SlideShare a Scribd company logo
Modeling Effective Grounding of
Grid Tied Inverters
5/6/14
EPRI Modeling Workshop
Taylor Hollis
Interconnections Requirements Analyst
Solar Business Unit
Schneider Electric
2
Contents
1 Background
2 Compliance Issues for Inverters
3 Potential Solutions
4 Modeling Considerations
5 Conclusions
304/26/14
In North America, more than 70% of circuit miles below 69kV are
three phase, four-wire multi-grounded distribution circuits.
In the event of a single phase-to-ground fault, circuit breakers at the
substation open. If the DR is of sufficient size to support the loads,
an unintentional island could be created. Based upon the method of
symmetrical components, the phase-to-ground voltages on the
unfaulted phases could increase up to 173% of the pre-fault voltage
level. This can damage single phase customers or utility surge
arresters.
Background
Source: Johnson et al.
405/6/14
Background
IEEE C62.92.1: a system is effectively grounded if the Coefficient of
Grounding is less than 0.8 where the COG is the ratio of max phase to
ground voltage divided by phase-to-phase voltage.
IEEE I42: “…for all points on the system the ratio of zero-sequence
reactance to the positive-sequence reactance is less than 3 and the
ratio of zero sequence resistance to positive sequence reactance is less
than 1 for any condition of operation and for any amount of connected
generator capacity.”
The X0/X1 and R0/X1 ratios are conditions that usually provide
compliance with the actual definition. The Industrial Application Society
of IEEE took the sequence ratios as the definition when they made their
"color books”, therefore many use the 142 definition, but it is a logical
consequence, not an a priori definition.
A Quick Word on Symmetrical Components
The methodology introduced in 1913 by Charles Fortescue, who
demonstrated that any set of unbalanced three-phase quantities
could be expressed as the sum of three symmetrical sets of balanced
phasors.
5
Background
604/26/14
In this diagram, representing a SLG fault, the generator is represented
by a balanced positive sequence voltage phasor. This is not accurate for
an inverter! If a current source is used, it is of vital importance to also
consider the topology of the load.
Source: Johnson et al.
Background
Traditionally, generators are modeled as a voltage behind a sub-
transient, transient and steady state reactances. These are physical
values that can be verified with proper test procedures. In their grid-
tied behavior the inverters modulate the switching of their transistor
bridges to inject current from their DC bus based upon the AC output
current. That is emphatically not a voltage source.
7
Compliance Issues for Inverters
The inverter does have an AC line inductor, but the impedance to
sequence currents vary with time as the switches open and close.
A PWM Switching PatternInverter H-Bridge
Transformer Based Solutions
For DER plants which install a new transformer, a Delta/Wye(g)
[gen/grid] transformer presents a grounded source to the utility and is
generally accepted as effectively grounded. This, may, however,
desensitize the ground fault relays (51N) at the substation.
For customers with an existing transformer Wye(g)/Delta or Wye(g)/
Wye, a grounding bank must be installed, which adds cost, project
delays, desensitizes the substation relay, and ignores other
mechanisms for TOV which may be more relevant to a given
application.
8
Potential Solutions
Controls Based Approaches
Based upon the IEEE C62.92.1 definition, if a generator limits over
voltages to less than 140% L-N it is effective grounded. Therefore,
any mechanism that achieves this should be valid.
Inverters have fast microprocessors onboard.
Fast gate blocking an extra high-voltage fast-trip setting is included by
most manufacturers for self-protection purposes.
Spain and Australia require TOV tests that determine the reaction to a
loss of load. They resemble the CBEMA/ITIC curve.
