risk Scheduling – don’t believe customers can create a smooth schedule Changes – short lead times mean engineering or specification changes can create problems Quality – limited by capital budgets, processes, or technology Lot sizes – small lot sizes may transfer costs to suppliers
  • 24. JIT Layout Table 16.1 Reduce waste due to movement JIT Layout Tactics Build work cells for families of products Include a large number operations in a small area Minimize distance Design little space for inventory Improve employee communication Use poka-yoke devices Build flexible or movable equipment Cross-train workers to add flexibility
  • 25. Distance Reduction Large lots and long production lines with single-purpose machinery are being replaced by smaller flexible cells Often U-shaped for shorter paths and improved communication Often using group technology concepts
  • 26. Increased Flexibility Cells designed to be rearranged as volume or designs change Applicable in office environments as well as production settings Facilitates both product and process improvement
  • 27. Impact on Employees Employees are cross trained for flexibility and efficiency Improved communications facilitate the passing on of important information about the process With little or no inventory buffer, getting it right the first time is critical
  • 28. Reduced Space and Inventory With reduced space, inventory must be in very small lots Units are always moving because there is no storage
  • 29. Inventory Inventory is at the minimum level necessary to keep operations running Table 16.2 JIT Inventory Tactics Use a pull system to move inventory Reduce lot sizes Develop just-in-time delivery systems with suppliers Deliver directly to point of use Perform to schedule Reduce setup time Use group technology
  • 30. Reduce Variability Inventory level Figure 16.3 Process downtime Scrap Setup time Late deliveries Quality problems
  • 31. Reduce Variability Inventory level Scrap Setup time Late deliveries Quality problems Process downtime Figure 16.3
  • 32. Reduce Lot Sizes Figure 16.4 200 – 100 – Inventory Time Q 2 When average order size = 100 average inventory is 50 Q 1 When average order size = 200 average inventory is 100
  • 33. Reduce Lot Sizes Ideal situation is to have lot sizes of one pulled from one process to the next Often not feasible Can use EOQ analysis to calculate desired setup time Two key changes necessary Improve material handling Reduce setup time
  • 34. Lot Size Example D = Annual demand = 400,000 units d = Daily demand = 400,000/250 = 1,600 per day p = Daily production rate = 4,000 units Q = EOQ desired = 400 H = Holding cost = $20 per unit S = Setup cost (to be determined) Setup time = $2.40/($30/hour) = 0.08 hr = 4.8 minutes Q = 2DS H(1 - d/p) Q 2 = 2DS H(1 - d/p) S = = = $2.40 (Q 2 )(H)(1 - d/p) 2D (3,200,000)(0.6) 800,000
  • 35. Reduce Setup Costs High setup costs encourage large lot sizes Reducing setup costs reduces lot size and reduces average inventory Setup time can be reduced through preparation prior to shutdown and changeover
  • 36. Lower Setup Costs Figure 16.5 Sum of ordering and holding costs Holding cost Setup cost curves (S 1 , S 2 ) T 1 S 1 T 2 S 2 Cost Lot size
  • 37. Reduce Setup Times Figure 16.6 Use one-touch system to eliminate adjustments (save 10 minutes) Step 4 Step 5 Training operators and standardizing work procedures (save 2 minutes) Initial Setup Time Step 2 Move material closer and improve material handling (save 20 minutes) Step 1 Separate setup into preparation and actual setup, doing as much as possible while the machine/process is operating (save 30 minutes) Step 3 Standardize and improve tooling (save 15 minutes) 90 min — 60 min — 45 min — 25 min — 15 min — 13 min — — Repeat cycle until subminute setup is achieved Step 6
  • 38. JIT Scheduling Schedules must be communicated inside and outside the organization Level schedules Process frequent small batches Freezing the schedule helps stability Kanban Signals used in a pull system
  • 39. JIT Scheduling Table 16.3 Better scheduling improves performance JIT Scheduling Tactics Communicate schedules to suppliers Make level schedules Freeze part of the schedule Perform to schedule Seek one-piece-make and one-piece move Eliminate waste Produce in small lots Use kanbans Make each operation produce a perfect part
  • 40. Level Schedules Process frequent small batches rather than a few large batches Make and move small lots so the level schedule is economical “ Jelly bean” scheduling Freezing the schedule closest to the due dates can improve performance
