SlideShare a Scribd company logo
KSC Constellation Ground Operations Project Office




                                                     Integrated Testing at KSC
                                                       between Constellation
                                                              Systems

                                                            Tim Honeycutt

                                                               February 2008

                                                          Timothy.R.Honeycutt@nasa.gov

                                                                  321-867-6567
                                                                  321- 867-
KSC Constellation Project Office
KSC Constellation Ground Operations Project Office



                                                                                      KSC Constellation
                                                                                        Project Office

                                                                     Business                                   Staff Office


                                                                Project Control                                  Logistics


                                                                    Operations &                            Systems Engineering
                                                                     Integration                                & Integration
                                                                                                              (including IT&V)



                                                     Crew Vehicle                           Ground                Command,
                                                                                          Systems (GS)            Control, and
                                                                                             Project            Communications
                                                                     Launch Vehicle




                                                                        GS Project         GS Project     GS Project Support
                                                                       Management         Integration &         Office
                                                                                          Requirements
                                                                                                                                  2
Presentation Outline
KSC Constellation Ground Operations Project Office




                                                     •   History of Multi-Element Integration Tests (MEITs)
                                                          – MEIT Concept
                                                          – Previous MEITs
                                                          – Major Problems Found
                                                          – Benefits

                                                     •   Integrated Testing at KSC for the Constellation Program
                                                          – Integrated Tests
                                                              • Multi-Element Integrated Tests (MEITs)
                                                              • Flight Element Integrated Tests (FEITs)
                                                              • Integrated Verification Tests (IVTs)

                                                     •   Summary


                                                                                                                   3
History
KSC Constellation Ground Operations Project Office



                                                     •   “Ship and shoot” was the strategy for the International Space
                                                         Station Program (ISSP) during the early 1990’s
                                                         – It proposed transporting flight elements directly from the factory to the
                                                           launch site and begin the mission without further testing.
                                                         – Factory level testing and element interface verifications at the
                                                           subsystem-level, and interface analysis were all that was planned.

                                                     •   Before the end of that decade a shift in testing strategy occurred
                                                         within the ISSP
                                                         – The ISSP adopted a more integrated approach for ground validation of
                                                           it’s flight hardware.
                                                         – Availability of elements at the launch site created a feasible opportunity
                                                           to test multiple elements together.
                                                         – The notion of validation testing on the ground was presented and
                                                           accepted by the ISSP due to the criticality of the on-orbit functionality,
                                                           including safety concerns for the crew .

                                                                                                                                        4
History (cont)
KSC Constellation Ground Operations Project Office



                                                     •   Multi Element Integration Tests (MEITs) and Integrated Systems
                                                         Tests (ISTs)
                                                         – Risk mitigation tests performed on the ground, used for validating the
                                                           operation of the flight elements and their systems in an environment that
                                                           is as flight-like as possible.
                                                         – These tests were used to demonstrate the interoperability and
                                                           functionality of Space Station elements as integrated “in-space”
                                                           assemblies on the ground before they were assembled in space for the
                                                           first time.
                                                             • Space Station element-to-element interface capability was verified as
                                                               well as systems end-to-end operability with hardware and software.
                                                             • Mission Sequence Testing (MST), also known as “end-to-end”
                                                               integration testing, included a full-up configuration with the Mission
                                                               Control Center, Tracking Data Relay Satellite System (TDRSS), and
                                                               the “station” operating on the ground.
                                                             • Also verified limited on-orbit system compatibility.

                                                                                                                                        5
KSC ISS MEIT/IST Experience
KSC Constellation Ground Operations Project Office



                                                     •   Planned/developed and implemented the following for ISSP:

                                                         – MEIT1:
                                                            • U.S. Lab, Z1, P6, SSRMS, Node1 (emulated)

                                                         – MEIT2:
                                                            • S0/MT/MBS, S1, P1, P3/4, US Lab (emulated)

                                                         – MEIT3:
                                                            • JEM, Node2, US Lab (emulated)

                                                         – Node2 Systems Test
                                                            • Node2, US LAB & Node1 (emulated)




                                                                                                                     6
MEIT                                                                                                                                                               Configurations
                                                                                                                                                                                         S
                                                                                                                                                                                    RM                                                                   SPDM              18
                                                                                                                                                                               SS                                               18         31       18

                                                                                                                                                                                                                      18              MBS                18

                                                                                                        External                                                                                                                           31
                                                                                                        Payload
                                                                                                                24                                                                                                                         31                                                                                 ULC (or SLP)
                                                                                                                     External
                                                                                                                                            CETA                                                                                                                                                                                                             SLP (or ULC)
                                                                                                                     Payload                          30                    CETA         30                                     30        MT        30                                                                                    25

                                                                                                                          24                                                                                                                                                                                                                                           25
                                                                                                                                                                                                                                                                                                                S-Band
             17                                                               17                                                                                                                                                                                                                                                                                                                   17                                                  17
                                                                                                                                             26                               26                                                           23            32
                                                                                                                24        24                          12                                                                                                                                                             12                                     25         25
             16       14                                                                   14                                                                                                                                                                                                                                                                                            14        16                                       14         16
                                                                              16


                 S6        11   11            S5                   8
                                                                  11 11            S4                  28            S3         22          22                S1                         22                22                             S0                      22                22                 P1                 22                   22                P3             28            P4           8
                                                                                                                                                                                                                                                                                                                                                                                                        11 11        P5           11 11          P6
             16                                                               16                                                                                                                                                                                                                                                                                                                   16                                                  16
                                                                                                                                                               13                                                                                                                                          13
                                                                                                                24        24                                                                                                               21
             17                                                               17                                                                               15           15                                                                                                                 15          15
                                                                                                                                                                                                                                                                                                                                                                  JEM ELM ES                       17                                                  17
                                                                                                                                                      15                                                                                                                                                             15
                                                                                                                24
                                                                                                                                                                                                                                                                                                                                                                            29
                                                                                                        External
                                                                                                                                                                                                                                                                                                                                                                            29
                                                                                                        Payload
                                                                                                                          24                                                                                                                                                                                                                                       JEM EF
                                                                                                                                                                                                                                                                           S0-to-Lab Struts
                                                                                                                     External
                                                                                                                                                                                                                                                                                                                                                                            29
                                                                                                                     Payload
                                                            5,7           5,7
                                                                                                                                                                                                                                                                                                                                                                            29

                                                            5,7           5,7
                                                                                                                                                                                                                                                                                     MEIT-2 Uses
                                                            5,7           5,7                                                                                                                                                                                                        US Lab Simulation                                                                               9        8     8   9
                                                                                                                                                                                                                                                                                                                                                                                                             JEM
                                                                                                                                                                                                                                                                                                                                                                                                            ELM PS
                                                                  SPP




