Audit Project
Six Sigma
DMADV Storyboard
Boise Potato Firm
ITIL Implementation Action Plan
(Hypothetical Project)
Created by Yuko Soma
Audit Project
Objectives: In Jan 2010, Start to develop and implement ITIL framework to reduce
e.g. average Incidents backlog to Sigma Level 6 after ITIL
implementation Go-Live (Aug. 2010) within 2 months (by Oct. 2010) to
help sales to meet their KPI in Dec. 2010
Impacts:
Assumptions:
1) Reducing average Incident backlogs/month will improve business
process efficiency across all BUs
2) Will increase sales opportunity and sales
3) Improve company brand image by disclosing ITIL implementation
to media for commercial purpose
The Quality of business processes across all business units
supported by IT services is a critical component of Sales increase.
Other Documents:
(Project Charter, Gantt
chart)
Background
Audit Project
Communication Plan
Stakeholder
Status
(See Key)
What to
Communicate
Frequency of
Contact
Method
Responsible
Person
CIO I Staring Committee Bi-Weekly WebEx James King
IT Director A
Alignment meeting and
Staring Committee
Weekly WebEx Jim White
IT Service
Management manager
R Alignment meeting, CAB meeting Weekly Face to face Yuko Soma
All Business Units
Representative
S
Alignment meeting and Staring
Committee
Monthly Face to face D. Dummy
(R) = Owns process/project
(A) = Who (R) reports to; approves work
(S) = Supportive; resource
Key:
Directions:
1.Identify Stakeholders & Status
2.Analyze person against criteria
3.Develop strategies to maintain support; mitigate
resistance
4.Establish priorities
(C) = To be consulted
(I) = Keep informed; not
consulted
Audit Project
SIPOC Worksheet
Process Name: ITIL Implementation
Process Owner: Yuko Soma
Date: Jan. 5, 2010
Prepared By:
Yuko Soma
Process
Suppliers
Process
Inputs
P
R
O
C
E
S
S
Process Outputs
Process
Customers
Finance Team
- Financial Month end data transfer
to the Oracle EBS system
- Budget Input to BI tool
- Correct/On Time data transfer to
the Oracle EBS system
- Correct/On--Time data analysis
reports by BI tool
CFO
Sales Team
Daily Sales Opportunity data to
Sales force system
- Correct/On-Time data transfer to
Sales force system
COO
Sales Oepration Team
Customer data update and register
on Sales force system
- Correct/On Time data update on
Sales force system
COO
HR Team
Send Newhire/Leaver data to ITSM
Tool
- Correct/On Time data update on
ITSM tool on time
HR Director
ITIL Process
All Business Process Activities Backlog Reduce
Services
Services
Inputs Outputs Outputs
Services
Sales Increase
Audit Project
Brake down “Planning” part of the whole business processes for BU
Core Business
Develop
Plans
Level 1
Communicate
Business
Plans
Execute
Plans
Evaluate IT Services
Performance
Level 2
Report
ITIL
Performance
Secure
ITIL
Resources
Determine
ITIL Needs
Execute
ITIL Action Plan
Marketing Logistics
Production
New Product
Introduction
Customer
Service
Planning
Sales
Business
Environmental
Data
D M A D V
Project Flow - 1
Audit Project
Project Scope
Define IT Director
Collect information and
protocols
Issue ITSM Reports to IT
and Business Units
Develop and submit CAP
Review CAP Execute CAP
Identify the current number of
backlog
Conduct: Confirming the status of the corrective actions taken against
the findings of previous incident backlog analysis.
Schedule
IT Service Manager Project Member
Schedule ITIL Design
Prepare
Complete ITIL design plan
Conduct
Conduct ITIL
implementation evaluation
Confirm findings
Report
Issue ITIL and ITSM tool
Summaries
CAP
D M A D V
Level 2 Process: Project Scope
Audit Project
1. For our team to get a common understanding, please tell us how
you interpret the term “ITIL framework”?
2. What do you see as the attributes of a successful ITIL
implementation ?
3. What are the top 3 attributes in order of importance?
4. How would you measure whether a ITIL meets your expectations
on these top 3 attributes?
Identified needs
arising from current
challenges
5. What are your top 3 issues related to IT services quality in your
organization today?
6. Do you see ITIL is helping to resolve these issues?
7. If so, how do you see a ITIL helping to resolve these issues?
8. What information should ITIL generates for your organization?
9. How will this information be used within your organization?
Identified
informational needs
and attributes
10. Is there anything else you would like to share with us? “Catch all”
Identified
key attributes
of the program
D M A D V
Project Interview Questions
Audit Project
・ In-depth standardized IT audit modular protocols for systems and compliance
・ Determine audit schedule, type, content and team appropriate for the IT auditee in
collaboration with local BU/Division
Clearly identify where the
current and potential risks and
problems
・ ITIL reporting roll-up process
Complete Communication
・ ISO20000 and ISO27001 certified by recognized 3rd party - Mechanism for benchmarking
against other companies to establish competitive advantage
Externally accepted ITIL
frameworks
・ Decision criteria and process for consistent ratings of individual findings and overall
business process performance by using IT
Consistent Improvement of
ITSM lifecycle
・ System for reporting status of findings and corrective actions
・ Corrective action escalation procedure
Verification of completeness of
Corrective Action
・ ITIL Expert certification (or ITIL Master) and Six Sigma Black belt
Fair ITIL & Six Sigma
・ Incorporation of Division Quality representative in IT audit team
・ ITSM expertise at BU level to implement and adopt locally
・ IT budget is owned at BU level to enable local initiative and adoption
・ Linked to ITIL Expert certification where appropriate
Locally Relevant
・ Internal validation process
・ Use external IT auditors only
・ Interdivisional IT audit teams
Independent IT Audits
Design Ideas
CTQ
D M A D V
Project Design Ideas
Audit Project
Potential synergies and
conflicts between design
ideas identified
“Inclusion of Division IT in ITIL
action team” and “Convertible
Rating System” conflict with
other design elements
Top 6 design elements
have no conflicts and
are synergistic
D M A D V
Project Trade-offs (Sample from textbook)
Audit Project
All Business Units needs and priorities were similar
・ Extracted solutions, issues and needs from interviews
・ 253 need statements transcribed to Post-it notes
・ Post-it notes color coded by Business Units segment
・ Top needs from each Business Units highlighted
・ Needs affinitized and sorted using tree diagrams
Project VOC Analysis
D M A D V
Audit Project
•Identify number of ITIL
process was used
•Establish maturity of
facility and rank
operations based on
potential risk. (Based on
Division assessment
against established
criteria)
•Determine ITIL type
required based on IT
Service maturity
•Determine additional IT
auditing needs (obtained
by use of the collaborative
routine established in the
GAP)
•Determine the preferred
ITIL Measurement timing
from the Divisions
Select the ITIL Action team
based on:
• Qualification
• Right process knowledge
• Language ability
• Availability
Develop ITIL schedule:
▪ Firm scheduling of compliance IT
audits (prioritized based on risk
profile)
Draft Schedule indicates:
▪ Availability of ITIL Expert
Confirmation of schedule
Communication of final schedule
How Much:
100% match of ITIL action team on process knowledge; In 2010 at least 50% of ITSM conducted with fully certified ITIL Expert;
2011 onwards 100% of ITSM conducted with fully certified ITL Expert.