  • 41. Scheduling Small Lots Figure 16.7 A B C A A A B B B B B C JIT Level Material-Use Approach A C A A A B B B B B C C B B B B A A Large-Lot Approach Time
  • 42. Kanban Kanban is the Japanese word for card The card is an authorization for the next container of material to be produced A sequence of kanbans pulls material through the process Many different sorts of signals are used, but the system is still called a kanban
  • 43. Kanban User removes a standard sized container Signal is seen by the producing department as authorization to replenish Figure 16.8 Part numbers mark location Signal marker on boxes
  • 44. Kanban Figure 16.9 Purchased Parts Supplier Work cell Raw Material Supplier Kanban Sub-assembly Ship Kanban Kanban Kanban Kanban Finished goods Customer order Final assembly Kanban
  • 45. More Kanban When the producer and user are not in visual contact, a card can be used When the producer and user are in visual contact, a light or flag or empty spot on the floor may be adequate Since several components may be required, several different kanban techniques may be employed
  • 46. More Kanban Usually each card controls a specific quantity or parts Multiple card systems may be used if there are several components or different lot sizes In an MRP system, the schedule can be thought of as a build authorization and the kanban a type of pull system that initiates actual production
  • 47. More Kanban Kanban cards provide a direct control and limit on the amount of work-in-process between cells If there is an immediate storage area, a two-card system can be used with one card circulating between the user and storage area and the other between the storage area and the producer
  • 48. The Number of Kanban Cards or Containers Need to know the lead time needed to produce a container of parts Need to know the amount of safety stock needed Number of kanbans (containers) Demand during Safety lead time + stock Size of container =
  • 49. Number of Kanbans Example Daily demand = 500 cakes Production lead time = 2 days (Wait time + Material handling time + Processing time) Safety stock = 1/2 day Container size = 250 cakes Demand during lead time = 2 days x 500 cakes = 1,000 Number of kanbans = = 5 1,000 + 250 250
  • 50. Advantages of Kanban Allow only limited amount of faulty or delayed material Problems are immediately evident Puts downward pressure on bad aspects of inventory Standardized containers reduce weight, disposal costs, wasted space, and labor
  • 51. Quality Strong relationship JIT cuts the cost of obtaining good quality because JIT exposes poor quality Because lead times are shorter, quality problems are exposed sooner Better quality means fewer buffers and allows simpler JIT systems to be used
  • 52. JIT Quality Tactics Table 16.4 Use statistical process control Empower employees Build fail-safe methods (poka-yoke, checklists, etc.) Expose poor quality with small lot JIT Provide immediate feedback
  • 53. Toyota Production System Continuous improvement Build an organizational culture and value system that stresses improvement of all processes Part of everyone’s job Respect for people People are treated as knowledge workers Engage mental and physical capabilities Empower employees
  • 54. Toyota Production System Standard work practice Work shall be completely specified as to content, sequence, timing, and outcome Internal and external customer-supplier connection are direct Product and service flows must be simple and direct Any improvement must be made in accordance with the scientific method at the lowest possible level of the organization
  • 55. Lean Operations Different from JIT in that it is externally focused on the customer Starts with understanding what the customer wants Optimize the entire process from the customer’s perspective
  • 56. Building a Lean Organization Transitioning to a lean system can be difficult Lean systems tend to have the following attributes Use JIT techniques Build systems that help employees produce perfect parts Reduce space requirements
  • 57. Building a Lean Organization Develop partnerships with suppliers Educate suppliers Eliminate all but value-added activities Develop employees Make jobs challenging Build worker flexibility
  • 58. JIT in Services The JIT techniques used in manufacturing are used in services Suppliers Layouts Inventory Scheduling