                                                                                                                                                                                                                      27
                                                            5,7           5,7
                                          RA
                                                                                                                                                                                                           27                        27
                                      E                                                                                                                                                               27                                  27
                                                                                                                                                                                                                                                                                                                                                            18
                                                                                                                                                                                                                                                                                                                                                                  JEM PM
                                                                                                                                                                                                 27                                            27
                                                                                                                                                                                                                CUPOLA                                                                                                                                                      9
                                                                                                                                                                                                                      8                                                                                                                                                     8
                                                                          6
                                                                                                                                               re
                                                                                                                                                 la                                                                                                                                                                                                                                                                                Primary Orbiter
                                                                    2                                                                        St                                                                                                                                                                                                                             8
                                                                                                   7 places
                                                                                                                                                                                                                      8
                                                                                                                                                                                                                                                                                                                                                                                                                                      Docking
                                                                                                                                                                                                                       9                                                                                                                                                  9
                                     12           5,7               2                                  12             5,7                                                                                            PORT
                                                                                                                                                                                                                                                                                          18                    21                                                      PORT                                                          Interface
                                                                                                                                     EFGF
                                                             Z      4                                                                                                                                                                                                                               ZENITH

             Progress 3                                 Service
                M1
                                 3    4       A
                                                        Module
                                                                          F 4          2           2        A          FGB                   F 4      1        1
                                                                                                                                                                   PMA1
                                                                                                                                                              PM
                                                                                                                                                                                             9        AFT                            FWD 9           8        8        9                 U.S. LAB                         9       8            8        9        AFT                 FWD 9          8       8
                                                             N      4
                                                                                                                      5,7
                                                                                                                                N      4
                                                                                                                                                                   A3                                                                                                                                                                                                                                           PMA2      4   1       1   PM       1
                                                                                                                                                                        sim
                                                  5,7
                                                                    2                                        18                        3
                                                                                                                                                                              ula                                                                                                                    NADIR

                                                                                                                                                                                    tion                                                                                             27
                                                                    2                                                                  3
                                                                    Z                                                                                                                                      NODE 1                                                                        Ku-Band
                                                                                                                                                                                                                                                                                                                                                                  NODE 2
                                                                                                                                     DSM
                                                                                                       DC                                                                                                  simulated                                                   CMGs (4)            12
                           RM-1           3             3   S              P 3                  3                                      3
                                                                                                       -2                                          CRV#1                                                                                                                        A          P
                                                             Universal
                                                             Docking
                                                                                                                                                          1                          8       9 NADIR                        ZENITH 9                 8        8    N
                                                                                                                                                                                                                                                                                    Z1              Z 11        MPLM          9       8        8    9 NADIR                      ZENITH 9           8       8    9   CAM
                                                              Module                                                             3
     Alternate                                                                                                                                            1                                                                                                                     F          S
                                                                                                                                                                                                                                                                            10
                                                            A              F 3                         RM-2                    Soyuz               CRV
  Orbiter Docking                                       3                                      3
                                                                                                                                TM
                                                                                                                                                   adapt
                                                                                                                                                                                                                     STBD                                                                                                                                               STBD
                                                                                                                                                                                                                       9                                                                                                                           18                     9
     Interface                                                      N                                                                                     8
                                                                                                                                                                                                                      8                                                                                                                                                     8
                                                                    3                                                                                                                                                                                     16       Beta Gimbal Assembly
                                                                                                                                                                                  NTA 20 20

                                                                                                                                                                                                                      8                                   17       Solar Array Deployment                                                                                   8
                                                                    3                                                                        8                                    NTA 20 20                                                               18       Power/Data Grapple Fixture (PDGF)                                                                                                            LEGEND
                                                                                                                8                                                                                                     9                                                                                                                                                     9
                                                                  Soyuz                                                                                                                                                                                   19       Orbiter ‘D’ Hatch                                                                                                                            Remotely actuated mechanisms
                                                                                                                9                            9
                            8                                      TM                                                                                                             OTA 20 20
                                                                                                                                                                                                            AIRLOCK                                       20       NTA/OTA Attachment Mechanism
         1   4   PMA3                                                                                       AFT                             STBD                                                                                                                                                                                                                                                                EVA operated mechanisms
                                                                                                                                                                                                                                                          21       Lab Cradle Assy / MTSAS
                                                                                                                     NODE 3                                                                                                19                             22       Segment to Segment Attach System (SSAS)                                                                                                      IVA operated mechanisms
1 Modified APAS
                                                                                   8       9       NADIR                                      ZENITH 9             8              OTA 20 20
                                                                                                                                                                                                                                                          23       Mobile Transporter Drive
                                                                                                                                                                                                                                                                                                                                                                       COF
                                                                                                            FWD                             PORT                                                                                                                                                                                                                                                                Articulating/Deployable mechanisms
2 Hybrid Docking Assembly (HDA)                                                                                                                                                                                                                           24       Payload Attach System (PAS)
3 Probe and Cone (P&C)
                                                                                                                9                            9                                                                  27
                                                                                                                                                                                                                                                          25       ULC Attach System (ULCAS)                                                                                                                    Translation mechanisms
                              Alternate MPLM
4 APAS Hatch                 Berthing Location                                                                  8                            8                                                                                                            26       CETA Rollers                                                                                                                                 passive                   active
5 RSA Solar Array Deploy Mechanism
                                                                                                                                                                        8     9
                                                                                                                                                                                                 U.S.                            9        8
                                                                                                                                                                                                                                                          27       Window Shutter
6 RSA Radiator Deploy Mechanism                                                    11      Rocketdyne Truss Attachment (RTAS)                                                                                                                             28       Solar Alpha Rotary Joint (SARJ)                                                                                                              MEIT 1 Completed 2/00
7 RSA Array Pointing Mechanism                                                     12      Deployable Antenna
                                                                                                                                                                                                 HAB                                                      29       JEM Berthing Mechanism                                                                                                                       MEIT 2 Completed 4/02
8 Common Berthing Mechanism (CBM)                                                  13      Thermal Radiator Rotary Joint (TRRJ)                                                                                                                           30       CETA Coupler
                                                                                                                                                                                                                                                                                                                                                                                                                MEIT 3 Completed 9/03
9 US Common Hatch                                                                  14      EPS Radiator Deployment                                                                                                                                        31       Common Attach System (CAS)
10 Manual Berthing Mechanism (MBM)                                                 15      TCS Radiator Deployment                                                                                                                                        32       Trailing Umbilical System (TUS) (2)
MEIT 2 Hardware at KSC
KSC Constellation Ground Operations Project Office



                                                                                          P3 Truss    P4 Truss
                                                                                P1Truss


                                                               S0 Truss                              US Lab
                                                                                                     Emulator


                                                     S1Truss




                                                                                                            8
Problems Found in MEITs (Top Examples)
KSC Constellation Ground Operations Project Office



                                                     •   P6 truss failed to power up due to Auxiliary Power Converter Unit
                                                         (APCU) under voltage trip condition.
                                                          – Impact: Unable to start P6 on Orbit.

