Reasons for Transferring Levels
There are a number or reasons for the transfer of
levels in substructure work. These include:
• To establish the level of the ground for
excavation (both oversite and trenches).
• To ensure materials such as concrete and
hardcore are laid to an accurate level.
• To establish datum for bricklaying, e.g. DPC
level.
• To establish a level for concrete formwork, e.g.
when constructing a concrete raft foundation.
Transferring Levels from the
Datum to the Foundation (Strip)
During the process of setting out, a datum
peg is positioned to mark a predetermined
level, such as DPC or floor level, this is
called a Temporary Bench Mark (TBM)
This is the level from which the bricklayer or
ground worker will transfer levels helping to
control the depth of the foundations and brick
footings.
Datum Peg Spirit level and
straight edge
Gauge Rod or
tape measure
Concrete
thickness pegConcrete
thickness
Multiple of
brick courses
Transferring Levels from the
Datum to the Foundation (Strip)
Having set the first peg to gauge from the datum,
the level must be transferred all around the
building’s foundation to provide a guide for the top
of the concrete when poured.
Optical or laser levels are most commonly used to
do this. However, at times the, bricklayer will find it
more convenient to simply transfer the levels
around the trench by the use of a straightedge
and spirit level.
Using a Straight Edge and Spirit level
It is essential to REVERSE the level and straightedge
at each peg reading. This ensures that any
discrepancy in the straightedge or level is not
repeated at every peg, but cancelled out at every
other reading.
Datum peg
Depth to work brick courses
Spirit level and straight edge
Boning Rods
Another method of transferring levels
around a trench is by the use of boning
rods.
Boning rods are made from timber and are
usually painted so that they are easily seen.
Boning rods are typically used in threes, the
middle one being known as the ‘traveller’.
Boning Rods
Traveller
Levelling pegs

More Related Content

PPTX
Tutor l1 setting out
PDF
Surveying by using Digital Theodolite
PPT
Introduction to Setting Out a Building
PDF
Setting out of Building
PPTX
A PowerPoint Presentation On Superstructure
PDF
1. Pile foundations (SL 1-143).pdf
PDF
SITEWORKS & SETTING OUT
Tutor l1 setting out
Surveying by using Digital Theodolite
Introduction to Setting Out a Building
Setting out of Building
A PowerPoint Presentation On Superstructure
1. Pile foundations (SL 1-143).pdf
SITEWORKS & SETTING OUT

What's hot (20)

PPTX
Surveying and levelling
PPTX
Formwork
PPTX
Compass Surveying
PPTX
Theodolite angle measurement
PPTX
Total Station surveying
PPTX
Setting out of building
PPTX
Foundations
PPTX
PPTX
BAR BENDING SCHEDULE.pptx
PDF
Setting out 12042018
PPTX
Setting out construction works 01
PDF
Masonry Presentation
PPT
Mass haul diagram
PDF
levelling and contouring
PPTX
Electronic distance measurement (EDM)
PPTX
Setting out work
PPTX
Tutor l1 setting out
PPTX
Chapter 11 temporary works
PDF
Site Surveying Leveling
PPT
Superstructure construction
Surveying and levelling
Formwork
Compass Surveying
Theodolite angle measurement
Total Station surveying
Setting out of building
Foundations
BAR BENDING SCHEDULE.pptx
Setting out 12042018
Setting out construction works 01
Masonry Presentation
Mass haul diagram
levelling and contouring
Electronic distance measurement (EDM)
Setting out work
Tutor l1 setting out
Chapter 11 temporary works
Site Surveying Leveling
Superstructure construction
Ad

More from Luke D'Arcy (20)

