INTRODUCTION OF PRADHAN MANTRI AWAS YOJANA ( HOUSING FOR ALL )
The Central Sector Scheme ‘Housing for All’ mission through Pradhan Mantri Awas
Yojana for Urban Area launched by the Ministry of Housing and Urban Poverty
Alleviation (MoHUPA) to be implemented during 2015-2022.
PRESENTATION ON THIRD PARTY QUALITY MONITORING REPORT OF
ISSR/AHP PROJECTS UNDER PMAY
The consultant shall organize it's activities in five groups as fallows:-
 PART A-ACTIVITIES FOR PREPARATION OF INCEPTION REPORT
 PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT AND PREPARATION OF SITE VISIT REPORT
 PART C- ACTIVITIES FOR PREPARATION OF QUARTERLY REPORT AND SUBMISSION
 PART D- ACTIVITIES FOR PREPARATION OF FINAL REPORT AND SUBMISSION
 PART E- ACTIVITIES OF COLLECTING AND ANALYSING DATA IN ANNEXURE 3
PART A-ACTIVITIES FOR PREPARATION OF INCEPTION
REPORT
PART A-ACTIVITIES FOR PREPARATION OF INCEPTION
REPORT
1. KICK-START MEETING & TEAM MOBILIZATION
It is proposed to kick-start the Consultancy assignment
with a formal meeting with SUDA and Urban Local
Bodies (ULBs) and other concerned
agencies/stakeholders. The consultant’s team shall also
start their work in accordance with the Work Schedule
finalized in consultation with the concerned authorities.
PART A-ACTIVITIES FOR PREPARATION OF INCEPTION
REPORT
2. COLLECTION OF SECONDARY DATA AND
PRELIMINARY SURVEY & INVESTIGATIONS
WAPCOS will collect report and data on projects under the
mission in the cluster area and other relevant data available.
WAPCOS team of experts shall visit the sites to assess the Housing
and Infrastructure conditions, socio-economic conditions for
innovative housing planning meeting all the guidelines under
HFPoA.
PART A-ACTIVITIES FOR PREPARATION OF INCEPTION
REPORT
3. PREPARATION OF THE INCEPTION REPORT
Based on the available data and its analysis an inception report
will be prepared. The report will contain background and
objective of the scheme, brief of existing situation of the city,
detailed approach, and methodology to carry out work, work
schedule, & manning schedule adopted by the consultant to
complete the work in time and quality deliverables to complete
the work, quality assurance procedures. List of documents,
guidelines, codes, and formats to be used to carry out the work
as per guidance.
PART A-ACTIVITIES FOR PREPARATION OF INCEPTION
REPORT
4. DATA FROM INSPECTION REPORT TO ANNEXURE 3
Most of the data collected in inspection report shall be initial
data for first site visit report in Annexure 3 ( the format for site
visit report )
PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT
AND PREPARATION OF SITE VISIT REPORT
1. COLLECTION OF DATA FROM INSPECTION REPORT.
Data specific to the ULB shall be presented in inspection report
and shall be transferred to the formats of Annexure-3. These data
may be project specific. Project may be inn various phases such as
under preparation, under sanction or submission and approved
project as well as projects under implementation.
PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT
AND PREPARATION OF SITE VISIT REPORT
2. PREPARATION OF SCHEDULE OF SITE VISITS.
Based on data collected so far, the consultant shall prepare an
efficient schedule for approval and implementation to the client
under objectives of maximum and best quality control of the
projects.
PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT
AND PREPARATION OF SITE VISIT REPORT
3.CARRY OUT SITE VISITS.
As per approved schedule the consultant shall visit site. Site visit
shall be carried out in such manner so that all possible relevant
information about the project shall be disclosed and
recommendation in improvement in quality and implementation
of the projects can be made.
PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT
AND PREPARATION OF SITE VISIT REPORT
4.PREPARATION OF SITE VISITS REPORT.
The consultant shall enter data specific to the project which may
not need any change such as information of cost and location of
the project, before the site visit and during the site visit. Rest of
the information shall be entered in the format during site visit.
However, recommendation shall be prepared during end of site
visit and after end of site visit. Approved schedule of the visit site
shall be fallowed. Site visit shall be carried out in such manner so
that all possible relevant information about the project shall be
disclosed and recommendation in improvement in quality and
implementation
PART C- ACTIVITIES FOR PREPARATION OF QUARTERLY REPORT AND SUBMISSION
1. DATA FROM INSPECTION REPORT
Data from the inspection report shall be entered relevant to the quarterly report as soon as
approval of inspection report.
2.DATA FROM SITE VISIT REPORT
Additional data shall be entered from site visit reports as soon as site visit report completed.
3.ADDITIONAL DATA
Due date of quarterly report is fixed as per financial year and instruction of the client.
Remaining data shall be collected from ULBs and client before due date and entered. Most
important aspect of quarterly report is its financial nature; Hence the consultant shall prepare
analysis of financial data in the report. The consultant shall propose to present a format of
quarterly report for approval to the client.
PART D- ACTIVITIES FOR PREPARATION OF FINAL
REPORT AND SUBMISSION
The consultant shall submit final report of a project after
completion of the project. The consultant shall compile final
report from inspection report, site visit reports, quarterly reports,
final handover report data from the contractor and data from
ULB. The final report shall include a report on fallow up of
recommendations made by the consultant and lesion learned
from the project completed also. The consultant shall prepare a
format for final report after approval of first quarterly report to
the client for necessary changes and approval of the format by
the client.
PART E- METHODOLOGY TO COLLECT AND ANALYSE
DATA IN ANNEXURE 3
Comments on tests already done but not found satisfactory (specify
action to be taken)
To deal with this issue contractor’s agreement, NBC codes and
applicable rules regulation shall be referred. The client shall be
briefed with the situation, implication, and all possible alternatives for
remedies. Best alternative to deal with the situation shall be
explained. The client shall need only to make decision.
ANNEXURE 3
Format 1- A Particulars of the project
The consultant activities would be as mentioned below:-
1. Some data from sanctioned DPR, contractor’s agreement from the ULB shall be
compiled in Format 1-A.
2. Name and contact details of engineers of consultant, name of state representative, name
of contractor’s representative and name of community representative and ULB
representative shall be mentioned as recorded in the site visit.
3. Scheduled dates of commencement and completion shall be recorded as per
contractor’s agreement, work order and schedule approved by authorities.
4. Actual dates of commencement and completion shall be recorded as per observations
during site visit.
5. Status of list of beneficiaries shall be collected from PMAY MIS.
6. Compliance to time limit, price escalation, legal clauses, liquidated damages, penalties
shall be recoded comparing the sanctioned DPR, agreement of the contractor and
financial & physical progress of the work and a checklist prepared for this purpose.
ANNEXURE 3 The Consultant Activity
Format 1
1 Name of the State /UT:
2 Name of the City:
3 Name of Project:
4 Project Code:
5
Implementing Agency (ULB/
DA/ HB/ UIT/ Slum
Rehabilitation Agency)
All these data are fixed, hence can be
entered before site visit.
A. PARTICULARS OF PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
A. PARTICULARS OF PROJECT
1 Name of the State /UT:
2 Name of the City:
3 Name of Project:
4 Project Code:
5
Implementing Agency (ULB/
DA/ HB/ UIT/ Slum
Rehabilitation Agency)
All these data are fixed, hence can be
entered before site visit.
ANNEXURE 3 The Consultant Activity
Format 1
A. PARTICULARS OF PROJECT
6
Location of the Project (Slum name,
Ward etc. (Annexe details in case of
multiple sites) as applicable)
This data shall be collected from ULB and
Inspection report.
7
Type of Project :(i) In-situ Slum
redevelopment (ISSR) (ii) Affordable
Housing in Partnership (AHP)
This data shall be collected from ULB and
Inspection report. This data may not
change after first visit.
8
Total Houses
(EWS/LIG/MIG/HIG) in the project.
9 No. of EWS Houses in the project
ANNEXURE 3 The Consultant Activity
Format 1
A. PARTICULARS OF PROJECT
10
Description of Work.
i. Carpet/ Built up area of
EWS house
ii. No. of EWS houses in one block
iii. No. of blocks iv. Total no. of houses
v. Type of Structure
(G,G+1,G+2 etc.)
vi. No. of storeys / floor.
This data shall be collected from ULB and
Inspection report. This data may not
change after first visit.
11 Date of Approval of project by SLSMC
This data shall be collected from SUDA /
SLSMC
ANNEXURE 3
Format 1
Central share State share
ULB/
Implementing
agency share
Beneficiary
share
Total
13
Date of sanction of 1stinstalment of central
assistance by CSMC
12 Approved Project Cost (Rs. Lakh):
This data can be collected from SUDA.
The Consultant Activity
A. PARTICULARS OF PROJECT
Above data can be collected from SUDA i.e. format 7 A
or 7 B of the guideline as submitted and sanctioned DPR
and project
ANNEXURE 3
Format 1
14 Duration of Project
This data can be collected from approved
project DPR, agreement of contractor.
(Annexe details in case of multiple contracts)
Multiple contract of a single project may
happen. In this situation, the consultant
shall make note/ report of the situation
The Consultant Activity
A. PARTICULARS OF PROJECT
15 Date of Award of work
ANNEXURE 3
Format 1
Scheduled Actual
This date shall be entered from contractor’s
agreement, work order and schedule
submitted by the contractor
This date shall be collected from site and
ULB
Scheduled Actual
This date shall be entered from contractor’s
agreement, work order and schedule
submitted by the contractor
This date shall be collected from site and
ULB
17 Date of completion
Date of commencement
A. PARTICULARS OF PROJECT
16
The Consultant Activity
ANNEXURE 3 The Consultant Activity
Format 1
A. PARTICULARS OF PROJECT
18
Inspection undertaken by (Name) With
Contact Details:
1.
2.
Name and contact details of Engineers of
the consultant who visited the site.
19
Name of State representative present
during visit
Name of State representative who visited
the site.
20
Name of ULB representative present
during visit
Name of ULB representative (SE/ AE/ EE)
21
Name of Contractor’s representative
present during visit
Contractor’s representative shall be
authorise representative.
22
Name of Community representative
present during visit
The consultant shall request ULB regarding
presence of any community representative.
ANNEXURE 3 The Consultant Activity
Format 1
23
Whether list of Beneficiaries finalised/
partially finalised/ not finalised
This list shall be checked in first visit and
observation shall be recorded in the site
visit report. If list be found partially or not
finalized a follow-on actions and
recommendations shall be made and
progress shall be reviewed on / before
next visit.
24
If finalised, whether uploaded in PMAY
MIS
To check PMAY MIS the consultant shall
request authorization
A. PARTICULARS OF PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
25
State any deviation from sanctioned
DPR in terms of number of houses or
size or location or Layout
Data of sanctioned DPR shall be collected
from SUDA any deviation from this shall be
checked in approved layout drawing
present in the site and actual progress in
the site.
26
Compliance of Tender conditions
matching to statutory requirements of
DPR w.r.t.
Compliance to time limit.
Compliance to price escalation.
Compliance to legal clauses.
Compliance to liquidated damages.
Compliance to penalties.
To inspect these conditions the consultant
shall compare the sanctioned DPR,
agreement of the contractor and financial
& physical progress of the work. For this
consultant shall prepare a checklist.
27 Any other comment
The consultant shall comment any fallow on
action recommendation.
A. PARTICULARS OF PROJECT
ANNEXURE 3
Format 1 B. Health & Safety Aspects (On Site)
The consultant activities would be as mentioned below:-
1 Availability and content of first aid box shall be checked
2 Fire Extinguishers shall be checked for its functionality. Expiry date and
manufacturing shall also be checked and noted.
3 It is being checked that blasting is being done or proposed to be done. If yes that
necessary permission shall be checked as per applicable rules and regulation. It shall be
checked that blasting shall be done under qualified staff.
4 Presence of Safety-Officer employed shall be checked during site visit.
ANNEXURE 3 The Consultant Activity
Format 1
1
Whether the drinking water facility is
provided on site?
The consultant shall check source of drinking
water assess numbers of users of drinking water,
quality, quantity, and adequacy of drinking water.
Relevant NBC code shall be fallowed.
2
Whether there are adequate no. of
toilets provided & maintained for site
staff / Workers?
This shall be checked for male and female
workforce present and to be employed in near
future of the work. Relevant NBC code shall be
fallowed.
3
Whether there is a board indicating the
safety norms to be observed?
The consultant shall fallow NBC code regarding
this issue If any deviation from compliance is
observed than observation shall be noted and
fallow on action recommendation shall be done.
B. HEALTH & SAFETY ASPECTS (ON SITE)
ANNEXURE 3 The Consultant Activity
Format 1
4
Whether the use of following is being
done by site staff
i. Safety Helmets
ii. Safety Shoes
iii. Safety Goggles
iv. Safety Jackets
5
Whether safety railings & safety tapes
have been provided around excavation
trenches /upper floors/ducts/lift well?
6
Whether approved quality & type
shoring-strutting scaffolding are
provided for excavation
trenches/Pits/Building work?
This issue shall be checked as per NBC code and
observation shall be recorded. If any deviation
from mandatory terms condition found than fallow
on action recommendation shall be done.
Observation and inquiry during site visit shall be
made than regarding this issue. Photographic
evidence shall be collected during site visit. If any
deviation from mandatory terms condition found
than fallow on action recommendation shall be
done.
B. HEALTH & SAFETY ASPECTS (ON SITE)
ANNEXURE 3 The Consultant Activity
Format 1
7
Whether 'FIRST AID' kit is available at
site?
Content of 'FIRST AID' kit shall be checked.
Knowledge of staff of contractor shall be checked.
Any necessary recommendation shall be made.
8
Whether Fire Extinguishers are
available at site?
Fire Extinguishers shall be checked for its
functionality. Expiry date and manufacturing shall
also be checked and noted. If any discrepancy
found than duly reported by the consultant.
9
Whether 'Blasting' is being done on
site? If yes, whether necessary
permissions have been obtained and
required precautions have been taken
for control blasting?
It is being checked that blasting is being done or
proposed to be done. If yes that necessary
permission shall be checked as per applicable rules
and regulation. It shall be checked that blasting
shall be done under qualified staff. The qualified
staff shall be enquired about knowledge,
procedures, and precautions regarding blasting.
10
Whether any Safety-Officer is
employed?
This issue shall be checked as per contractor’s
agreement and NBC code.
11 Any other comment
In this point fallow on action recommendation
shall be referred.
B. HEALTH & SAFETY ASPECTS (ON SITE)
ANNEXURE 3
Format 1 C. Quality Assurance In The Project
The consultant activities would be as mentioned below:-
1 Availability of DPR, contract document, structural drawings and copies of
specifications shall be checked during site visit.
2 Inspection Registers, Site order book shall be checked for frequency of visit of officers/
engineers, and Quality control Test registers and their proper maintaince during site visit
shall be done. Method of stacking of cement and cement register shall be checked for proper
consumption of cement in works as per schedule.
3 Whether cement register is maintained and checked at site.
4 List of ISI marked/approved materials used in site shall be prepared. Manufacturer's
test certificates shall be checked.
5 Testing facilities shall be checked as per contractor's agreement.
6 "Site test reports and Structural Designs shall be checked forissues ilke, proper
approval from competent authoriries, proper codes have been fallowed, fit for execution,
any disaster related compliance etc. The work is being executed as per the approved
drawings fit for execution shall be checked during site visit."
ANNEXURE 3
Format 1 C. Quality Assurance In The Project
7 Mandatory tests of construction material, and works and their frequency shall be checked.
8 Centring, shuttering, staging & propping shall be checked for line & level, dimensions, cleaning and
safety of concrete work.
9 RCC work shall be checked for issues like , mixing by full bag capacity, hopper fed mixer, control of
slump, placing/ compaction with vibrator etc.
10 "Concrete mix design mix and mode of concrete mixing shall be checked."
11 Cover, line, length, and plumb of reinforcement shall be checked during site visit.
12 Seepage, cracks and honey combing shall be checked to find reason.
13 Precautions taken for dewatering and protecting site from flooding shall be checked.
14 Adequacy of plinth height shall be checked.
15 Overall assessment of quality in view of structural stability, non structural work and workmanship
shall be done including video/photograph.
ANNEXURE 3 The Consultant Activity
Format 1
1
Whether authenticated copy of DPR,
contract document, structural drawings and
copies of specifications are available at site?
This is important observation and shall be noted
by the consultant. If any deviation found than
fallow on action recommendation shall be made.
2
Whether the Inspection Registers, Site order
book and Quality control Test registers are
maintained at the site properly and
endorsed by the Engineer–incharge?
All these documents shall be checked for proper
entries and fallow up. Detailed observation and
fallow on action recommendation shall be made.
3
Whether list of ISI marked/approved
materials to be used is available at site?
A report shall be prepared regarding this issue and
fallow on action recommendation shall be made.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
4
Is there a provision in Contract/Tender to
provide'Test facilities on site”?
Contractor’s contact document shall be checked
regarding this issue with NBC code or and any
relevant codes.
5
Whether testing facilities to check quality of
material is available at site? if yes attach list
of Equipments
If testing facilities available than list of equipment
shall be prepared including celebration reports and
standards of equipments.
6
Whether the structural Designs are
approved / Proof checked by competent
Authority
Name of the approving authority for
structural design.
Whether the statuary certificate for disaster
resistance design and compliance of codal
provision is endorsed by the structural
designer on the structural drawings fit for
execution, especially in case of multi-
storeyed construction.
The work is being executed as per the
approved drawings fit for execution.
All structural drawing and design documents shall
be checked for the issues mentioned. Completed,
ongoing and upcoming work in site shall be
compared with the drawings for adequacy and
fitness for execution. In any case fallow on action
recommendation shall be made.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
7
Whether manufacturer test certificate for
cement, steel, pipes etc. have been obtained
with supply and records are being
maintained?
