SlideShare a Scribd company logo
1
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
Part 2: EMTP Modeling and Case Studies
David D. Shipp, PE
Fellow, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
Thomas J. Dionise, PE
Senior Member, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
2
2
Transient Analysis Tools
• Electromagnetic Transients Program (EMTP)
• Developed by Hermann Dommel brought to BPA
• Major contributors: Scott Meyer & Dr. Liu at BPA
• Alternative Transients Program (ATP)
• Alternative to commercialized EMTP
• Free to all if agree not to commercialize it
• EMTP-RV
• PSCAD EMT/DC
2
3
3
ATP
• ATP Draw interface
• 3-phase modeling
• Solution method - Trapezoidal integration
• Robust for wide variety of modeling needs
• Extensive library of models
• Many options and features
4
4
Source Model
• “3-phase wye cosine”
• Resistance in ohms
• Inductance in mili-Henries
• Source Impedance
• Z1 and X/R
• Z0 and X/R
SYSTEM SOURCE
AT 13.8 KV
XUTIL
RUTIL
VUTIL
UN
U UT
3
5
5
Cable Model
• “Pi Model”
• Resistance in ohms
• Inductance in mili-Henries
• Cable charging in micro-Farads
• ½ charging on sending end
• ½ charning on receiving end
• Multiple pi models in some cases
CABLE
13.8KV
C1 LCABLE
RCABLE C2
C/2C/2
6
6
Breaker Model
• “Switch”
• Time dependent switch
• Open or close at a specific time
• Opens at current zero unless specify otherwise
• Current dependent switch
• Needed for current chopping
• Define current at which to open switch
• Independent Poles (A, B and C independent)
• Data request
• Vacuum or SF6 breaker nameplate
• Current chop (ask manufacturer)
• Transient Recovery Voltage Ratings – T2, E2 and RRV
VCB
BKR
4
7
7
Transformer Model
• “Three Phase Model”
• Resistance in ohms
• Inductance in mili-Henries
• Magnetizing current
• Winding capacitance
• CH and CL for dry-types
• CHL for oil-filled
• More detailed modeling
• Saturation
• Hysteresis
• Data Request
• %Z and X/R, MVA
• BIL
TRANSFORMER
RLRG
LTRAN RTRANT1 T2
CH CL
N:1
8
8
Complete System Model
TRANSFORMER
RLRG
LTRAN
RTRANT1 T2
CH CL
N:1
CABLE
13.8KV
C1 LCABLE
RCABLE C2
C/2C/2
SYSTEM SOURCE
AT 13.8 KV
XUTIL
RUTIL
VUTIL
UN
U UT
VCB
BKR
5
9
9
Time Step
• Time Step – Integration Time Step
• Choice depends on frequency of expected transient
• Too large – miss high frequency effects
• Too small – excessive simulation times
• Nyquist Criteria
• Minimum sample rate = 2 x frequency
• Example 10-20KHz ring for VCB transient
10
10
Switching Transient Simulations
• Switching transient simulations
• EMTP and model requirements
• Case studies
• Data Center
• Ferry Propulsion
• Laddle Melt Furnace
• Successful techniques/solutions
6
11
11
Ferry Propulsion
Highlights
• 60K passengers per day
• 20M passengers per year
• 4160V distribution
• 3 x 2865kW diesel gens
• 2 x 1865KW forward propulsion motors
• 2 x 1865KW reverse propulsion
12
12
Problem
• Forward propulsion drives ferry
• Upon reaching dock, reverse propulsion stops ferry
• July 1, 2009, reverse propulsion was lost entering dock
• lost power and hit a pier at full speed
• one serious injury and nine minor injuries
• 750 to 800 passengers were aboard
• impact did not send any passengers overboard
• 1185KVA rectifier transformer failed on reverse propulsion
motor
• Evidence of insulation failure on first few turns of primary
winding
• Investigation into source of such failure VCB switching
7
13
13
Ferry - Oneline
Vacuum
Breaker
Short
Cable
Dry-Type
Transformer
Forward Reverse
14
14
Ferry – Electrical Highlights
• 3 x 2865kW diesel generators
• 4160V, 3-bus system
• Vacuum circuit breakers – 630A mains, ties,
feeders
• 2 x 1865kW motors (forward propulsion)
• 2 x 1865kW motors (reverse propulsion)
• 8 x 1185KVA dry-type transformers, 30kV BIL
• 3-winding rectifier transformers
• 12-pulse effective (6-pulse VFD per winding)
• Feeder cable lengths of 50 feet each
8
15
15
Worst Case Scenarios
• Feeder cable lengths of 50 feet
• Each 1185KVA transformer has one 4160V feeder
• Need to examine both feeders for each transformer
• “Worst Case” Switching Transient Simulations
• Close 4160V VCB to transf. with 50ft. cable (model validation)
• Close 4160V VCB to transf. with 50ft. cable (re-ignition)
• Open 4160V VCB to transf. with 50ft. cable (current chop)
• Repeat each case with Snubber
16
16
Measurements
Transient Overvoltages at Primary of Rectifier Transformer – VCB Closes
9
17
17
Study Cases
• Case 1 – Closing the 4.16 kV feeder breaker feeding the three
winding rectifier transformer with the distance of 50 feet.