The inverter shuts down upon seeing a high terminal voltage. Typically,
1.4 p.u., in 50 ms. Note: these are single phase tests and do not
account for different transformer configurations.
9
Potential Solutions
Problem: There are many ways to accomplish the
aforementioned behavior. Therefore, it is challenging to
generalize a given inverter’s behavior.
“Rotating machines are 90% physics and 10% engineering
design. Inverters are the exact opposite.”- Reigh Walling
This is the main issue in predicting the behavior of an
inverter during a TOV event.
10
Modeling Considerations
11
Modeling Considerations
1
2
3
4
5
Modeling Considerations
Variables:
1. Current Sense: RMS or instantaneous in control loop, sequence
measurements, phasor average or independent control loops,
sampling frequency.
2. Voltage Sensing: 1 or 3 phase, L-N or L-L, phasor average or
independent control loops, RMS or instantaneous, sampling rates.
3. Current Control Loop: independent phase control or 3 phase space
vector, saturated controls, different inverter bridge topologies.
4. Phase Lock Loop: αβ transform phase angle error.
5. Power Control: reactive power support, Volt/Var functions, power
limiting.
12
There is an open debate whether defining the symmetrical component
impedances of an inverter has merit. But it is generally accepted that
a current source model is more accurate. However, this approach
has its limitations as well.
• Abnormal voltages producing imbalanced currents - non idealized
behavior.
• Constant power regulation is more common than constant current.
Power is regulated in the steady state by an outer loop, typically with
slower dynamics than the inner loop which regulates current at high
bandwidth. Power regulation also will tend to have limits so that
excess current is not ordered during undervoltage conditions.
• New functions like LVRT change everything in a snap of the fingers.
100% real power to 100%, VARS in 10ms! How is that accounted
for?
• Furthermore, most inverters do not inject zero sequence current.
Even if the switch controls permitted it, the unit is typically a 3 wire
connection without a neutral return.
13
Modeling Considerations
Model validation is of course necessary
Proposed UL 1741 SLG TOV Test Setup
14
Modeling Considerations
Keep in mind: There is more than one mechanism of TOV at play here.
Modeling can be a potential powerful tool for assessing the impact of
inverters on distribution systems. However, to date, most software
packages do not have an accurate model for the inverter.
Inverter manufacturers and simulations vendors need to define a library
of models that manufacturers can certify their products to. Otherwise
there is way too much variability for a generic model to be accurate.
Transformers and loads must be considered when simulating an inverter
and EPS. The dynamics are determined partly by Ohm’s Law,
because of the current-source inverter pushing current into the loads;
and partly by the controls of the inverter itself, because its ability to
source current does depend on its terminal voltage. In any case, it’s
all about the interaction between the inverter and the loads, and not
about an inherent GFO mechanism in the inverter, because it doesn’t
have one.
15
Conclusions
Thank you for your attention!
With Special Thanks to Michael Ropp, Northern Plains
Power Technologies
and
Reigh Walling, Walling Energy Systems Consulting
16
Questions
1704/26/14 Effective Grounding
Slide References
1. Protection for Unexpected Delta Sources
Ken Behrendt Schweitzer Engineering Laboratories, Inc. New Berlin, WI USA
2. A Review of System Grounding Methods and Zero Sequence Current Sources
Gerald Johnson (Basler Electric), Mark Schroeder (Dominion VA Power)
and Gerald Dalke (Power System Relay Services).
3. Advanced Grid Planning and Operations
Mark McGranaghan, Thomas Ortmeyer, David Crudele, Thomas Key, Jeff Smith, Phil
Barker.
4. Alternate Energy Customer Interconnection Requirements
PECO Solar Conference. Barry Hornberger. June 1, 2011.
5. PECO Grey Book
17