Observation regarding this issue shall be recorded
fallow on action recommendation shall be made.
8
Whether all mandatory tests of construction
material, road work, sanitary work, plumbing
work, electrical work and concrete in
foundations, beams, columns and slabs etc
are carried out at stipulated frequency?
Frequency of tests shall be checked with
contractor’s agreements IS codes and NBC codes.
Test reports shall be checked for progressive sum
of quantity of items as per progress of work and
materials. Observations and any discrepancies shall
be recorded. In any case fallow on action
recommendations shall be made.
9
Whether regular tests of materials and
construction products are being got done
from accredited labs also? If yes, details of
such labs
Contractor’s agreement shall be checked for
percentage of tests to be done from accredited
labs and mandatory performance of tests from
accredited labs. Observations shall be recorded.
Any deviation and irregularities shall be recorded
and recommendations for improvement in situation
shall be done.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
10
Whether soil investigations of the site
proper have been done before the structural
design and soil parameters have been
accounted for in the structural design/
drawings? If yes, attach copy of soil
investigation report.
Structural design/ drawings and soil investigation
reports shall be compared. Comparison report and
any recommendation shall be made including soil
investigation report.
11
Whether centring /shuttering is checked for
staging & propping, line & level, dimensions,
cleaning etc. and its quality approved before
each stage and record maintained.
For this issue NBC code and contractor’s
agreement shall be fallowed. Information related
to specification and load bearing capacity of
centring /shuttering and staging shall be
ascertained from the contractor as well as
methodology for the work. Checking on
methodology for the work shall be done for safety
and acceptable tolerance in line & level,
dimensions. Records regarding this issue shall be
checked and recorded. Fallow on action
recommendation shall be done.
12
Specific control on RCC work like: mixing by
full bag capacity hopper fed mixer, control of
slump, placing/ compaction with vibrator.
(proportioning with boxes not permitted)
For this issue contractor’s agreement, item
specification and NBC code shall be studied for
manufacturing of concrete. Observation and any
action follow on recommendation shall be done.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
13
Whether cement register is maintained and
checked at site. Comment on method of
stacking.
Previous dated entries of cement register shall be
checked as per progress of work and theoretical
consumption of cement.
14
Whether concrete mix is nominal or design
mix? (Nominal mix not permitted for quality
concrete).
Concrete mix shall be checked in site. Concrete
mix reference shall be checked in contractor’s
agreement, structural drawing and design,
specification, IS codes and NBC codes. Relevant
test shall be checked. Observation shall be
recorded.
15
What is the Mode of
Concrete mixing (batch mix/ manual)? In
case of manual mixing, whether mixing is by
weight or by volume of ingredients?
(Volumetric mixing not permitted).
Mode of concrete mixing shall be checked and
recorded. Follow on action recommendation shall
be made.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
16
Whether Mixer/Vibrator as specified is
available at site with adequate means to run
them during concreting?
Mixer/Vibrator as specified shall be checked.
Their working shall be checked. Inspection and
inquiry shall be done to ensure proper working. In
case of noncompliance follow on action
recommendation shall be made.
17
Whether RMC is being used in work? If yes,
detail of control and checks done at plant
site. Comment on Quality of aggregates,
Slump test, Cube test etc.
RMC plant, manufacturing documents and
procedure shall be checked along with lead and
admixture. NBC code shall be fallowed to ascertain
quality and method of products and production.
Fallow on action recommendation shall be made to
ensure acceptable quality of concrete.
18
Suitability of water for construction
What is the source of water
Has water been tested and approved by
Engineer-in-charge before construction
Has water been tested subsequently as per
Requirement
Source of water shall be checked for consistent
quality and quantity and environmental aspects.
Testing of water as approved by engineer-in-
charge shall be checked. Routine check of water
shall be ensured. Fallow on action recommendation
shall be done.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
19
Quality of work and workmanship,
Comments on
Workers shall be interested to ascertain skill and
knowledge level. Workmanship shall be checked
during work in progress. Fallow on action
recommendation shall be made.
19 i
RCC work (concrete, Reinforcement
detailing, cover to reinforcement). Whether
Columns are in plumb (check for verticality).
Cover, line, length, and plumb shall be checked as
much as possible during site visit. Any non-
confirmation shall be reported. Remedial actions
shall be recommended. Reasons for deviation from
tolerance shall be find out and recorded. Proper
procedure and mix of cover block shall be
inspected and standard practice shall be
recommended.
19 ii
Masonry (Joint details, verticality). Check
adequate RCC bands are provided.
Quality of masonry joints, RCC bands shall be
inspected as well as method of work. Fallow on
action recommendation shall be made.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
19 iii
iii. Shuttering (Type of material-
pucca/katcha, support spacing )
Shuttering shall be checked with respect to
contractor’s agreement and specifications.
Properties of shuttering shall be ascertained to
ensure quality, safety, and tolerance of RCC works.
19 iv
iv. Bar bending and stirrups bending ,
placement and cover to reinforcement bars.
Procedure and product of bar bending, binding,
and placing of reinforcement shall be checked.
Proper procedure shall be recommended. Skill
level of bar binders shall be ascertained.
19 v Plastering
Proper procedure and finish of plastering shall be
checked. Skill of meson shall be ascertained.
Mortar mixing shall be inspected, and proper
method shall be recommended.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
19 vi Doors and windows
Material and workmanship of doors and windows
shall be checked including fittings.
Recommendation shall be made for method of
work and materials used.
19 vii Seepage, if any
Preventive measures for seepage shall be
recommended. Adequate method for eradication
and prevention of seepage shall be recommended.
Any seepage and reason of seepage shall be
carefully recorded for fallow on action
recommendation.
19 viii Cracks, if any
Location, seriousness, and possible reason of
cracks shall be recorded. Inquiry for reason of
cracks shall be made. Fallow on action
recommendation shall be made.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
19 ix Honey combing, if any
Proper procedure for repair of honey combing
shall be recommended. Rework can be
recommended as per site conditions and possible
effect of honey combing in the structure. Reasons
of honeycombing shall be recorded such as faulty
shuttering or/and inadequate compaction.
19 x Any other
Any other issue shall be recorded and follow on
action recommendation shall be made.
20
Whether floor slope (especially) in bath, WC,
kitchen, terrace and balcony etc. are proper?
Floor slope shall be checked as per drawings and
codes. In case of non-conformance rework shall be
suggested as per contractor’s agreement and
applicable codes.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
21
Whether dampness/ leakages noticed? If
yes, state location and probable reasons.
Reason of dampness/leakages shall be carefully
checked and fallow on action recommendation
shall be made.
22
Whether remedial measures are undertaken
by/ ULB to stop Dampness & Leakages? If
any.
There shall be inquiry for remedial measures for
prevention of dampness and leakages. There shall
be an inquiry regarding actions taken on fallow on
action recommendation on previous site visits. In
case of noncompliance a detailed report shall be
prepared with several alternate recommendations.
23
Whether Service lines (Electrical, Plumbing,
Others) if any, provided before
commencement of concrete?
Proper sequence and methodology of contractor
to do the work shall be checked as per
contractor’s agreement. NBC code shall be
referred regarding this issue. Observation and
fallow on action recommendation shall be
fallowed.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
24
Whether disaster resistant features have
been incorporated?
Disaster resistance features shall be checked as
per applicable codes. A proper report shall be
made for this issue.
25
Whether precautions taken for dewatering
and protecting site from flooding as
applicable?
A proper plan shall be there for flooding and
dewatering as per locality. A report on this issue
shall be made. Any precautions taken shall be
inspected and reported. In absence of any
precautionary measures there shall be a fallow on
action recommendation.
26
Whether sample units/items are completed
and approved by competent ULB official /
CLTC member before start of mass finishing
work?
Observation and inquiry shall be made regarding
this issue and shall be reported.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
27
Whether Adequate plinth height (above the
general ground level) is provided to the
ground floor of the building to avoid
possibility of rainwater and reptiles in the
building.
Drawings and site shall be checked for this issue.
Proposed level of road in front of the block /
dwelling unit shall be checked for this issue. As
per checking proper recommendation shall be
made.
28
Comments on tests already done but not
found satisfactory (specify action to be
taken)
To deal with this issue contractor’s agreement,
NBC codes and applicable rules regulation shall be
referred. The client shall be briefed with the
situation, implication, and all possible alternatives
for remedies. Best alternative to deal with the
situation shall be explained. The client shall need
only to make decision.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
29
Frequency of visit by
SLNA/ULB officials and
SLTC/CLTC member
Numbers of visits and dates of SLNA/ULB officials
and
SLTC/CLTC member along with name and
designation shall be recorded. Site order book
entries and other recordes shall be used to gather
this information.
30 Any other comments
Any important observation which not covered in
this format shall be entered in this heading.
31
Overall assessment of quality (in view of
structural stability, non structural work and
workmanship)*video/photogra
phs of the ongoingworks maintained by
ULB/Implementation Agency may be
referred as the case may be.
Video/photographs of the ongoing works
maintained by agencies including
video/photographs of TPQMA shall be gathered
relevant to a assement of quality in headings of
structural and non structural work.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3
Format 1 D. Beneficiary Participation In The Project
1. List of Beneficiaries shall be checked for it’s completion in first visit and observation
shall be recorded in the site visit report.
2. Plan and status of identification and allotment of houses shall be checked. The
consultant shall prepare a report on this.
3. Involvement of beneficiaries in the project preparation and construction work shall be
checked with the ULB and site order book / visitor book.
4. Any suggestion of the beneficiaries in the construction recorded in site order book /
visitor book during construction shall be recorded in the Format 1 D.
ANNEXURE 3 The Consultant Activity
Format 1
1 Whether list of Beneficiaries is prepared
This list shall be checked in first visit and
observation shall be recorded in the site visit
report. If list be found partially or not finalized a
follow-on actions and recommendations shall be
made and progress shall be reviewed on / before
next visit.
2 Whether houses are identified and allotted
Process of allotement of shall be checked. Plan
and status of identification and allotement shall
be checked. The consultant shall prepare a report
on this.
3
Whether the Beneficiaries are involved in
the project preparation and construction
work.
This information shall be obtained from the ULB.
4
Whether the Beneficiaries are visiting the
site or not
This information shall be obtained from the ULB
and contractor.
5
Any suggestion of the beneficiaries in the
construction
This information shall be obtained from the ULB
and contractor and from beneficiaries during site
visit.
D. BENEFICIARY PARTICIPATION IN THE PROJECT
ANNEXURE 3
Format 1 E. Progress - Housing Components
1 Information about numbers of houses sanctioned, in progress and completion the project
shall be obtained from approved DPR, contractor's contract and observation during site visits
and progress reports.
2 Progress report of stages of housing construction such as foundation, superstructure,
brickwork, finishing in numbers of housing units shall be recorded during site visit.
3 Information about numbers of houses sanctioned but construction not started and
numbers of houses occupied and non-occupied shall be recorded during site visit and with
meetings with ULB and Beneficiaries .
4 Physical progress of housing in percentage shall be recorded.
5 Any revision of building plan and NBC norms conformity shall be recorded.
6 If any deviation found than the deviation, probable reason of deviation, its implication
shall be recorded.
7 Use of any innovative/ cost effective/ green technology shall be recoded.
ANNEXURE 3 The Consultant Activity
Format 1
1 Numbers of houses sanctioned in the project
This information shall be obtained from approved
DPR.
2 Numbers of houses in progress
This information shall be obtained from contract
of the contractor, approved DPR and ULB.
3 Numbers of houses Completed
This information shall be obtained from contract
of the contractor, approved DPR , ULB, progress
report and site visit.
( Specify No. of Units)
This information shall be obtained and recoreded
during site visit.
E. PROGRESS - HOUSING COMPONENTS
Stages of Progress (Multi storied buildings) :
i) Foundation/ Plinth level (Nos.)
ii) Superstructure (Frame work) Level(Nos.)
4
ANNEXURE 3 The Consultant Activity
Format 1
5 Numbers of houses not started
This information shall be obtained and recoreded
during site visit and other relevent data.
6 Reason for non-starter of houses, if any
This information shall be obtained and recoreded
during site visit,other relevent data and meeting
with the ULB, SUDA and the contractor.
7
Numbers of houses occupied by the
Beneficiaries
This information shall be obtained and recoreded
during site visit and the ULB.
8
Reasons for Non-occupation of houses (If
any)-specific reasons to be given
This information shall be obtained and recoreded
during site visit, the ULB and meeting with
beneficieries.
E. PROGRESS - HOUSING COMPONENTS
ANNEXURE 3
Format 1
9 Size of Unit (Carpet Area) Sanctioned As per Implementation
10 Overall physical progress of Housing (in %)
This information shall
be obtained from the
approved DPR
This information shall
be obtained during site
visit.
11
Whether the building plan(s) conform to NBC
norms?
12
Whether authenticated building plans and
revisions if any, are available?
This information shall be obtained during site
vist, comparison of drawings approved and
executed in site, the approved DPR and NBC
codes applicable.
This information shall be obtained during site
vist, comparison of drawings approved and
executed in site, the approved DPR and revisons
of drawings and meeting with the ULB.
E. PROGRESS - HOUSING COMPONENTS
The Consultant Activity
ANNEXURE 3 The Consultant Activity
Format 1
13 Deviation, if any
If any deviation found than the deviation,
probable reason of deviation, its implication shall
be recorded.
14
Any innovative/ cost effective/ green
technology has been used?
This information shall be recorded after
comparing all data available.
15 Any other comment
Any relevent observation which doesnot be
covered in other points shall be recorded in this
point.
E. PROGRESS - HOUSING COMPONENTS
ANNEXURE 3
Format 1 F. Progress- Civic Infrastructure Components
1. The approved DPR and contract of the contractor shall be checked to obtain information about for infrastructure
components such as water supply, Sewerage, Drainage, Roads, SWM have been awarded.
If no, time line for award of contract for infrastructure works shall be obtained from the ULB. The approved DPR and
contract of the contractor shall be checked to obtain this information and meeting with the ULB shall be done to obtain
to probable schedule for award of contract for infrastructure works. If Yes, progress of work in % shall be recorded in
the site visit. and details shall be reported in Annexure 2A.
2. If any deviation found comparing sanctioned DPR, contractor's contract and work executed in site, than it shall be
recorded.
3. Observations on quality of construction of Infrastructure works shall be recorded during site visit.
4. Information about the proposed infrastructure components are independent and/or integrated with city level
infrastructure shall be collected and compiled by meeting with the ULB, observations during site visit, collection of
data related to city level infrastructure such as data of water supply system, sewer treatment plant and sewer line
network, study of city development plan etc.
5. information about Transit Accommodation to beneficiaries shall be shall be collected from beneficiaries, The ULB
and the contractor. If case of Transit Accommodation not being provided to the beneficiaries than any alternate
measures have been taken for the displaced families shall be recorded.
6. Information about overall physical progress of civic infrastructure in percentage and any cost reduction in
infrastructure components (To be reported in case of deviation from sanctioned quantity) shall be recorded. This
information shall be obtained by comparing financial and physical progress recorded by the ULB, sanctioned DPR,
contractor’s agreement and observations in the site during site visit.
ANNEXURE 3 The Consultant Activity
Format 1
1
Whether Contract for infrastructure
components (i.e. water supply, Sewerage,
Drainage, Roads, SWM etc.) have been
awarded?
The approved DPR and contract of the contractor
shall be checked to obtain this information.
i) If no, Time line for award of contract for
infrastructure works.
The approved DPR and contract of the contractor
shall be checked to obtain this information and
meeting with the ULB shall be done to obtain to
probable schedule for award of contract for
infrastructure works.
ii) If Yes, State the progress of work in %
a. Water Supply
b. Sewerage
c. Drainage
d. Roads
e. Solid Waste
Management
f. Electrification
g. Any other component (as per sanctioned
components)
*(Provide detailed report in Annexure 2A)
This report shall be prepared by obtaining
information from the approved DPR and contract
of the contractor, drawings, schedule and progress
of work observed during site visit.
F. PROGRESS- CIVIC INFRASTRUCTURE COMPONENTS
ANNEXURE 3 The Consultant Activity
Format 1
2 iii) Deviation if any as per sanctioned DPR
This report shall be prepared by comparing data
collected during site visit and sanctioned DPR.
3
Comments on quality of construction of
Infrastructure works
Observations on quality of construction of
Infrastructure works shall be recorded during site
visit.
4
Whether the proposed infrastructure
components are independent and/or
integrated with city level infrastructure?
This information shall be collected and compiled
by meeting with the ULB, observations during site
visit, collection of data related to city level
infrastructure such as data of water supply system,
sewer treatment plant and sewer line network,
study of city development plan etc.
F. PROGRESS- CIVIC INFRASTRUCTURE COMPONENTS
ANNEXURE 3 The Consultant Activity
Format 1
5
Whether Transit Accommodation has been
provided. If not what measures have been
taken for the displaced families?
This information shall be collected from
beneficiaries, The ULB and the contractor.
6
Overall physical progress of civic
infrastructure (in %)
This information shall be compiled by compacting,
contractor’s contract, sanctioned DPR, physical
progress observed during site visit.
7
Cost reduction in infrastructure components
(To be reported in case of deviation from
sanctioned quantity)
This information shall be obtained by comparing
financial and physical progress recorded by the
ULB, sanctioned DPR, contractor’s agreement and
observations in the site during site visit.
F. PROGRESS- CIVIC INFRASTRUCTURE COMPONENTS
ANNEXURE 3
Format 1 G. Social Infrastructure Components
1.Information about contract and timeline for Social Amenities such as Community
centre, Livelihood centre etc. have been awarded shall be collected from the sanctioned
DPR, contractor’s agreement, meeting with ULB and physical progress observed of social
amenities during site visit.If no, Time line for award of contract for Social If Yes, than
progress of work in % Community centre,Livelihood centre, Informal Sector Market,
Any other component shall be recorded.