Simulated to match the Siemens measurements to ensure that
the computer model is accurate. (Model Validation)
• Case 2 – Same as Case 1, except with the RC snubber.
• Case 3 - Closing the 4.16 kV feeder breaker feeding the three
winding rectifier transformer, then the 4.16 kV feeder breaker
opens during the inrush current. Shows the possibility of the
vacuum breaker re-ignition. (Re-ignition)
• Case 4 - Same as Case 3, except with the RC snubber.
• Case 5 - Open the 4.16 kV feeder breaker feeding the three
winding rectifier transformer under the light load condition.
(Current Chop)
• Case 6 – Same as Case 5, except with the RC snubber.
18
18
Case 1 – Model Validation
Transformer primary voltage
V max of 4.96kV < 30kV BIL
Oscillation of 20,203Hz > 1000Hz
10
19
19
Case 2 – Valid Model with Snubber
Transformer primary voltage
V max of 3.982kV < 30kV BIL
Oscillation of < 1000Hz
20
20
Case 3 – Re-ignition
Transient Recovery Voltage (TRV) at VCB
11
21
21
Case 4 – Re-ignition with Snubber
Transient Recovery Voltage (TRV) at VCB
22
22
Case 5 – Current Chop
Transformer primary voltage
V max of 31.9kV > 30kV BIL
Oscillation of 958Hz ~ 1000Hz
12
23
23
Case 6 – Current Chop with Snubber
Transformer primary voltage
V max of 8.9kV < 30kV BIL
Oscillation of 299Hz < 1000Hz
24
24
Summary of Current Chop Cases
13
25
25
Summary of Re-Ignition Cases
26
26
Recommendations
• Install snubber at primary of each 1185KVA
rectifier transformer
• 40ohm resistor
• Non-inductive
• Peak voltage – 6 kVpeak
• Peak energy – 2100 Joules
• Average power – 190 Watt
• 0.5uF capacitor
• Rated voltage - 4.16kV
14
27
27
Data Center
Highlights
• Tier III
• LEEDS Certified
• 12.5MVA Capacity
• 13.2KV Ring Bus
28
28
Data Center - Oneline
Vacuum
Breaker
Short
Cable
Cast-Coil
Transformer
15
29
29
Data Center – Electrical Highlights
• 2 x 24.9 kV lines from Factory Shoals and Buzzard
Roast
• 2 x 12.5 MVA transformers
• 13.2 kV “ring-bus” configuration
• MSA and MSB and generator bus GPS
• Vacuum circuit breakers – 600A mains & ties, 200A feeders
• 3 x 2250 KW generators
• 6 x 3750KVA cast coil transformers, 90kV BIL
• 3 x DE Subs CSA, CSB and CSC
• 3 x SE Subs MDSA, MDSB and MLB
• Feeder cable lengths vary from 109 to 249 Feet
30
30
Worst Case Scenario
• Feeder cable lengths vary from 109 to 249 Feet
• Each 3750KVA transformer has two 13.2kV feeders
• Need to examine both feeders for each transformer
• Shortest of all 13.2kV cable runs to 3750KVA
Transformers
• MSB to Transformer CSC – 109 feet
• MSA to Transformer CSC – 111 feet
• “Worst Case” Switching Transient Simulation
• Open 13.2 kV VCB at MSB to CSC with 109ft. cable
• Open 13.2 kV VCB at MSA to CSC with 111ft. cable
16
31
31
Worst Case – Study Case 13
• Study Case 13 - Open the 13.2 kV feeder breaker at
Bus MSB feeding the 3,750 kVA dry type transformer
CSC with the shorter distance of 109 feet. The result
for this case will represent the “worst-case” condition,
the other feeder from Bus MSA has a longer feeder
distance of 111 feet.
• Study Case 14 – Same as Case 13, except with the
application of the 0.25 μF surge capacitor.
• Study Case 15 – Same as Case 13, except with the
application of the snubber circuit with 30ohm and 0.25
μF surge capacitor.