                                                     •   US Lab critical activation took 36 hours during the first MEIT Power-up
                                                         (computer/procedure problems), Requirement <2 hrs. During MEIT
                                                         regression Mission Sequence Test, Critical Activation took 1 hr, 15
                                                         minutes.
                                                          – Impact: Loss of Lab element during on-orbit activation due to
                                                            thermal loading.

                                                     •   Command and Control (C&C) computers failed several times due to
                                                         task overrun problems (CPU utilization problems).
                                                          – Impact: Significant operational issues (Loss of Vehicle
                                                            commanding, Vehicle health visibility, visibility to crew/ground)
                                                            would occur because of continued loss of C&C computers.

                                                                                                                                   9
Problems Found in MEITs (Top Examples)
                                                                                (continued)
KSC Constellation Ground Operations Project Office



                                                     •   Video lines were swapped between Trailing Umbilical Systems 1,
                                                         2 (NASA) and Mobile Base System (Canadian Space Agency).
                                                         – Impact: Significant operational impact to manually route video
                                                           signals. Extra Vehicular Activity (EVA) would have been required
                                                           to replace two harnesses to correct the problem.

                                                     •   C&C computers failed when performing synchronization to
                                                         Global Positioning System (GPS) time.
                                                         – Impact: Loss of accurate GPS capability, degraded attitude
                                                           control capability until development /testing and on-orbit upload of
                                                           new software patch.

                                                     •   Quality of Space to Ground Audio was unacceptable.
                                                         – Impact: Operation and potential safety impact to crew due to lack
                                                           of understanding between Crew/Ground.

                                                                                                                               10
MEIT Benefits
KSC Constellation Ground Operations Project Office


                                                     • Significant findings from MEIT have created an opportunity to
                                                       correct major operational problems which would have resulted in:
                                                         – Cost/Schedule Slip
                                                          • Major milestone slippage in the Program
                                                         – Critical On-orbit Operations impacts
                                                          • Safety concerns for the crew
                                                          • Loss of mission objectives
                                                          • Loss of flight hardware
                                                         – Nominal Operations impacts
                                                          • Unknown operation risks (loss of redundancy capability)
                                                         – Unplanned EVA’s

                                                          The cumulative effect of identifying & resolving integrated
                                                         hardware, software and procedure problems before flight has
                                                         proven to save the International Space Station Program major
                                                         on-orbit issues.
                                                                                                                          11
Integrated Testing at KSC
                                                                   for the Constellation Program (CxP)
KSC Constellation Ground Operations Project Office




                                                     •   Testing that occurs between two or more individual Constellation
                                                         Systems to verify the interfaces between those Systems and to
                                                         validate the integrated Systems' functionality and interoperability.

                                                     •   Includes testing mechanical, electrical, data and fluid interfaces.

                                                     •   Integrated testing applies to the in-space flight and integrated
                                                         vehicle stack configurations.
                                                          – Multi-Element Integration Testing (MEIT)
                                                          – Flight Element Integration Testing (FEIT)
                                                          – Interface Verification Testing (IVT)




                                                                                                                                12
Constellation Architecture
KSC Constellation Ground Operations Project Office


                                                                                                               Crew Exploration Vehicle – CEV/Orion
                                                                               Constellation                           Lunar Lander – Lander/Altair
                                                                                                                  Crew Launch Vehicle – CLV/Ares I
                                                                               Architecture                    Cargo Launch Vehicle – CaLV/Ares V


                                                     Crew Vehicles   Launch Vehicles              Ground & Mission
                                                      & Systems        & Systems                      Systems



                                                                                                    Ground
                                                         CEV               CLV                                                   Future
                                                                                                    Systems

                                                        Lunar                                       Mission
                                                                           CaLV
                                                        Lander                                      Systems

                                                         EVA                      CLV Elements
                                                                                  -1st Stage
                                                       Systems                    -Upper Stage
                                                                                  -Upper Stage Engine        CxProgram    Architecture   Level 2

                                                     Flight Crew                                              Project                    Level 3
                                                                     CEV Elements                                            System
                                                        Equip.       -Launch Abort System (LAS)
                                                                     -Crew Module (CM)                                      Element      Level 4
                                                        Lunar        -Service Module (SM)                                  Subsystem     Level 5
                                                       Surface       -Spacecraft Adapter (SA)
                                                       Systems
                                                                     Subsystems: examples include                             Future
                                                                       data, power, thermal, etc.
                                                                                                                                                   13
Multi-Element Integration Test (MEIT)
KSC Constellation Ground Operations Project Office


                                                     MEIT:
                                                     •   An integration test between two or more flight systems that will be launched
                                                         on separate launch vehicles and integrated together for the first time in
                                                         space.
                                                          – Interfaces between the flight systems, mission systems, and other
                                                            appropriate CxP/ISSP and external systems may be also tested as part
                                                            of each MEIT.

                                                     •   The primary objectives of MEIT are:
                                                          – Demonstrate the interoperability, functionality, and stability of the flight
                                                            systems, elements, and sub-systems as an integrated “in-space” vehicle
                                                            assembly on the ground before they are assembled in space for the first
                                                            time.
                                                          – Validate critical mission sequence activities and flight procedures prior to
                                                            their first-time execution in-flight.