2. Deviation if any as per sanctioned DPR, Comments on quality of construction of Social
Amenities, Overall physical progress of Social Infrastructure and Overall physical
progress of the project shall be recorded.
3. Whether livelihood linkages have been ensured?. This information shall be recorded.
ANNEXURE 3 The Consultant Activity
Format 1
1
Whether Contract for Social Amenities (i.e.
Community centre, Livelihood centre etc.)
have been awarded?
This information shall be obtained from the
sanctioned DPR, contractor’s agreement, meeting
with ULB and physical progress observed of social
amenities during site visit.
1 i)
If no, Time line for award of contract for
Social Amenities.
If no social amenities have been provided in the
sanctioned DPR, contractor’s agreement than
meeting with the ULB shall be done to find
information regarding timeline / schedule for the
tender/ contract for Social Amenities.
1ii)
If Yes, State the progress of work in %
a. Community centre
b. Livelihood centre
c. Informal Sector Market
d. Any other component (as per sanctioned
components)
*(Provide detailed report in Annexure-2A)
This information shall be obtained from the
sanctioned DPR, contractor’s agreement, meeting
with ULB and physical progress observed of social
amenities during site visit.
G. SOCIAL INFRASTRUCTURE COMPONENTS
ANNEXURE 3 The Consultant Activity
Format 1
2 iii) Deviation if any as per sanctioned DPR
This information shall be obtained by comparing
financial and physical progress recorded by the
ULB, sanctioned DPR, contractor’s agreement and
observations in the site during site visit.
3
Comments on quality of construction of
Social Amenities
Observations on quality of construction of
Infrastructure works shall be recorded during site
visit.
4
Whether livelihood linkages have been
ensured?
This information shall be obtained from,
sanctioned DPR, the ULB and beneficiaries.
5
Overall physical progress of Social
Infrastructure (in %)
This information shall be obtained from physical
progress observed during site visit, sanctioned
DPR and contractor’s agreement.
6
Overall physical progress of the project (in
%)
This information shall be obtained from physical
progress observed during site visit, sanctioned
DPR and contractor’s agreement.
G. SOCIAL INFRASTRUCTURE COMPONENTS
ANNEXURE 3
Format 1 H. Physical Progress Of The Project/Packages
1. Information about an approved program / schedule of work and it's availablity at
site office shall be recorded.
2. Overall Percentage progress at the time of inspection visa-vis expected as per
contract and the approved program / schedule shall be recored.
3. Details of milestones as per contract vis-à-vis their achievement any delay and a
reasons for delay shall be recorded.
ANNEXURE 3 The Consultant Activity
Format 1
1
Is there an approved program / schedule of
work & whether the same is available at site
office
During site visit documents shall be checked to
see availability of the approved program /
schedule of work. If the approved program /
schedule of work doesn’t available in the site than
the issue shall be recorded and reported. If the
approved program / schedule of work is available
than that shall be checked in comparison to the
progress of the site to ascertain whether progress
is at per or behind or ahead of the approved
program / schedule of work.
2
Overall Percentage progress at the time of
inspection visa-vis expected as per contract.
For this contractor’s contract approved program /
schedule of work and progress of work at site shall
be compared in percentage.
3 Package wise % of progress (Attach package-wise Annexure)
4
Details of milestones as per contract vis-à-
vis their achievement
Meeting shall be needed with ULB and information
regarding contractor’s contract and packages shall
be obtained for details of milestones. Milestones
achieved and milestones yet to be achieved
comparison to progress as per schedule shall be
recorded.
5 Reasons for delay
If and milestone or progress is found behind the
schedule, then reasons shall be found in
documents of previous progress reports submitted
so far, hindrance register, procurement records
etc. Actual reasons shall be recorded carefully and
impartially.
H. PHYSICAL PROGRESS OF THE PROJECT/PACKAGES
ANNEXURE 3
Format 1 I. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. In Lakh)
1. Information about sanctioned fund for entire project shall be collected from senctioned DPR,
contractor's contract from ULBs and SUDA.
2. Information about funds received up to date shall be collected from ULBs and SUDA.
3. Up-to date expenditure information shall be collected from ULBs and SUDA.
4. Amount of funds Utilized (out of received) shall be collected from ULBs and SUDA.
5. Amount of Expenditure by ULB (ULB Contribution + Beneficiaries contribution) shall be
collected from ULBs and SUDA and compiled.
6. Balance funds Expected/due from various stakeholders shall be compiled based on data
collected so far.
7. Package wise Expenditure shall be compiled based on data collected so far.
8. Over All Financial Progress in %= Total Expenditure / Total of Tendered Amount x100 shall
be compiled based on data collected so far.
9. An analysis shall be prepared based on financial data collected so far, contractor’s
agreements bills of contractors, actual measurements entered in measurement books, progress
reports and approved schedule and progress of work against approved schedule. The analysis
shall disclose any delay and cause of delay in work.
ANNEXURE 3 The Consultant Activity
Format 1
1 Sanctioned fund for entire project.
Information about project’s sanctioned fund shall
be collected from ULBs and SUDA.
2 Amount of funds received up to date
Information about funds received shall be
collected from ULBs and SUDA.
3 Up-to date Expenditure
Information about Up-to date expenditure shall
be collected from ULBs and SUDA.
4 Amount of funds Utilized (out of received)
Information about funds utilized shall be collected
from ULBs and SUDA.
5
Amount of Expenditure by
ULB (ULB Contribution +
Beneficiaries contribution)
This information shall be collected from ULBs and
SUDA and compiled.
I. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. in Lakh)
ANNEXURE 3 The Consultant Activity
Format 1
6
Balance funds Expected/due from various
stakeholders
This information shall be compiled based on data
collected so far.
7 Package wise Expenditure
This information shall be compiled based on data
collected so far.
8
Over All Financial Progress %= Total
Expenditure / Total of Tendered Amount
x100
This information shall be compiled based on data
collected so far.
9
Whether the work is delayed for non
payment of any pending bills after
construction (to be specified)?
An analysis shall be prepared based on financial
data collected so far, contractor’s agreements bills
of contractors, actual measurements entered in
measurement books, progress reports and
approved schedule and progress of work against
approved schedule. The analysis shall disclose any
delay and cause of delay.
I. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. in Lakh)
1
Are there any major
variation because of:
To find variation fallowing documents shall be compared:
i. Specifications
Specification as per contractor’s
agreement, approved drawings.
Specification of work actually executed in
the site, various test reports, procurement
reports, site order book etc.
ii. Quality
Specification as per contractor’s
agreement, approved drawings, various
applicable codes.
Quality test reports, site observations and
other site documents.
iii. Quantity
Contractor’s agreement, approved
drawings and design including working
drawings, bill of quality, DPR, sanctioned
project details.
Measurements taken in site, physical
progress reports, bills of contractor,
material registers, any revised drawings
etc.
iv. Designs
(Architectural /
Structural)
Approved drawings and design including
working drawings
Any revised drawing, site order book ,
other site documents, any instructions of
authorities for change in architectural and
Structural aspects of the project, actual
observations in site.
v. Period of
Construction
(Increase/Decrease)
Approved programme, schedule and
milestones.
actual progress reports marked in
approved programme, schedule and
milestones
ANNEXURE 3
Format 1 J. VARIATIONS w.r.t. SANCTIONED COVENNANTS
ANNEXURE 3
Format 1
1 Whether there is cost variation?
If yes what are the reasons:
i. Change in Quantities
ii. New/Additional Items of work
iii. Price Escalation Any other (to be specified)
1 Whether there is time overrun?
If yes what are the reasons:
i. Change in Quantities
ii. New/Additional Items of work
iii. Price Escalation Any other (to be specified)
iv. Delay in actual start of work by the
Contractor
v. Delay in procurement of material ( give
reasons)
vi. Delay due to lack of interdepartmental
coordination Any other (to be specified)
Any other (to be specified)
The Consultant Activity
K. COST VARIATION and TIME-OVERRUNS
To find variation fallowing documents shall be
compared:
Cost Variation:
Contractor’s agreement,
approved drawings and
design including
working drawings, bill
of qualtity, DPR,
sanctioned project
details.
Measurements taken in
site, physical progress
reports, bills of
contractor, material
registers, any revisited
drawings etc.
2
Time Overruns:
To find variation fallowing documents shall be
compared:
2
Contractor’s agreement,
approved drawings and
design including
working drawings, bill
of quality, DPR,
sanctioned project
details.
Measurements taken in
site, physical progress
reports, bills of
contractor, material
registers, any revised
drawings etc.
ANNEXURE 3
Format 1
1 Physical Progress
After analysing data if physical progress found
behind the schedule, the revised schedule shall be
recommended with consent of ULB and the
contractor for balance work to achieve
subsequent milestones within time. Additional
resources of manpower, material, tools, plants
and machinery needed to be deployed shall be
ensured.
2 Financial Progress
Financial data shall be analysed to find out:-
Whether cash flow of the project is behind the
schedule due to any hindrances. Whether financial
progress if behind the schedule due to physical
progress is behind the schedule. Probable reasons
of non-utilization or underutilization of fund is
there. Once reasons of poor performance of
financial progress found, recommendation to
improve cause of reasons can be made.
3 Quality management
Quality of the work depends on quality of
material, methodologies, workmanship,
equipments, tools and plants. If any deviation
from standards and applicable codes found that
recommendations to improve quality on shall be
made.
4 Comments and suggestions of TPQMA on above
Continuous and effective communication
between stakeholders is needed for improve
progress and quality.
The Consultant Activity
L. REMEDIAL MEASURES TO IMPROVE PROGRESS AND QUALITY
Undertaken by Implementation agency to improve the:
ANNEXURE 3
Format 1
1 ( To be specified)
In case of any litigation or court case, information
shall be collected from legal officer and reports
and suggestion to improve project
implementation shall be made.
2
The Consultant Activity
M. COURT CASES AND LITIGATIONS
ANNEXURE 3
Format 1
1
Feedback of beneficiaries regarding provision of
Physical & Social infrastructure.
Feedback from beneficiaries shall be taken with
coordination of the ULB. List of beneficiaries
including address and telephone numbers shall be
collected to contact beneficiaries.
2 Any specific observation by the beneficiary This observation shall be recorded carefully.
Overall observation on the project (with adequate
photographs covering project to a large extent
including quality issues as applicable)
1. Critical observations
2. Action suggested by TPQMA to SLNA and IA
Action taken report on previous report:
i. Observations of TPQMA
ii Action suggested by TPQMA
iv Whether TPQMA is satisfied with the action
taken by IA
4
TPQMA’s Overview of the Project (in 400-500
words) in a separate sheet
Overall summery of the project and it’s status
shall be written.
Action and fallow on observations and comment
and action recommended shall be reported
previously to SLNA shall be reported in this
section.
3
3
Observations and comment and action
recommended shall be reported to SLNA.
The Consultant Activity
N. OTHERS
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 GSR/UGSR
2 ELSR/OHT
3 Intake-Jack-well
4 WTP
5 Pipelines
6 Pump sets.
7 Rain Water Harvesting pits
8 Sump
9 Tube wells
The Consultant Activity
B. CIVIC INFRASTRUCTURE WORKS:
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
a. WATER SUPPLY:
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 Sewer Trap Connect. Chamber
2 Collection network pipes
3 Inspection chambers
4 Sewerage pump Stn (SPS)
5 SPS to STP Pipeline
6 STP
7 Septic tank
8 Soak-pit
B. CIVIC INFRASRUCTURE WORKS:
b. SEWERAGE:
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
The Consultant Activity
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 Drains
2 Open channel
3 Closed RCC Pipes
4 In-Situ RCC Box-pipes
5 Type of Grating/Jali
6 Inspection Chambers
7
Point of disposal (Nallah, Canal,
River, Creek)
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
c. STORM WATER DRAINS:
This information shall be
as per site visit
observation
The Consultant Activity
B. CIVIC INFRASRUCTURE WORKS:
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 Roads
2 Pavements
3 Jogging track
4 Plantation
5 Restoration
6 Culverts ( Masonry / RCC)
The Consultant Activity
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
B. CIVIC INFRASRUCTURE WORKS:
d. ROADS & CULVERTS:
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 H.T. Supply lines
2 L.T. Supply lines
3 Transformer
4 Street Lighting
The Consultant Activity
B. CIVIC INFRASRUCTURE WORKS:
e. ELECTRIFICATION:
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 S. W. Collection System
2 Dust Bins/Containers
3 S. W. Transport System
4 Temp. store yards
5 S.W. Disposal area
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
The Consultant Activity
B. CIVIC INFRASRUCTURE WORKS:
f. SOLID WASTE MANAGEMENT:
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 Compound/Boundary wall
2 Entrance Gate
1 Retaining wall
2 Any other (to be specified)
The Consultant Activity
B. CIVIC INFRASRUCTURE WORKS:
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
h. MISCELLANEOUS:
g. COMPOUND WALL:
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 Community Centre
2 Livelihood Centre
3 Any Other
1 Public Health Centre
2 Anganwadi
3 Primary School
4 Secondary School
5 Higher Secondary School
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
The Consultant Activity
C. REPORT ON SOCIAL INFRASRUCTURE WORKS:
a. COMMUNITY FACILITIES:
b. HEALTH /EDUCATION FACILITIES:
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 Vegetable Market
2 Meat-Fish Market
3 Medical Store
4 Any Other
1
2
3
d. ANY OTHER ( To be specified)
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
The Consultant Activity
C. REPORT ON SOCIAL INFRASRUCTURE WORKS:
c. INFORMAL SECTOR MARKET
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
Format 2 A
S. No. Component
Whether in progress (Yes
/ No)
Whether Inspected (Yes /
No)
Comments
1 Earthwork
2
Concrete work (Sub-
structure /up to plinth)
3
RCC work (Above plinth /
Super Structure)
4 Brick / Block work
5 Stonework
6 Marble work
7 Wood work
8 Steel work
9 Flooring
10 Roofing
11 Finishing
12 Internal services
13 External Services
This information shall be
as per site visit
observation
This information shall be
as per site visit
observation
If the work is being completed before site visit than inspection
not done comment shall appear. If the work is in progress during
the site visit than in the work in progress comment shall appear.
Any comment in quality, execution and safety of the work shall
appear in comment.
A. BUILDING WORK:
DETAILED REPORT ON PROPOSED WORKS
The Consultant Activity
Format 4 The Consultant Activity
Name of TPQM Agency Name of the consultant shall be entered
Date of Visit
Current Visit No.
Previous visit with date
Current and previous dates of visits shall
be entered as visit happens however those
dates shall be scheduled for entire work as
soon as inspection report completed and
approved by the client.
Third Party Quality Monitoring Report of ISSR/AHP projects under PMAY
Format 4 The Consultant Activity
1 Name of the State /UT:
2 Name of the City:
3 Name of Project:
4 Project Code:
5 Implementing Agency/ ULB
A. PARTICULARS OF PROJECT
All these data are fixed, hence can be
entered before site visit.
Format 4 The Consultant Activity
6
Location of the Project ( Slum name,
Ward etc. as applicable)
This data shall be collected from ULB and
Inspection report.
7
Type of Project :(i) BLC (New
Construction) (ii) BLC (Enhancement)
8 No. of EWS Houses in the project
9 Date of Approval by SLSMC
This data shall be collected from ULB and
Inspection report. This data may not
change after first visit.
A. PARTICULARS OF PROJECT
Format 4
Central share State share
ULB/
Implementing
agency share
Beneficiary
share
Total
11
Date of sanction of 1stinstalment of central
assistance by CSMC
12 Duration of Project
The Consultant Activity
A. PARTICULARS OF PROJECT
Above data can be collected from SUDA i.e. format 7 A or 7 B
of the guideline as submitted and sanctioned DPR and project
This data can be collected from approved project DPR,
agreement of contractor.
10 Approved Project Cost (Rs. Lakh):
This data can be collected from SUDA.
Format 4
Scheduled Actual
This date shall be entered from contractor’s
agreement, work order and schedule
submitted by the contractor
This date shall be collected from site and
ULB
Scheduled Actual
This date shall be entered from contractor’s
agreement, work order and schedule
submitted by the contractor
This date shall be collected from site and
ULB
13 Date of commencement
14 Date of completion
A. PARTICULARS OF PROJECT
The Consultant Activity
Format 4 The Consultant Activity
1
2
Name and contact details of Engineers of the
consultant who visited the site.
16
Name of State representative present
during visit
Name of State representative who visited the site.
17
Name of ULB representative present
during visit
Name of ULB representative (SE/ AE/ EE)
18
Name of Community representative
present during visit
The consultant shall request ULB regarding
presence of any community representative.
15
Inspection undertaken by (Name)
With Contact Details:
A. PARTICULARS OF PROJECT
Format 4 The Consultant Activity
19
Whether list of Beneficiaries
finalised/ partially finalised/ not
finalised
This list shall be checked in first visit and
observation shall be recorded in the site visit
report. If list be found partially or not finalized a
follow-on actions and recommendations shall be
made and progress shall be reviewed on / before
next visit.
20
If finalised, whether uploaded in
PMAY MIS
To check PMAY MIS the consultant shall request
authorization
21
State any deviation from sanctioned
DPR in terms of number of houses or
size or location or Layout
Data of sanctioned DPR shall be collected from
SUDA any deviation from this shall be checked in
approved layout drawing present in the site and
actual progress in the site.
22 Any other comment
The consultant shall comment any fallow on action
recommendation.
A. PARTICULARS OF PROJECT
ANNEXURE 3 The Consultant Activity
Format 4
1
Whether ULB/ State have organized
workshop/ training programmes to educate
the beneficiaries about quality, construction
methods, adherence to disaster resistant
technologies etc.
This information shall be recorded in consultation
with the ULB and SUDA.