Firm scheduling routines to have the right team at the right location conducting the right IT audit
D M A D V
Project Flow - 2
Level 2 Report
ITIL
Performance
Secure
Resources
Determine
ITIL Needs
Execute
ITIL Action Plan
Level 3 Schedule ITIL
Design
Identify ITIL
Type
Establish
Current Status
Identify ITIL Action
Team Required
Audit Project
Secure IT
Resources
ITIL Expert Certification Program - Internal and external ITSM staffs have the
right skills and competences
Selection
Periodic re-training and
evaluation
Select using criteria for:
• Personal Atributes
• Education
• Related experience
How much:
10 % of internal ITSM staffs
are recruited/transitioned.
How much:
100% match of ITIL action
team on ITIL process
knowledge
How much
In 2010 at least 50% of
ITSM conducted with 3
certified ITIL Expert, 5 ITIL
Practitioner and 25 ITIL
Foundation 2011
How much:
Maintain steady state of
100% of ITSM staffs
Train ITIL Expert in:
• ITIL principles
• ITIL execution
• Business Processes
• ISMS
• Laws and regulations
• Six Sigma Black belt,
Green belt
・ Certify ITIL Expert,
Practitioner and ITIL
foundation 2011
D M A D V
Project Flow - 3
Level 3 Certification
Maintenance
Training
Selection Certification
Level 2 Report
ITIL
Performance
Secure
Resources
Determine
ITIL Needs
Execute
ITIL Action Plan
Audit Project
Standardized ITIL protocol module for
planning, execution and reporting of
individual outcomes
Standardized modules to evaluate
compliance of processes and
systems during individual ITIL based
tasks
In-depth protocols and decision criteria deliver consistent and fair IT audits
How Much:
• 50% of ITSM tool modules completed by June. 2010
• 100% of ITIL design modules completed by Aug. 2010
D M A D V
Project Flow - 4
Level 3
Perform ITIL
Plan ITIL
Design
Level 2 Report
ITIL
Performance
Secure
Resources
Determine
ITIL Needs
Execute
ITIL Action Plan
Audit Project
• Incorporate reporting of ITIL
information into established
management routines for Quality
performance at the BU level.
Information can be used to drive
resource allocation at the BU
and Division level.
• ITIL summary provided to BOD.
Information will be used as input
to resource allocation, and
greater understanding of the
risks in the organization.
• Detailed ITIL report issued to IT
Auditee that identifies critical and
systemic risks
• IT Service manager uses report
information to drive program
improvement
• Formalized communication of high
risk findings to appropriate
management levels.
• Gather, analyze and trend data to
create a summary report that
includes identification of high risk
issues, status of corrective action,
successful practices and
learnings.
• ITIL summary to provide
comparative data of Division / BU
performance against our
performance.
Actionable audit information available – IT Auditee to BOD
How Much:
Provide bi-monthly reports for BOD meetings; provide monthly reports to Steering Committee, Quality Division
and BU/Vision heads by Aug. 2010
D M A D V
Project Flow - 5
Level 2 Report
ITIL
Performance
Secure
ITIL
Resources
Determine
ITIL Needs
Execute
ITIL Action Plan
Summarize ITIL Data
Communicate Detailed
ITIL Findings
Level 3 Communicate
Summarized Info
Audit Project
D M A D V
1. Average delay awaiting closing the backlog incident tickets
2. Maximum delay awaiting closing the backlog Incident tickets
3. Average the number of Incident backlog tickets
4. Maximum backlog Incident tickets
Questions:
・ Is the backlog a chance event required a permanent change of process ?
・ Which type of job skills are required?
・ Will additional semi-automated process required to reduce backlog Incident
thickets?
・ Will ITIL solve this problem?
The Simulation
Audit Project
Hows (Design Requirements)
Needs (Whats)
Rating
TCCC
Certified
auditors
In-depth
standardized
audit
modular
protocols
for
systems
&
compliance
Determine
audit
&
audit
team
appropriate
for
the
auditee
in
collaboration
with
local
SBU/division
Decision
criteria
and
process
for
consistent
ratings
of
individual
findings
and
overall
facility
performance
Global
audit
program
certified
by
recognized
3rd
party
to
ISO
19011
Global
audit
reporting
roll-up
process
for
BOD
&
Executive
Comm.
Clearly Identifying current and potential risk
and problems 48 9 9 9 9 9
Independent Audits 39 1 9
The Global Program is locally relevant 36 3 9
Fair Audits 30 9 1 3 9 9
Consistent Audits 24 9 9 3 9 9
Verification of completeness of corrective
action 21 9 9 1 9
Externally accepted audits 21 3 1 3
Complete communication 16 9 9 3 3 9
Importance 1422 1071 987 966 900 765
Options
Needs (Whats)
Weight
Determined
using
TCCQS
Maturity
continiuum
only
Determined
by
Quality
Indicator
only
Determined
by
Previous
Audit
result
Determined
by
Audit
Manager
Determined
by
Auditee
Determined
by
Division
QA
Manager
Hub
Audit
Manager
Select
Team
Lead
Auditor
Selects
Team
Div
QA
Mgr
Selects
Team
Decentralised
Scheduling
Centralised
Scheudling
Process
TCCC Certified auditors 1422
In-depth standardised audit modular protocols
for systems & compliance
1071
Determine audit & audit team appropriate for the
auditee in collaboration with local SBU/division
987 3 1 3 1 3 3 9 3 1 9 1
Decision criteria and process for consistent
ratings of individual findings and overall facility
performance
966
Global audit program certified by recognized 3rd
party to ISO 19011
900 9 9 1 3 3
Global audit reporting roll-up process for BOD &
Executive Committee
765
Importance 2961 987 2961 987 2961 2961 16983 11061 1887 11583 3687
TEAM SELECTION SCHEDULING
AUDIT TYPE
P R I M E D O T S Actions
1 Update of EMS with new plant information X Quarterly review and update plant information on EMS
2 Determine number of plants to be audited (EMS)
3 Request information on plant maturity, risk and audit timing
4 Evaluate every plant against agreed criteria (DIVISION)
5 Prioritize based on risk and audit timing (DIVISION)
6 Comunicate prioritized plant list to audit group (DIVISION) X Ask for required information in advance and frequent follow up.