                                                     •   A secondary objective of MEIT is:
                                                          – To collect functional and performance data from the integrated flight
                                                            systems to support validation of the different interface test tool sets,
                                                            emulators, and simulators used by the Projects in accepting future serial
                                                            numbers of those flight systems.
                                                                                                                                           14
MEIT (continued)
KSC Constellation Ground Operations Project Office


                                                     •   MEIT serves as a training ground for:
                                                          – Flight crews and trainers
                                                          – Mission Operations Division (MOD)/Mission Control Center (MCC)
                                                            personnel
                                                          – Constellation system engineers
                                                     •   MEITs are executed after all of the system-level requirements have
                                                         been satisfied by the involved Project offices and those offices declare
                                                         their system designs as verified for flight.
                                                     •   MEITs are one time tests with a potential for a follow-on regression
                                                         test.
                                                          – Performed prior to first crewed missions
                                                     •   Use of flight-like emulators and cables/connectors may be used when
                                                         integration between the flight systems is not practical.
                                                     •   Planned MEITs:
                                                          – CEV to International Space Station (ISS) (using ISS emulation)
                                                          – CEV to Lunar Lander/Earth Departure Stage (EDS) (using EDS
                                                            emulation)                                                          15
MEIT 1
KSC Constellation Ground Operations Project Office




                                                                  MEIT 1 Test Configuration
                                                     (performed in the Multi-Payload Processing Facility)




                                                                                                            16
MEIT 1: CEV to ISS (Emulator)
KSC Constellation Ground Operations Project Office



                                                     •   CEV-International Space Station (ISS) MEIT
                                                         – To be performed in the year 2012, prior to first ISS flight.
                                                         – Tests interoperability/functionality and all functional interfaces: data,
                                                           audio, video, RF, power.
                                                         – End-to-end test with Mission Control performed via TDRSS.
                                                         – Uses emulation in place of ISS flight hardware.
                                                         – Mated with flight-like cables and connectors.
                                                                  CEV                            ISS Flight Emulator
                                                                                    LIDS




                                                                                                                                       17
CEV-ISS Interfaces
KSC Constellation Ground Operations Project Office


                                                     – Mechanical
                                                        • CxP will utilize newly developed Low Impact Docking System
                                                          (LIDS)
                                                        • LIDS is not compatible with ISS Docking System (APAS:
                                                          Androgynous Peripheral Attach System)
                                                        • CxP will construct two APAS To LIDS Adapter Segments (ATLAS)
                                                        • ATLAS will be installed permanently on Peripheral Mating
                                                          Adapters (PMAs) 2 and 3
                                                        • Provides power and data pass through capability
                                                     – Power
                                                        • ISS will provide 120 VDC to CEV via two redundant power feeds
                                                        • CEV will convert 120 VDC ISS power to 28 VDC for internal buses
                                                     – Fluids/Gases
                                                        • Only requirements are for Inter Module Ventilation (IMV) air
                                                          circulation – essentially same as for Shuttle orbiter
                                                                                                                          18
CEV-ISS Interfaces
KSC Constellation Ground Operations Project Office



                                                     – Avionics
                                                        • Audio, video, and data are distributed internally to CEV over a
                                                          Gigabit Ethernet network
                                                        • CEV bus would connect to CxP provided Common
                                                          Communications Adapter (CCA) which would provide
                                                          conversion to legacy ISS networks.
                                                            – CCA required for MIL-STD-1553 (ISS) and Gigabit Ethernet
                                                              (CEV) data conversions
                                                            – CCA installed on ISS
                                                            – CCA or prototype would be integrated into ISS emulator and
                                                              tested with CEV in MEIT
                                                        • Separate CEV to ISS S-Band RF link would be implemented for
                                                          rendezvous/proximity ops


                                                                                                                            19
MEIT 2
KSC Constellation Ground Operations Project Office




                                                              MEIT 2 Test Configurations (TCs)
                                                     (performed in the Space Station Processing Facility)




                                                                                                            20
MEIT 2: Test Configuration #1
                                                                (TC1)
KSC Constellation Ground Operations Project Office




                                                       CEV to Lunar Lander
                                                       with EDS Emulation



                                                                          EDS
                                                        LIDS

                                                               LIDS

                                                                          (Emulation)




                                                                                        21
MEIT 2: Test Configuration #2
                                                                (TC2)
KSC Constellation Ground Operations Project Office




                                                         CEV to Lunar Lander




                                                                  LIDS



                                                                         LIDS




                                                                                     22
Flight Element Integration Test (FEIT)
KSC Constellation Ground Operations Project Office


                                                         FEIT:
                                                          – An integration test between the new or significantly modified systems
                                                            and elements being assembled into an integrated launch vehicle for
                                                            the first time.
                                                              • Interfaces between the flight systems, ground systems, mission
                                                                systems, and other appropriate CxP and external systems may be
                                                                also tested as part of each FEIT.

                                                     •   The primary objectives of the FEIT are:
                                                          – Demonstrate the interoperability, functionality, and stability of the flight
                                                            systems, elements, and sub-systems as an integrated “launch
                                                            vehicle” assembly prior to the first operational test flight of that
                                                            particular launch vehicle configuration.
                                                          – Validate critical mission sequence activities and flight procedures prior
                                                            to their first-time execution.

                                                     •   A secondary objective of the FEIT is:
                                                          – To collect functional and performance data from the integrated flight
                                                            systems to support validation of the different interface test tool sets,
                                                            emulators, and simulators used by the Projects in accepting future
                                                            serial numbers of those flight systems.
                                                                                                                                           23
FEIT (continued)
KSC Constellation Ground Operations Project Office




                                                     •   FEITs are executed after all of the system-level requirements have
                                                         been satisfied by the involved Project offices and those offices
                                                         declare their system designs as verified for flight.

                                                     •   FEITs are planned and scheduled as part of the assembly and
                                                         preparation of the integrated launch vehicle.

                                                     •   FEITs are currently planned for every test flight (except for Ares 1-X).

                                                     •   Planned FEITs:
                                                          – CEV/CLV
                                                          – Lunar Lander/EDS/CaLV




                                                                                                                                    24
FEIT 1
KSC Constellation Ground Operations Project Office




                                                              FEIT 1 Test Configuration
                                                     (performed in the Vehicle Assembly Building)




                                                                                                    25
FEIT 1 – Ares 1 Launch Vehicle Stack
KSC Constellation Ground Operations Project Office


                                                                           •   Test Configuration:
                                                                               –   CEV/CLV Integrated Stack
                                                                               –   Ground Systems
                                                                               –   Missions Systems
                                                                               –   SCaN (Space Communications
                                                                                   and Navigation)



                                                                                                     CEV


                                                                                                     CLV Upper
                                                                                                     Stage




                                                                                                     CLV 1st Stage




                                                                                                                 26
FEIT 2
KSC Constellation Ground Operations Project Office




                                                            FEIT 2 Test Configurations (TCs)
                                                     (performed in the Vehicle Assembly Building)




                                                                                                    27
FEIT 2 – Ares V Launch Vehicle Stack
KSC Constellation Ground Operations Project Office




                                                                                                  E                 E
                                                                                                  D                 D
                                                                                                  S                 S




                                                                                                  Launch Vehicle
                                                                                                                   TC2




                                                                                                  TC1

                                                     •   Test Configurations:            •   Both test configurations include:
                                                         – Lunar Lander/EDS/CaLV (TC1)        – Ground Systems
                                                              • Integrated Stack              – Missions Systems
                                                         – Lunar Lander/EDS (TC2)             – SCaN (Space Communications
                                                              • On-orbit Configuration          and Navigation)
                                                                                                                                 28
Interface Verification Testing (IVT)
KSC Constellation Ground Operations Project Office



                                                     •   Interface Verification Testing (IVT) verifies the mechanical and/or
                                                         electrical interfaces between two or more flight systems after these
                                                         systems have been mated.