2
Whether testing facilities to check quality of
material is available?
If testing facilities available than list of equipment
shall be prepared including celebration reports and
standards of equipments.
3
Whether regular tests of materials and
construction products tests of materials are
being done from accredited labs also?
This information shall be checked in documents
related to material testing available in site during
site visit and any record available in the ULB.
B. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
(i) Whether the structural Designs are
approved / Proof checked by competent
Authority
(ii) Name of the approving authority for
structural design.
(iii) Whether the statuary certificate for
disaster resistance design and compliance of
codal provision is endorsed by the structural
designer on the structural drawings fit for
execution, Specially in case of multi-
storeyed construction.
(iv) The work is being executed as per the
approved drawings fit for execution.
C. QUALITY ASSURANCE IN THE PROJECT
4
All structural drawing and design documents shall
be checked for the issues mentioned. Completed,
ongoing and upcoming work in site shall be
compared with the drawings for adequacy and
fitness for execution. In any case fallow on action
recommendation shall be made.
ANNEXURE 3 The Consultant Activity
Format 1
5
Whether the Inspection Registers, Site order
book and Quality control Test registers are
maintained and endorsed by the Engineer–in-
charge?
All these documents shall be checked for proper
entries and fallow up. Detailed observation and
fallow on action recommendation shall be made.
6
Whether cement, steel, aggregates etc.
being used in the work, got tested before
use?
Material testing documents shall be checked.
7
Whether manufacturer test certificate for
cement, steel, pipes etc. have been obtained
with supply and records are being
maintained?
Observation regarding this issue shall be recorded
fallow on action recommendation shall be made.
8
Whether Cement is free from lumps and is
stacked properly to prevent contact with
moisture?
This shall be checked during site visit.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
9
Whether soil investigations of the site
proper have been done before the structural
design and soil parameters have been
accounted for in the structural design/
drawings? If yes, attach copy of soil
investigation report.
Structural design/ drawings and soil investigation
reports shall be compared. Comparison report and
any recommendation shall be made including soil
investigation report.
10
Whether centring /shuttering is checked for
staging & propping, line & level, dimensions,
cleaning etc. and its quality approved before
each stage and record maintained.
For this issue NBC code and contractor’s
agreement shall be fallowed. Information related
to specification and load bearing capacity of
centring /shuttering and staging shall be
ascertained from the contractor as well as
methodology for the work. Checking on
methodology for the work shall be done for safety
and acceptable tolerance in line & level,
dimensions. Records regarding this issue shall be
checked and recorded. Fallow on action
recommendation shall be done.
11
Specific control on RCC work like: mixing by
full bag capacity hopper fed mixer, control of
slump, placing/ compaction with vibrator.
(proportioning with boxes not permitted)
For this issue contractor’s agreement, item
specification and NBC code shall be studied for
manufacturing of concrete. Observation and any
action follow on recommendation shall be done.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
12
Whether cement register is maintained and
checked at site. Comment on method of
stacking.
Previous dated entries of cement register shall be
checked as per progress of work and theoretical
consumption of cement.
13
Whether concrete mix is nominal or design
mix? (Nominal mix not permitted for quality
concrete).
Concrete mix shall be checked in site. Concrete
mix reference shall be checked in contractor’s
agreement, structural drawing and design,
specification, IS codes and NBC codes. Relevant
test shall be checked. Observation shall be
recorded.
14
What is the Mode of
Concrete mixing (batch mix/ manual)? In
case of manual mixing, whether mixing is by
weight or by volume of ingredients?
(Volumetric mixing not permitted).
Mode of concrete mixing shall be checked and
recorded. Follow on action recommendation shall
be made.
15
Whether Mixer/Vibrator as specified is
available at site with adequate means to run
them during concreting?
Mixer/Vibrator as specified shall be checked.
Their working shall be checked. Inspection and
inquiry shall be done to ensure proper working. In
case of noncompliance follow on action
recommendation shall be made.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
16
Whether Surface of reinforcement is clean
and free from rust?
17
Whether potable water is used for
construction ?
18
Whether proper water / cement ratio has
been ensured?
19
Whether the concrete being cured
adequately as per requirements?
20
Whether bricks are well burnt, of
rectangular shape, with sharp edges, free
from cracks and of correct size?
This information shall be checked during site visit.
C. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 1
Whether
i) Execution of Depth & width of
Foundation is as per drawing/ adequate &
bottom levelled
ii) Plinth height is as per
drawing/adequate
iii) Horizontal bands (as applicable) have
been provided
22
Whether quality has been checked by
TPQMA/ State agency? If yes, details
thereof?
This information shall be checked in site order
book and any other relevent document during site
visit.
This information shall be checked during site visit.
C. QUALITY ASSURANCE IN THE PROJECT
21
ANNEXURE 3 The Consultant Activity
Format 4
23
Quality of work and workmanship,
Comments on
Workers shall be interested to ascertain skill and
knowledge level. Workmanship shall be checked
during work in progress. Fallow on action
recommendation shall be made.
24
Whether provision has been made for
Service lines (Electrical, Water Supply,
Sanitation etc.)
Observation and inquiry shall be made regarding
this issue and shall be reported.
25
Whether floor slope (especially) in bath, WC,
kitchen, terrace and balcony etc. are proper?
Floor slope shall be checked as per drawings and
codes. In case of non-conformance rework shall be
suggested as per contractor’s agreement and
applicable codes.
26
Whether Adequate plinth height (above the
general ground level) is provided to the
ground floor of the building to avoid
possibility of rainwater and reptiles in the
building.
Drawings and site shall be checked for this issue.
Proposed level of road in front of the block /
dwelling unit shall be checked for this issue. As
per checking proper recommendation shall be
made.
B. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 4
27
Whether dampness/ leakages noticed? If
yes, state location and probable reasons.
Reason of dampness/leakages shall be carefully
checked and fallow on action recommendation
shall be made.
28
Whether remedial measures are undertaken
by/ ULB to stop Dampness & Leakages? If
any.
There shall be inquiry for remedial measures for
prevention of dampness and leakages. There shall
be an inquiry regarding actions taken on fallow on
action recommendation on previous site visits. In
case of noncompliance a detailed report shall be
prepared with several alternate recommendations.
29
Whether disaster resistant features have
been incorporated?
Disaster resistance features shall be checked as
per applicable codes. A proper report shall be
made for this issue.
30 Any other comments
Any important observation which not covered in
this format shall be entered in this heading.
Minimum 500 words (To be enclosed separately)
Overall assesement shall consist any relevent
observation whuch is not covered in the formats
and summery of information gathered.
Recommendations shall be part of the
assessement.
31 Report on Overall assessment of quality
B. QUALITY ASSURANCE IN THE PROJECT
ANNEXURE 3 The Consultant Activity
Format 4
1 Numbers of houses sanctioned in the project
This information shall be obtained from approved
DPR.
2 Numbers of houses Completed
This information shall be obtained from contract
of the contractor, approved DPR , ULB, progress
report and site visit.
3 Numbers of houses in progress
This information shall be obtained from contract
of the contractor, approved DPR and ULB.
Stages of Progress : ( Specify No. of Units)
i) Foundation/ Plinth level (Nos.)
ii. Lintel level (Nos.)
iii. Roof level (Nos.)
iv. Finishing level (Nos.)
v. Total units completed (Nos.)
C. PROGRESS - HOUSING COMPONENTS
This information shall be obtained and recoreded
during site visit.
4
ANNEXURE 3 The Consultant Activity
Format 4
5 Numbers of houses not started
This information shall be obtained and recoreded
during site visit and other relevent data.
6 Reason for non-starter of houses, if any
This information shall be obtained and recoreded
during site visit,other relevent data and meeting
with the ULB, SUDA and the contractor.
7
Numbers of houses occupied by the
Beneficiaries
This information shall be obtained and recoreded
during site visit and the ULB.
8
Reasons for Non-occupation of houses (If
any)-specific reasons to be given
This information shall be obtained and recoreded
during site visit, the ULB and meeting with
beneficieries.
C. PROGRESS - HOUSING COMPONENTS
ANNEXURE 3
Format 4
9 Size of Unit (Carpet Area) Sanctioned As per Implementation
10 Overall physical progress of Housing (in %)
This information shall
be obtained from the
approved DPR
This information shall
be obtained during site
visit.
11
Whether the progress of houses has been
ensured through geo-tagged photographs at
various construction level?
12
Whether DBT of fund to individual
beneficiary is ensured in the project?
13
Whether the building plan(s) conform to NBC
norms?
14
Whether authenticated building plans and
revisions if any, are available?
15 Deviation, if any
16 Any other comment
This information shall be obtained during site
vist, comparison of drawings approved and
executed in site, the approved DPR and revisons
of drawings and meeting with the ULB.
If any deviation found than the deviation,
probable reason of deviation, its implication shall
be recorded.
Any relevent observation which doesnot be
covered in other points shall be recorded in this
point.
For this data from ULB shall be analyzed and
report shall be prepared.
This information shall be obtained during site
vist, comparison of drawings approved and
executed in site, the approved DPR and NBC
codes applicable.
C. PROGRESS - HOUSING COMPONENTS
The Consultant Activity
This data shall be collected from the consultant
responcible for geo-tagging, ULB and SUDA.
ANNEXURE 3 The Consultant Activity
Format 4
1
Whether Contract for infrastructure
components (i.e. water supply, Sewerage,
Drainage, Roads, SWM etc.) have been
awarded?
The approved DPR and contract of the contractor
shall be checked to obtain this information.
2
Whether the Existing/proposed
infrastructure components are independent
and/or integrated with city level
infrastructure?
The approved DPR, contract of the contractor,
city level infrastracture in city development plan
and other schemes with ULB consultation shall be
checked to obtain this information.
3 Any other comments Any other relevent observation shall be recoded
D. CIVIC INFRASTRUCTURE
ANNEXURE 3 The Consultant Activity
Format 4
1 Sanctioned fund for entire project.
Information about project’s sanctioned fund shall
be collected from ULBs and SUDA.
2 Amount of funds received up to date
Information about funds received shall be
collected from ULBs and SUDA.
3 Up-to date Expenditure
Information about Up-to date expenditure shall
be collected from ULBs and SUDA.
4 Amount of funds Utilized (out of received)
Information about funds utilized shall be collected
from ULBs and SUDA.
5 Amount of Expenditure by ULB
This information shall be collected from ULBs and
SUDA and compiled.
F. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. in Lakh)
ANNEXURE 3 The Consultant Activity
Format 4
6 Amount of Expenditure by Beneficiaries
This information shall be collected from ULBs and
Beneficiaries and compiled.
7
Balance funds Expected/due from various
stakeholders
This information shall be compiled based on data
collected so far.
F. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. in Lakh)
ANNEXURE 3
Format 4
Contractor’s agreement,
approved drawings and
design including
working drawings, bill
of qualtity, DPR,
senctioned project
details.
Measurements taken in
site, physical progress
reports, bills of
contractor, material
registers, any revisied
drawings etc.
Contractor’s agreement,
approved drawings and
design including
working drawings, bill
of qualtity, DPR,
senctioned project
details.
Measurements taken in
site, physical progress
reports, bills of
contractor, material
registers, any revisied
drawings etc.
To find variation fallowing documents shall be
compared:
1
Whether there is time overrun? If
yes, what are the reasons?
To find variation fallowing documents shall be
compared:
1
Whether there is cost variation?
If yes, what are the reasons?
G. COST VARIATION and TIME-OVERRUNS Cost variation:
The Consultant Activity
Time Overruns:
ANNEXURE 3
Format 4
1 Physical Progress
After analysing data if physical progress found
behind the schedule, the revised schedule shall be
recommended with consent of ULB and the
contractor for balance work to achieve
subsequent milestones within time. Additional
resources of manpower, material, tools, plants
and machinery needed to be deployed shall be
ensured.
2 Financial Progress
Financial data shall be analysed to find out:-
Whether cash flow of the project is behind the
schedule due to any hindrances. Whether financial
progress if behind the schedule due to physical
progress is behind the schedule. Probable reasons
of non-utilization or underutilization of fund is
there. Once reasons of poor performance of
financial progress found, recommendation to
improve cause of reasons can be made.
3 Quality management
Quality of the work depends on quality of
material, methodologies, workmanship,
equipments, tools and plants. If any deviation
from standards and applicable codes found that
recommendations to improve quality on shall be
made.
4 Comments and suggestions of TPQMA on above
Continuous and effective communication
between stakeholders is needed for improve
progress and quality.
Undertaken by Implementation agency to improve the:
The Consultant Activity
H. REMEDIAL MEASURES TO IMPROVE PROGRESS AND QUALITY
ANNEXURE 3
Format 4
1 ( To be specified)
In case of any litigation or court case, information
shall be collected from legal officer and reports
and suggestion to improve project
implementation shall be made.
The Consultant Activity
I. COURT CASES AND LITIGATIONS
ANNEXURE 3
Format 4
1
Any innovative/ cost effective/ green technology
has been used
The consultant shall see all project related
documents and site and record relevent
information.
2
Feedback of beneficiaries regarding provision of
Physical & Social infrastructure:
ULB and beneficiaries shall be contacted for this
feedback.
3
Reasons for delay in completion of housing and
Infrastructure, if any:
Reason shall ascertained by analyzing schedule
and progress reports.
4 Any specific observation by the beneficiary
Beneficieries comment and observation shall be
carefully recorded.
Overall observation on the project (with adequate
photographs covering project to a large extent
including quality issues as applicable)
1. Critical observations
2. Action suggested by TPQMA to SLNA and IA
Action taken report on previous report:
i. Observations of TPQMA
ii Action suggested by TPQMA
iii. Action taken by Beneficiaries/ IA
(Implementation Agency)
iv Whether TPQMA is satisfied with the action
taken by IA
7
TPQMA’s Overview of the Project (in 400-500
words) in a separate sheet
Overall summery of the project and it’s status
shall be written.
Observations and comment and action
recommended shall be reported to SLNA.
5
Action and fallow on observations and comment
and action recommended shall be reported
previously to SLNA shall be reported in this
section.
6
The Consultant Activity
J. OTHERS
SUMMERY
In summery the consultant shall use expert knowledge to explain fully
proposed, ongoing, and planned quality related issues. The consultant
shall brief all stakeholders best quality practices and implementation.
The consultant shall assess and report quality of man, materials tools,
and plants. The consultant shall always suggest fallow on action and
recommendation to deal with any negative as well as positive quality
related issues. The consultant shall report actual and useable report of
the projects in the cluster area. The consultant shall plan its activities as
per objectives of the client. The consultant shall be source for knowledge
and expertise. The consultant shall be aware of various guidelines,
circulers and instructions of central government and state government
authorities.
Thank You

More Related Content

DOC
Guidelines for the monitoring officers
DOC
CV_Tarun Kumar Behera
DOCX
Group proposal
DOC
Lou Fanglin's Document Control Procedure and DOC Experience Summary
DOCX
Maaden Exp.
PPTX
SLOPE intro we have a new project!
DOC
Peter White CV - Latest
PDF
General circular 8-2015
Guidelines for the monitoring officers
CV_Tarun Kumar Behera
Group proposal
Lou Fanglin's Document Control Procedure and DOC Experience Summary
Maaden Exp.
SLOPE intro we have a new project!
Peter White CV - Latest
General circular 8-2015

What's hot (20)

DOC
Updated CV
PDF
(Presentation) Cis utilization of earned value management for monitoring prod...
PDF
Building ssr 2013-14
PDF
Color coded Multi-Project Monitoring (CPM)
DOC
Peter White CV
PPTX
Presentation of Quarterly Report_Deborah Ighagbon
PDF
AP state schedule of rates 2012
PDF
Cssr 2014-15
PPT
Guidance for Progress Report (10.09.2013)
PDF
Development Plan Review Process
PDF
Major Subdivision Review Process
PDF
Curriculum Vitae of Kamashen Naicker
PDF
SARF-IRF 2014 EXPOSE Chief TAMBE OK2 [Mode de compatibilité]
PPTX
THIRD PARTY VALIDATION FOR RESETTLEMENT (SOCIAL SAFEGUARD) - MDTF- ERRP Pk...
PPTX
Project Monitoring System (PMIS)
PDF
Bo Q Preamble Td2 3 Jan 20
PDF
Checklist for Cost Control Dept in Contracting Company
PDF
Methodologies of Project Progress Measurement
PDF
Brian Nicholls resume 2016-08-11
PPTX
Permission & Clearance for Real Estate Projects in Haryana
Updated CV
(Presentation) Cis utilization of earned value management for monitoring prod...
Building ssr 2013-14
Color coded Multi-Project Monitoring (CPM)
Peter White CV
Presentation of Quarterly Report_Deborah Ighagbon
AP state schedule of rates 2012
Cssr 2014-15
Guidance for Progress Report (10.09.2013)
Development Plan Review Process
Major Subdivision Review Process
Curriculum Vitae of Kamashen Naicker
SARF-IRF 2014 EXPOSE Chief TAMBE OK2 [Mode de compatibilité]
THIRD PARTY VALIDATION FOR RESETTLEMENT (SOCIAL SAFEGUARD) - MDTF- ERRP Pk...
Project Monitoring System (PMIS)
Bo Q Preamble Td2 3 Jan 20
Checklist for Cost Control Dept in Contracting Company
Methodologies of Project Progress Measurement
Brian Nicholls resume 2016-08-11
Permission & Clearance for Real Estate Projects in Haryana
Ad

Similar to Tpqma r5 to upload in slide share (20)

PDF
Technical report writing skills for civil engineers pdf
PPTX
Urban Planning Studio Project Orientation.pptx
DOCX
Class Project 1 City Case StudiesIn this project student groups
DOCX
Dissertation for consultancy project
PDF
Planning skill.pdf
PDF
POM 100 11 NOVEMBER STADIO NOTES GUIDE.pdf
PPTX
Comp Plan Update 2015
PPSX
Raistec business solutions company profile
PPTX
Formation of Design Brief and Project Conceptualization for Urban Design Prof...