7 Collect prioritized list from divisions
8 Any new process identified in the prioritized list?
9 Request information regarding new process
10 Provide information regarding new process
11 Development and inclusion of the new module X Quarterly survey with Division to identify new processes.
12 Update prioritized list
13 Compare mandays required with mandays available
14 Are sufficient auditors available within SBU? X X Identify and prepare an external pool of auditors
15 Are there auditors available in other SBU´that can be used? X Get access to information on auditors in other SBU´s
16 Re-evaluate prioritized list to focus on risk priority X Ensure there are sufficient trained auditors available with the required skills
17 Do auditors have required process knowledge? X Ensure there are sufficient trained auditors available with the required skills
18 Do auditors have required language skill? X Ensure there are sufficient trained auditors available with the required skills
19 Is location of auditors suitable for conducting audits? X Ensure there are sufficient trained auditors available with the required skills in yours
SBU
20 Can audit be re-scheduled?
21 Is there a lead auditor available? X Ensure there are sufficient trained auditors available with the required skills in yours
SBU
22 Allocate resources to the prioritized list
23 Prepare/Review Draft Schedule X Note: Minimize this loop with more active involvement with the Divisons in the early
stage of the scheduling process.
24 Communicate Draft Schedule to Divisions
25 Agree with draft schedule? (DIVISION)
26 Communicate proposed changes (DIVISION) X Note: Minimize this loop with more active involvement with the Divisons in the early
stage of the scheduling process. Alternately commit the Division to respond within
an agreed timeframe or the schedule would be accepted as it is.
27 Are changes feasible?
28 Communicate to Divison that changes are not possible
29 Prepare final schedule
30 Communicate final schedule
PRODUCTIVITY ANALYSIS
STEP
Detailed design options selected, flowcharted and measures identified
CTQs
High Level
Design
Elements
QFD #1
High Level
Design
Elements
Detailed
Design
Options
QFD #2
Value-Added Analysis
VA BVA NVA
1 Update of EMS with new plant information X
2 Determine number of plants to be audited (EMS) X
3 Request information on plant maturity, risk and audit timing X
4 Evaluate every plant against agreed criteria (DIVISION) X
5 Prioritize based on risk and audit timing (DIVISION) X
6 Comunicate prioritized plant list to audit group (DIVISION) X
7 Collect prioritized list from divisions X
8 Any new process identified in the prioritized list? X
YES (10), NO(12)
9 Request information regarding new process X
10 Provide information regarding new process X
11 Development and inclusion of the new module X
12 Update prioritized list X Perform updating of EMS each quarter and detec new processes
13 Compare mandays required with mandays available X
14 Are sufficient auditors available within SBU? X
15 Are there auditors available in other SBU´that can be used? X
16 Re-evaluate prioritized list to focus on risk priority X Define sufficient number of auditors, based on process knowledge, language skill,
location, leading. Reduce number of audits based on risk evaluation
17 Do auditors have required process knowledge? X
18 Do auditors have required language skill? X
19 Is location of auditors suitable for conducting audits? X
20 Can audit be re-scheduled? X
21 Is there a lead auditor available? X
22 Allocate resources to the prioritized list X
23 Prepare/Review Draft Schedule X Note: Minimize this loop with more active involvement with the Divisons in the early
stage of the scheduling process.
24 Communicate Draft Schedule to Divisions X
25 Agree with draft schedule? (DIVISION) X Note: Minimize this loop with more active involvement with the Divisons in the early
stage of the scheduling process.
26 Communicate proposed changes (DIVISION) X Note: Minimize this loop with more active involvement with the Divisons in the early
stage of the scheduling process.
27 Are changes feasible? X
28 Communicate to Divison that changes are not possible X Note: Minimize this loop with more active involvement with the Divisons in the early
stage of the scheduling process.
29 Prepare final schedule X
30 Communicate final schedule X
VALUE CATEGORY
ACTION
STEP
Preliminary Flowchart
Productivity Analysis
Error Proofing
Final Flowchart
Potential Causes Current Controls Actions Recommended Resp. Actions Taken
What causes the
Key Input to go
wrong?
What are the existing
controls and
procedures (inspection
and test) that prevent
either the cause or the
Failure Mode?
What are the actions for reducing the
occurrence of the cause, or improving
detection?
What are the
completed
actions taken
with the
recalculated
RPN?
10
Did not provide the
information or update the
EMS
4 no current controls 10 400
Establish routines to quarterly for divisions to review
current status against current EMS content
GAP
Mngr
10 2 5
9
Planning of resources
ineffective
4 no current controls 10 360
Define a procedure for rigorous planning. Use
auditor pool across SBU's while building SBU
capability. Identify multiple external certification
bodies in design phase.
GAP
Mngr
9 2 4
8
Process for updating is
not followed
4 no current controls 10 320 Audit the updating process at a local level
GAP
Mngr
8 2 4
S
E
V
E
R
I
T
Y
O
C
C
U
R
R
E
N
C
E
D
E
T
E
C
T
I
O
N
S
E
V
E
R
I
T
Y
O
C
C
U
R
R
E
N
C
E
D
E
T
E
C
T
I
O
N
R
P
N
Critical Risk Flow Process
Auditee
Hub Q.A. Audit Group Lead Auditor Division
PVP
ID of critical/high
risk (1)
Communicate
finding to auditee
(2)
Discussion and
confirmation of
evidence (3)
Confirmation of
finding (4)
Confirm with
audit manager
(5)
Continue audit
(6)
Telephonic
discussion
with auditor
(7)
Agree
(8)
No
Yes
No
Confirm with
Hub Q.A. (9)
Yes
Telephonic
discussion
with audit
manager (10)
Agree
(11)
No
Yes
Inform auditor
(12)
Continue audit based on
audit manager comment
(13)
Confirmation
with audit
manager (14)
Telephonic
discussion with
division to get a
plan for action
(15)
Discussion with
bottler &
preparation of
CAP (16)
Forward plan by
email to audit
manager (17)
Agree with
content of CAP
(18)
Inform Hub
Q.A.and copy
division
technical
director (19)
Yes
No
Voice mail to SBU
Pres. Copy PVP, Div.