                                                     •   IVT consists of the minimal set of activities to verify the integrity of all
                                                         physical and functional interfaces between the systems involved for
                                                         each specific vehicle stack configuration.

                                                     •   IVTs are performed as a subset of the FEITs during the flight tests
                                                         and then performed for every flight after Full Operational Capability
                                                         (FOC) has been obtained with the flight and ground Systems.

                                                     •   Performed in the Vehicle Assembly Building.

                                                     •   MEITs/FEITs would be required if any significant design upgrades or
                                                         modifications have occurred.


                                                                                                                                        29
Summary
KSC Constellation Ground Operations Project Office


                                                     •   Based on the previous success of MEITs for the International Space
                                                         Station Program, these type of integrated tests have also been
                                                         planned for the Constellation Program:
                                                          – MEIT
                                                              • CEV to ISS (emulated)
                                                              • CEV to Lunar Lander/EDS (emulated)
                                                              • Future: Lunar Surface Systems and Mars Missions
                                                          – FEIT
                                                              • CEV/CLV
                                                              • Lunar Lander/EDS/CaLV
                                                          – IVT
                                                              • Performed as a subset of the FEITs during the flight tests and then
                                                                performed for every flight after Full Operational Capability (FOC) has
                                                                been obtained with the flight and ground Systems.

                                                         "Standing alone, components may function adequately, and failure modes
                                                         may be anticipated. Yet when components are integrated into a total system
                                                         and work in concert, unanticipated interactions can occur that can lead to
                                                         catastrophic outcomes." (Columbia Accident Investigation Report (CAIB)
                                                         Report 2003)
                                                                                                                                         30

More Related Content

PPTX
Bilardo.vince
PPTX
Dumbacher2012 pmchallenge
PDF
Les.sorge
PDF
Ed.mango
PPT
Armstrong
PPTX
Carsile.azarbain
PDF
Krishen
PPTX
Bauer.frank
Bilardo.vince
Dumbacher2012 pmchallenge
Les.sorge
Ed.mango
Armstrong
Carsile.azarbain
Krishen
Bauer.frank

What's hot (19)

PPT
Woods.edwards.pm challenge bpr presentation 2012 v1
PDF
Daisy.mueller
PDF
David.oberhettinger
PPTX
D brown gbezos_shirshorn
PDF
Bladwin.kristen
PDF
Ingoldsby.k.lee.y
PPTX
Lau.cheevon
PPTX
Ortiz
PDF
Keer.beth
PDF
Newman lengyel dartpm-chal_case
PPTX
Majerowicz
PPTX
Hill.terry
PDF
Baldwin.kristen
PDF
Jim.free
PDF
Mullane stanley-hamilton-wise
PDF
Barth simpkins
PPTX
Saltzman.john
PDF
Graham dave
PDF
Kirsch.mike
Woods.edwards.pm challenge bpr presentation 2012 v1
Daisy.mueller
David.oberhettinger
D brown gbezos_shirshorn
Bladwin.kristen
Ingoldsby.k.lee.y
Lau.cheevon
Ortiz
Keer.beth
Newman lengyel dartpm-chal_case
Majerowicz
Hill.terry
Baldwin.kristen
Jim.free
Mullane stanley-hamilton-wise
Barth simpkins
Saltzman.john
Graham dave
Kirsch.mike
Ad

Similar to Tim.honeycutt (20)

PDF
Ed.mango
PDF
Stock gahm
PDF
Hanley jeff
PDF
Mitskevich amanda
PDF
Thomas.diegelman
PDF
Krasa.lee
PDF
Carol.scott
PDF
Carol.scott
PDF
Smith.marshall.bryant
PDF
Smith.marshall.bryant
PDF
ATI Courses Professional Development Short Course Spacecraft Quality Assuranc...
PDF
ARCtek_Charts_Post_ETu
PDF
Fred.ouellette
PDF
Fred.ouellette
PDF
How to Architect Family of Complex Space Systems and Networks?
PPTX
Ruszkowski.james
PDF
Ingenious Services Group, Llc 2012 Service Offerings Detail
PPTX
Kelly.michael
PDF
Barth simpkins
PDF
Small Spacecraft Mission Enterprise
Ed.mango
Stock gahm
Hanley jeff
Mitskevich amanda
Thomas.diegelman
Krasa.lee
Carol.scott
Carol.scott
Smith.marshall.bryant
Smith.marshall.bryant
ATI Courses Professional Development Short Course Spacecraft Quality Assuranc...
ARCtek_Charts_Post_ETu
Fred.ouellette
Fred.ouellette
How to Architect Family of Complex Space Systems and Networks?
Ruszkowski.james
Ingenious Services Group, Llc 2012 Service Offerings Detail
Kelly.michael
Barth simpkins
Small Spacecraft Mission Enterprise
Ad

More from NASAPMC (20)

PDF
Bejmuk bo
PDF
Baniszewski john
PDF
Yew manson
PDF
Wood frank
PDF
Wood frank
PDF
Wessen randi (cd)
PDF
Vellinga joe
PDF
Trahan stuart
PDF
Snow lee
PDF
Smalley sandra
PDF
Seftas krage
PDF
Sampietro marco
PDF
Rudolphi mike
PDF
Roberts karlene
PDF
Rackley mike
PDF
Paradis william
PDF
Osterkamp jeff
PDF
O'keefe william
PDF
Muller ralf
PDF
Mulenburg jerry
Bejmuk bo
Baniszewski john
Yew manson
Wood frank
Wood frank
Wessen randi (cd)
Vellinga joe
Trahan stuart
Snow lee
Smalley sandra
Seftas krage
Sampietro marco
Rudolphi mike
Roberts karlene
Rackley mike
Paradis william
Osterkamp jeff
O'keefe william
Muller ralf
Mulenburg jerry

Recently uploaded (20)

PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PDF
Approach and Philosophy of On baking technology
PDF
NewMind AI Weekly Chronicles - August'25-Week II
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PPTX
Group 1 Presentation -Planning and Decision Making .pptx
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PPTX
Machine Learning_overview_presentation.pptx
PPTX
1. Introduction to Computer Programming.pptx
PDF
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
PPT
Teaching material agriculture food technology
PDF
gpt5_lecture_notes_comprehensive_20250812015547.pdf
PDF
Encapsulation_ Review paper, used for researhc scholars
PPTX
Spectroscopy.pptx food analysis technology
PDF
Network Security Unit 5.pdf for BCA BBA.
PDF
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
PPTX
MYSQL Presentation for SQL database connectivity
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PDF
cuic standard and advanced reporting.pdf
Diabetes mellitus diagnosis method based random forest with bat algorithm
Approach and Philosophy of On baking technology
NewMind AI Weekly Chronicles - August'25-Week II
“AI and Expert System Decision Support & Business Intelligence Systems”
Building Integrated photovoltaic BIPV_UPV.pdf
Group 1 Presentation -Planning and Decision Making .pptx
Dropbox Q2 2025 Financial Results & Investor Presentation
Machine Learning_overview_presentation.pptx
1. Introduction to Computer Programming.pptx
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
Teaching material agriculture food technology
gpt5_lecture_notes_comprehensive_20250812015547.pdf
Encapsulation_ Review paper, used for researhc scholars
Spectroscopy.pptx food analysis technology
Network Security Unit 5.pdf for BCA BBA.
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
MYSQL Presentation for SQL database connectivity
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
cuic standard and advanced reporting.pdf