DOC
project on construction of house report.
DOCX
PDF
Schedule Review
PDF
MG6088 SOFTWARE PROJECT MANAGEMENT
PPTX
Environment Social Health and Safety (ESHS) safeguard
PDF
David Chan Profile And Experience
PDF
Project management final report
PPT
june'15
PPTX
Project Charter - How To
PPTX
Lecture-03-The main elements of Urban Design.pptx
DOCX
Project management final report.By- SANKET SENAPATI
Technical report writing skills for civil engineers pdf
Urban Planning Studio Project Orientation.pptx
Class Project 1 City Case StudiesIn this project student groups
Dissertation for consultancy project
Planning skill.pdf
POM 100 11 NOVEMBER STADIO NOTES GUIDE.pdf
Comp Plan Update 2015
Raistec business solutions company profile
Formation of Design Brief and Project Conceptualization for Urban Design Prof...
project on construction of house report.
Schedule Review
MG6088 SOFTWARE PROJECT MANAGEMENT
Environment Social Health and Safety (ESHS) safeguard
David Chan Profile And Experience
Project management final report
june'15
Project Charter - How To
Lecture-03-The main elements of Urban Design.pptx
Project management final report.By- SANKET SENAPATI
Ad

More from Rajiva Gupta (12)

PDF
Horticulture and landscape
PDF
Aluminum work
PDF
Water proofing treatement
PDF
Pilework
PDF
Drainage
PDF
Water supply
PDF
Sanotary installation
PDF
Roadwork
PDF
Concrete works
PDF
Mortars
PDF
Roadwork from CPWD specification
PPTX
Earthwork
Horticulture and landscape
Aluminum work
Water proofing treatement
Pilework
Drainage
Water supply
Sanotary installation
Roadwork
Concrete works
Mortars
Roadwork from CPWD specification
Earthwork

Recently uploaded (20)

PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
PPT on Performance Review to get promotions
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
web development for engineering and engineering
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPT
Project quality management in manufacturing
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
additive manufacturing of ss316l using mig welding
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
Artificial Intelligence
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
Current and future trends in Computer Vision.pptx
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Foundation to blockchain - A guide to Blockchain Tech
PPT on Performance Review to get promotions
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
web development for engineering and engineering
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Automation-in-Manufacturing-Chapter-Introduction.pdf
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Project quality management in manufacturing
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
additive manufacturing of ss316l using mig welding
Operating System & Kernel Study Guide-1 - converted.pdf
Safety Seminar civil to be ensured for safe working.
Artificial Intelligence
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Current and future trends in Computer Vision.pptx
CYBER-CRIMES AND SECURITY A guide to understanding
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf

Tpqma r5 to upload in slide share

  • 1. INTRODUCTION OF PRADHAN MANTRI AWAS YOJANA ( HOUSING FOR ALL ) The Central Sector Scheme ‘Housing for All’ mission through Pradhan Mantri Awas Yojana for Urban Area launched by the Ministry of Housing and Urban Poverty Alleviation (MoHUPA) to be implemented during 2015-2022. PRESENTATION ON THIRD PARTY QUALITY MONITORING REPORT OF ISSR/AHP PROJECTS UNDER PMAY
  • 2. The consultant shall organize it's activities in five groups as fallows:-  PART A-ACTIVITIES FOR PREPARATION OF INCEPTION REPORT  PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT AND PREPARATION OF SITE VISIT REPORT  PART C- ACTIVITIES FOR PREPARATION OF QUARTERLY REPORT AND SUBMISSION  PART D- ACTIVITIES FOR PREPARATION OF FINAL REPORT AND SUBMISSION  PART E- ACTIVITIES OF COLLECTING AND ANALYSING DATA IN ANNEXURE 3
  • 3. PART A-ACTIVITIES FOR PREPARATION OF INCEPTION REPORT
  • 4. PART A-ACTIVITIES FOR PREPARATION OF INCEPTION REPORT 1. KICK-START MEETING & TEAM MOBILIZATION It is proposed to kick-start the Consultancy assignment with a formal meeting with SUDA and Urban Local Bodies (ULBs) and other concerned agencies/stakeholders. The consultant’s team shall also start their work in accordance with the Work Schedule finalized in consultation with the concerned authorities.
  • 5. PART A-ACTIVITIES FOR PREPARATION OF INCEPTION REPORT 2. COLLECTION OF SECONDARY DATA AND PRELIMINARY SURVEY & INVESTIGATIONS WAPCOS will collect report and data on projects under the mission in the cluster area and other relevant data available. WAPCOS team of experts shall visit the sites to assess the Housing and Infrastructure conditions, socio-economic conditions for innovative housing planning meeting all the guidelines under HFPoA.
  • 6. PART A-ACTIVITIES FOR PREPARATION OF INCEPTION REPORT 3. PREPARATION OF THE INCEPTION REPORT Based on the available data and its analysis an inception report will be prepared. The report will contain background and objective of the scheme, brief of existing situation of the city, detailed approach, and methodology to carry out work, work schedule, & manning schedule adopted by the consultant to complete the work in time and quality deliverables to complete the work, quality assurance procedures. List of documents, guidelines, codes, and formats to be used to carry out the work as per guidance.
  • 7. PART A-ACTIVITIES FOR PREPARATION OF INCEPTION REPORT 4. DATA FROM INSPECTION REPORT TO ANNEXURE 3 Most of the data collected in inspection report shall be initial data for first site visit report in Annexure 3 ( the format for site visit report )
  • 8. PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT AND PREPARATION OF SITE VISIT REPORT 1. COLLECTION OF DATA FROM INSPECTION REPORT. Data specific to the ULB shall be presented in inspection report and shall be transferred to the formats of Annexure-3. These data may be project specific. Project may be inn various phases such as under preparation, under sanction or submission and approved project as well as projects under implementation.
  • 9. PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT AND PREPARATION OF SITE VISIT REPORT 2. PREPARATION OF SCHEDULE OF SITE VISITS. Based on data collected so far, the consultant shall prepare an efficient schedule for approval and implementation to the client under objectives of maximum and best quality control of the projects.
  • 10. PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT AND PREPARATION OF SITE VISIT REPORT 3.CARRY OUT SITE VISITS. As per approved schedule the consultant shall visit site. Site visit shall be carried out in such manner so that all possible relevant information about the project shall be disclosed and recommendation in improvement in quality and implementation of the projects can be made.
  • 11. PART B- ACTIVITIES FOR PREPARATION OF SITE VISIT AND PREPARATION OF SITE VISIT REPORT 4.PREPARATION OF SITE VISITS REPORT. The consultant shall enter data specific to the project which may not need any change such as information of cost and location of the project, before the site visit and during the site visit. Rest of the information shall be entered in the format during site visit. However, recommendation shall be prepared during end of site visit and after end of site visit. Approved schedule of the visit site shall be fallowed. Site visit shall be carried out in such manner so that all possible relevant information about the project shall be disclosed and recommendation in improvement in quality and implementation
  • 12. PART C- ACTIVITIES FOR PREPARATION OF QUARTERLY REPORT AND SUBMISSION 1. DATA FROM INSPECTION REPORT Data from the inspection report shall be entered relevant to the quarterly report as soon as approval of inspection report. 2.DATA FROM SITE VISIT REPORT Additional data shall be entered from site visit reports as soon as site visit report completed. 3.ADDITIONAL DATA Due date of quarterly report is fixed as per financial year and instruction of the client. Remaining data shall be collected from ULBs and client before due date and entered. Most important aspect of quarterly report is its financial nature; Hence the consultant shall prepare analysis of financial data in the report. The consultant shall propose to present a format of quarterly report for approval to the client.
  • 13. PART D- ACTIVITIES FOR PREPARATION OF FINAL REPORT AND SUBMISSION The consultant shall submit final report of a project after completion of the project. The consultant shall compile final report from inspection report, site visit reports, quarterly reports, final handover report data from the contractor and data from ULB. The final report shall include a report on fallow up of recommendations made by the consultant and lesion learned from the project completed also. The consultant shall prepare a format for final report after approval of first quarterly report to the client for necessary changes and approval of the format by the client.
  • 14. PART E- METHODOLOGY TO COLLECT AND ANALYSE DATA IN ANNEXURE 3 Comments on tests already done but not found satisfactory (specify action to be taken) To deal with this issue contractor’s agreement, NBC codes and applicable rules regulation shall be referred. The client shall be briefed with the situation, implication, and all possible alternatives for remedies. Best alternative to deal with the situation shall be explained. The client shall need only to make decision.
  • 15. ANNEXURE 3 Format 1- A Particulars of the project The consultant activities would be as mentioned below:- 1. Some data from sanctioned DPR, contractor’s agreement from the ULB shall be compiled in Format 1-A. 2. Name and contact details of engineers of consultant, name of state representative, name of contractor’s representative and name of community representative and ULB representative shall be mentioned as recorded in the site visit. 3. Scheduled dates of commencement and completion shall be recorded as per contractor’s agreement, work order and schedule approved by authorities. 4. Actual dates of commencement and completion shall be recorded as per observations during site visit. 5. Status of list of beneficiaries shall be collected from PMAY MIS. 6. Compliance to time limit, price escalation, legal clauses, liquidated damages, penalties shall be recoded comparing the sanctioned DPR, agreement of the contractor and financial & physical progress of the work and a checklist prepared for this purpose.
  • 16. ANNEXURE 3 The Consultant Activity Format 1 1 Name of the State /UT: 2 Name of the City: 3 Name of Project: 4 Project Code: 5 Implementing Agency (ULB/ DA/ HB/ UIT/ Slum Rehabilitation Agency) All these data are fixed, hence can be entered before site visit. A. PARTICULARS OF PROJECT
  • 17. ANNEXURE 3 The Consultant Activity Format 1 A. PARTICULARS OF PROJECT 1 Name of the State /UT: 2 Name of the City: 3 Name of Project: 4 Project Code: 5 Implementing Agency (ULB/ DA/ HB/ UIT/ Slum Rehabilitation Agency) All these data are fixed, hence can be entered before site visit.
  • 18. ANNEXURE 3 The Consultant Activity Format 1 A. PARTICULARS OF PROJECT 6 Location of the Project (Slum name, Ward etc. (Annexe details in case of multiple sites) as applicable) This data shall be collected from ULB and Inspection report. 7 Type of Project :(i) In-situ Slum redevelopment (ISSR) (ii) Affordable Housing in Partnership (AHP) This data shall be collected from ULB and Inspection report. This data may not change after first visit. 8 Total Houses (EWS/LIG/MIG/HIG) in the project. 9 No. of EWS Houses in the project
  • 19. ANNEXURE 3 The Consultant Activity Format 1 A. PARTICULARS OF PROJECT 10 Description of Work. i. Carpet/ Built up area of EWS house ii. No. of EWS houses in one block iii. No. of blocks iv. Total no. of houses v. Type of Structure (G,G+1,G+2 etc.) vi. No. of storeys / floor. This data shall be collected from ULB and Inspection report. This data may not change after first visit. 11 Date of Approval of project by SLSMC This data shall be collected from SUDA / SLSMC
  • 20. ANNEXURE 3 Format 1 Central share State share ULB/ Implementing agency share Beneficiary share Total 13 Date of sanction of 1stinstalment of central assistance by CSMC 12 Approved Project Cost (Rs. Lakh): This data can be collected from SUDA. The Consultant Activity A. PARTICULARS OF PROJECT Above data can be collected from SUDA i.e. format 7 A or 7 B of the guideline as submitted and sanctioned DPR and project
  • 21. ANNEXURE 3 Format 1 14 Duration of Project This data can be collected from approved project DPR, agreement of contractor. (Annexe details in case of multiple contracts) Multiple contract of a single project may happen. In this situation, the consultant shall make note/ report of the situation The Consultant Activity A. PARTICULARS OF PROJECT 15 Date of Award of work
  • 22. ANNEXURE 3 Format 1 Scheduled Actual This date shall be entered from contractor’s agreement, work order and schedule submitted by the contractor This date shall be collected from site and ULB Scheduled Actual This date shall be entered from contractor’s agreement, work order and schedule submitted by the contractor This date shall be collected from site and ULB 17 Date of completion Date of commencement A. PARTICULARS OF PROJECT 16 The Consultant Activity
  • 23. ANNEXURE 3 The Consultant Activity Format 1 A. PARTICULARS OF PROJECT 18 Inspection undertaken by (Name) With Contact Details: 1. 2. Name and contact details of Engineers of the consultant who visited the site. 19 Name of State representative present during visit Name of State representative who visited the site. 20 Name of ULB representative present during visit Name of ULB representative (SE/ AE/ EE) 21 Name of Contractor’s representative present during visit Contractor’s representative shall be authorise representative. 22 Name of Community representative present during visit The consultant shall request ULB regarding presence of any community representative.
  • 24. ANNEXURE 3 The Consultant Activity Format 1 23 Whether list of Beneficiaries finalised/ partially finalised/ not finalised This list shall be checked in first visit and observation shall be recorded in the site visit report. If list be found partially or not finalized a follow-on actions and recommendations shall be made and progress shall be reviewed on / before next visit. 24 If finalised, whether uploaded in PMAY MIS To check PMAY MIS the consultant shall request authorization A. PARTICULARS OF PROJECT
  • 25. ANNEXURE 3 The Consultant Activity Format 1 25 State any deviation from sanctioned DPR in terms of number of houses or size or location or Layout Data of sanctioned DPR shall be collected from SUDA any deviation from this shall be checked in approved layout drawing present in the site and actual progress in the site. 26 Compliance of Tender conditions matching to statutory requirements of DPR w.r.t. Compliance to time limit. Compliance to price escalation. Compliance to legal clauses. Compliance to liquidated damages. Compliance to penalties. To inspect these conditions the consultant shall compare the sanctioned DPR, agreement of the contractor and financial & physical progress of the work. For this consultant shall prepare a checklist. 27 Any other comment The consultant shall comment any fallow on action recommendation. A. PARTICULARS OF PROJECT
  • 26. ANNEXURE 3 Format 1 B. Health & Safety Aspects (On Site) The consultant activities would be as mentioned below:- 1 Availability and content of first aid box shall be checked 2 Fire Extinguishers shall be checked for its functionality. Expiry date and manufacturing shall also be checked and noted. 3 It is being checked that blasting is being done or proposed to be done. If yes that necessary permission shall be checked as per applicable rules and regulation. It shall be checked that blasting shall be done under qualified staff. 4 Presence of Safety-Officer employed shall be checked during site visit.
  • 27. ANNEXURE 3 The Consultant Activity Format 1 1 Whether the drinking water facility is provided on site? The consultant shall check source of drinking water assess numbers of users of drinking water, quality, quantity, and adequacy of drinking water. Relevant NBC code shall be fallowed. 2 Whether there are adequate no. of toilets provided & maintained for site staff / Workers? This shall be checked for male and female workforce present and to be employed in near future of the work. Relevant NBC code shall be fallowed. 3 Whether there is a board indicating the safety norms to be observed? The consultant shall fallow NBC code regarding this issue If any deviation from compliance is observed than observation shall be noted and fallow on action recommendation shall be done. B. HEALTH & SAFETY ASPECTS (ON SITE)
  • 28. ANNEXURE 3 The Consultant Activity Format 1 4 Whether the use of following is being done by site staff i. Safety Helmets ii. Safety Shoes iii. Safety Goggles iv. Safety Jackets 5 Whether safety railings & safety tapes have been provided around excavation trenches /upper floors/ducts/lift well? 6 Whether approved quality & type shoring-strutting scaffolding are provided for excavation trenches/Pits/Building work? This issue shall be checked as per NBC code and observation shall be recorded. If any deviation from mandatory terms condition found than fallow on action recommendation shall be done. Observation and inquiry during site visit shall be made than regarding this issue. Photographic evidence shall be collected during site visit. If any deviation from mandatory terms condition found than fallow on action recommendation shall be done. B. HEALTH & SAFETY ASPECTS (ON SITE)
  • 29. ANNEXURE 3 The Consultant Activity Format 1 7 Whether 'FIRST AID' kit is available at site? Content of 'FIRST AID' kit shall be checked. Knowledge of staff of contractor shall be checked. Any necessary recommendation shall be made. 8 Whether Fire Extinguishers are available at site? Fire Extinguishers shall be checked for its functionality. Expiry date and manufacturing shall also be checked and noted. If any discrepancy found than duly reported by the consultant. 9 Whether 'Blasting' is being done on site? If yes, whether necessary permissions have been obtained and required precautions have been taken for control blasting? It is being checked that blasting is being done or proposed to be done. If yes that necessary permission shall be checked as per applicable rules and regulation. It shall be checked that blasting shall be done under qualified staff. The qualified staff shall be enquired about knowledge, procedures, and precautions regarding blasting. 10 Whether any Safety-Officer is employed? This issue shall be checked as per contractor’s agreement and NBC code. 11 Any other comment In this point fallow on action recommendation shall be referred. B. HEALTH & SAFETY ASPECTS (ON SITE)
  • 30. ANNEXURE 3 Format 1 C. Quality Assurance In The Project The consultant activities would be as mentioned below:- 1 Availability of DPR, contract document, structural drawings and copies of specifications shall be checked during site visit. 2 Inspection Registers, Site order book shall be checked for frequency of visit of officers/ engineers, and Quality control Test registers and their proper maintaince during site visit shall be done. Method of stacking of cement and cement register shall be checked for proper consumption of cement in works as per schedule. 3 Whether cement register is maintained and checked at site. 4 List of ISI marked/approved materials used in site shall be prepared. Manufacturer's test certificates shall be checked. 5 Testing facilities shall be checked as per contractor's agreement. 6 "Site test reports and Structural Designs shall be checked forissues ilke, proper approval from competent authoriries, proper codes have been fallowed, fit for execution, any disaster related compliance etc. The work is being executed as per the approved drawings fit for execution shall be checked during site visit."