More Related Content

PDF
Resonance of a distribution feeder with a saturable core fault current limiter
PDF
Modeling and test validation of a 15 kV - 24 MVA superconducting fault curren...
PPTX
5 emi ac bridges (with marking)
PDF
Power Spikes Isolation to avoid corruption within sensitive ICs Solutions
PPTX
Three Phase Fault Analysis With Auto Reset On Temporary Fault And Permanent Trip
PDF
L 21(dp)(pe) ((ee)nptel)
PPTX
PDF
Automated Electrical Protection System For Domestic Application
Resonance of a distribution feeder with a saturable core fault current limiter
Modeling and test validation of a 15 kV - 24 MVA superconducting fault curren...
5 emi ac bridges (with marking)
Power Spikes Isolation to avoid corruption within sensitive ICs Solutions
Three Phase Fault Analysis With Auto Reset On Temporary Fault And Permanent Trip
L 21(dp)(pe) ((ee)nptel)
Automated Electrical Protection System For Domestic Application

What's hot (20)

PPTX
Resonant Converter
PDF
Distance Protection
PDF
Fault analysis
PPT
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
PPTX
Fault Level Calculation
DOCX
New microsoft office word document (3)
PPTX
Enhancement of power quality in distribution system using d statcom
PPTX
Grid Voltage Regulation
PPTX
MPLC Inverter
PPT
An Ultra-Compact and Efficient Li-ion Battery Charger
PPTX
220 KV Substation Operation & Maintenance
PPTX
INVERTER BY PANKAJ CHAUDHARY
PPTX
Transformer Seminar - Buck-Boost
PDF
Analysis of the Performance of Active Type SFCL and FCL for Reduction Capabil...
DOCX
Feasibility Analysis of the Positioning of Superconducting Fault Current Limi...
PPTX
Power control and power flow analysis
DOCX
Simple 100 w inverter circuit
PPTX
Zvs dc-dc converter for PHEV charger
PDF
Substation design-guideliness
Resonant Converter
Distance Protection
Fault analysis
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
Fault Level Calculation
New microsoft office word document (3)
Enhancement of power quality in distribution system using d statcom
Grid Voltage Regulation
MPLC Inverter
An Ultra-Compact and Efficient Li-ion Battery Charger
220 KV Substation Operation & Maintenance
INVERTER BY PANKAJ CHAUDHARY
Transformer Seminar - Buck-Boost
Analysis of the Performance of Active Type SFCL and FCL for Reduction Capabil...
Feasibility Analysis of the Positioning of Superconducting Fault Current Limi...
Power control and power flow analysis
Simple 100 w inverter circuit
Zvs dc-dc converter for PHEV charger
Substation design-guideliness
Ad

Viewers also liked (20)

PDF
2014 PV Distribution System Modeling Workshop: Modeling as a Community with M...
PDF
11 reno sandia_dgi_reno_sand2016-4701 pe
PDF
Open-E DSS V7 Active-Active Load Balanced iSCSI HA Cluster (without bonding)
PDF
5.1_Empowering Clean Energy_Nasle_EPRI/SNL Microgrid
PDF
2014 PV Distribution System Modeling Workshop: Interaction and Coordination w...
PPTX
Dishant ppt
PPTX
4.2_Microgrid Design Toolkit_Eddy_EPRI/SNL Microgrid
PDF
2014 PV Distribution System Modeling Workshop: Determining Recommended Settin...
PPTX
4.4_Micro Grid Design_Bello_EPRI/SNL Microgrid
PDF
2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebast...
PDF
2014 PV Distribution System Modeling Workshop: IEEE Test Feeders for Advanced...
PPT
Power quality unit i ANNA UNIVERSITY SYALLABUS
PDF
2014 PV Distribution System Modeling Workshop: Hosting Capacity Analysis and ...
PPTX
4.1_Simulation & Analysis Tools for Microgrids_Weng and Cortes_EPRI/SNL Micro...
PDF
2014 PV Distribution System Modeling Workshop: Data and Models for High Penet...
PDF
3.5_Microgrid Market Operations with Distribution System Operators_Shahidehpo...
PPTX
Density based traffic signal system
PPT
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
PDF
2014 PV Reliability, Operations & Maintenance Workshop: Arizona Public Servic...
2014 PV Distribution System Modeling Workshop: Modeling as a Community with M...
11 reno sandia_dgi_reno_sand2016-4701 pe
Open-E DSS V7 Active-Active Load Balanced iSCSI HA Cluster (without bonding)
5.1_Empowering Clean Energy_Nasle_EPRI/SNL Microgrid
2014 PV Distribution System Modeling Workshop: Interaction and Coordination w...
Dishant ppt
4.2_Microgrid Design Toolkit_Eddy_EPRI/SNL Microgrid
2014 PV Distribution System Modeling Workshop: Determining Recommended Settin...
4.4_Micro Grid Design_Bello_EPRI/SNL Microgrid
2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebast...
2014 PV Distribution System Modeling Workshop: IEEE Test Feeders for Advanced...
Power quality unit i ANNA UNIVERSITY SYALLABUS
2014 PV Distribution System Modeling Workshop: Hosting Capacity Analysis and ...
4.1_Simulation & Analysis Tools for Microgrids_Weng and Cortes_EPRI/SNL Micro...
2014 PV Distribution System Modeling Workshop: Data and Models for High Penet...
3.5_Microgrid Market Operations with Distribution System Operators_Shahidehpo...
Density based traffic signal system
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
2014 PV Reliability, Operations & Maintenance Workshop: Arizona Public Servic...
Ad