32
32
Case 13 – no surge protection
Load current at 13.2kV VCB
Load current of 10A
Chopped current of 6A
17
33
33
Case 13 – no surge protection
Transformer CSC primary voltage
VC max of 65.3kV > 95kV BIL
VB max of 116kV > 95kV BIL
VA max of 123kV > 95kV BIL
Oscillation of 969Hz > 1000Hz
34
34
Case 14 – 0.25uF surge cap
Load current at 13.2kV VCB
Load current of 10A
Chopped current of 6A
18
35
35
Case 14 – 0.25uF surge cap
Transformer CSC primary voltage
VA max of 29.4kV < 95kV BIL
VB max of 19.1kV < 95kV BIL
VC max of 15.7kV < 95kV BIL
Oscillation of 215Hz < 1000Hz
36
36
Case 15 – snubber 30ohm and 0.25uF
Load current at 13.2kV VCB
Load current of 10A
Chopped current of 6A
19
37
37
Case 15 – snubber 30ohm and 0.25uF
Transformer CSC primary voltage
VB max of 28.6kV < 95kV BIL
VA max of 19.4kV < 95kV BIL
VC max of 15.9kV < 95kV BIL
Oscillation of 215Hz < 1000Hz
38
38
Case 15 – snubber 30ohm and 0.25uF
Snubber Current – important for duty on resistor and capacitor
IC peak of 7.7A
IB peak of 8.0A
IA peak of 6.8A
20
39
39
Comparison of Results
No
Snubber
0.25uF
surge cap
Snubber
R=30ohm
C=0.25uF
40
40
Measured Transients with Snubber
21
41
41
Recommendations
• Install snubber at primary of each 3750KVA cast coil
transformer 30ohm and 0.25uF
• Install surge caps 0.25uF at each emergency
generator
• Install surge arresters at the following locations:
• both incoming power transformers
• every distribution dry type transformer
• every generator
• line side of both main circuit breakers
• line side of the three generator circuit breakers
• load side of every feeder breaker and every tie circuit breaker
42
42
Laddle Melt Furnace
Highlights
• Retiring 3 x 38MW EAFs
• Adding 1 x 155MVA EAF
• Adding 2 x 138kV lines to new EAF
• Adding SVC at 34.5kV
• Adding 1 x 20MW LMF
22
43
43
LMF & EAF - Oneline
Vacuum
Breaker
Short
Bus
Oil-Filled
Transformer
Existing
EAF New
LMF
44
44
138KV
UTILITY
4713MVA 3PH SC
9.26 X/R
50/66/83MVA
135.3/26.4KV
7.5%Z
SF-6 BREAKER
2000A
1600A
27KV
13OHM
AUTO LTC
56MVA
27-10KV
3.3%Z
ALUMINUM
IPS BUS
53FEET
VACUUM BREAKER
1200A
LMF XFMR
50/56MVA
25/.53KV
2.5%Z
HEAVY DUTY
COPPER PIPE
28FEET
LMF
20MW
LMF
Vacuum
Breaker
Short
Bus
Oil-Filled
Furnace
Transformer
New
LMF
SF6
Breaker
Short
Bus
Oil-Filled
Auto-Regulating
Transformer
23
45
45
LMF Circuit – Electrical Highlights
• 50MVA Power Transformer 135/26.4kV
• 27kV system
• SF6 circuit breaker – 2000A
• Bus length of 53 feet
• 56MVA autoregulating transformer, 200kV BIL
• Vacuum circuit breaker – 1200A
• Bus length of 28 feet
• 50MVA oil-filled LMF transformer, 200kV BIL
• 20MW LMF
46
46
Worst Case Scenarios
• Examine switching transients at both transformers
• “Worst Case” Switching Transients for Auto-Reg Transf
• Open SF6 breaker to transf. with 53ft. bus (6A current chop)
• 3 cycles after energizing Auto-Reg Tran, open SF6 bkr to transf.
with 53ft. bus (re-ignition) highly inductive current
• “Worst Case” Switching Transients for LMF Transf
• Open VCB to transf. with 28ft. bus (6A current chop)
• 3 cycles after energizing LMF Tran, open VCB to transf. with
28ft. bus (re-ignition) highly inductive current
• Repeat each case with Snubber
24
47
47
Case 1 – Open VCB
LMF Transformer primary voltage
V max of 386kV > 200kV BIL
Oscillation of 1217Hz > 1000Hz
48
48
Case 2 – Open VCB with Snubber
LMF Transformer primary voltage
V max of 56.4kV < 200kV BIL
Oscillation of 200Hz < 1000Hz
25
49
49
Case 3 – Open SF6 Breaker
Auto-regulating Transformer primary voltage
V max of 23kV < 200kV BIL
No oscillating frequency
50
50
Case 4 – Open SF6 Breaker with Snubber
Auto-regulating Transformer primary voltage
VB max of 54.7kV < 200kV BIL
Oscillation of 197Hz < 1000Hz
26
51
51
Case 5 – VCB Re-ignition
Transient Recovery Voltage for VCB
52
52
Case 5 – Highly Inductive Current
Inrush current to LMF transformer
6000A Peak
Inrush
VCB
Opens
VCB
Closes
27
53
53
Case 6 – VCB Re-ignition & Snubber
Transient Recovery Voltage for VCB
54
54
Case 7 – SF6 Breaker Re-ignition
Transient Recovery Voltage for Siemens SF6
28
55
55
Case 7 – Highly Inductive Current
Inrush current to Auto-Regulating transformer
14000A Peak
Inrush
SF6 CB
Opens
SF6 CB
Closes
56
56
Case 8 – SF6 Breaker Re-ignition & Snubber
Transient Recovery Voltage for SF6 Breaker
29
57
57
Summary of Current Chop Cases
58
58
Summary of Re-Ignition Cases
30
59
59
Recommendations
• Install snubber (100ohm and 0.15uF) at primary of
each transformer
• 100ohm resistor
• Non-inductive
• Peak voltage – 38 kVpeak
• Peak energy – 17,500 Joules
• Average power – 1000 Watt
• 0.15uF, 34.5kV surge capacitor (not available)
• 1-pole, 24kV, 0.13uF
• 2-pole, 14.4kV, 0.5uF
• Series combination gives 0.103uF

More Related Content

PPTX
Installation testing and_commissioning_o (1)
PPTX
Introduction of transfromer
PDF
Original MOSFET N-CHANNEL R5205CND R5205 5205 5A 30V TO-252 New
PPTX
APEC 2010 ACDC Live Demo Tech SessionPresentation_Feb 19 2010
PDF
As built and proposed SLD
PDF
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
PPTX
TI’s Next Great Leap: Introducing the NexFET™ 100V Power MOSFETs!