PPT
Tutor types of foundation
PPT
Tutor transferring levels
PPT
Tutor sustainability
PPT
Tutor stability
PPT
Tutor solid ground floors
PPT
Tutor site clearance
PPT
Tutor retaining reinforced brickwork
PPT
Tutor brickwork below ground level
PPT
Basic bricklaying skills power point 2015
PPTX
Health and safety c and g
PPT
Tutor solid walls c and g level2
PPT
Tutor masonry cladding ppt 2
PPT
Tutor methods of communication ppt2
PPT
Tutor construction administration documents ppt3
PPT
Tutor construction activity documents ppt4
PPT
Tutor communication skills ppt1
PPT
Tutor solid wall and arches
PPT
Tutor isolated and attached piers .ppt1
PPT
Tutor wall ties in cavity walls .ppt 2
PPT
Tutor cavity insulation .ppt 4
Tutor types of foundation
Tutor transferring levels
Tutor sustainability
Tutor stability
Tutor solid ground floors
Tutor site clearance
Tutor retaining reinforced brickwork
Tutor brickwork below ground level
Basic bricklaying skills power point 2015
Health and safety c and g
Tutor solid walls c and g level2
Tutor masonry cladding ppt 2
Tutor methods of communication ppt2
Tutor construction administration documents ppt3
Tutor construction activity documents ppt4
Tutor communication skills ppt1
Tutor solid wall and arches
Tutor isolated and attached piers .ppt1
Tutor wall ties in cavity walls .ppt 2
Tutor cavity insulation .ppt 4
Ad

Recently uploaded (20)

PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PDF
advance database management system book.pdf
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PPTX
20th Century Theater, Methods, History.pptx
PDF
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
My India Quiz Book_20210205121199924.pdf
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PPTX
Unit 4 Computer Architecture Multicore Processor.pptx
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
PPTX
Introduction to pro and eukaryotes and differences.pptx
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PDF
AI-driven educational solutions for real-life interventions in the Philippine...
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
PDF
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
PPTX
Introduction to Building Materials
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
advance database management system book.pdf
Chinmaya Tiranga quiz Grand Finale.pdf
Paper A Mock Exam 9_ Attempt review.pdf.
20th Century Theater, Methods, History.pptx
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
My India Quiz Book_20210205121199924.pdf
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
Unit 4 Computer Architecture Multicore Processor.pptx
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
Introduction to pro and eukaryotes and differences.pptx
A powerpoint presentation on the Revised K-10 Science Shaping Paper
AI-driven educational solutions for real-life interventions in the Philippine...
LDMMIA Reiki Yoga Finals Review Spring Summer
B.Sc. DS Unit 2 Software Engineering.pptx
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
Introduction to Building Materials

Tutor transferring levels

  • 2. Reasons for Transferring Levels There are a number or reasons for the transfer of levels in substructure work. These include: • To establish the level of the ground for excavation (both oversite and trenches). • To ensure materials such as concrete and hardcore are laid to an accurate level. • To establish datum for bricklaying, e.g. DPC level. • To establish a level for concrete formwork, e.g. when constructing a concrete raft foundation.
  • 3. Transferring Levels from the Datum to the Foundation (Strip) During the process of setting out, a datum peg is positioned to mark a predetermined level, such as DPC or floor level, this is called a Temporary Bench Mark (TBM) This is the level from which the bricklayer or ground worker will transfer levels helping to control the depth of the foundations and brick footings.
  • 4. Datum Peg Spirit level and straight edge Gauge Rod or tape measure Concrete thickness pegConcrete thickness Multiple of brick courses Transferring Levels from the Datum to the Foundation (Strip)
  • 5. Having set the first peg to gauge from the datum, the level must be transferred all around the building’s foundation to provide a guide for the top of the concrete when poured. Optical or laser levels are most commonly used to do this. However, at times the, bricklayer will find it more convenient to simply transfer the levels around the trench by the use of a straightedge and spirit level.
  • 6. Using a Straight Edge and Spirit level It is essential to REVERSE the level and straightedge at each peg reading. This ensures that any discrepancy in the straightedge or level is not repeated at every peg, but cancelled out at every other reading. Datum peg Depth to work brick courses Spirit level and straight edge
  • 7. Boning Rods Another method of transferring levels around a trench is by the use of boning rods. Boning rods are made from timber and are usually painted so that they are easily seen. Boning rods are typically used in threes, the middle one being known as the ‘traveller’. Boning Rods Traveller Levelling pegs