Similar to 2014 PV Distribution System Modeling Workshop: Modeling Effective Grounding for Grid Tied Inverters: Taylor Hollis, Schneider Electric (20)

PDF
A practical primer for paralleling electric systems
PDF
fault ride through- doubly fed induction generator
PPT
POWER QUALITY IMPROVEMENT AND FAULT RIDE THROUGH OF GRID CONNECTED WIND ENE...
PPTX
Relay operation principles
PDF
Short circuit current calculations
PDF
IRJET- Review on Various Topologis used for Decoupling of Fluctuating Power i...
PDF
voltage scaling
PPT
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
PDF
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
PPTX
DESIGN AND IMPLEMENTATION OF ACTIVE POWER FILTER.pptx
DOC
New microsoft word document (3)
PDF
Concurrent Detection and Classification of Faults in Matrix Converter using T...
PDF
Energy Storage Systems – Grid Connection Using Synchronverters
PDF
Review of Reduction of Leakage Current in Cascaded Multilevel Inverter
PDF
[7] a generalized parameter tuning method of proportional resonant controller...
PPTX
DC link ripple analysis on five phase pwm voltage source inverter with unbala...
PDF
General electric
PDF
Droop control approach for power sharing in AC microgrid
PDF
Y04408126132
PDF
A Generalized Parameter Tuning Method of Proportional-Resonant Controllers fo...
A practical primer for paralleling electric systems
fault ride through- doubly fed induction generator
POWER QUALITY IMPROVEMENT AND FAULT RIDE THROUGH OF GRID CONNECTED WIND ENE...
Relay operation principles
Short circuit current calculations
IRJET- Review on Various Topologis used for Decoupling of Fluctuating Power i...
voltage scaling
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
DESIGN AND IMPLEMENTATION OF ACTIVE POWER FILTER.pptx
New microsoft word document (3)
Concurrent Detection and Classification of Faults in Matrix Converter using T...
Energy Storage Systems – Grid Connection Using Synchronverters
Review of Reduction of Leakage Current in Cascaded Multilevel Inverter
[7] a generalized parameter tuning method of proportional resonant controller...
DC link ripple analysis on five phase pwm voltage source inverter with unbala...
General electric
Droop control approach for power sharing in AC microgrid
Y04408126132
A Generalized Parameter Tuning Method of Proportional-Resonant Controllers fo...

More from Sandia National Laboratories: Energy & Climate: Renewables (20)