Pres, SBU QA, SBU
Tech, Div Tech
detailing critical status
(20)
D M A D V
Determine ITIL Needs (Sample from text )
Audit Project
Document Management
ITIL implementation and its control of procedures, incorporating:
• Document creation
• Document review
• Document distribution
• Document archiving
(Above done with electronic workflow)
Recordkeeping
ITSM maturity and operational data
Audit reports
• Field for high risk, corrective action
status and successful practices
• Status of corrective action receipt
• Audit schedule status
• Search of reports by:
• Risk
• BU
• Division
ITSM Staffs Capability
• Personnel information:
• Education
• Work Experience
• ITSM tool training
• EXIN ITIL foundation Certification to all
Technical Staffs
• Languages, nationality, location
• Course and skill profiles
• Filter/search capability
This functionality is available with current solutions and/or off-the-shelf software
• Document revision
• Document approval
• Document control
D M A D V
Features of ITIL framework
Audit Project
・ New Standard; Install ISO20000-1 and ISO27001
・ Modify quality appraisal and IT audit criteria
・ Update prices of product to increase sales
Implementation of ITIL makes price increase of company products possible
・ Revise IT budgets
・ Revise manpower forecasts
Not meant labor cost saving. Reallocate IT technical staffs to right positions.
D M A D V
Hard-Won Gains
Audit Project
• The ITIL Design was completed on schedule and full scale
implementation began Jan. 2010
• Preliminary results indicate all CTQs will be met
• An estimated backlog/month reducing to Sigma Level 6.0 by ITIL in
Oct. 2010
• After full ITIL implementation, the sales resulted at least 1,000,000
increase in Oct. 2010 – Dec. 2010 (FY2010 Q4)
Summary
Audit Project
References
Thomas Pyzdek, and Paul Leller (2014). “The Six Sigma Handbook, Fourth
Edition”, USA: McGraw-Hill Education.
SIX SIGMA ONLINE templates, Aveta Business Institute.

More Related Content

PPT
SixSigma Training Course homework in 2016
PPT
IT frameworks
ODP
CobiT, Val IT & Balanced Scorecards
PPTX
Marcos cobi t -e-itil-v040811
PPT
Allstate- Cathy Kirch- Release -Final
PPT
RDrew ITIL Presentation
PPT
Measuring Success Ryan Ibm May 2010
PDF
Cobit, itil and cmmi - a tutorial
SixSigma Training Course homework in 2016
IT frameworks
CobiT, Val IT & Balanced Scorecards
Marcos cobi t -e-itil-v040811
Allstate- Cathy Kirch- Release -Final
RDrew ITIL Presentation
Measuring Success Ryan Ibm May 2010
Cobit, itil and cmmi - a tutorial

Similar to SixSigma 【Continuous Study】 (20)

PPT
IT PMO Charter (Linkedin)
PPTX
Frameworks For Predictability
DOCX
WLS Services Brochure March 2013
PPT
Msp It Goverance And Service Delivery Process
PPT
Itil introduction
PPT
Disa Itsm V1.3
PDF
The relation in between ITIL, Cobit, Togaf and CMMI.
PPT
Itil & Process Concepts Awareness Tadawul 5 Of March 2007
PDF
Vinay_Patange_StanChart_Cannes_2010_Ver2
DOC
Qwr iso20000 auditor m04 implementing audit and tooling us 06 apr14
PPTX
Implementing IT Service Management: A Guide to Success
PDF
IT Governance - COBIT 5 Capability Assessment
PPTX
Common d ashboards
DOC
itil process maturity assessment
PPTX
IT NPI Process
PPT
54 - How to Become an ITIL STAR
PDF
How Your Organization Can Become ISO Certified...It's easier than you think
PPT
ITIL version 2: Foundation Training
PPTX
Measuring Success in the Lean IT World
PPTX
Cloud Operating Model Design
IT PMO Charter (Linkedin)
Frameworks For Predictability
WLS Services Brochure March 2013
Msp It Goverance And Service Delivery Process
Itil introduction
Disa Itsm V1.3
The relation in between ITIL, Cobit, Togaf and CMMI.
Itil & Process Concepts Awareness Tadawul 5 Of March 2007
Vinay_Patange_StanChart_Cannes_2010_Ver2
Qwr iso20000 auditor m04 implementing audit and tooling us 06 apr14
Implementing IT Service Management: A Guide to Success
IT Governance - COBIT 5 Capability Assessment
Common d ashboards
itil process maturity assessment
IT NPI Process
54 - How to Become an ITIL STAR
How Your Organization Can Become ISO Certified...It's easier than you think
ITIL version 2: Foundation Training
Measuring Success in the Lean IT World
Cloud Operating Model Design
Ad

More from Boise State University - College of Engineering (20)

PDF
ISACA CISM Study memo - Japanese version in 2025
PPTX
How do we fix the Messed Up Corporation’s System diagram?
PDF
Integration of Information Security Governance and Corporate Governance
PDF
Step-by-Step Procedure for Creating Security Policies Across All Industries i...
PDF
GAP Analysis between Japanese Data Privacy law; APPI and Privacy Mark Standar...
PDF
Step by Step Procesure for Creating Security Policies Across All Industries ...
PDF
The GAP Analysis of the ISO27002 2024 and ISO27002 2014 (in Japanese)
PDF
The GAP Analysis of the ISO27002 2024 and ISO27002 2014 (English)
PDF
The GAP Analysis for NIST SP 800-171 Rev. 3 and ISO/IEC 27001:2022 Comparison...
PDF
The GAP Analysis for NIST SP 800-171 Rev. 3 and ISO/IEC 27001:2022 Comparison...