  • 31. ANNEXURE 3 Format 1 C. Quality Assurance In The Project 7 Mandatory tests of construction material, and works and their frequency shall be checked. 8 Centring, shuttering, staging & propping shall be checked for line & level, dimensions, cleaning and safety of concrete work. 9 RCC work shall be checked for issues like , mixing by full bag capacity, hopper fed mixer, control of slump, placing/ compaction with vibrator etc. 10 "Concrete mix design mix and mode of concrete mixing shall be checked." 11 Cover, line, length, and plumb of reinforcement shall be checked during site visit. 12 Seepage, cracks and honey combing shall be checked to find reason. 13 Precautions taken for dewatering and protecting site from flooding shall be checked. 14 Adequacy of plinth height shall be checked. 15 Overall assessment of quality in view of structural stability, non structural work and workmanship shall be done including video/photograph.
  • 32. ANNEXURE 3 The Consultant Activity Format 1 1 Whether authenticated copy of DPR, contract document, structural drawings and copies of specifications are available at site? This is important observation and shall be noted by the consultant. If any deviation found than fallow on action recommendation shall be made. 2 Whether the Inspection Registers, Site order book and Quality control Test registers are maintained at the site properly and endorsed by the Engineer–incharge? All these documents shall be checked for proper entries and fallow up. Detailed observation and fallow on action recommendation shall be made. 3 Whether list of ISI marked/approved materials to be used is available at site? A report shall be prepared regarding this issue and fallow on action recommendation shall be made. C. QUALITY ASSURANCE IN THE PROJECT
  • 33. ANNEXURE 3 The Consultant Activity Format 1 4 Is there a provision in Contract/Tender to provide'Test facilities on site”? Contractor’s contact document shall be checked regarding this issue with NBC code or and any relevant codes. 5 Whether testing facilities to check quality of material is available at site? if yes attach list of Equipments If testing facilities available than list of equipment shall be prepared including celebration reports and standards of equipments. 6 Whether the structural Designs are approved / Proof checked by competent Authority Name of the approving authority for structural design. Whether the statuary certificate for disaster resistance design and compliance of codal provision is endorsed by the structural designer on the structural drawings fit for execution, especially in case of multi- storeyed construction. The work is being executed as per the approved drawings fit for execution. All structural drawing and design documents shall be checked for the issues mentioned. Completed, ongoing and upcoming work in site shall be compared with the drawings for adequacy and fitness for execution. In any case fallow on action recommendation shall be made. C. QUALITY ASSURANCE IN THE PROJECT
  • 34. ANNEXURE 3 The Consultant Activity Format 1 7 Whether manufacturer test certificate for cement, steel, pipes etc. have been obtained with supply and records are being maintained? Observation regarding this issue shall be recorded fallow on action recommendation shall be made. 8 Whether all mandatory tests of construction material, road work, sanitary work, plumbing work, electrical work and concrete in foundations, beams, columns and slabs etc are carried out at stipulated frequency? Frequency of tests shall be checked with contractor’s agreements IS codes and NBC codes. Test reports shall be checked for progressive sum of quantity of items as per progress of work and materials. Observations and any discrepancies shall be recorded. In any case fallow on action recommendations shall be made. 9 Whether regular tests of materials and construction products are being got done from accredited labs also? If yes, details of such labs Contractor’s agreement shall be checked for percentage of tests to be done from accredited labs and mandatory performance of tests from accredited labs. Observations shall be recorded. Any deviation and irregularities shall be recorded and recommendations for improvement in situation shall be done. C. QUALITY ASSURANCE IN THE PROJECT
  • 35. ANNEXURE 3 The Consultant Activity Format 1 10 Whether soil investigations of the site proper have been done before the structural design and soil parameters have been accounted for in the structural design/ drawings? If yes, attach copy of soil investigation report. Structural design/ drawings and soil investigation reports shall be compared. Comparison report and any recommendation shall be made including soil investigation report. 11 Whether centring /shuttering is checked for staging & propping, line & level, dimensions, cleaning etc. and its quality approved before each stage and record maintained. For this issue NBC code and contractor’s agreement shall be fallowed. Information related to specification and load bearing capacity of centring /shuttering and staging shall be ascertained from the contractor as well as methodology for the work. Checking on methodology for the work shall be done for safety and acceptable tolerance in line & level, dimensions. Records regarding this issue shall be checked and recorded. Fallow on action recommendation shall be done. 12 Specific control on RCC work like: mixing by full bag capacity hopper fed mixer, control of slump, placing/ compaction with vibrator. (proportioning with boxes not permitted) For this issue contractor’s agreement, item specification and NBC code shall be studied for manufacturing of concrete. Observation and any action follow on recommendation shall be done. C. QUALITY ASSURANCE IN THE PROJECT
  • 36. ANNEXURE 3 The Consultant Activity Format 1 13 Whether cement register is maintained and checked at site. Comment on method of stacking. Previous dated entries of cement register shall be checked as per progress of work and theoretical consumption of cement. 14 Whether concrete mix is nominal or design mix? (Nominal mix not permitted for quality concrete). Concrete mix shall be checked in site. Concrete mix reference shall be checked in contractor’s agreement, structural drawing and design, specification, IS codes and NBC codes. Relevant test shall be checked. Observation shall be recorded. 15 What is the Mode of Concrete mixing (batch mix/ manual)? In case of manual mixing, whether mixing is by weight or by volume of ingredients? (Volumetric mixing not permitted). Mode of concrete mixing shall be checked and recorded. Follow on action recommendation shall be made. C. QUALITY ASSURANCE IN THE PROJECT
  • 37. ANNEXURE 3 The Consultant Activity Format 1 16 Whether Mixer/Vibrator as specified is available at site with adequate means to run them during concreting? Mixer/Vibrator as specified shall be checked. Their working shall be checked. Inspection and inquiry shall be done to ensure proper working. In case of noncompliance follow on action recommendation shall be made. 17 Whether RMC is being used in work? If yes, detail of control and checks done at plant site. Comment on Quality of aggregates, Slump test, Cube test etc. RMC plant, manufacturing documents and procedure shall be checked along with lead and admixture. NBC code shall be fallowed to ascertain quality and method of products and production. Fallow on action recommendation shall be made to ensure acceptable quality of concrete. 18 Suitability of water for construction What is the source of water Has water been tested and approved by Engineer-in-charge before construction Has water been tested subsequently as per Requirement Source of water shall be checked for consistent quality and quantity and environmental aspects. Testing of water as approved by engineer-in- charge shall be checked. Routine check of water shall be ensured. Fallow on action recommendation shall be done. C. QUALITY ASSURANCE IN THE PROJECT
  • 38. ANNEXURE 3 The Consultant Activity Format 1 19 Quality of work and workmanship, Comments on Workers shall be interested to ascertain skill and knowledge level. Workmanship shall be checked during work in progress. Fallow on action recommendation shall be made. 19 i RCC work (concrete, Reinforcement detailing, cover to reinforcement). Whether Columns are in plumb (check for verticality). Cover, line, length, and plumb shall be checked as much as possible during site visit. Any non- confirmation shall be reported. Remedial actions shall be recommended. Reasons for deviation from tolerance shall be find out and recorded. Proper procedure and mix of cover block shall be inspected and standard practice shall be recommended. 19 ii Masonry (Joint details, verticality). Check adequate RCC bands are provided. Quality of masonry joints, RCC bands shall be inspected as well as method of work. Fallow on action recommendation shall be made. C. QUALITY ASSURANCE IN THE PROJECT
  • 39. ANNEXURE 3 The Consultant Activity Format 1 19 iii iii. Shuttering (Type of material- pucca/katcha, support spacing ) Shuttering shall be checked with respect to contractor’s agreement and specifications. Properties of shuttering shall be ascertained to ensure quality, safety, and tolerance of RCC works. 19 iv iv. Bar bending and stirrups bending , placement and cover to reinforcement bars. Procedure and product of bar bending, binding, and placing of reinforcement shall be checked. Proper procedure shall be recommended. Skill level of bar binders shall be ascertained. 19 v Plastering Proper procedure and finish of plastering shall be checked. Skill of meson shall be ascertained. Mortar mixing shall be inspected, and proper method shall be recommended. C. QUALITY ASSURANCE IN THE PROJECT
  • 40. ANNEXURE 3 The Consultant Activity Format 1 19 vi Doors and windows Material and workmanship of doors and windows shall be checked including fittings. Recommendation shall be made for method of work and materials used. 19 vii Seepage, if any Preventive measures for seepage shall be recommended. Adequate method for eradication and prevention of seepage shall be recommended. Any seepage and reason of seepage shall be carefully recorded for fallow on action recommendation. 19 viii Cracks, if any Location, seriousness, and possible reason of cracks shall be recorded. Inquiry for reason of cracks shall be made. Fallow on action recommendation shall be made. C. QUALITY ASSURANCE IN THE PROJECT
  • 41. ANNEXURE 3 The Consultant Activity Format 1 19 ix Honey combing, if any Proper procedure for repair of honey combing shall be recommended. Rework can be recommended as per site conditions and possible effect of honey combing in the structure. Reasons of honeycombing shall be recorded such as faulty shuttering or/and inadequate compaction. 19 x Any other Any other issue shall be recorded and follow on action recommendation shall be made. 20 Whether floor slope (especially) in bath, WC, kitchen, terrace and balcony etc. are proper? Floor slope shall be checked as per drawings and codes. In case of non-conformance rework shall be suggested as per contractor’s agreement and applicable codes. C. QUALITY ASSURANCE IN THE PROJECT
  • 42. ANNEXURE 3 The Consultant Activity Format 1 21 Whether dampness/ leakages noticed? If yes, state location and probable reasons. Reason of dampness/leakages shall be carefully checked and fallow on action recommendation shall be made. 22 Whether remedial measures are undertaken by/ ULB to stop Dampness & Leakages? If any. There shall be inquiry for remedial measures for prevention of dampness and leakages. There shall be an inquiry regarding actions taken on fallow on action recommendation on previous site visits. In case of noncompliance a detailed report shall be prepared with several alternate recommendations. 23 Whether Service lines (Electrical, Plumbing, Others) if any, provided before commencement of concrete? Proper sequence and methodology of contractor to do the work shall be checked as per contractor’s agreement. NBC code shall be referred regarding this issue. Observation and fallow on action recommendation shall be fallowed. C. QUALITY ASSURANCE IN THE PROJECT
  • 43. ANNEXURE 3 The Consultant Activity Format 1 24 Whether disaster resistant features have been incorporated? Disaster resistance features shall be checked as per applicable codes. A proper report shall be made for this issue. 25 Whether precautions taken for dewatering and protecting site from flooding as applicable? A proper plan shall be there for flooding and dewatering as per locality. A report on this issue shall be made. Any precautions taken shall be inspected and reported. In absence of any precautionary measures there shall be a fallow on action recommendation. 26 Whether sample units/items are completed and approved by competent ULB official / CLTC member before start of mass finishing work? Observation and inquiry shall be made regarding this issue and shall be reported. C. QUALITY ASSURANCE IN THE PROJECT
  • 44. ANNEXURE 3 The Consultant Activity Format 1 27 Whether Adequate plinth height (above the general ground level) is provided to the ground floor of the building to avoid possibility of rainwater and reptiles in the building. Drawings and site shall be checked for this issue. Proposed level of road in front of the block / dwelling unit shall be checked for this issue. As per checking proper recommendation shall be made. 28 Comments on tests already done but not found satisfactory (specify action to be taken) To deal with this issue contractor’s agreement, NBC codes and applicable rules regulation shall be referred. The client shall be briefed with the situation, implication, and all possible alternatives for remedies. Best alternative to deal with the situation shall be explained. The client shall need only to make decision. C. QUALITY ASSURANCE IN THE PROJECT
  • 45. ANNEXURE 3 The Consultant Activity Format 1 29 Frequency of visit by SLNA/ULB officials and SLTC/CLTC member Numbers of visits and dates of SLNA/ULB officials and SLTC/CLTC member along with name and designation shall be recorded. Site order book entries and other recordes shall be used to gather this information. 30 Any other comments Any important observation which not covered in this format shall be entered in this heading. 31 Overall assessment of quality (in view of structural stability, non structural work and workmanship)*video/photogra phs of the ongoingworks maintained by ULB/Implementation Agency may be referred as the case may be. Video/photographs of the ongoing works maintained by agencies including video/photographs of TPQMA shall be gathered relevant to a assement of quality in headings of structural and non structural work. C. QUALITY ASSURANCE IN THE PROJECT
  • 46. ANNEXURE 3 Format 1 D. Beneficiary Participation In The Project 1. List of Beneficiaries shall be checked for it’s completion in first visit and observation shall be recorded in the site visit report. 2. Plan and status of identification and allotment of houses shall be checked. The consultant shall prepare a report on this. 3. Involvement of beneficiaries in the project preparation and construction work shall be checked with the ULB and site order book / visitor book. 4. Any suggestion of the beneficiaries in the construction recorded in site order book / visitor book during construction shall be recorded in the Format 1 D.
  • 47. ANNEXURE 3 The Consultant Activity Format 1 1 Whether list of Beneficiaries is prepared This list shall be checked in first visit and observation shall be recorded in the site visit report. If list be found partially or not finalized a follow-on actions and recommendations shall be made and progress shall be reviewed on / before next visit. 2 Whether houses are identified and allotted Process of allotement of shall be checked. Plan and status of identification and allotement shall be checked. The consultant shall prepare a report on this. 3 Whether the Beneficiaries are involved in the project preparation and construction work. This information shall be obtained from the ULB. 4 Whether the Beneficiaries are visiting the site or not This information shall be obtained from the ULB and contractor. 5 Any suggestion of the beneficiaries in the construction This information shall be obtained from the ULB and contractor and from beneficiaries during site visit. D. BENEFICIARY PARTICIPATION IN THE PROJECT
  • 48. ANNEXURE 3 Format 1 E. Progress - Housing Components 1 Information about numbers of houses sanctioned, in progress and completion the project shall be obtained from approved DPR, contractor's contract and observation during site visits and progress reports. 2 Progress report of stages of housing construction such as foundation, superstructure, brickwork, finishing in numbers of housing units shall be recorded during site visit. 3 Information about numbers of houses sanctioned but construction not started and numbers of houses occupied and non-occupied shall be recorded during site visit and with meetings with ULB and Beneficiaries . 4 Physical progress of housing in percentage shall be recorded. 5 Any revision of building plan and NBC norms conformity shall be recorded. 6 If any deviation found than the deviation, probable reason of deviation, its implication shall be recorded. 7 Use of any innovative/ cost effective/ green technology shall be recoded.
  • 49. ANNEXURE 3 The Consultant Activity Format 1 1 Numbers of houses sanctioned in the project This information shall be obtained from approved DPR. 2 Numbers of houses in progress This information shall be obtained from contract of the contractor, approved DPR and ULB. 3 Numbers of houses Completed This information shall be obtained from contract of the contractor, approved DPR , ULB, progress report and site visit. ( Specify No. of Units) This information shall be obtained and recoreded during site visit. E. PROGRESS - HOUSING COMPONENTS Stages of Progress (Multi storied buildings) : i) Foundation/ Plinth level (Nos.) ii) Superstructure (Frame work) Level(Nos.) 4
  • 50. ANNEXURE 3 The Consultant Activity Format 1 5 Numbers of houses not started This information shall be obtained and recoreded during site visit and other relevent data. 6 Reason for non-starter of houses, if any This information shall be obtained and recoreded during site visit,other relevent data and meeting with the ULB, SUDA and the contractor. 7 Numbers of houses occupied by the Beneficiaries This information shall be obtained and recoreded during site visit and the ULB. 8 Reasons for Non-occupation of houses (If any)-specific reasons to be given This information shall be obtained and recoreded during site visit, the ULB and meeting with beneficieries. E. PROGRESS - HOUSING COMPONENTS
  • 51. ANNEXURE 3 Format 1 9 Size of Unit (Carpet Area) Sanctioned As per Implementation 10 Overall physical progress of Housing (in %) This information shall be obtained from the approved DPR This information shall be obtained during site visit. 11 Whether the building plan(s) conform to NBC norms? 12 Whether authenticated building plans and revisions if any, are available? This information shall be obtained during site vist, comparison of drawings approved and executed in site, the approved DPR and NBC codes applicable. This information shall be obtained during site vist, comparison of drawings approved and executed in site, the approved DPR and revisons of drawings and meeting with the ULB. E. PROGRESS - HOUSING COMPONENTS The Consultant Activity
  • 52. ANNEXURE 3 The Consultant Activity Format 1 13 Deviation, if any If any deviation found than the deviation, probable reason of deviation, its implication shall be recorded. 14 Any innovative/ cost effective/ green technology has been used? This information shall be recorded after comparing all data available. 15 Any other comment Any relevent observation which doesnot be covered in other points shall be recorded in this point. E. PROGRESS - HOUSING COMPONENTS
  • 53. ANNEXURE 3 Format 1 F. Progress- Civic Infrastructure Components 1. The approved DPR and contract of the contractor shall be checked to obtain information about for infrastructure components such as water supply, Sewerage, Drainage, Roads, SWM have been awarded. If no, time line for award of contract for infrastructure works shall be obtained from the ULB. The approved DPR and contract of the contractor shall be checked to obtain this information and meeting with the ULB shall be done to obtain to probable schedule for award of contract for infrastructure works. If Yes, progress of work in % shall be recorded in the site visit. and details shall be reported in Annexure 2A. 2. If any deviation found comparing sanctioned DPR, contractor's contract and work executed in site, than it shall be recorded. 3. Observations on quality of construction of Infrastructure works shall be recorded during site visit. 4. Information about the proposed infrastructure components are independent and/or integrated with city level infrastructure shall be collected and compiled by meeting with the ULB, observations during site visit, collection of data related to city level infrastructure such as data of water supply system, sewer treatment plant and sewer line network, study of city development plan etc. 5. information about Transit Accommodation to beneficiaries shall be shall be collected from beneficiaries, The ULB and the contractor. If case of Transit Accommodation not being provided to the beneficiaries than any alternate measures have been taken for the displaced families shall be recorded. 6. Information about overall physical progress of civic infrastructure in percentage and any cost reduction in infrastructure components (To be reported in case of deviation from sanctioned quantity) shall be recorded. This information shall be obtained by comparing financial and physical progress recorded by the ULB, sanctioned DPR, contractor’s agreement and observations in the site during site visit.