PDF
M4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339r
PDF
Sand2018 0581 o metadata for presentations 011918 lac
PPTX
11 Testing Shear Strength and Deformation along Discontinuities in Salt
PPTX
10 Current status of research in the Joint Project WEIMOS
PPTX
26 Current research on deep borehole disposal of nuclear spent fuel and high-...
PPTX
25 Basin-Scale Density-Dependent Groundwater Flow Near a Salt Repository
PPTX
24 Actinide and brine chemistry in salt repositories: Updates from ABC Salt (V)
PPTX
23 Sandia’s Salt Design Concept for High Level Waste and Defense Spent Nuclea...
PPTX
22 WIPP Future Advancements and Operational Safety
PPTX
21 WIPP recovery and Operational Safety
PPTX
20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP
PPTX
19 Repository designs in bedded salt, the KOSINA-Project
PPTX
18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)
PPTX
16 Reconsolidation of granular salt (DAEF report)
PPTX
PPTX
14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...
PPTX
13 "New results of the KOSINA project - Generic geological models / Integrity...
PPTX
12 Salt testing: Low deviatoric stress data
PDF
09 Invited Lecture: Salt Creep at Low Deviatoric Stress
M4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339r
Sand2018 0581 o metadata for presentations 011918 lac
11 Testing Shear Strength and Deformation along Discontinuities in Salt
10 Current status of research in the Joint Project WEIMOS
26 Current research on deep borehole disposal of nuclear spent fuel and high-...
25 Basin-Scale Density-Dependent Groundwater Flow Near a Salt Repository
24 Actinide and brine chemistry in salt repositories: Updates from ABC Salt (V)
23 Sandia’s Salt Design Concept for High Level Waste and Defense Spent Nuclea...
22 WIPP Future Advancements and Operational Safety
21 WIPP recovery and Operational Safety
20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP
19 Repository designs in bedded salt, the KOSINA-Project
18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)
16 Reconsolidation of granular salt (DAEF report)
14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...
13 "New results of the KOSINA project - Generic geological models / Integrity...
12 Salt testing: Low deviatoric stress data
09 Invited Lecture: Salt Creep at Low Deviatoric Stress

Recently uploaded (20)

PPTX
School Education Programs for Social Impact Learn with Parramatta Mission
PPTX
Weekly Report 17-10-2024_cybersecutity.pptx
PDF
PPT - Primary Rules of Interpretation (1).pdf
PPTX
GOVERNMENT-ACCOUNTING1. bsa 4 government accounting
DOCX
EAPP.docxdffgythjyuikuuiluikluikiukuuuuuu
PDF
Item # 4 -- 328 Albany St. compt. review
PDF
Item # 2 - 934 Patterson Specific Use Permit (SUP)
DOCX
Alexistogel: Solusi Tepat untuk Anda yang Cari Bandar Toto Macau Resmi
PPTX
The DFARS - Part 250 - Extraordinary Contractual Actions
PDF
About Karen Miner-Romanoff - Academic & nonprofit consultant
DOC
LU毕业证学历认证,赫尔大学毕业证硕士的学历和学位
PDF
Abhay Bhutada Foundation’s Integration With SEBI's 2021 ESG Guidelines
PPTX
Social_Medias_Parents_Education_PPT.pptx
PDF
Abhay Bhutada and Other Visionary Leaders Reinventing Governance in India
PPTX
Omnibus rules on leave administration.pptx
PDF
buyers sellers meeting of mangoes in mahabubnagar.pdf
PDF
4_Key Concepts Structure and Governance plus UN.pdf okay
PPTX
SOMANJAN PRAMANIK_3500032 2042.pptx
PDF
ISO-9001-2015-internal-audit-checklist2-sample.pdf
PDF
26.1.2025 venugopal K Awarded with commendation certificate.pdf
School Education Programs for Social Impact Learn with Parramatta Mission
Weekly Report 17-10-2024_cybersecutity.pptx
PPT - Primary Rules of Interpretation (1).pdf
GOVERNMENT-ACCOUNTING1. bsa 4 government accounting
EAPP.docxdffgythjyuikuuiluikluikiukuuuuuu
Item # 4 -- 328 Albany St. compt. review
Item # 2 - 934 Patterson Specific Use Permit (SUP)
Alexistogel: Solusi Tepat untuk Anda yang Cari Bandar Toto Macau Resmi
The DFARS - Part 250 - Extraordinary Contractual Actions
About Karen Miner-Romanoff - Academic & nonprofit consultant
LU毕业证学历认证,赫尔大学毕业证硕士的学历和学位
Abhay Bhutada Foundation’s Integration With SEBI's 2021 ESG Guidelines
Social_Medias_Parents_Education_PPT.pptx
Abhay Bhutada and Other Visionary Leaders Reinventing Governance in India
Omnibus rules on leave administration.pptx
buyers sellers meeting of mangoes in mahabubnagar.pdf
4_Key Concepts Structure and Governance plus UN.pdf okay
SOMANJAN PRAMANIK_3500032 2042.pptx
ISO-9001-2015-internal-audit-checklist2-sample.pdf
26.1.2025 venugopal K Awarded with commendation certificate.pdf