PDF
(Revised) My Gap analysis results between ISO27001: 2022 and 2013 version
PDF
Compliance with Personal Information Protection Laws in Global Supply Chains ...
PDF
Considerations on the International Situation and Intercultural Perspectives ...
PDF
ITIL Implementation in the IT Departments of Global Enterprises ―Adapting to ...
PDF
ITILv4 Implementation for Business Hotel Operations ―Using Business Frameworks―
PDF
Case Studies in Business Strategy ―Using the ITIL 2011 Edition Framework―
PDF
Another ITIL4 story of a Japanese business hotel
PDF
ITILv3 /2011 Edition Case Study for New Service Managers to Understand Old ITIL.
PDF
(Old version) My Gap analysis results between ISO27001: 2022 and 2013 version.
ISACA CISM Study memo - Japanese version in 2025
How do we fix the Messed Up Corporation’s System diagram?
Integration of Information Security Governance and Corporate Governance
Step-by-Step Procedure for Creating Security Policies Across All Industries i...
GAP Analysis between Japanese Data Privacy law; APPI and Privacy Mark Standar...
Step by Step Procesure for Creating Security Policies Across All Industries ...
The GAP Analysis of the ISO27002 2024 and ISO27002 2014 (in Japanese)
The GAP Analysis of the ISO27002 2024 and ISO27002 2014 (English)
The GAP Analysis for NIST SP 800-171 Rev. 3 and ISO/IEC 27001:2022 Comparison...
The GAP Analysis for NIST SP 800-171 Rev. 3 and ISO/IEC 27001:2022 Comparison...
(Revised) My Gap analysis results between ISO27001: 2022 and 2013 version
Compliance with Personal Information Protection Laws in Global Supply Chains ...
Considerations on the International Situation and Intercultural Perspectives ...
ITIL Implementation in the IT Departments of Global Enterprises ―Adapting to ...
ITILv4 Implementation for Business Hotel Operations ―Using Business Frameworks―
Case Studies in Business Strategy ―Using the ITIL 2011 Edition Framework―
Another ITIL4 story of a Japanese business hotel
ITILv3 /2011 Edition Case Study for New Service Managers to Understand Old ITIL.
(Old version) My Gap analysis results between ISO27001: 2022 and 2013 version.
Ad

Recently uploaded (20)

PDF
Recruitment and Placement PPT.pdfbjfibjdfbjfobj
PDF
Launch Your Data Science Career in Kochi – 2025
PDF
TRAFFIC-MANAGEMENT-AND-ACCIDENT-INVESTIGATION-WITH-DRIVING-PDF-FILE.pdf
PPTX
Major-Components-ofNKJNNKNKNKNKronment.pptx
PPTX
IB Computer Science - Internal Assessment.pptx
PPTX
Introduction to Knowledge Engineering Part 1
PPTX
Introduction to Firewall Analytics - Interfirewall and Transfirewall.pptx
PPTX
mbdjdhjjodule 5-1 rhfhhfjtjjhafbrhfnfbbfnb
PPT
Quality review (1)_presentation of this 21
PPTX
ALIMENTARY AND BILIARY CONDITIONS 3-1.pptx
PPTX
Introduction-to-Cloud-ComputingFinal.pptx
PDF
Clinical guidelines as a resource for EBP(1).pdf
PPTX
DISORDERS OF THE LIVER, GALLBLADDER AND PANCREASE (1).pptx
PPTX
Computer network topology notes for revision
PPTX
Moving the Public Sector (Government) to a Digital Adoption
PDF
BF and FI - Blockchain, fintech and Financial Innovation Lesson 2.pdf
PPTX
advance b rammar.pptxfdgdfgdfsgdfgsdgfdfgdfgsdfgdfgdfg
PPTX
climate analysis of Dhaka ,Banglades.pptx
PPTX
05. PRACTICAL GUIDE TO MICROSOFT EXCEL.pptx
PDF
Galatica Smart Energy Infrastructure Startup Pitch Deck
Recruitment and Placement PPT.pdfbjfibjdfbjfobj
Launch Your Data Science Career in Kochi – 2025
TRAFFIC-MANAGEMENT-AND-ACCIDENT-INVESTIGATION-WITH-DRIVING-PDF-FILE.pdf
Major-Components-ofNKJNNKNKNKNKronment.pptx
IB Computer Science - Internal Assessment.pptx
Introduction to Knowledge Engineering Part 1
Introduction to Firewall Analytics - Interfirewall and Transfirewall.pptx
mbdjdhjjodule 5-1 rhfhhfjtjjhafbrhfnfbbfnb
Quality review (1)_presentation of this 21
ALIMENTARY AND BILIARY CONDITIONS 3-1.pptx
Introduction-to-Cloud-ComputingFinal.pptx
Clinical guidelines as a resource for EBP(1).pdf
DISORDERS OF THE LIVER, GALLBLADDER AND PANCREASE (1).pptx
Computer network topology notes for revision
Moving the Public Sector (Government) to a Digital Adoption
BF and FI - Blockchain, fintech and Financial Innovation Lesson 2.pdf
advance b rammar.pptxfdgdfgdfsgdfgsdgfdfgdfgsdfgdfgdfg
climate analysis of Dhaka ,Banglades.pptx
05. PRACTICAL GUIDE TO MICROSOFT EXCEL.pptx
Galatica Smart Energy Infrastructure Startup Pitch Deck

SixSigma 【Continuous Study】

  • 1. Audit Project Six Sigma DMADV Storyboard Boise Potato Firm ITIL Implementation Action Plan (Hypothetical Project) Created by Yuko Soma
  • 2. Audit Project Objectives: In Jan 2010, Start to develop and implement ITIL framework to reduce e.g. average Incidents backlog to Sigma Level 6 after ITIL implementation Go-Live (Aug. 2010) within 2 months (by Oct. 2010) to help sales to meet their KPI in Dec. 2010 Impacts: Assumptions: 1) Reducing average Incident backlogs/month will improve business process efficiency across all BUs 2) Will increase sales opportunity and sales 3) Improve company brand image by disclosing ITIL implementation to media for commercial purpose The Quality of business processes across all business units supported by IT services is a critical component of Sales increase. Other Documents: (Project Charter, Gantt chart) Background
  • 3. Audit Project Communication Plan Stakeholder Status (See Key) What to Communicate Frequency of Contact Method Responsible Person CIO I Staring Committee Bi-Weekly WebEx James King IT Director A Alignment meeting and Staring Committee Weekly WebEx Jim White IT Service Management manager R Alignment meeting, CAB meeting Weekly Face to face Yuko Soma All Business Units Representative S Alignment meeting and Staring Committee Monthly Face to face D. Dummy (R) = Owns process/project (A) = Who (R) reports to; approves work (S) = Supportive; resource Key: Directions: 1.Identify Stakeholders & Status 2.Analyze person against criteria 3.Develop strategies to maintain support; mitigate resistance 4.Establish priorities (C) = To be consulted (I) = Keep informed; not consulted
  • 4. Audit Project SIPOC Worksheet Process Name: ITIL Implementation Process Owner: Yuko Soma Date: Jan. 5, 2010 Prepared By: Yuko Soma Process Suppliers Process Inputs P R O C E S S Process Outputs Process Customers Finance Team - Financial Month end data transfer to the Oracle EBS system - Budget Input to BI tool - Correct/On Time data transfer to the Oracle EBS system - Correct/On--Time data analysis reports by BI tool CFO Sales Team Daily Sales Opportunity data to Sales force system - Correct/On-Time data transfer to Sales force system COO Sales Oepration Team Customer data update and register on Sales force system - Correct/On Time data update on Sales force system COO HR Team Send Newhire/Leaver data to ITSM Tool - Correct/On Time data update on ITSM tool on time HR Director ITIL Process All Business Process Activities Backlog Reduce Services Services Inputs Outputs Outputs Services Sales Increase