PDF
Original N - Channel Mosfet IRFR3709ZTRPBF FR3709Z 3709 FR3709 TO-252 New IR
Installation testing and_commissioning_o (1)
Introduction of transfromer
Original MOSFET N-CHANNEL R5205CND R5205 5205 5A 30V TO-252 New
APEC 2010 ACDC Live Demo Tech SessionPresentation_Feb 19 2010
As built and proposed SLD
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
TI’s Next Great Leap: Introducing the NexFET™ 100V Power MOSFETs!
Original N - Channel Mosfet IRFR3709ZTRPBF FR3709Z 3709 FR3709 TO-252 New IR

What's hot (20)

PPSX
Energy conservation Activites of thermal power plant
PDF
Power Topologies_Full Deck_04251964_Mappus
PPTX
Wide Vin DC/DC Converters: Reliable Power for Demanding Applications
DOC
Protection settings calculation
PDF
Current_Shap_Strat_Buck_PFC
PPTX
Flyback Converters v4
PPTX
Cuk dc dc+converter
PPTX
Project 2 Cascode
DOCX
Simple SF6 CB Testing for Switchyard Equipment.
PPTX
Transformer tests
PDF
Fat procedure for lv switchboards
PDF
40 MVA TX
PPT
Meter Multiplier
PPTX
Testing of transformer
PPT
Meter Shunt (Ammeter)
PPT
Low dropout regulator(ldo)
PDF
Chapter 5 mukesh gurjar
PPS
Distribution Transformer testing, West Bengal, India
DOCX
Simple Current Transformer (CT) Testing for Switchyard Equipment.
PDF
Testing of Transformers.
Energy conservation Activites of thermal power plant
Power Topologies_Full Deck_04251964_Mappus
Wide Vin DC/DC Converters: Reliable Power for Demanding Applications
Protection settings calculation
Current_Shap_Strat_Buck_PFC
Flyback Converters v4
Cuk dc dc+converter
Project 2 Cascode
Simple SF6 CB Testing for Switchyard Equipment.
Transformer tests
Fat procedure for lv switchboards
40 MVA TX
Meter Multiplier
Testing of transformer
Meter Shunt (Ammeter)
Low dropout regulator(ldo)
Chapter 5 mukesh gurjar
Distribution Transformer testing, West Bengal, India
Simple Current Transformer (CT) Testing for Switchyard Equipment.
Testing of Transformers.
Ad

Viewers also liked (19)

PPTX
Stranke u dnevnoj štampi - 24.03.-19.04.2016
PDF
FTI CEO Transition Study
PDF
psicomotricidad
DOCX
Arttherapyworkshopposter
PDF
Kazakh law 1
PDF
Aula Marca Pós-Moderna
PPTX
Mehalithic
PDF
Reference_Wates_10Oct08
DOCX
VAISAKH- Resume
PDF
How To Use SCRIBD.pdf
PDF
Digital Archiving and Process Centralization for Financial and Insurance Comp...
PDF
Ent101 - Product Development (by Minalytix)
PPS
Samrat Travel Presentation
PPTX
The art of one device fits all
PPTX
Minimum wages ppt
PDF
Travel tips for kailash mansarovar yatra
PDF
Approaches for the Integration of Visual and Computational Analysis of Biomed...
PDF
Ramayana Tour Legend Comes Alive in Sri Lanka
Stranke u dnevnoj štampi - 24.03.-19.04.2016
FTI CEO Transition Study
psicomotricidad
Arttherapyworkshopposter
Kazakh law 1
Aula Marca Pós-Moderna
Mehalithic
Reference_Wates_10Oct08
VAISAKH- Resume
How To Use SCRIBD.pdf
Digital Archiving and Process Centralization for Financial and Insurance Comp...