2014 PV Distribution System Modeling Workshop: Modeling Effective Grounding for Grid Tied Inverters: Taylor Hollis, Schneider Electric

  • 1. Modeling Effective Grounding of Grid Tied Inverters 5/6/14 EPRI Modeling Workshop Taylor Hollis Interconnections Requirements Analyst Solar Business Unit Schneider Electric
  • 2. 2 Contents 1 Background 2 Compliance Issues for Inverters 3 Potential Solutions 4 Modeling Considerations 5 Conclusions
  • 3. 304/26/14 In North America, more than 70% of circuit miles below 69kV are three phase, four-wire multi-grounded distribution circuits. In the event of a single phase-to-ground fault, circuit breakers at the substation open. If the DR is of sufficient size to support the loads, an unintentional island could be created. Based upon the method of symmetrical components, the phase-to-ground voltages on the unfaulted phases could increase up to 173% of the pre-fault voltage level. This can damage single phase customers or utility surge arresters. Background Source: Johnson et al.
  • 4. 405/6/14 Background IEEE C62.92.1: a system is effectively grounded if the Coefficient of Grounding is less than 0.8 where the COG is the ratio of max phase to ground voltage divided by phase-to-phase voltage. IEEE I42: “…for all points on the system the ratio of zero-sequence reactance to the positive-sequence reactance is less than 3 and the ratio of zero sequence resistance to positive sequence reactance is less than 1 for any condition of operation and for any amount of connected generator capacity.” The X0/X1 and R0/X1 ratios are conditions that usually provide compliance with the actual definition. The Industrial Application Society of IEEE took the sequence ratios as the definition when they made their "color books”, therefore many use the 142 definition, but it is a logical consequence, not an a priori definition.
  • 5. A Quick Word on Symmetrical Components The methodology introduced in 1913 by Charles Fortescue, who demonstrated that any set of unbalanced three-phase quantities could be expressed as the sum of three symmetrical sets of balanced phasors. 5 Background
  • 6. 604/26/14 In this diagram, representing a SLG fault, the generator is represented by a balanced positive sequence voltage phasor. This is not accurate for an inverter! If a current source is used, it is of vital importance to also consider the topology of the load. Source: Johnson et al. Background
  • 7. Traditionally, generators are modeled as a voltage behind a sub- transient, transient and steady state reactances. These are physical values that can be verified with proper test procedures. In their grid- tied behavior the inverters modulate the switching of their transistor bridges to inject current from their DC bus based upon the AC output current. That is emphatically not a voltage source. 7 Compliance Issues for Inverters The inverter does have an AC line inductor, but the impedance to sequence currents vary with time as the switches open and close. A PWM Switching PatternInverter H-Bridge
  • 8. Transformer Based Solutions For DER plants which install a new transformer, a Delta/Wye(g) [gen/grid] transformer presents a grounded source to the utility and is generally accepted as effectively grounded. This, may, however, desensitize the ground fault relays (51N) at the substation. For customers with an existing transformer Wye(g)/Delta or Wye(g)/ Wye, a grounding bank must be installed, which adds cost, project delays, desensitizes the substation relay, and ignores other mechanisms for TOV which may be more relevant to a given application. 8 Potential Solutions
  • 9. Controls Based Approaches Based upon the IEEE C62.92.1 definition, if a generator limits over voltages to less than 140% L-N it is effective grounded. Therefore, any mechanism that achieves this should be valid. Inverters have fast microprocessors onboard. Fast gate blocking an extra high-voltage fast-trip setting is included by most manufacturers for self-protection purposes. Spain and Australia require TOV tests that determine the reaction to a loss of load. They resemble the CBEMA/ITIC curve. The inverter shuts down upon seeing a high terminal voltage. Typically, 1.4 p.u., in 50 ms. Note: these are single phase tests and do not account for different transformer configurations. 9 Potential Solutions