  • 5. Audit Project Brake down “Planning” part of the whole business processes for BU Core Business Develop Plans Level 1 Communicate Business Plans Execute Plans Evaluate IT Services Performance Level 2 Report ITIL Performance Secure ITIL Resources Determine ITIL Needs Execute ITIL Action Plan Marketing Logistics Production New Product Introduction Customer Service Planning Sales Business Environmental Data D M A D V Project Flow - 1
  • 6. Audit Project Project Scope Define IT Director Collect information and protocols Issue ITSM Reports to IT and Business Units Develop and submit CAP Review CAP Execute CAP Identify the current number of backlog Conduct: Confirming the status of the corrective actions taken against the findings of previous incident backlog analysis. Schedule IT Service Manager Project Member Schedule ITIL Design Prepare Complete ITIL design plan Conduct Conduct ITIL implementation evaluation Confirm findings Report Issue ITIL and ITSM tool Summaries CAP D M A D V Level 2 Process: Project Scope
  • 7. Audit Project 1. For our team to get a common understanding, please tell us how you interpret the term “ITIL framework”? 2. What do you see as the attributes of a successful ITIL implementation ? 3. What are the top 3 attributes in order of importance? 4. How would you measure whether a ITIL meets your expectations on these top 3 attributes? Identified needs arising from current challenges 5. What are your top 3 issues related to IT services quality in your organization today? 6. Do you see ITIL is helping to resolve these issues? 7. If so, how do you see a ITIL helping to resolve these issues? 8. What information should ITIL generates for your organization? 9. How will this information be used within your organization? Identified informational needs and attributes 10. Is there anything else you would like to share with us? “Catch all” Identified key attributes of the program D M A D V Project Interview Questions
  • 8. Audit Project ・ In-depth standardized IT audit modular protocols for systems and compliance ・ Determine audit schedule, type, content and team appropriate for the IT auditee in collaboration with local BU/Division Clearly identify where the current and potential risks and problems ・ ITIL reporting roll-up process Complete Communication ・ ISO20000 and ISO27001 certified by recognized 3rd party - Mechanism for benchmarking against other companies to establish competitive advantage Externally accepted ITIL frameworks ・ Decision criteria and process for consistent ratings of individual findings and overall business process performance by using IT Consistent Improvement of ITSM lifecycle ・ System for reporting status of findings and corrective actions ・ Corrective action escalation procedure Verification of completeness of Corrective Action ・ ITIL Expert certification (or ITIL Master) and Six Sigma Black belt Fair ITIL & Six Sigma ・ Incorporation of Division Quality representative in IT audit team ・ ITSM expertise at BU level to implement and adopt locally ・ IT budget is owned at BU level to enable local initiative and adoption ・ Linked to ITIL Expert certification where appropriate Locally Relevant ・ Internal validation process ・ Use external IT auditors only ・ Interdivisional IT audit teams Independent IT Audits Design Ideas CTQ D M A D V Project Design Ideas
  • 9. Audit Project Potential synergies and conflicts between design ideas identified “Inclusion of Division IT in ITIL action team” and “Convertible Rating System” conflict with other design elements Top 6 design elements have no conflicts and are synergistic D M A D V Project Trade-offs (Sample from textbook)
  • 10. Audit Project All Business Units needs and priorities were similar ・ Extracted solutions, issues and needs from interviews ・ 253 need statements transcribed to Post-it notes ・ Post-it notes color coded by Business Units segment ・ Top needs from each Business Units highlighted ・ Needs affinitized and sorted using tree diagrams Project VOC Analysis D M A D V
  • 11. Audit Project •Identify number of ITIL process was used •Establish maturity of facility and rank operations based on potential risk. (Based on Division assessment against established criteria) •Determine ITIL type required based on IT Service maturity •Determine additional IT auditing needs (obtained by use of the collaborative routine established in the GAP) •Determine the preferred ITIL Measurement timing from the Divisions Select the ITIL Action team based on: • Qualification • Right process knowledge • Language ability • Availability Develop ITIL schedule: ▪ Firm scheduling of compliance IT audits (prioritized based on risk profile) Draft Schedule indicates: ▪ Availability of ITIL Expert Confirmation of schedule Communication of final schedule How Much: 100% match of ITIL action team on process knowledge; In 2010 at least 50% of ITSM conducted with fully certified ITIL Expert; 2011 onwards 100% of ITSM conducted with fully certified ITL Expert. Firm scheduling routines to have the right team at the right location conducting the right IT audit D M A D V Project Flow - 2 Level 2 Report ITIL Performance Secure Resources Determine ITIL Needs Execute ITIL Action Plan Level 3 Schedule ITIL Design Identify ITIL Type Establish Current Status Identify ITIL Action Team Required
  • 12. Audit Project Secure IT Resources ITIL Expert Certification Program - Internal and external ITSM staffs have the right skills and competences Selection Periodic re-training and evaluation Select using criteria for: • Personal Atributes • Education • Related experience How much: 10 % of internal ITSM staffs are recruited/transitioned. How much: 100% match of ITIL action team on ITIL process knowledge How much In 2010 at least 50% of ITSM conducted with 3 certified ITIL Expert, 5 ITIL Practitioner and 25 ITIL Foundation 2011 How much: Maintain steady state of 100% of ITSM staffs Train ITIL Expert in: • ITIL principles • ITIL execution • Business Processes • ISMS • Laws and regulations • Six Sigma Black belt, Green belt ・ Certify ITIL Expert, Practitioner and ITIL foundation 2011 D M A D V Project Flow - 3 Level 3 Certification Maintenance Training Selection Certification Level 2 Report ITIL Performance Secure Resources Determine ITIL Needs Execute ITIL Action Plan