Ent101 - Product Development (by Minalytix)
Samrat Travel Presentation
The art of one device fits all
Minimum wages ppt
Travel tips for kailash mansarovar yatra
Approaches for the Integration of Visual and Computational Analysis of Biomed...
Ramayana Tour Legend Comes Alive in Sri Lanka
Ad

Similar to Transformer Failure Due to Circuit Breaker Induced Switching Transients (20)

PDF
Transformer Failure Due to Circuit Breaker Induced Switching Transients
PDF
Transformer Failure Due to Circuit Breaker Induced Switching Transients
PDF
ABB Price List of Capacitors 008
PDF
High Voltage Capacitors Webinar
PPTX
Chapter 3 Generation of high voltages and current
PDF
Power transformers rating
PDF
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
PPT
Hvdc dad
PDF
220kV Substation Equipment Bus Scheme & Operation Procedure Testing & Mainten...
PDF
220 66 kv nrs sub report
PPTX
INDUSTRIAL SEMINAR PRESENTATION
PDF
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
PDF
Pamphlet on important psi parameters rdso
PPTX
per_unit_system.pptx
PPTX
C.S.P.D.C.L.AMBIKAPUR (TOWN)
PPTX
ct pt testing...........................................
PPTX
EET402_ electrical system design Module3_problem.pptx
PPT
Transformers.ppt
PPT
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
PDF
Deltatron or Engetron
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
ABB Price List of Capacitors 008
High Voltage Capacitors Webinar
Chapter 3 Generation of high voltages and current
Power transformers rating
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
Hvdc dad
220kV Substation Equipment Bus Scheme & Operation Procedure Testing & Mainten...
220 66 kv nrs sub report
INDUSTRIAL SEMINAR PRESENTATION
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
Pamphlet on important psi parameters rdso
per_unit_system.pptx
C.S.P.D.C.L.AMBIKAPUR (TOWN)
ct pt testing...........................................
EET402_ electrical system design Module3_problem.pptx
Transformers.ppt
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
Deltatron or Engetron

More from michaeljmack (20)

PDF
Auburn, NY - 200 Years of History 1793-1993
PDF
Auburn High School, Auburn, NY, 1982 Yearbook
PDF
Auburn High School, Auburn, NY, 1980 Yearbook
PDF
Surge Protection
PDF
Diesel Particulate Filters Control Systems
PDF
Understanding Arc Flash
PDF
Siemens MV GIS Switchgear
PDF
Fundamentals of transformer inrush
PDF
Building information modeling
PDF
15 years of experience stator ground fault protection
PPT
Emergency, Legally Required and Optional Standby Systems
PDF
Lighting Control Solutions for Daylit Spaces
PDF
COPS: An Arresting Look at NEC Article 708
PDF
Seismic Compliance of Electrical Distribution
PDF
Generator Set Transient Performance
PDF
Modeling of a digital protective relay in a RT Digital Simulator
PDF
Facts on Grid Friendly Wind Plants
PDF
Power Plant Horror Stories
PDF
Blackout Avoidance & Undervoltage Load Shedding
PDF
Transformer Fundamentals
Auburn, NY - 200 Years of History 1793-1993
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
Surge Protection
Diesel Particulate Filters Control Systems
Understanding Arc Flash
Siemens MV GIS Switchgear
Fundamentals of transformer inrush
Building information modeling
15 years of experience stator ground fault protection
Emergency, Legally Required and Optional Standby Systems
Lighting Control Solutions for Daylit Spaces
COPS: An Arresting Look at NEC Article 708
Seismic Compliance of Electrical Distribution
Generator Set Transient Performance
Modeling of a digital protective relay in a RT Digital Simulator
Facts on Grid Friendly Wind Plants
Power Plant Horror Stories
Blackout Avoidance & Undervoltage Load Shedding
Transformer Fundamentals

Recently uploaded (20)

PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PDF
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PPTX
Current and future trends in Computer Vision.pptx
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PPT
Total quality management ppt for engineering students
PDF
Soil Improvement Techniques Note - Rabbi
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PPTX
Module 8- Technological and Communication Skills.pptx
PPTX
communication and presentation skills 01
PDF
August 2025 - Top 10 Read Articles in Network Security & Its Applications
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
Automation-in-Manufacturing-Chapter-Introduction.pdf
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