  • 10. Problem: There are many ways to accomplish the aforementioned behavior. Therefore, it is challenging to generalize a given inverter’s behavior. “Rotating machines are 90% physics and 10% engineering design. Inverters are the exact opposite.”- Reigh Walling This is the main issue in predicting the behavior of an inverter during a TOV event. 10 Modeling Considerations
  • 12. Modeling Considerations Variables: 1. Current Sense: RMS or instantaneous in control loop, sequence measurements, phasor average or independent control loops, sampling frequency. 2. Voltage Sensing: 1 or 3 phase, L-N or L-L, phasor average or independent control loops, RMS or instantaneous, sampling rates. 3. Current Control Loop: independent phase control or 3 phase space vector, saturated controls, different inverter bridge topologies. 4. Phase Lock Loop: αβ transform phase angle error. 5. Power Control: reactive power support, Volt/Var functions, power limiting. 12
  • 13. There is an open debate whether defining the symmetrical component impedances of an inverter has merit. But it is generally accepted that a current source model is more accurate. However, this approach has its limitations as well. • Abnormal voltages producing imbalanced currents - non idealized behavior. • Constant power regulation is more common than constant current. Power is regulated in the steady state by an outer loop, typically with slower dynamics than the inner loop which regulates current at high bandwidth. Power regulation also will tend to have limits so that excess current is not ordered during undervoltage conditions. • New functions like LVRT change everything in a snap of the fingers. 100% real power to 100%, VARS in 10ms! How is that accounted for? • Furthermore, most inverters do not inject zero sequence current. Even if the switch controls permitted it, the unit is typically a 3 wire connection without a neutral return. 13 Modeling Considerations
  • 14. Model validation is of course necessary Proposed UL 1741 SLG TOV Test Setup 14 Modeling Considerations Keep in mind: There is more than one mechanism of TOV at play here.
  • 15. Modeling can be a potential powerful tool for assessing the impact of inverters on distribution systems. However, to date, most software packages do not have an accurate model for the inverter. Inverter manufacturers and simulations vendors need to define a library of models that manufacturers can certify their products to. Otherwise there is way too much variability for a generic model to be accurate. Transformers and loads must be considered when simulating an inverter and EPS. The dynamics are determined partly by Ohm’s Law, because of the current-source inverter pushing current into the loads; and partly by the controls of the inverter itself, because its ability to source current does depend on its terminal voltage. In any case, it’s all about the interaction between the inverter and the loads, and not about an inherent GFO mechanism in the inverter, because it doesn’t have one. 15 Conclusions
  • 16. Thank you for your attention! With Special Thanks to Michael Ropp, Northern Plains Power Technologies and Reigh Walling, Walling Energy Systems Consulting 16 Questions
  • 17. 1704/26/14 Effective Grounding Slide References 1. Protection for Unexpected Delta Sources Ken Behrendt Schweitzer Engineering Laboratories, Inc. New Berlin, WI USA 2. A Review of System Grounding Methods and Zero Sequence Current Sources Gerald Johnson (Basler Electric), Mark Schroeder (Dominion VA Power) and Gerald Dalke (Power System Relay Services). 3. Advanced Grid Planning and Operations Mark McGranaghan, Thomas Ortmeyer, David Crudele, Thomas Key, Jeff Smith, Phil Barker. 4. Alternate Energy Customer Interconnection Requirements PECO Solar Conference. Barry Hornberger. June 1, 2011. 5. PECO Grey Book 17