The document describes the transfer reactances between a generator and infinite bus bar under various conditions, including pre-fault, during fault, and post-fault. It then asks to determine the maximum load that can be transferred without loss of stability if the fault is cleared when the rotor has advanced 600 electrical degrees from its prefault position. Through calculations using the reactance values and rotor position, it determines the maximum load is 127.3 MW.