Tim.honeycutt

  • 1. KSC Constellation Ground Operations Project Office Integrated Testing at KSC between Constellation Systems Tim Honeycutt February 2008 Timothy.R.Honeycutt@nasa.gov 321-867-6567 321- 867-
  • 2. KSC Constellation Project Office KSC Constellation Ground Operations Project Office KSC Constellation Project Office Business Staff Office Project Control Logistics Operations & Systems Engineering Integration & Integration (including IT&V) Crew Vehicle Ground Command, Systems (GS) Control, and Project Communications Launch Vehicle GS Project GS Project GS Project Support Management Integration & Office Requirements 2
  • 3. Presentation Outline KSC Constellation Ground Operations Project Office • History of Multi-Element Integration Tests (MEITs) – MEIT Concept – Previous MEITs – Major Problems Found – Benefits • Integrated Testing at KSC for the Constellation Program – Integrated Tests • Multi-Element Integrated Tests (MEITs) • Flight Element Integrated Tests (FEITs) • Integrated Verification Tests (IVTs) • Summary 3
  • 4. History KSC Constellation Ground Operations Project Office • “Ship and shoot” was the strategy for the International Space Station Program (ISSP) during the early 1990’s – It proposed transporting flight elements directly from the factory to the launch site and begin the mission without further testing. – Factory level testing and element interface verifications at the subsystem-level, and interface analysis were all that was planned. • Before the end of that decade a shift in testing strategy occurred within the ISSP – The ISSP adopted a more integrated approach for ground validation of it’s flight hardware. – Availability of elements at the launch site created a feasible opportunity to test multiple elements together. – The notion of validation testing on the ground was presented and accepted by the ISSP due to the criticality of the on-orbit functionality, including safety concerns for the crew . 4
  • 5. History (cont) KSC Constellation Ground Operations Project Office • Multi Element Integration Tests (MEITs) and Integrated Systems Tests (ISTs) – Risk mitigation tests performed on the ground, used for validating the operation of the flight elements and their systems in an environment that is as flight-like as possible. – These tests were used to demonstrate the interoperability and functionality of Space Station elements as integrated “in-space” assemblies on the ground before they were assembled in space for the first time. • Space Station element-to-element interface capability was verified as well as systems end-to-end operability with hardware and software. • Mission Sequence Testing (MST), also known as “end-to-end” integration testing, included a full-up configuration with the Mission Control Center, Tracking Data Relay Satellite System (TDRSS), and the “station” operating on the ground. • Also verified limited on-orbit system compatibility. 5
  • 6. KSC ISS MEIT/IST Experience KSC Constellation Ground Operations Project Office • Planned/developed and implemented the following for ISSP: – MEIT1: • U.S. Lab, Z1, P6, SSRMS, Node1 (emulated) – MEIT2: • S0/MT/MBS, S1, P1, P3/4, US Lab (emulated) – MEIT3: • JEM, Node2, US Lab (emulated) – Node2 Systems Test • Node2, US LAB & Node1 (emulated) 6
  • 7. MEIT Configurations S RM SPDM 18 SS 18 31 18 18 MBS 18 External 31 Payload 24 31 ULC (or SLP) External CETA SLP (or ULC) Payload 30 CETA 30 30 MT 30 25 24 25 S-Band 17 17 17 17 26 26 23 32 24 24 12 12 25 25 16 14 14 14 16 14 16 16 S6 11 11 S5 8 11 11 S4 28 S3 22 22 S1 22 22 S0 22 22 P1 22 22 P3 28 P4 8 11 11 P5 11 11 P6 16 16 16 16 13 13 24 24 21 17 17 15 15 15 15 JEM ELM ES 17 17 15 15 24 29 External 29 Payload 24 JEM EF S0-to-Lab Struts External 29 Payload 5,7 5,7 29 5,7 5,7 MEIT-2 Uses 5,7 5,7 US Lab Simulation 9 8 8 9 JEM ELM PS SPP 27 5,7 5,7 RA 27 27 E 27 27 18 JEM PM 27 27 CUPOLA 9 8 8 6 re la Primary Orbiter 2 St 8 7 places 8 Docking 9 9 12 5,7 2 12 5,7 PORT 18 21 PORT Interface EFGF Z 4 ZENITH Progress 3 Service M1 3 4 A Module F 4 2 2 A FGB F 4 1 1 PMA1 PM 9 AFT FWD 9 8 8 9 U.S. LAB 9 8 8 9 AFT FWD 9 8 8 N 4 5,7 N 4 A3 PMA2 4 1 1 PM 1 sim 5,7 2 18 3 ula NADIR tion 27 2 3 Z NODE 1 Ku-Band NODE 2 DSM DC simulated CMGs (4) 12 RM-1 3 3 S P 3 3 3 -2 CRV#1 A P Universal Docking 1 8 9 NADIR ZENITH 9 8 8 N Z1 Z 11 MPLM 9 8 8 9 NADIR ZENITH 9 8 8 9 CAM Module 3 Alternate 1 F S 10 A F 3 RM-2 Soyuz CRV Orbiter Docking 3 3 TM adapt STBD STBD 9 18 9 Interface N 8 8 8 3 16 Beta Gimbal Assembly NTA 20 20 8 17 Solar Array Deployment 8 3 8 NTA 20 20 18 Power/Data Grapple Fixture (PDGF) LEGEND 8 9 9 Soyuz 19 Orbiter ‘D’ Hatch Remotely actuated mechanisms 9 9 8 TM OTA 20 20 AIRLOCK 20 NTA/OTA Attachment Mechanism 1 4 PMA3 AFT STBD EVA operated mechanisms 21 Lab Cradle Assy / MTSAS NODE 3 19 22 Segment to Segment Attach System (SSAS) IVA operated mechanisms 1 Modified APAS 8 9 NADIR ZENITH 9 8 OTA 20 20 23 Mobile Transporter Drive COF FWD PORT Articulating/Deployable mechanisms 2 Hybrid Docking Assembly (HDA) 24 Payload Attach System (PAS) 3 Probe and Cone (P&C) 9 9 27 25 ULC Attach System (ULCAS) Translation mechanisms Alternate MPLM 4 APAS Hatch Berthing Location 8 8 26 CETA Rollers passive active 5 RSA Solar Array Deploy Mechanism 8 9 U.S. 9 8 27 Window Shutter 6 RSA Radiator Deploy Mechanism 11 Rocketdyne Truss Attachment (RTAS) 28 Solar Alpha Rotary Joint (SARJ) MEIT 1 Completed 2/00 7 RSA Array Pointing Mechanism 12 Deployable Antenna HAB 29 JEM Berthing Mechanism MEIT 2 Completed 4/02 8 Common Berthing Mechanism (CBM) 13 Thermal Radiator Rotary Joint (TRRJ) 30 CETA Coupler MEIT 3 Completed 9/03 9 US Common Hatch 14 EPS Radiator Deployment 31 Common Attach System (CAS) 10 Manual Berthing Mechanism (MBM) 15 TCS Radiator Deployment 32 Trailing Umbilical System (TUS) (2)
  • 8. MEIT 2 Hardware at KSC KSC Constellation Ground Operations Project Office P3 Truss P4 Truss P1Truss S0 Truss US Lab Emulator S1Truss 8
  • 9. Problems Found in MEITs (Top Examples) KSC Constellation Ground Operations Project Office • P6 truss failed to power up due to Auxiliary Power Converter Unit (APCU) under voltage trip condition. – Impact: Unable to start P6 on Orbit. • US Lab critical activation took 36 hours during the first MEIT Power-up (computer/procedure problems), Requirement <2 hrs. During MEIT regression Mission Sequence Test, Critical Activation took 1 hr, 15 minutes. – Impact: Loss of Lab element during on-orbit activation due to thermal loading. • Command and Control (C&C) computers failed several times due to task overrun problems (CPU utilization problems). – Impact: Significant operational issues (Loss of Vehicle commanding, Vehicle health visibility, visibility to crew/ground) would occur because of continued loss of C&C computers. 9
  • 10. Problems Found in MEITs (Top Examples) (continued) KSC Constellation Ground Operations Project Office • Video lines were swapped between Trailing Umbilical Systems 1, 2 (NASA) and Mobile Base System (Canadian Space Agency). – Impact: Significant operational impact to manually route video signals. Extra Vehicular Activity (EVA) would have been required to replace two harnesses to correct the problem. • C&C computers failed when performing synchronization to Global Positioning System (GPS) time. – Impact: Loss of accurate GPS capability, degraded attitude control capability until development /testing and on-orbit upload of new software patch. • Quality of Space to Ground Audio was unacceptable. – Impact: Operation and potential safety impact to crew due to lack of understanding between Crew/Ground. 10
  • 11. MEIT Benefits KSC Constellation Ground Operations Project Office • Significant findings from MEIT have created an opportunity to correct major operational problems which would have resulted in: – Cost/Schedule Slip • Major milestone slippage in the Program – Critical On-orbit Operations impacts • Safety concerns for the crew • Loss of mission objectives • Loss of flight hardware – Nominal Operations impacts • Unknown operation risks (loss of redundancy capability) – Unplanned EVA’s The cumulative effect of identifying & resolving integrated hardware, software and procedure problems before flight has proven to save the International Space Station Program major on-orbit issues. 11
  • 12. Integrated Testing at KSC for the Constellation Program (CxP) KSC Constellation Ground Operations Project Office • Testing that occurs between two or more individual Constellation Systems to verify the interfaces between those Systems and to validate the integrated Systems' functionality and interoperability. • Includes testing mechanical, electrical, data and fluid interfaces. • Integrated testing applies to the in-space flight and integrated vehicle stack configurations. – Multi-Element Integration Testing (MEIT) – Flight Element Integration Testing (FEIT) – Interface Verification Testing (IVT) 12