Fundamentals of safety and accident prevention -final (1).pptx
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
Current and future trends in Computer Vision.pptx
Categorization of Factors Affecting Classification Algorithms Selection
Total quality management ppt for engineering students
Soil Improvement Techniques Note - Rabbi
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Module 8- Technological and Communication Skills.pptx
communication and presentation skills 01
August 2025 - Top 10 Read Articles in Network Security & Its Applications
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt

Transformer Failure Due to Circuit Breaker Induced Switching Transients

  • 1. 1 Transformer Failure Due to Circuit Breaker Induced Switching Transients Part 2: EMTP Modeling and Case Studies David D. Shipp, PE Fellow, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 Thomas J. Dionise, PE Senior Member, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 2 2 Transient Analysis Tools • Electromagnetic Transients Program (EMTP) • Developed by Hermann Dommel brought to BPA • Major contributors: Scott Meyer & Dr. Liu at BPA • Alternative Transients Program (ATP) • Alternative to commercialized EMTP • Free to all if agree not to commercialize it • EMTP-RV • PSCAD EMT/DC
  • 2. 2 3 3 ATP • ATP Draw interface • 3-phase modeling • Solution method - Trapezoidal integration • Robust for wide variety of modeling needs • Extensive library of models • Many options and features 4 4 Source Model • “3-phase wye cosine” • Resistance in ohms • Inductance in mili-Henries • Source Impedance • Z1 and X/R • Z0 and X/R SYSTEM SOURCE AT 13.8 KV XUTIL RUTIL VUTIL UN U UT
  • 3. 3 5 5 Cable Model • “Pi Model” • Resistance in ohms • Inductance in mili-Henries • Cable charging in micro-Farads • ½ charging on sending end • ½ charning on receiving end • Multiple pi models in some cases CABLE 13.8KV C1 LCABLE RCABLE C2 C/2C/2 6 6 Breaker Model • “Switch” • Time dependent switch • Open or close at a specific time • Opens at current zero unless specify otherwise • Current dependent switch • Needed for current chopping • Define current at which to open switch • Independent Poles (A, B and C independent) • Data request • Vacuum or SF6 breaker nameplate • Current chop (ask manufacturer) • Transient Recovery Voltage Ratings – T2, E2 and RRV VCB BKR
  • 4. 4 7 7 Transformer Model • “Three Phase Model” • Resistance in ohms • Inductance in mili-Henries • Magnetizing current • Winding capacitance • CH and CL for dry-types • CHL for oil-filled • More detailed modeling • Saturation • Hysteresis • Data Request • %Z and X/R, MVA • BIL TRANSFORMER RLRG LTRAN RTRANT1 T2 CH CL N:1 8 8 Complete System Model TRANSFORMER RLRG LTRAN RTRANT1 T2 CH CL N:1 CABLE 13.8KV C1 LCABLE RCABLE C2 C/2C/2 SYSTEM SOURCE AT 13.8 KV XUTIL RUTIL VUTIL UN U UT VCB BKR
  • 5. 5 9 9 Time Step • Time Step – Integration Time Step • Choice depends on frequency of expected transient • Too large – miss high frequency effects • Too small – excessive simulation times • Nyquist Criteria • Minimum sample rate = 2 x frequency • Example 10-20KHz ring for VCB transient 10 10 Switching Transient Simulations • Switching transient simulations • EMTP and model requirements • Case studies • Data Center • Ferry Propulsion • Laddle Melt Furnace • Successful techniques/solutions
  • 6. 6 11 11 Ferry Propulsion Highlights • 60K passengers per day • 20M passengers per year • 4160V distribution • 3 x 2865kW diesel gens • 2 x 1865KW forward propulsion motors • 2 x 1865KW reverse propulsion 12 12 Problem • Forward propulsion drives ferry • Upon reaching dock, reverse propulsion stops ferry • July 1, 2009, reverse propulsion was lost entering dock • lost power and hit a pier at full speed • one serious injury and nine minor injuries • 750 to 800 passengers were aboard • impact did not send any passengers overboard • 1185KVA rectifier transformer failed on reverse propulsion motor • Evidence of insulation failure on first few turns of primary winding • Investigation into source of such failure VCB switching
  • 7. 7 13 13 Ferry - Oneline Vacuum Breaker Short Cable Dry-Type Transformer Forward Reverse 14 14 Ferry – Electrical Highlights • 3 x 2865kW diesel generators • 4160V, 3-bus system • Vacuum circuit breakers – 630A mains, ties, feeders • 2 x 1865kW motors (forward propulsion) • 2 x 1865kW motors (reverse propulsion) • 8 x 1185KVA dry-type transformers, 30kV BIL • 3-winding rectifier transformers • 12-pulse effective (6-pulse VFD per winding) • Feeder cable lengths of 50 feet each