  • 54. ANNEXURE 3 The Consultant Activity Format 1 1 Whether Contract for infrastructure components (i.e. water supply, Sewerage, Drainage, Roads, SWM etc.) have been awarded? The approved DPR and contract of the contractor shall be checked to obtain this information. i) If no, Time line for award of contract for infrastructure works. The approved DPR and contract of the contractor shall be checked to obtain this information and meeting with the ULB shall be done to obtain to probable schedule for award of contract for infrastructure works. ii) If Yes, State the progress of work in % a. Water Supply b. Sewerage c. Drainage d. Roads e. Solid Waste Management f. Electrification g. Any other component (as per sanctioned components) *(Provide detailed report in Annexure 2A) This report shall be prepared by obtaining information from the approved DPR and contract of the contractor, drawings, schedule and progress of work observed during site visit. F. PROGRESS- CIVIC INFRASTRUCTURE COMPONENTS
  • 55. ANNEXURE 3 The Consultant Activity Format 1 2 iii) Deviation if any as per sanctioned DPR This report shall be prepared by comparing data collected during site visit and sanctioned DPR. 3 Comments on quality of construction of Infrastructure works Observations on quality of construction of Infrastructure works shall be recorded during site visit. 4 Whether the proposed infrastructure components are independent and/or integrated with city level infrastructure? This information shall be collected and compiled by meeting with the ULB, observations during site visit, collection of data related to city level infrastructure such as data of water supply system, sewer treatment plant and sewer line network, study of city development plan etc. F. PROGRESS- CIVIC INFRASTRUCTURE COMPONENTS
  • 56. ANNEXURE 3 The Consultant Activity Format 1 5 Whether Transit Accommodation has been provided. If not what measures have been taken for the displaced families? This information shall be collected from beneficiaries, The ULB and the contractor. 6 Overall physical progress of civic infrastructure (in %) This information shall be compiled by compacting, contractor’s contract, sanctioned DPR, physical progress observed during site visit. 7 Cost reduction in infrastructure components (To be reported in case of deviation from sanctioned quantity) This information shall be obtained by comparing financial and physical progress recorded by the ULB, sanctioned DPR, contractor’s agreement and observations in the site during site visit. F. PROGRESS- CIVIC INFRASTRUCTURE COMPONENTS
  • 57. ANNEXURE 3 Format 1 G. Social Infrastructure Components 1.Information about contract and timeline for Social Amenities such as Community centre, Livelihood centre etc. have been awarded shall be collected from the sanctioned DPR, contractor’s agreement, meeting with ULB and physical progress observed of social amenities during site visit.If no, Time line for award of contract for Social If Yes, than progress of work in % Community centre,Livelihood centre, Informal Sector Market, Any other component shall be recorded. 2. Deviation if any as per sanctioned DPR, Comments on quality of construction of Social Amenities, Overall physical progress of Social Infrastructure and Overall physical progress of the project shall be recorded. 3. Whether livelihood linkages have been ensured?. This information shall be recorded.
  • 58. ANNEXURE 3 The Consultant Activity Format 1 1 Whether Contract for Social Amenities (i.e. Community centre, Livelihood centre etc.) have been awarded? This information shall be obtained from the sanctioned DPR, contractor’s agreement, meeting with ULB and physical progress observed of social amenities during site visit. 1 i) If no, Time line for award of contract for Social Amenities. If no social amenities have been provided in the sanctioned DPR, contractor’s agreement than meeting with the ULB shall be done to find information regarding timeline / schedule for the tender/ contract for Social Amenities. 1ii) If Yes, State the progress of work in % a. Community centre b. Livelihood centre c. Informal Sector Market d. Any other component (as per sanctioned components) *(Provide detailed report in Annexure-2A) This information shall be obtained from the sanctioned DPR, contractor’s agreement, meeting with ULB and physical progress observed of social amenities during site visit. G. SOCIAL INFRASTRUCTURE COMPONENTS
  • 59. ANNEXURE 3 The Consultant Activity Format 1 2 iii) Deviation if any as per sanctioned DPR This information shall be obtained by comparing financial and physical progress recorded by the ULB, sanctioned DPR, contractor’s agreement and observations in the site during site visit. 3 Comments on quality of construction of Social Amenities Observations on quality of construction of Infrastructure works shall be recorded during site visit. 4 Whether livelihood linkages have been ensured? This information shall be obtained from, sanctioned DPR, the ULB and beneficiaries. 5 Overall physical progress of Social Infrastructure (in %) This information shall be obtained from physical progress observed during site visit, sanctioned DPR and contractor’s agreement. 6 Overall physical progress of the project (in %) This information shall be obtained from physical progress observed during site visit, sanctioned DPR and contractor’s agreement. G. SOCIAL INFRASTRUCTURE COMPONENTS
  • 60. ANNEXURE 3 Format 1 H. Physical Progress Of The Project/Packages 1. Information about an approved program / schedule of work and it's availablity at site office shall be recorded. 2. Overall Percentage progress at the time of inspection visa-vis expected as per contract and the approved program / schedule shall be recored. 3. Details of milestones as per contract vis-à-vis their achievement any delay and a reasons for delay shall be recorded.
  • 61. ANNEXURE 3 The Consultant Activity Format 1 1 Is there an approved program / schedule of work & whether the same is available at site office During site visit documents shall be checked to see availability of the approved program / schedule of work. If the approved program / schedule of work doesn’t available in the site than the issue shall be recorded and reported. If the approved program / schedule of work is available than that shall be checked in comparison to the progress of the site to ascertain whether progress is at per or behind or ahead of the approved program / schedule of work. 2 Overall Percentage progress at the time of inspection visa-vis expected as per contract. For this contractor’s contract approved program / schedule of work and progress of work at site shall be compared in percentage. 3 Package wise % of progress (Attach package-wise Annexure) 4 Details of milestones as per contract vis-à- vis their achievement Meeting shall be needed with ULB and information regarding contractor’s contract and packages shall be obtained for details of milestones. Milestones achieved and milestones yet to be achieved comparison to progress as per schedule shall be recorded. 5 Reasons for delay If and milestone or progress is found behind the schedule, then reasons shall be found in documents of previous progress reports submitted so far, hindrance register, procurement records etc. Actual reasons shall be recorded carefully and impartially. H. PHYSICAL PROGRESS OF THE PROJECT/PACKAGES
  • 62. ANNEXURE 3 Format 1 I. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. In Lakh) 1. Information about sanctioned fund for entire project shall be collected from senctioned DPR, contractor's contract from ULBs and SUDA. 2. Information about funds received up to date shall be collected from ULBs and SUDA. 3. Up-to date expenditure information shall be collected from ULBs and SUDA. 4. Amount of funds Utilized (out of received) shall be collected from ULBs and SUDA. 5. Amount of Expenditure by ULB (ULB Contribution + Beneficiaries contribution) shall be collected from ULBs and SUDA and compiled. 6. Balance funds Expected/due from various stakeholders shall be compiled based on data collected so far. 7. Package wise Expenditure shall be compiled based on data collected so far. 8. Over All Financial Progress in %= Total Expenditure / Total of Tendered Amount x100 shall be compiled based on data collected so far. 9. An analysis shall be prepared based on financial data collected so far, contractor’s agreements bills of contractors, actual measurements entered in measurement books, progress reports and approved schedule and progress of work against approved schedule. The analysis shall disclose any delay and cause of delay in work.
  • 63. ANNEXURE 3 The Consultant Activity Format 1 1 Sanctioned fund for entire project. Information about project’s sanctioned fund shall be collected from ULBs and SUDA. 2 Amount of funds received up to date Information about funds received shall be collected from ULBs and SUDA. 3 Up-to date Expenditure Information about Up-to date expenditure shall be collected from ULBs and SUDA. 4 Amount of funds Utilized (out of received) Information about funds utilized shall be collected from ULBs and SUDA. 5 Amount of Expenditure by ULB (ULB Contribution + Beneficiaries contribution) This information shall be collected from ULBs and SUDA and compiled. I. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. in Lakh)
  • 64. ANNEXURE 3 The Consultant Activity Format 1 6 Balance funds Expected/due from various stakeholders This information shall be compiled based on data collected so far. 7 Package wise Expenditure This information shall be compiled based on data collected so far. 8 Over All Financial Progress %= Total Expenditure / Total of Tendered Amount x100 This information shall be compiled based on data collected so far. 9 Whether the work is delayed for non payment of any pending bills after construction (to be specified)? An analysis shall be prepared based on financial data collected so far, contractor’s agreements bills of contractors, actual measurements entered in measurement books, progress reports and approved schedule and progress of work against approved schedule. The analysis shall disclose any delay and cause of delay. I. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. in Lakh)
  • 65. 1 Are there any major variation because of: To find variation fallowing documents shall be compared: i. Specifications Specification as per contractor’s agreement, approved drawings. Specification of work actually executed in the site, various test reports, procurement reports, site order book etc. ii. Quality Specification as per contractor’s agreement, approved drawings, various applicable codes. Quality test reports, site observations and other site documents. iii. Quantity Contractor’s agreement, approved drawings and design including working drawings, bill of quality, DPR, sanctioned project details. Measurements taken in site, physical progress reports, bills of contractor, material registers, any revised drawings etc. iv. Designs (Architectural / Structural) Approved drawings and design including working drawings Any revised drawing, site order book , other site documents, any instructions of authorities for change in architectural and Structural aspects of the project, actual observations in site. v. Period of Construction (Increase/Decrease) Approved programme, schedule and milestones. actual progress reports marked in approved programme, schedule and milestones ANNEXURE 3 Format 1 J. VARIATIONS w.r.t. SANCTIONED COVENNANTS
  • 66. ANNEXURE 3 Format 1 1 Whether there is cost variation? If yes what are the reasons: i. Change in Quantities ii. New/Additional Items of work iii. Price Escalation Any other (to be specified) 1 Whether there is time overrun? If yes what are the reasons: i. Change in Quantities ii. New/Additional Items of work iii. Price Escalation Any other (to be specified) iv. Delay in actual start of work by the Contractor v. Delay in procurement of material ( give reasons) vi. Delay due to lack of interdepartmental coordination Any other (to be specified) Any other (to be specified) The Consultant Activity K. COST VARIATION and TIME-OVERRUNS To find variation fallowing documents shall be compared: Cost Variation: Contractor’s agreement, approved drawings and design including working drawings, bill of qualtity, DPR, sanctioned project details. Measurements taken in site, physical progress reports, bills of contractor, material registers, any revisited drawings etc. 2 Time Overruns: To find variation fallowing documents shall be compared: 2 Contractor’s agreement, approved drawings and design including working drawings, bill of quality, DPR, sanctioned project details. Measurements taken in site, physical progress reports, bills of contractor, material registers, any revised drawings etc.
  • 67. ANNEXURE 3 Format 1 1 Physical Progress After analysing data if physical progress found behind the schedule, the revised schedule shall be recommended with consent of ULB and the contractor for balance work to achieve subsequent milestones within time. Additional resources of manpower, material, tools, plants and machinery needed to be deployed shall be ensured. 2 Financial Progress Financial data shall be analysed to find out:- Whether cash flow of the project is behind the schedule due to any hindrances. Whether financial progress if behind the schedule due to physical progress is behind the schedule. Probable reasons of non-utilization or underutilization of fund is there. Once reasons of poor performance of financial progress found, recommendation to improve cause of reasons can be made. 3 Quality management Quality of the work depends on quality of material, methodologies, workmanship, equipments, tools and plants. If any deviation from standards and applicable codes found that recommendations to improve quality on shall be made. 4 Comments and suggestions of TPQMA on above Continuous and effective communication between stakeholders is needed for improve progress and quality. The Consultant Activity L. REMEDIAL MEASURES TO IMPROVE PROGRESS AND QUALITY Undertaken by Implementation agency to improve the:
  • 68. ANNEXURE 3 Format 1 1 ( To be specified) In case of any litigation or court case, information shall be collected from legal officer and reports and suggestion to improve project implementation shall be made. 2 The Consultant Activity M. COURT CASES AND LITIGATIONS
  • 69. ANNEXURE 3 Format 1 1 Feedback of beneficiaries regarding provision of Physical & Social infrastructure. Feedback from beneficiaries shall be taken with coordination of the ULB. List of beneficiaries including address and telephone numbers shall be collected to contact beneficiaries. 2 Any specific observation by the beneficiary This observation shall be recorded carefully. Overall observation on the project (with adequate photographs covering project to a large extent including quality issues as applicable) 1. Critical observations 2. Action suggested by TPQMA to SLNA and IA Action taken report on previous report: i. Observations of TPQMA ii Action suggested by TPQMA iv Whether TPQMA is satisfied with the action taken by IA 4 TPQMA’s Overview of the Project (in 400-500 words) in a separate sheet Overall summery of the project and it’s status shall be written. Action and fallow on observations and comment and action recommended shall be reported previously to SLNA shall be reported in this section. 3 3 Observations and comment and action recommended shall be reported to SLNA. The Consultant Activity N. OTHERS
  • 70. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 GSR/UGSR 2 ELSR/OHT 3 Intake-Jack-well 4 WTP 5 Pipelines 6 Pump sets. 7 Rain Water Harvesting pits 8 Sump 9 Tube wells The Consultant Activity B. CIVIC INFRASTRUCTURE WORKS: If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment. a. WATER SUPPLY: This information shall be as per site visit observation This information shall be as per site visit observation
  • 71. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 Sewer Trap Connect. Chamber 2 Collection network pipes 3 Inspection chambers 4 Sewerage pump Stn (SPS) 5 SPS to STP Pipeline 6 STP 7 Septic tank 8 Soak-pit B. CIVIC INFRASRUCTURE WORKS: b. SEWERAGE: If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment. This information shall be as per site visit observation This information shall be as per site visit observation The Consultant Activity
  • 72. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 Drains 2 Open channel 3 Closed RCC Pipes 4 In-Situ RCC Box-pipes 5 Type of Grating/Jali 6 Inspection Chambers 7 Point of disposal (Nallah, Canal, River, Creek) This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment. c. STORM WATER DRAINS: This information shall be as per site visit observation The Consultant Activity B. CIVIC INFRASRUCTURE WORKS:
  • 73. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 Roads 2 Pavements 3 Jogging track 4 Plantation 5 Restoration 6 Culverts ( Masonry / RCC) The Consultant Activity This information shall be as per site visit observation This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment. B. CIVIC INFRASRUCTURE WORKS: d. ROADS & CULVERTS:
  • 74. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 H.T. Supply lines 2 L.T. Supply lines 3 Transformer 4 Street Lighting The Consultant Activity B. CIVIC INFRASRUCTURE WORKS: e. ELECTRIFICATION: This information shall be as per site visit observation This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment.
  • 75. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 S. W. Collection System 2 Dust Bins/Containers 3 S. W. Transport System 4 Temp. store yards 5 S.W. Disposal area This information shall be as per site visit observation This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment. The Consultant Activity B. CIVIC INFRASRUCTURE WORKS: f. SOLID WASTE MANAGEMENT:
  • 76. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 Compound/Boundary wall 2 Entrance Gate 1 Retaining wall 2 Any other (to be specified) The Consultant Activity B. CIVIC INFRASRUCTURE WORKS: This information shall be as per site visit observation This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. This information shall be as per site visit observation This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. h. MISCELLANEOUS: g. COMPOUND WALL:
  • 77. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 Community Centre 2 Livelihood Centre 3 Any Other 1 Public Health Centre 2 Anganwadi 3 Primary School 4 Secondary School 5 Higher Secondary School This information shall be as per site visit observation This information shall be as per site visit observation This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment. This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment. The Consultant Activity C. REPORT ON SOCIAL INFRASRUCTURE WORKS: a. COMMUNITY FACILITIES: b. HEALTH /EDUCATION FACILITIES:
  • 78. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 Vegetable Market 2 Meat-Fish Market 3 Medical Store 4 Any Other 1 2 3 d. ANY OTHER ( To be specified) This information shall be as per site visit observation This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment. The Consultant Activity C. REPORT ON SOCIAL INFRASRUCTURE WORKS: c. INFORMAL SECTOR MARKET This information shall be as per site visit observation This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment.
  • 79. Format 2 A S. No. Component Whether in progress (Yes / No) Whether Inspected (Yes / No) Comments 1 Earthwork 2 Concrete work (Sub- structure /up to plinth) 3 RCC work (Above plinth / Super Structure) 4 Brick / Block work 5 Stonework 6 Marble work 7 Wood work 8 Steel work 9 Flooring 10 Roofing 11 Finishing 12 Internal services 13 External Services This information shall be as per site visit observation This information shall be as per site visit observation If the work is being completed before site visit than inspection not done comment shall appear. If the work is in progress during the site visit than in the work in progress comment shall appear. Any comment in quality, execution and safety of the work shall appear in comment. A. BUILDING WORK: DETAILED REPORT ON PROPOSED WORKS The Consultant Activity
  • 80. Format 4 The Consultant Activity Name of TPQM Agency Name of the consultant shall be entered Date of Visit Current Visit No. Previous visit with date Current and previous dates of visits shall be entered as visit happens however those dates shall be scheduled for entire work as soon as inspection report completed and approved by the client. Third Party Quality Monitoring Report of ISSR/AHP projects under PMAY
  • 81. Format 4 The Consultant Activity 1 Name of the State /UT: 2 Name of the City: 3 Name of Project: 4 Project Code: 5 Implementing Agency/ ULB A. PARTICULARS OF PROJECT All these data are fixed, hence can be entered before site visit.
