Microsoft Project 101:  How to Build a Project Plan
Overview After this course you will understand and be able to: Set up a project document using best practices Enter task details Enter durations against tasks Link tasks Assign resources Baseline the plan Manage the project plan and track progress
Project Setup Best Practices Iterative Saves and Versions Project information dialog box Project defaults (check them before starting a new project) Project calendar adjustments (holidays, etc..) Task Sheet View for initial task entry  Add columns
Project Information
Project Defaults
Project Defaults
Project Calendars
Views and Columns Task Sheet view Add or hide a columns as necessary Suggested columns: Task Name % Complete Duration Work  Start  Finish Resources
Exercise 1 Setting project defaults
Tasks Project Summary Task Summary Tasks Sub-tasks Task Types  Fixed Units Fixed Work Fixed Duration (recommended) Effort driven
Project Summary Task The project summary task has unique characteristics: ID = 0 Unique ID = 0 Outline Level = 0 Summary – Yes Only project summary tasks can be created at Outline Level 0.
Summary Tasks
Subtasks
Task Types Fixed units  – tasks where the resources are a fixed value & changes to the amount of work or the duration do not affect the resources  Fixed work  – tasks where the amount of work is a fixed value & changes to the duration or the number of resources do not affect the work.  Fixed duration  (recommended) – tasks where the duration is a fixed value & changes to the work or the resources don't affect the duration. Effort Driven  – the duration of a task shortens or lengthens as resources are added or removed from a task while the effort (work) remains the same.
Task Types
Exercise 2 Entering tasks
Task Information Task Information Form Milestone tasks Durations Constraints Dependencies (predecessors)
Task Information Form
Task Information Form
Task Information Form
Task Information Form
Task Information
Milestones
Task Duration When entering task durations, enter the amount of time expected to complete the task Duration abbreviations M = Minutes H = Hours D = Days W = Weeks M = Months
Task Constraints Field dependencies Constraint types As late as possible As soon as possible Finish no earlier than Finish no later than Must finish on Must start on Start no earlier than Start no later than
Task Dependencies Predecessors Finish to Start (FS default) Start to Finish (SF) Start to Start (SS) Finish to Finish (FF rarely used)
Exercise 3 Setting constraints, durations and predecessors
Resources Resource types Entering resources  Assigning resources to a task Understanding “work”
Resource Types Work (people) Material (expenditures) Rates (hourly rate or cost of hardware)
Entering Resources Best done after tasks are entered and linked Assign names and work effort for each individual Duration is the length of time the task will take to complete, entered in days Work is the amount of effort needed to complete the  task, entered in hours
Exercise 4 Entering Resources
Tracking Base lining the project Entering actual information
Base lining the Project Purpose of base lining How to do it Tools, Tracking, Save Baseline Remember to baseline the ENTIRE project!
Entering Actuals Task sheet view Enter actual start date Break links as needed Enter actual duration Enter actual time commitments Set task completion at 100% Sequence is VERY important
Exercise 5 Base lining Entering Actuals
Views, Tables & Filters Views Task Views Gantt Chart Tracking Gantt Chart Custom Views Tables Filters and Groups
Task Sheet Task Sheet Used for reporting Basis for most custom forms
Gantt Chart View
Tracking Gantt
Custom Views Views are made up of Tables Filters Groupings It is highly recommended that you copy the view AND any tables, filters and groups that are used to achieve that view.
Tables A table is the actual spreadsheet presentation of the rows and columns It stores which fields you see and how the columns are ordered
Filters & Groups Filters - a way to select a subset of tasks to be shown in a view.  Groups - a way to organize rows based on field content.  Filters and groups can be used together to order the data or they can be used independently.  Filters and groups can be created using one or more conditions
Exercise 6 Views
Summary Tip of the iceberg (much more capability). MS Project is a tool that aids planning, it won’t plan for you. Need to invest in mastering the tool. MS Project training guides located at  http://www.k-state.edu/InfoTech/epm/training/index.html Iterative saves
Contact Information Peer support – call if you need help Chuck Gould  532- 4923 [email_address] Lloyd Walker 532- 2616 [email_address] Ashley Wondra 532-4761 [email_address]

More Related Content

PDF
Practical Guide to Useful Project Management Plan
PPTX
Business project plan
PDF
Monitoring of project implementation
PDF
How to monitor your project progress
PDF
A brief on project time management
PPTX
Project Management
PPT
Process of Project Planning
PPTX
Project Planning | Accounting
Practical Guide to Useful Project Management Plan
Business project plan
Monitoring of project implementation
How to monitor your project progress
A brief on project time management
Project Management
Process of Project Planning
Project Planning | Accounting

What's hot (20)