  • 13. Constellation Architecture KSC Constellation Ground Operations Project Office Crew Exploration Vehicle – CEV/Orion Constellation Lunar Lander – Lander/Altair Crew Launch Vehicle – CLV/Ares I Architecture Cargo Launch Vehicle – CaLV/Ares V Crew Vehicles Launch Vehicles Ground & Mission & Systems & Systems Systems Ground CEV CLV Future Systems Lunar Mission CaLV Lander Systems EVA CLV Elements -1st Stage Systems -Upper Stage -Upper Stage Engine CxProgram Architecture Level 2 Flight Crew Project Level 3 CEV Elements System Equip. -Launch Abort System (LAS) -Crew Module (CM) Element Level 4 Lunar -Service Module (SM) Subsystem Level 5 Surface -Spacecraft Adapter (SA) Systems Subsystems: examples include Future data, power, thermal, etc. 13
  • 14. Multi-Element Integration Test (MEIT) KSC Constellation Ground Operations Project Office MEIT: • An integration test between two or more flight systems that will be launched on separate launch vehicles and integrated together for the first time in space. – Interfaces between the flight systems, mission systems, and other appropriate CxP/ISSP and external systems may be also tested as part of each MEIT. • The primary objectives of MEIT are: – Demonstrate the interoperability, functionality, and stability of the flight systems, elements, and sub-systems as an integrated “in-space” vehicle assembly on the ground before they are assembled in space for the first time. – Validate critical mission sequence activities and flight procedures prior to their first-time execution in-flight. • A secondary objective of MEIT is: – To collect functional and performance data from the integrated flight systems to support validation of the different interface test tool sets, emulators, and simulators used by the Projects in accepting future serial numbers of those flight systems. 14
  • 15. MEIT (continued) KSC Constellation Ground Operations Project Office • MEIT serves as a training ground for: – Flight crews and trainers – Mission Operations Division (MOD)/Mission Control Center (MCC) personnel – Constellation system engineers • MEITs are executed after all of the system-level requirements have been satisfied by the involved Project offices and those offices declare their system designs as verified for flight. • MEITs are one time tests with a potential for a follow-on regression test. – Performed prior to first crewed missions • Use of flight-like emulators and cables/connectors may be used when integration between the flight systems is not practical. • Planned MEITs: – CEV to International Space Station (ISS) (using ISS emulation) – CEV to Lunar Lander/Earth Departure Stage (EDS) (using EDS emulation) 15
  • 16. MEIT 1 KSC Constellation Ground Operations Project Office MEIT 1 Test Configuration (performed in the Multi-Payload Processing Facility) 16
  • 17. MEIT 1: CEV to ISS (Emulator) KSC Constellation Ground Operations Project Office • CEV-International Space Station (ISS) MEIT – To be performed in the year 2012, prior to first ISS flight. – Tests interoperability/functionality and all functional interfaces: data, audio, video, RF, power. – End-to-end test with Mission Control performed via TDRSS. – Uses emulation in place of ISS flight hardware. – Mated with flight-like cables and connectors. CEV ISS Flight Emulator LIDS 17
  • 18. CEV-ISS Interfaces KSC Constellation Ground Operations Project Office – Mechanical • CxP will utilize newly developed Low Impact Docking System (LIDS) • LIDS is not compatible with ISS Docking System (APAS: Androgynous Peripheral Attach System) • CxP will construct two APAS To LIDS Adapter Segments (ATLAS) • ATLAS will be installed permanently on Peripheral Mating Adapters (PMAs) 2 and 3 • Provides power and data pass through capability – Power • ISS will provide 120 VDC to CEV via two redundant power feeds • CEV will convert 120 VDC ISS power to 28 VDC for internal buses – Fluids/Gases • Only requirements are for Inter Module Ventilation (IMV) air circulation – essentially same as for Shuttle orbiter 18
  • 19. CEV-ISS Interfaces KSC Constellation Ground Operations Project Office – Avionics • Audio, video, and data are distributed internally to CEV over a Gigabit Ethernet network • CEV bus would connect to CxP provided Common Communications Adapter (CCA) which would provide conversion to legacy ISS networks. – CCA required for MIL-STD-1553 (ISS) and Gigabit Ethernet (CEV) data conversions – CCA installed on ISS – CCA or prototype would be integrated into ISS emulator and tested with CEV in MEIT • Separate CEV to ISS S-Band RF link would be implemented for rendezvous/proximity ops 19
  • 20. MEIT 2 KSC Constellation Ground Operations Project Office MEIT 2 Test Configurations (TCs) (performed in the Space Station Processing Facility) 20
  • 21. MEIT 2: Test Configuration #1 (TC1) KSC Constellation Ground Operations Project Office CEV to Lunar Lander with EDS Emulation EDS LIDS LIDS (Emulation) 21
  • 22. MEIT 2: Test Configuration #2 (TC2) KSC Constellation Ground Operations Project Office CEV to Lunar Lander LIDS LIDS 22
  • 23. Flight Element Integration Test (FEIT) KSC Constellation Ground Operations Project Office FEIT: – An integration test between the new or significantly modified systems and elements being assembled into an integrated launch vehicle for the first time. • Interfaces between the flight systems, ground systems, mission systems, and other appropriate CxP and external systems may be also tested as part of each FEIT. • The primary objectives of the FEIT are: – Demonstrate the interoperability, functionality, and stability of the flight systems, elements, and sub-systems as an integrated “launch vehicle” assembly prior to the first operational test flight of that particular launch vehicle configuration. – Validate critical mission sequence activities and flight procedures prior to their first-time execution. • A secondary objective of the FEIT is: – To collect functional and performance data from the integrated flight systems to support validation of the different interface test tool sets, emulators, and simulators used by the Projects in accepting future serial numbers of those flight systems. 23
  • 24. FEIT (continued) KSC Constellation Ground Operations Project Office • FEITs are executed after all of the system-level requirements have been satisfied by the involved Project offices and those offices declare their system designs as verified for flight. • FEITs are planned and scheduled as part of the assembly and preparation of the integrated launch vehicle. • FEITs are currently planned for every test flight (except for Ares 1-X). • Planned FEITs: – CEV/CLV – Lunar Lander/EDS/CaLV 24
  • 25. FEIT 1 KSC Constellation Ground Operations Project Office FEIT 1 Test Configuration (performed in the Vehicle Assembly Building) 25
  • 26. FEIT 1 – Ares 1 Launch Vehicle Stack KSC Constellation Ground Operations Project Office • Test Configuration: – CEV/CLV Integrated Stack – Ground Systems – Missions Systems – SCaN (Space Communications and Navigation) CEV CLV Upper Stage CLV 1st Stage 26
  • 27. FEIT 2 KSC Constellation Ground Operations Project Office FEIT 2 Test Configurations (TCs) (performed in the Vehicle Assembly Building) 27
  • 28. FEIT 2 – Ares V Launch Vehicle Stack KSC Constellation Ground Operations Project Office E E D D S S Launch Vehicle TC2 TC1 • Test Configurations: • Both test configurations include: – Lunar Lander/EDS/CaLV (TC1) – Ground Systems • Integrated Stack – Missions Systems – Lunar Lander/EDS (TC2) – SCaN (Space Communications • On-orbit Configuration and Navigation) 28
  • 29. Interface Verification Testing (IVT) KSC Constellation Ground Operations Project Office • Interface Verification Testing (IVT) verifies the mechanical and/or electrical interfaces between two or more flight systems after these systems have been mated. • IVT consists of the minimal set of activities to verify the integrity of all physical and functional interfaces between the systems involved for each specific vehicle stack configuration. • IVTs are performed as a subset of the FEITs during the flight tests and then performed for every flight after Full Operational Capability (FOC) has been obtained with the flight and ground Systems. • Performed in the Vehicle Assembly Building. • MEITs/FEITs would be required if any significant design upgrades or modifications have occurred. 29
  • 30. Summary KSC Constellation Ground Operations Project Office • Based on the previous success of MEITs for the International Space Station Program, these type of integrated tests have also been planned for the Constellation Program: – MEIT • CEV to ISS (emulated) • CEV to Lunar Lander/EDS (emulated) • Future: Lunar Surface Systems and Mars Missions – FEIT • CEV/CLV • Lunar Lander/EDS/CaLV – IVT • Performed as a subset of the FEITs during the flight tests and then performed for every flight after Full Operational Capability (FOC) has been obtained with the flight and ground Systems. "Standing alone, components may function adequately, and failure modes may be anticipated. Yet when components are integrated into a total system and work in concert, unanticipated interactions can occur that can lead to catastrophic outcomes." (Columbia Accident Investigation Report (CAIB) Report 2003) 30