  • 13. Audit Project Standardized ITIL protocol module for planning, execution and reporting of individual outcomes Standardized modules to evaluate compliance of processes and systems during individual ITIL based tasks In-depth protocols and decision criteria deliver consistent and fair IT audits How Much: • 50% of ITSM tool modules completed by June. 2010 • 100% of ITIL design modules completed by Aug. 2010 D M A D V Project Flow - 4 Level 3 Perform ITIL Plan ITIL Design Level 2 Report ITIL Performance Secure Resources Determine ITIL Needs Execute ITIL Action Plan
  • 14. Audit Project • Incorporate reporting of ITIL information into established management routines for Quality performance at the BU level. Information can be used to drive resource allocation at the BU and Division level. • ITIL summary provided to BOD. Information will be used as input to resource allocation, and greater understanding of the risks in the organization. • Detailed ITIL report issued to IT Auditee that identifies critical and systemic risks • IT Service manager uses report information to drive program improvement • Formalized communication of high risk findings to appropriate management levels. • Gather, analyze and trend data to create a summary report that includes identification of high risk issues, status of corrective action, successful practices and learnings. • ITIL summary to provide comparative data of Division / BU performance against our performance. Actionable audit information available – IT Auditee to BOD How Much: Provide bi-monthly reports for BOD meetings; provide monthly reports to Steering Committee, Quality Division and BU/Vision heads by Aug. 2010 D M A D V Project Flow - 5 Level 2 Report ITIL Performance Secure ITIL Resources Determine ITIL Needs Execute ITIL Action Plan Summarize ITIL Data Communicate Detailed ITIL Findings Level 3 Communicate Summarized Info
  • 15. Audit Project D M A D V 1. Average delay awaiting closing the backlog incident tickets 2. Maximum delay awaiting closing the backlog Incident tickets 3. Average the number of Incident backlog tickets 4. Maximum backlog Incident tickets Questions: ・ Is the backlog a chance event required a permanent change of process ? ・ Which type of job skills are required? ・ Will additional semi-automated process required to reduce backlog Incident thickets? ・ Will ITIL solve this problem? The Simulation
  • 16. Audit Project Hows (Design Requirements) Needs (Whats) Rating TCCC Certified auditors In-depth standardized audit modular protocols for systems & compliance Determine audit & audit team appropriate for the auditee in collaboration with local SBU/division Decision criteria and process for consistent ratings of individual findings and overall facility performance Global audit program certified by recognized 3rd party to ISO 19011 Global audit reporting roll-up process for BOD & Executive Comm. Clearly Identifying current and potential risk and problems 48 9 9 9 9 9 Independent Audits 39 1 9 The Global Program is locally relevant 36 3 9 Fair Audits 30 9 1 3 9 9 Consistent Audits 24 9 9 3 9 9 Verification of completeness of corrective action 21 9 9 1 9 Externally accepted audits 21 3 1 3 Complete communication 16 9 9 3 3 9 Importance 1422 1071 987 966 900 765 Options Needs (Whats) Weight Determined using TCCQS Maturity continiuum only Determined by Quality Indicator only Determined by Previous Audit result Determined by Audit Manager Determined by Auditee Determined by Division QA Manager Hub Audit Manager Select Team Lead Auditor Selects Team Div QA Mgr Selects Team Decentralised Scheduling Centralised Scheudling Process TCCC Certified auditors 1422 In-depth standardised audit modular protocols for systems & compliance 1071 Determine audit & audit team appropriate for the auditee in collaboration with local SBU/division 987 3 1 3 1 3 3 9 3 1 9 1 Decision criteria and process for consistent ratings of individual findings and overall facility performance 966 Global audit program certified by recognized 3rd party to ISO 19011 900 9 9 1 3 3 Global audit reporting roll-up process for BOD & Executive Committee 765 Importance 2961 987 2961 987 2961 2961 16983 11061 1887 11583 3687 TEAM SELECTION SCHEDULING AUDIT TYPE P R I M E D O T S Actions 1 Update of EMS with new plant information X Quarterly review and update plant information on EMS 2 Determine number of plants to be audited (EMS) 3 Request information on plant maturity, risk and audit timing 4 Evaluate every plant against agreed criteria (DIVISION) 5 Prioritize based on risk and audit timing (DIVISION) 6 Comunicate prioritized plant list to audit group (DIVISION) X Ask for required information in advance and frequent follow up. 7 Collect prioritized list from divisions 8 Any new process identified in the prioritized list? 9 Request information regarding new process 10 Provide information regarding new process 11 Development and inclusion of the new module X Quarterly survey with Division to identify new processes. 12 Update prioritized list 13 Compare mandays required with mandays available 14 Are sufficient auditors available within SBU? X X Identify and prepare an external pool of auditors 15 Are there auditors available in other SBU´that can be used? X Get access to information on auditors in other SBU´s 16 Re-evaluate prioritized list to focus on risk priority X Ensure there are sufficient trained auditors available with the required skills 17 Do auditors have required process knowledge? X Ensure there are sufficient trained auditors available with the required skills 18 Do auditors have required language skill? X Ensure there are sufficient trained auditors available with the required skills 19 Is location of auditors suitable for conducting audits? X Ensure there are sufficient trained auditors available with the required skills in yours SBU 20 Can audit be re-scheduled? 21 Is there a lead auditor available? X Ensure there are sufficient trained auditors available with the required skills in yours SBU 22 Allocate resources to the prioritized list 23 Prepare/Review Draft Schedule X Note: Minimize this loop with more active involvement with the Divisons in the early stage of the scheduling process. 24 Communicate Draft Schedule to Divisions 25 Agree with draft schedule? (DIVISION) 26 Communicate proposed changes (DIVISION) X Note: Minimize this loop with more active involvement with the Divisons in the early stage of the scheduling process. Alternately commit the Division to respond within an agreed timeframe or the schedule would be accepted as it is. 27 Are changes feasible? 