  • 8. 8 15 15 Worst Case Scenarios • Feeder cable lengths of 50 feet • Each 1185KVA transformer has one 4160V feeder • Need to examine both feeders for each transformer • “Worst Case” Switching Transient Simulations • Close 4160V VCB to transf. with 50ft. cable (model validation) • Close 4160V VCB to transf. with 50ft. cable (re-ignition) • Open 4160V VCB to transf. with 50ft. cable (current chop) • Repeat each case with Snubber 16 16 Measurements Transient Overvoltages at Primary of Rectifier Transformer – VCB Closes
  • 9. 9 17 17 Study Cases • Case 1 – Closing the 4.16 kV feeder breaker feeding the three winding rectifier transformer with the distance of 50 feet. Simulated to match the Siemens measurements to ensure that the computer model is accurate. (Model Validation) • Case 2 – Same as Case 1, except with the RC snubber. • Case 3 - Closing the 4.16 kV feeder breaker feeding the three winding rectifier transformer, then the 4.16 kV feeder breaker opens during the inrush current. Shows the possibility of the vacuum breaker re-ignition. (Re-ignition) • Case 4 - Same as Case 3, except with the RC snubber. • Case 5 - Open the 4.16 kV feeder breaker feeding the three winding rectifier transformer under the light load condition. (Current Chop) • Case 6 – Same as Case 5, except with the RC snubber. 18 18 Case 1 – Model Validation Transformer primary voltage V max of 4.96kV < 30kV BIL Oscillation of 20,203Hz > 1000Hz
  • 10. 10 19 19 Case 2 – Valid Model with Snubber Transformer primary voltage V max of 3.982kV < 30kV BIL Oscillation of < 1000Hz 20 20 Case 3 – Re-ignition Transient Recovery Voltage (TRV) at VCB
  • 11. 11 21 21 Case 4 – Re-ignition with Snubber Transient Recovery Voltage (TRV) at VCB 22 22 Case 5 – Current Chop Transformer primary voltage V max of 31.9kV > 30kV BIL Oscillation of 958Hz ~ 1000Hz
  • 12. 12 23 23 Case 6 – Current Chop with Snubber Transformer primary voltage V max of 8.9kV < 30kV BIL Oscillation of 299Hz < 1000Hz 24 24 Summary of Current Chop Cases
  • 13. 13 25 25 Summary of Re-Ignition Cases 26 26 Recommendations • Install snubber at primary of each 1185KVA rectifier transformer • 40ohm resistor • Non-inductive • Peak voltage – 6 kVpeak • Peak energy – 2100 Joules • Average power – 190 Watt • 0.5uF capacitor • Rated voltage - 4.16kV
  • 14. 14 27 27 Data Center Highlights • Tier III • LEEDS Certified • 12.5MVA Capacity • 13.2KV Ring Bus 28 28 Data Center - Oneline Vacuum Breaker Short Cable Cast-Coil Transformer
  • 15. 15 29 29 Data Center – Electrical Highlights • 2 x 24.9 kV lines from Factory Shoals and Buzzard Roast • 2 x 12.5 MVA transformers • 13.2 kV “ring-bus” configuration • MSA and MSB and generator bus GPS • Vacuum circuit breakers – 600A mains & ties, 200A feeders • 3 x 2250 KW generators • 6 x 3750KVA cast coil transformers, 90kV BIL • 3 x DE Subs CSA, CSB and CSC • 3 x SE Subs MDSA, MDSB and MLB • Feeder cable lengths vary from 109 to 249 Feet 30 30 Worst Case Scenario • Feeder cable lengths vary from 109 to 249 Feet • Each 3750KVA transformer has two 13.2kV feeders • Need to examine both feeders for each transformer • Shortest of all 13.2kV cable runs to 3750KVA Transformers • MSB to Transformer CSC – 109 feet • MSA to Transformer CSC – 111 feet • “Worst Case” Switching Transient Simulation • Open 13.2 kV VCB at MSB to CSC with 109ft. cable • Open 13.2 kV VCB at MSA to CSC with 111ft. cable
  • 16. 16 31 31 Worst Case – Study Case 13 • Study Case 13 - Open the 13.2 kV feeder breaker at Bus MSB feeding the 3,750 kVA dry type transformer CSC with the shorter distance of 109 feet. The result for this case will represent the “worst-case” condition, the other feeder from Bus MSA has a longer feeder distance of 111 feet. • Study Case 14 – Same as Case 13, except with the application of the 0.25 μF surge capacitor. • Study Case 15 – Same as Case 13, except with the application of the snubber circuit with 30ohm and 0.25 μF surge capacitor. 32 32 Case 13 – no surge protection Load current at 13.2kV VCB Load current of 10A Chopped current of 6A
  • 17. 17 33 33 Case 13 – no surge protection Transformer CSC primary voltage VC max of 65.3kV > 95kV BIL VB max of 116kV > 95kV BIL VA max of 123kV > 95kV BIL Oscillation of 969Hz > 1000Hz 34 34 Case 14 – 0.25uF surge cap Load current at 13.2kV VCB Load current of 10A Chopped current of 6A