PPT
Project Execution
PPTX
Project management life cycle
PPTX
Project Management Steps
PPS
Project Implementation Process
PPTX
Project execution and implementation
PDF
Project Implementation
PPTX
Project engineer
PPTX
Project time management
PPT
5. project activity and risk planning
PPT
Project planning and Scheduling
PDF
Project implimentation
PPTX
Project Management Presentation material
PPTX
Project Planning and Approval Process
PDF
Project Management Training in Indonesia - Module 03 Project Planning Process
PDF
[Guide] How to create a realistic project schedule
PPT
5 project management project planning
PDF
Project Time Management | Project Schedule Management | Edureka
PDF
06 project time management m
PPT
Project managment ppt
PPTX
Project Schedule Management - PMBOK6
Project Execution
Project management life cycle
Project Management Steps
Project Implementation Process
Project execution and implementation
Project Implementation
Project engineer
Project time management
5. project activity and risk planning
Project planning and Scheduling
Project implimentation
Project Management Presentation material
Project Planning and Approval Process
Project Management Training in Indonesia - Module 03 Project Planning Process
[Guide] How to create a realistic project schedule
5 project management project planning
Project Time Management | Project Schedule Management | Edureka
06 project time management m
Project managment ppt
Project Schedule Management - PMBOK6
Ad

Viewers also liked (15)

PPSX
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
PPT
Assessing Strengths and Weaknesses
PPT
The Art Of Assertiveness
PPT
Project Plan Development - A FlackVentures Training Example
PPTX
Assertiveness skills
PPT
Chap 6 Developing A Project Plan
PPT
ASSERTIVENESS POWERPOINT
PDF
Alpha Case Study - Project Management Plan Sample
PPT
Project planning and control
DOC
Project Management Plan Template
PPT
The Project Management Process - Week 1
PPT
Fundamentals of Project Management
PDF
Project Management Concepts (from PMBOK 5th Ed)
PPTX
PMI Project Management Principles
PPTX
Project planning and project work plan
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
Assessing Strengths and Weaknesses
The Art Of Assertiveness
Project Plan Development - A FlackVentures Training Example
Assertiveness skills
Chap 6 Developing A Project Plan
ASSERTIVENESS POWERPOINT
Alpha Case Study - Project Management Plan Sample
Project planning and control
Project Management Plan Template
The Project Management Process - Week 1
Fundamentals of Project Management
Project Management Concepts (from PMBOK 5th Ed)
PMI Project Management Principles
Project planning and project work plan
Ad

Similar to Microsoft_Project_101_How_to_Build_a_Project_Plan. (20)

PPT
Ms Project
PDF
Microsoft Project Course with PMP Concepts
PPT
Ms Project 2007(Basic)
PPTX
Microsoft Project Foundations Course.pptx
PPTX
PMP Muzette Charles_Spring2019_Week3_Chapter6
PPT
Project Planning Basics - Everything you need to start managing a project
PPT
PMP Exam Prep - Time Management
PPT
Project management teaching
PPS
MS Project Svcs Productivity
PPT
Project Planning Scheduling
PPT
Ch03
PPT
Training pm jan 11 part b
PPT
Production & Operation Management
PPT
Project Planning
 
PPTX
MIS Project management
PPSX
Planning and Resourcing a Project
PPT
Business Intelligence Project
PDF
Ms project2007 quickguide
PDF
Ms project2007 quickguide
PPT
Job Design and Work Measurement
Ms Project
Microsoft Project Course with PMP Concepts
Ms Project 2007(Basic)
Microsoft Project Foundations Course.pptx
PMP Muzette Charles_Spring2019_Week3_Chapter6
Project Planning Basics - Everything you need to start managing a project
PMP Exam Prep - Time Management
Project management teaching
MS Project Svcs Productivity
Project Planning Scheduling
Ch03
Training pm jan 11 part b
Production & Operation Management
Project Planning
 
MIS Project management
Planning and Resourcing a Project
Business Intelligence Project
Ms project2007 quickguide
Ms project2007 quickguide
Job Design and Work Measurement

More from TURKI , PMP (10)

PDF
Human Resources KPIs
PPT
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
PDF
Microsoft Office Excel 2007 for Project Managers
PDF
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
PDF
Project Management Definitions
PDF
PMP Question Bank
PPT
How To Build A PMO
PPT
PMO Presentation
PPT
Implementing PMO
PPT
Microsoft_Office_Visio_Professional_2007_for_IT_How_to_Use_Visio_
Human Resources KPIs
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Microsoft Office Excel 2007 for Project Managers
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Project Management Definitions
PMP Question Bank
How To Build A PMO
PMO Presentation
Implementing PMO
Microsoft_Office_Visio_Professional_2007_for_IT_How_to_Use_Visio_

Recently uploaded (20)

PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PDF
Laughter Yoga Basic Learning Workshop Manual
PPTX
Probability Distribution, binomial distribution, poisson distribution
PDF
How to Get Funding for Your Trucking Business
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PDF
MSPs in 10 Words - Created by US MSP Network
PPT
Data mining for business intelligence ch04 sharda
PPTX
Lecture (1)-Introduction.pptx business communication
PPTX
Business Ethics - An introduction and its overview.pptx
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PPTX
5 Stages of group development guide.pptx
PDF
Roadmap Map-digital Banking feature MB,IB,AB
DOCX
Euro SEO Services 1st 3 General Updates.docx
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PPTX
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
340036916-American-Literature-Literary-Period-Overview.ppt
Laughter Yoga Basic Learning Workshop Manual
Probability Distribution, binomial distribution, poisson distribution
How to Get Funding for Your Trucking Business
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
MSPs in 10 Words - Created by US MSP Network
Data mining for business intelligence ch04 sharda
Lecture (1)-Introduction.pptx business communication
Business Ethics - An introduction and its overview.pptx
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
New Microsoft PowerPoint Presentation - Copy.pptx
5 Stages of group development guide.pptx
Roadmap Map-digital Banking feature MB,IB,AB
Euro SEO Services 1st 3 General Updates.docx
COST SHEET- Tender and Quotation unit 2.pdf
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx

Microsoft_Project_101_How_to_Build_a_Project_Plan.

  • 1. Microsoft Project 101: How to Build a Project Plan
  • 2. Overview After this course you will understand and be able to: Set up a project document using best practices Enter task details Enter durations against tasks Link tasks Assign resources Baseline the plan Manage the project plan and track progress
  • 3. Project Setup Best Practices Iterative Saves and Versions Project information dialog box Project defaults (check them before starting a new project) Project calendar adjustments (holidays, etc..) Task Sheet View for initial task entry Add columns
  • 8. Views and Columns Task Sheet view Add or hide a columns as necessary Suggested columns: Task Name % Complete Duration Work Start Finish Resources
  • 9. Exercise 1 Setting project defaults
  • 10. Tasks Project Summary Task Summary Tasks Sub-tasks Task Types Fixed Units Fixed Work Fixed Duration (recommended) Effort driven
  • 11. Project Summary Task The project summary task has unique characteristics: ID = 0 Unique ID = 0 Outline Level = 0 Summary – Yes Only project summary tasks can be created at Outline Level 0.
  • 14. Task Types Fixed units – tasks where the resources are a fixed value & changes to the amount of work or the duration do not affect the resources Fixed work – tasks where the amount of work is a fixed value & changes to the duration or the number of resources do not affect the work. Fixed duration (recommended) – tasks where the duration is a fixed value & changes to the work or the resources don't affect the duration. Effort Driven – the duration of a task shortens or lengthens as resources are added or removed from a task while the effort (work) remains the same.
  • 17. Task Information Task Information Form Milestone tasks Durations Constraints Dependencies (predecessors)
  • 24. Task Duration When entering task durations, enter the amount of time expected to complete the task Duration abbreviations M = Minutes H = Hours D = Days W = Weeks M = Months
  • 25. Task Constraints Field dependencies Constraint types As late as possible As soon as possible Finish no earlier than Finish no later than Must finish on Must start on Start no earlier than Start no later than
  • 26. Task Dependencies Predecessors Finish to Start (FS default) Start to Finish (SF) Start to Start (SS) Finish to Finish (FF rarely used)
  • 27. Exercise 3 Setting constraints, durations and predecessors
  • 28. Resources Resource types Entering resources Assigning resources to a task Understanding “work”
  • 29. Resource Types Work (people) Material (expenditures) Rates (hourly rate or cost of hardware)
  • 30. Entering Resources Best done after tasks are entered and linked Assign names and work effort for each individual Duration is the length of time the task will take to complete, entered in days Work is the amount of effort needed to complete the task, entered in hours
  • 31. Exercise 4 Entering Resources
  • 32. Tracking Base lining the project Entering actual information
  • 33. Base lining the Project Purpose of base lining How to do it Tools, Tracking, Save Baseline Remember to baseline the ENTIRE project!
  • 34. Entering Actuals Task sheet view Enter actual start date Break links as needed Enter actual duration Enter actual time commitments Set task completion at 100% Sequence is VERY important
  • 35. Exercise 5 Base lining Entering Actuals
  • 36. Views, Tables & Filters Views Task Views Gantt Chart Tracking Gantt Chart Custom Views Tables Filters and Groups
  • 37. Task Sheet Task Sheet Used for reporting Basis for most custom forms
  • 40. Custom Views Views are made up of Tables Filters Groupings It is highly recommended that you copy the view AND any tables, filters and groups that are used to achieve that view.
  • 41. Tables A table is the actual spreadsheet presentation of the rows and columns It stores which fields you see and how the columns are ordered
  • 42. Filters & Groups Filters - a way to select a subset of tasks to be shown in a view. Groups - a way to organize rows based on field content. Filters and groups can be used together to order the data or they can be used independently. Filters and groups can be created using one or more conditions
  • 44. Summary Tip of the iceberg (much more capability). MS Project is a tool that aids planning, it won’t plan for you. Need to invest in mastering the tool. MS Project training guides located at http://www.k-state.edu/InfoTech/epm/training/index.html Iterative saves
  • 45. Contact Information Peer support – call if you need help Chuck Gould 532- 4923 [email_address] Lloyd Walker 532- 2616 [email_address] Ashley Wondra 532-4761 [email_address]