  • 82. Format 4 The Consultant Activity 6 Location of the Project ( Slum name, Ward etc. as applicable) This data shall be collected from ULB and Inspection report. 7 Type of Project :(i) BLC (New Construction) (ii) BLC (Enhancement) 8 No. of EWS Houses in the project 9 Date of Approval by SLSMC This data shall be collected from ULB and Inspection report. This data may not change after first visit. A. PARTICULARS OF PROJECT
  • 83. Format 4 Central share State share ULB/ Implementing agency share Beneficiary share Total 11 Date of sanction of 1stinstalment of central assistance by CSMC 12 Duration of Project The Consultant Activity A. PARTICULARS OF PROJECT Above data can be collected from SUDA i.e. format 7 A or 7 B of the guideline as submitted and sanctioned DPR and project This data can be collected from approved project DPR, agreement of contractor. 10 Approved Project Cost (Rs. Lakh): This data can be collected from SUDA.
  • 84. Format 4 Scheduled Actual This date shall be entered from contractor’s agreement, work order and schedule submitted by the contractor This date shall be collected from site and ULB Scheduled Actual This date shall be entered from contractor’s agreement, work order and schedule submitted by the contractor This date shall be collected from site and ULB 13 Date of commencement 14 Date of completion A. PARTICULARS OF PROJECT The Consultant Activity
  • 85. Format 4 The Consultant Activity 1 2 Name and contact details of Engineers of the consultant who visited the site. 16 Name of State representative present during visit Name of State representative who visited the site. 17 Name of ULB representative present during visit Name of ULB representative (SE/ AE/ EE) 18 Name of Community representative present during visit The consultant shall request ULB regarding presence of any community representative. 15 Inspection undertaken by (Name) With Contact Details: A. PARTICULARS OF PROJECT
  • 86. Format 4 The Consultant Activity 19 Whether list of Beneficiaries finalised/ partially finalised/ not finalised This list shall be checked in first visit and observation shall be recorded in the site visit report. If list be found partially or not finalized a follow-on actions and recommendations shall be made and progress shall be reviewed on / before next visit. 20 If finalised, whether uploaded in PMAY MIS To check PMAY MIS the consultant shall request authorization 21 State any deviation from sanctioned DPR in terms of number of houses or size or location or Layout Data of sanctioned DPR shall be collected from SUDA any deviation from this shall be checked in approved layout drawing present in the site and actual progress in the site. 22 Any other comment The consultant shall comment any fallow on action recommendation. A. PARTICULARS OF PROJECT
  • 87. ANNEXURE 3 The Consultant Activity Format 4 1 Whether ULB/ State have organized workshop/ training programmes to educate the beneficiaries about quality, construction methods, adherence to disaster resistant technologies etc. This information shall be recorded in consultation with the ULB and SUDA. 2 Whether testing facilities to check quality of material is available? If testing facilities available than list of equipment shall be prepared including celebration reports and standards of equipments. 3 Whether regular tests of materials and construction products tests of materials are being done from accredited labs also? This information shall be checked in documents related to material testing available in site during site visit and any record available in the ULB. B. QUALITY ASSURANCE IN THE PROJECT
  • 88. ANNEXURE 3 The Consultant Activity Format 1 (i) Whether the structural Designs are approved / Proof checked by competent Authority (ii) Name of the approving authority for structural design. (iii) Whether the statuary certificate for disaster resistance design and compliance of codal provision is endorsed by the structural designer on the structural drawings fit for execution, Specially in case of multi- storeyed construction. (iv) The work is being executed as per the approved drawings fit for execution. C. QUALITY ASSURANCE IN THE PROJECT 4 All structural drawing and design documents shall be checked for the issues mentioned. Completed, ongoing and upcoming work in site shall be compared with the drawings for adequacy and fitness for execution. In any case fallow on action recommendation shall be made.
  • 89. ANNEXURE 3 The Consultant Activity Format 1 5 Whether the Inspection Registers, Site order book and Quality control Test registers are maintained and endorsed by the Engineer–in- charge? All these documents shall be checked for proper entries and fallow up. Detailed observation and fallow on action recommendation shall be made. 6 Whether cement, steel, aggregates etc. being used in the work, got tested before use? Material testing documents shall be checked. 7 Whether manufacturer test certificate for cement, steel, pipes etc. have been obtained with supply and records are being maintained? Observation regarding this issue shall be recorded fallow on action recommendation shall be made. 8 Whether Cement is free from lumps and is stacked properly to prevent contact with moisture? This shall be checked during site visit. C. QUALITY ASSURANCE IN THE PROJECT
  • 90. ANNEXURE 3 The Consultant Activity Format 1 9 Whether soil investigations of the site proper have been done before the structural design and soil parameters have been accounted for in the structural design/ drawings? If yes, attach copy of soil investigation report. Structural design/ drawings and soil investigation reports shall be compared. Comparison report and any recommendation shall be made including soil investigation report. 10 Whether centring /shuttering is checked for staging & propping, line & level, dimensions, cleaning etc. and its quality approved before each stage and record maintained. For this issue NBC code and contractor’s agreement shall be fallowed. Information related to specification and load bearing capacity of centring /shuttering and staging shall be ascertained from the contractor as well as methodology for the work. Checking on methodology for the work shall be done for safety and acceptable tolerance in line & level, dimensions. Records regarding this issue shall be checked and recorded. Fallow on action recommendation shall be done. 11 Specific control on RCC work like: mixing by full bag capacity hopper fed mixer, control of slump, placing/ compaction with vibrator. (proportioning with boxes not permitted) For this issue contractor’s agreement, item specification and NBC code shall be studied for manufacturing of concrete. Observation and any action follow on recommendation shall be done. C. QUALITY ASSURANCE IN THE PROJECT
  • 91. ANNEXURE 3 The Consultant Activity Format 1 12 Whether cement register is maintained and checked at site. Comment on method of stacking. Previous dated entries of cement register shall be checked as per progress of work and theoretical consumption of cement. 13 Whether concrete mix is nominal or design mix? (Nominal mix not permitted for quality concrete). Concrete mix shall be checked in site. Concrete mix reference shall be checked in contractor’s agreement, structural drawing and design, specification, IS codes and NBC codes. Relevant test shall be checked. Observation shall be recorded. 14 What is the Mode of Concrete mixing (batch mix/ manual)? In case of manual mixing, whether mixing is by weight or by volume of ingredients? (Volumetric mixing not permitted). Mode of concrete mixing shall be checked and recorded. Follow on action recommendation shall be made. 15 Whether Mixer/Vibrator as specified is available at site with adequate means to run them during concreting? Mixer/Vibrator as specified shall be checked. Their working shall be checked. Inspection and inquiry shall be done to ensure proper working. In case of noncompliance follow on action recommendation shall be made. C. QUALITY ASSURANCE IN THE PROJECT
  • 92. ANNEXURE 3 The Consultant Activity Format 1 16 Whether Surface of reinforcement is clean and free from rust? 17 Whether potable water is used for construction ? 18 Whether proper water / cement ratio has been ensured? 19 Whether the concrete being cured adequately as per requirements? 20 Whether bricks are well burnt, of rectangular shape, with sharp edges, free from cracks and of correct size? This information shall be checked during site visit. C. QUALITY ASSURANCE IN THE PROJECT
  • 93. ANNEXURE 3 The Consultant Activity Format 1 Whether i) Execution of Depth & width of Foundation is as per drawing/ adequate & bottom levelled ii) Plinth height is as per drawing/adequate iii) Horizontal bands (as applicable) have been provided 22 Whether quality has been checked by TPQMA/ State agency? If yes, details thereof? This information shall be checked in site order book and any other relevent document during site visit. This information shall be checked during site visit. C. QUALITY ASSURANCE IN THE PROJECT 21
  • 94. ANNEXURE 3 The Consultant Activity Format 4 23 Quality of work and workmanship, Comments on Workers shall be interested to ascertain skill and knowledge level. Workmanship shall be checked during work in progress. Fallow on action recommendation shall be made. 24 Whether provision has been made for Service lines (Electrical, Water Supply, Sanitation etc.) Observation and inquiry shall be made regarding this issue and shall be reported. 25 Whether floor slope (especially) in bath, WC, kitchen, terrace and balcony etc. are proper? Floor slope shall be checked as per drawings and codes. In case of non-conformance rework shall be suggested as per contractor’s agreement and applicable codes. 26 Whether Adequate plinth height (above the general ground level) is provided to the ground floor of the building to avoid possibility of rainwater and reptiles in the building. Drawings and site shall be checked for this issue. Proposed level of road in front of the block / dwelling unit shall be checked for this issue. As per checking proper recommendation shall be made. B. QUALITY ASSURANCE IN THE PROJECT
  • 95. ANNEXURE 3 The Consultant Activity Format 4 27 Whether dampness/ leakages noticed? If yes, state location and probable reasons. Reason of dampness/leakages shall be carefully checked and fallow on action recommendation shall be made. 28 Whether remedial measures are undertaken by/ ULB to stop Dampness & Leakages? If any. There shall be inquiry for remedial measures for prevention of dampness and leakages. There shall be an inquiry regarding actions taken on fallow on action recommendation on previous site visits. In case of noncompliance a detailed report shall be prepared with several alternate recommendations. 29 Whether disaster resistant features have been incorporated? Disaster resistance features shall be checked as per applicable codes. A proper report shall be made for this issue. 30 Any other comments Any important observation which not covered in this format shall be entered in this heading. Minimum 500 words (To be enclosed separately) Overall assesement shall consist any relevent observation whuch is not covered in the formats and summery of information gathered. Recommendations shall be part of the assessement. 31 Report on Overall assessment of quality B. QUALITY ASSURANCE IN THE PROJECT
  • 96. ANNEXURE 3 The Consultant Activity Format 4 1 Numbers of houses sanctioned in the project This information shall be obtained from approved DPR. 2 Numbers of houses Completed This information shall be obtained from contract of the contractor, approved DPR , ULB, progress report and site visit. 3 Numbers of houses in progress This information shall be obtained from contract of the contractor, approved DPR and ULB. Stages of Progress : ( Specify No. of Units) i) Foundation/ Plinth level (Nos.) ii. Lintel level (Nos.) iii. Roof level (Nos.) iv. Finishing level (Nos.) v. Total units completed (Nos.) C. PROGRESS - HOUSING COMPONENTS This information shall be obtained and recoreded during site visit. 4
  • 97. ANNEXURE 3 The Consultant Activity Format 4 5 Numbers of houses not started This information shall be obtained and recoreded during site visit and other relevent data. 6 Reason for non-starter of houses, if any This information shall be obtained and recoreded during site visit,other relevent data and meeting with the ULB, SUDA and the contractor. 7 Numbers of houses occupied by the Beneficiaries This information shall be obtained and recoreded during site visit and the ULB. 8 Reasons for Non-occupation of houses (If any)-specific reasons to be given This information shall be obtained and recoreded during site visit, the ULB and meeting with beneficieries. C. PROGRESS - HOUSING COMPONENTS
  • 98. ANNEXURE 3 Format 4 9 Size of Unit (Carpet Area) Sanctioned As per Implementation 10 Overall physical progress of Housing (in %) This information shall be obtained from the approved DPR This information shall be obtained during site visit. 11 Whether the progress of houses has been ensured through geo-tagged photographs at various construction level? 12 Whether DBT of fund to individual beneficiary is ensured in the project? 13 Whether the building plan(s) conform to NBC norms? 14 Whether authenticated building plans and revisions if any, are available? 15 Deviation, if any 16 Any other comment This information shall be obtained during site vist, comparison of drawings approved and executed in site, the approved DPR and revisons of drawings and meeting with the ULB. If any deviation found than the deviation, probable reason of deviation, its implication shall be recorded. Any relevent observation which doesnot be covered in other points shall be recorded in this point. For this data from ULB shall be analyzed and report shall be prepared. This information shall be obtained during site vist, comparison of drawings approved and executed in site, the approved DPR and NBC codes applicable. C. PROGRESS - HOUSING COMPONENTS The Consultant Activity This data shall be collected from the consultant responcible for geo-tagging, ULB and SUDA.
  • 99. ANNEXURE 3 The Consultant Activity Format 4 1 Whether Contract for infrastructure components (i.e. water supply, Sewerage, Drainage, Roads, SWM etc.) have been awarded? The approved DPR and contract of the contractor shall be checked to obtain this information. 2 Whether the Existing/proposed infrastructure components are independent and/or integrated with city level infrastructure? The approved DPR, contract of the contractor, city level infrastracture in city development plan and other schemes with ULB consultation shall be checked to obtain this information. 3 Any other comments Any other relevent observation shall be recoded D. CIVIC INFRASTRUCTURE
  • 100. ANNEXURE 3 The Consultant Activity Format 4 1 Sanctioned fund for entire project. Information about project’s sanctioned fund shall be collected from ULBs and SUDA. 2 Amount of funds received up to date Information about funds received shall be collected from ULBs and SUDA. 3 Up-to date Expenditure Information about Up-to date expenditure shall be collected from ULBs and SUDA. 4 Amount of funds Utilized (out of received) Information about funds utilized shall be collected from ULBs and SUDA. 5 Amount of Expenditure by ULB This information shall be collected from ULBs and SUDA and compiled. F. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. in Lakh)
  • 101. ANNEXURE 3 The Consultant Activity Format 4 6 Amount of Expenditure by Beneficiaries This information shall be collected from ULBs and Beneficiaries and compiled. 7 Balance funds Expected/due from various stakeholders This information shall be compiled based on data collected so far. F. FINANCIAL PROGRESS & FUND UTILIZATION (Rs. in Lakh)
  • 102. ANNEXURE 3 Format 4 Contractor’s agreement, approved drawings and design including working drawings, bill of qualtity, DPR, senctioned project details. Measurements taken in site, physical progress reports, bills of contractor, material registers, any revisied drawings etc. Contractor’s agreement, approved drawings and design including working drawings, bill of qualtity, DPR, senctioned project details. Measurements taken in site, physical progress reports, bills of contractor, material registers, any revisied drawings etc. To find variation fallowing documents shall be compared: 1 Whether there is time overrun? If yes, what are the reasons? To find variation fallowing documents shall be compared: 1 Whether there is cost variation? If yes, what are the reasons? G. COST VARIATION and TIME-OVERRUNS Cost variation: The Consultant Activity Time Overruns:
  • 103. ANNEXURE 3 Format 4 1 Physical Progress After analysing data if physical progress found behind the schedule, the revised schedule shall be recommended with consent of ULB and the contractor for balance work to achieve subsequent milestones within time. Additional resources of manpower, material, tools, plants and machinery needed to be deployed shall be ensured. 2 Financial Progress Financial data shall be analysed to find out:- Whether cash flow of the project is behind the schedule due to any hindrances. Whether financial progress if behind the schedule due to physical progress is behind the schedule. Probable reasons of non-utilization or underutilization of fund is there. Once reasons of poor performance of financial progress found, recommendation to improve cause of reasons can be made. 3 Quality management Quality of the work depends on quality of material, methodologies, workmanship, equipments, tools and plants. If any deviation from standards and applicable codes found that recommendations to improve quality on shall be made. 4 Comments and suggestions of TPQMA on above Continuous and effective communication between stakeholders is needed for improve progress and quality. Undertaken by Implementation agency to improve the: The Consultant Activity H. REMEDIAL MEASURES TO IMPROVE PROGRESS AND QUALITY
  • 104. ANNEXURE 3 Format 4 1 ( To be specified) In case of any litigation or court case, information shall be collected from legal officer and reports and suggestion to improve project implementation shall be made. The Consultant Activity I. COURT CASES AND LITIGATIONS
  • 105. ANNEXURE 3 Format 4 1 Any innovative/ cost effective/ green technology has been used The consultant shall see all project related documents and site and record relevent information. 2 Feedback of beneficiaries regarding provision of Physical & Social infrastructure: ULB and beneficiaries shall be contacted for this feedback. 3 Reasons for delay in completion of housing and Infrastructure, if any: Reason shall ascertained by analyzing schedule and progress reports. 4 Any specific observation by the beneficiary Beneficieries comment and observation shall be carefully recorded. Overall observation on the project (with adequate photographs covering project to a large extent including quality issues as applicable) 1. Critical observations 2. Action suggested by TPQMA to SLNA and IA Action taken report on previous report: i. Observations of TPQMA ii Action suggested by TPQMA iii. Action taken by Beneficiaries/ IA (Implementation Agency) iv Whether TPQMA is satisfied with the action taken by IA 7 TPQMA’s Overview of the Project (in 400-500 words) in a separate sheet Overall summery of the project and it’s status shall be written. Observations and comment and action recommended shall be reported to SLNA. 5 Action and fallow on observations and comment and action recommended shall be reported previously to SLNA shall be reported in this section. 6 The Consultant Activity J. OTHERS
  • 106. SUMMERY In summery the consultant shall use expert knowledge to explain fully proposed, ongoing, and planned quality related issues. The consultant shall brief all stakeholders best quality practices and implementation. The consultant shall assess and report quality of man, materials tools, and plants. The consultant shall always suggest fallow on action and recommendation to deal with any negative as well as positive quality related issues. The consultant shall report actual and useable report of the projects in the cluster area. The consultant shall plan its activities as per objectives of the client. The consultant shall be source for knowledge and expertise. The consultant shall be aware of various guidelines, circulers and instructions of central government and state government authorities.