  • 18. 18 35 35 Case 14 – 0.25uF surge cap Transformer CSC primary voltage VA max of 29.4kV < 95kV BIL VB max of 19.1kV < 95kV BIL VC max of 15.7kV < 95kV BIL Oscillation of 215Hz < 1000Hz 36 36 Case 15 – snubber 30ohm and 0.25uF Load current at 13.2kV VCB Load current of 10A Chopped current of 6A
  • 19. 19 37 37 Case 15 – snubber 30ohm and 0.25uF Transformer CSC primary voltage VB max of 28.6kV < 95kV BIL VA max of 19.4kV < 95kV BIL VC max of 15.9kV < 95kV BIL Oscillation of 215Hz < 1000Hz 38 38 Case 15 – snubber 30ohm and 0.25uF Snubber Current – important for duty on resistor and capacitor IC peak of 7.7A IB peak of 8.0A IA peak of 6.8A
  • 20. 20 39 39 Comparison of Results No Snubber 0.25uF surge cap Snubber R=30ohm C=0.25uF 40 40 Measured Transients with Snubber
  • 21. 21 41 41 Recommendations • Install snubber at primary of each 3750KVA cast coil transformer 30ohm and 0.25uF • Install surge caps 0.25uF at each emergency generator • Install surge arresters at the following locations: • both incoming power transformers • every distribution dry type transformer • every generator • line side of both main circuit breakers • line side of the three generator circuit breakers • load side of every feeder breaker and every tie circuit breaker 42 42 Laddle Melt Furnace Highlights • Retiring 3 x 38MW EAFs • Adding 1 x 155MVA EAF • Adding 2 x 138kV lines to new EAF • Adding SVC at 34.5kV • Adding 1 x 20MW LMF
  • 22. 22 43 43 LMF & EAF - Oneline Vacuum Breaker Short Bus Oil-Filled Transformer Existing EAF New LMF 44 44 138KV UTILITY 4713MVA 3PH SC 9.26 X/R 50/66/83MVA 135.3/26.4KV 7.5%Z SF-6 BREAKER 2000A 1600A 27KV 13OHM AUTO LTC 56MVA 27-10KV 3.3%Z ALUMINUM IPS BUS 53FEET VACUUM BREAKER 1200A LMF XFMR 50/56MVA 25/.53KV 2.5%Z HEAVY DUTY COPPER PIPE 28FEET LMF 20MW LMF Vacuum Breaker Short Bus Oil-Filled Furnace Transformer New LMF SF6 Breaker Short Bus Oil-Filled Auto-Regulating Transformer
  • 23. 23 45 45 LMF Circuit – Electrical Highlights • 50MVA Power Transformer 135/26.4kV • 27kV system • SF6 circuit breaker – 2000A • Bus length of 53 feet • 56MVA autoregulating transformer, 200kV BIL • Vacuum circuit breaker – 1200A • Bus length of 28 feet • 50MVA oil-filled LMF transformer, 200kV BIL • 20MW LMF 46 46 Worst Case Scenarios • Examine switching transients at both transformers • “Worst Case” Switching Transients for Auto-Reg Transf • Open SF6 breaker to transf. with 53ft. bus (6A current chop) • 3 cycles after energizing Auto-Reg Tran, open SF6 bkr to transf. with 53ft. bus (re-ignition) highly inductive current • “Worst Case” Switching Transients for LMF Transf • Open VCB to transf. with 28ft. bus (6A current chop) • 3 cycles after energizing LMF Tran, open VCB to transf. with 28ft. bus (re-ignition) highly inductive current • Repeat each case with Snubber
  • 24. 24 47 47 Case 1 – Open VCB LMF Transformer primary voltage V max of 386kV > 200kV BIL Oscillation of 1217Hz > 1000Hz 48 48 Case 2 – Open VCB with Snubber LMF Transformer primary voltage V max of 56.4kV < 200kV BIL Oscillation of 200Hz < 1000Hz
  • 25. 25 49 49 Case 3 – Open SF6 Breaker Auto-regulating Transformer primary voltage V max of 23kV < 200kV BIL No oscillating frequency 50 50 Case 4 – Open SF6 Breaker with Snubber Auto-regulating Transformer primary voltage VB max of 54.7kV < 200kV BIL Oscillation of 197Hz < 1000Hz
  • 26. 26 51 51 Case 5 – VCB Re-ignition Transient Recovery Voltage for VCB 52 52 Case 5 – Highly Inductive Current Inrush current to LMF transformer 6000A Peak Inrush VCB Opens VCB Closes
  • 27. 27 53 53 Case 6 – VCB Re-ignition & Snubber Transient Recovery Voltage for VCB 54 54 Case 7 – SF6 Breaker Re-ignition Transient Recovery Voltage for Siemens SF6
  • 28. 28 55 55 Case 7 – Highly Inductive Current Inrush current to Auto-Regulating transformer 14000A Peak Inrush SF6 CB Opens SF6 CB Closes 56 56 Case 8 – SF6 Breaker Re-ignition & Snubber Transient Recovery Voltage for SF6 Breaker
  • 29. 29 57 57 Summary of Current Chop Cases 58 58 Summary of Re-Ignition Cases
  • 30. 30 59 59 Recommendations • Install snubber (100ohm and 0.15uF) at primary of each transformer • 100ohm resistor • Non-inductive • Peak voltage – 38 kVpeak • Peak energy – 17,500 Joules • Average power – 1000 Watt • 0.15uF, 34.5kV surge capacitor (not available) • 1-pole, 24kV, 0.13uF • 2-pole, 14.4kV, 0.5uF • Series combination gives 0.103uF