28 Communicate to Divison that changes are not possible 29 Prepare final schedule 30 Communicate final schedule PRODUCTIVITY ANALYSIS STEP Detailed design options selected, flowcharted and measures identified CTQs High Level Design Elements QFD #1 High Level Design Elements Detailed Design Options QFD #2 Value-Added Analysis VA BVA NVA 1 Update of EMS with new plant information X 2 Determine number of plants to be audited (EMS) X 3 Request information on plant maturity, risk and audit timing X 4 Evaluate every plant against agreed criteria (DIVISION) X 5 Prioritize based on risk and audit timing (DIVISION) X 6 Comunicate prioritized plant list to audit group (DIVISION) X 7 Collect prioritized list from divisions X 8 Any new process identified in the prioritized list? X YES (10), NO(12) 9 Request information regarding new process X 10 Provide information regarding new process X 11 Development and inclusion of the new module X 12 Update prioritized list X Perform updating of EMS each quarter and detec new processes 13 Compare mandays required with mandays available X 14 Are sufficient auditors available within SBU? X 15 Are there auditors available in other SBU´that can be used? X 16 Re-evaluate prioritized list to focus on risk priority X Define sufficient number of auditors, based on process knowledge, language skill, location, leading. Reduce number of audits based on risk evaluation 17 Do auditors have required process knowledge? X 18 Do auditors have required language skill? X 19 Is location of auditors suitable for conducting audits? X 20 Can audit be re-scheduled? X 21 Is there a lead auditor available? X 22 Allocate resources to the prioritized list X 23 Prepare/Review Draft Schedule X Note: Minimize this loop with more active involvement with the Divisons in the early stage of the scheduling process. 24 Communicate Draft Schedule to Divisions X 25 Agree with draft schedule? (DIVISION) X Note: Minimize this loop with more active involvement with the Divisons in the early stage of the scheduling process. 26 Communicate proposed changes (DIVISION) X Note: Minimize this loop with more active involvement with the Divisons in the early stage of the scheduling process. 27 Are changes feasible? X 28 Communicate to Divison that changes are not possible X Note: Minimize this loop with more active involvement with the Divisons in the early stage of the scheduling process. 29 Prepare final schedule X 30 Communicate final schedule X VALUE CATEGORY ACTION STEP Preliminary Flowchart Productivity Analysis Error Proofing Final Flowchart Potential Causes Current Controls Actions Recommended Resp. Actions Taken What causes the Key Input to go wrong? What are the existing controls and procedures (inspection and test) that prevent either the cause or the Failure Mode? What are the actions for reducing the occurrence of the cause, or improving detection? What are the completed actions taken with the recalculated RPN? 10 Did not provide the information or update the EMS 4 no current controls 10 400 Establish routines to quarterly for divisions to review current status against current EMS content GAP Mngr 10 2 5 9 Planning of resources ineffective 4 no current controls 10 360 Define a procedure for rigorous planning. Use auditor pool across SBU's while building SBU capability. Identify multiple external certification bodies in design phase. GAP Mngr 9 2 4 8 Process for updating is not followed 4 no current controls 10 320 Audit the updating process at a local level GAP Mngr 8 2 4 S E V E R I T Y O C C U R R E N C E D E T E C T I O N S E V E R I T Y O C C U R R E N C E D E T E C T I O N R P N Critical Risk Flow Process Auditee Hub Q.A. Audit Group Lead Auditor Division PVP ID of critical/high risk (1) Communicate finding to auditee (2) Discussion and confirmation of evidence (3) Confirmation of finding (4) Confirm with audit manager (5) Continue audit (6) Telephonic discussion with auditor (7) Agree (8) No Yes No Confirm with Hub Q.A. (9) Yes Telephonic discussion with audit manager (10) Agree (11) No Yes Inform auditor (12) Continue audit based on audit manager comment (13) Confirmation with audit manager (14) Telephonic discussion with division to get a plan for action (15) Discussion with bottler & preparation of CAP (16) Forward plan by email to audit manager (17) Agree with content of CAP (18) Inform Hub Q.A.and copy division technical director (19) Yes No Voice mail to SBU Pres. Copy PVP, Div. Pres, SBU QA, SBU Tech, Div Tech detailing critical status (20) D M A D V Determine ITIL Needs (Sample from text )
  • 17. Audit Project Document Management ITIL implementation and its control of procedures, incorporating: • Document creation • Document review • Document distribution • Document archiving (Above done with electronic workflow) Recordkeeping ITSM maturity and operational data Audit reports • Field for high risk, corrective action status and successful practices • Status of corrective action receipt • Audit schedule status • Search of reports by: • Risk • BU • Division ITSM Staffs Capability • Personnel information: • Education • Work Experience • ITSM tool training • EXIN ITIL foundation Certification to all Technical Staffs • Languages, nationality, location • Course and skill profiles • Filter/search capability This functionality is available with current solutions and/or off-the-shelf software • Document revision • Document approval • Document control D M A D V Features of ITIL framework
  • 18. Audit Project ・ New Standard; Install ISO20000-1 and ISO27001 ・ Modify quality appraisal and IT audit criteria ・ Update prices of product to increase sales Implementation of ITIL makes price increase of company products possible ・ Revise IT budgets ・ Revise manpower forecasts Not meant labor cost saving. Reallocate IT technical staffs to right positions. D M A D V Hard-Won Gains
  • 19. Audit Project • The ITIL Design was completed on schedule and full scale implementation began Jan. 2010 • Preliminary results indicate all CTQs will be met • An estimated backlog/month reducing to Sigma Level 6.0 by ITIL in Oct. 2010 • After full ITIL implementation, the sales resulted at least 1,000,000 increase in Oct. 2010 – Dec. 2010 (FY2010 Q4) Summary
  • 20. Audit Project References Thomas Pyzdek, and Paul Leller (2014). “The Six Sigma Handbook, Fourth Edition”, USA: McGraw-Hill Education. SIX SIGMA ONLINE templates, Aveta Business Institute.