2
Contents
Introduction.................................................................................................................................................3
Change Request Process Flow ...................................................................................................................3
Change Control Board ...............................................................................................................................4
Change Request Template: ........................................................................................................................5
Change Log..................................................................................................................................................6
3
Introduction
The Change Management Plan of our project documents and tracks the necessary information
required to effectively manage project change from project inception to delivery. The Change
Management Plan has been created during the Planning Phase of the project and is included in the
planning document.
Change Request Process Flow
Step Description
Generate Change
Request
A submitter completes a CR request and sends the completed request to the
Change Manager
Log Change
Request Status
The Change Manager enters the CR into the CR Log. The CR’s status is updated
throughout the CR process as needed.
Evaluate Change
Request
Project personnel review the CR and provide an estimated level of effort to
process, and develop a proposed solution for the suggested change
Authorize Approval to move forward with incorporating the suggested change into the
project
Implement If approved, make the necessary adjustments to carry out the requested change
and communicate CR status to the submitter and other stakeholders
Change requests are evaluated and assigned one or more of the following change types:
Scope Time Change affecting time Duration Change affecting duration Cost Change affecting
time Resources Change affecting resources Deliverables Change affecting deliverables Product
Change affecting product Processes product Quality Change affecting quality
Type Description
Scope Change affecting scope
Time Change affecting time
Duration Change affecting time
Cost Change affecting cost
Resources Change affecting resources
Deliverables Change affecting deliverables
Product Change affecting product
Processes Change affecting Processes
Quality Change affecting Quality
4
Change requests are evaluated and assigned one of the following status types:
Status Description
Open Entered/Open but not yet approved or assigned
Work in
Progress
CR approved, assigned, and work is progressing
In review CR approved, assigned, and work is progressing
Testing CR work has been reviewed and is being tested
Closed CR work is complete, has passed all tests, and updates have been released.
Change Control Board
Name Position CCB Role
Md. Adiluzzaman Adil Project Manager CCB Manager
Kishan kumar Ganguly
Md. Rakib Hossain
Software Architect & Developer CCB Member
Minhas Kamal
A.H.M. Azimul Haque
Designer & Developer CCB Member
Mostaque Ahmed
Israt Fatema Shantu
Documentation CCB Member
5
Change Request Template:
We have used the following form template for change request:
Change Request
Project: Date:
Change Requestor: Change No:
Change Category (Check all that apply):
□ Schedule □ Cost □ Scope □ Requirements/Deliverables
□ Testing/Quality □ Resources
Does this Change Affect (Check all that apply):
□ Corrective Action □ Preventative Action □ Defect Repair □ Updates
□ Other
Describe the Change Being Requested:
Describe the Reason for the Change:
Describe all Alternatives Considered:
Describe any Technical Changes Required to Implement this Change:
Describe Risks to be Considered for this Change:
Estimate Resources and Costs Needed to Implement this Change:
Describe the Implications to Quality:
Disposition:
□ Approve □ Reject □ Defer
Justification of Approval, Rejection, or Deferral:
Change Board Approval:
Name Signature Date
6
Change Log
Change Log
Project: Network Upgrade Project Date: 04/01/20xx
Change
No.
Change
Type
Description of
Change
Requestor Date
Submitted
Date
Approved
Status Comments
CR001 Equipment This change
request calls
for the
purchase of
wlan routers.
Minhas
Kamal
07/08/16 08/08/16 Denied This request was
denied by the
change control
board because
there is not
adequate funding
available for the
purchase of new
routers and
because the
request is outside
of the project's
scope.
CR002 Schedule This change
request calls
for delaying
the existing
schedule by
one week to
ensure all
applications
are backed up
which was not
considered in
the original
project plan.
Kishan
Kumar
Ganguly
03/11/16 08/11/16 Approved This request was
approved to
ensure the
security and
continuity of all
applications. One
week will be
added to the
project schedule
and the project
manager will
communicate the
impact of this
change to all
stakeholders.

More Related Content

PDF
DevSecOps: Taking a DevOps Approach to Security
PPTX
Oracle Forms to APEX conversion tool
PPTX
Automation Testing
PDF
Inverting The Testing Pyramid
PPTX
Code Review Best Practices
PPSX
HP ALM QC
DevSecOps: Taking a DevOps Approach to Security
Oracle Forms to APEX conversion tool
Automation Testing
Inverting The Testing Pyramid
Code Review Best Practices
HP ALM QC

What's hot (20)

PPTX
Software testing and quality assurance
PDF
Getting Started With Cypress
PPSX
HP ALM
PPT
Configuration Management
PDF
Tech Talk #5 : Code Analysis SonarQube - Lương Trọng Nghĩa
PDF
An Introduction To Automated API Testing
PPTX
Track code quality with SonarQube - short version
PPTX
Api testing
PPTX
Jira overview
PDF
Performance testing presentation
PPTX
Test planning
ODP
API Testing With Katalon Studio
PDF
Official "push" and real-time capabilities for Symfony and API Platform (Merc...
PPT
JIRA-An intro
PDF
QA interview questions and answers
PDF
QA Center Of Excellence (TCoE)
PPTX
Test Case Management Tools
PDF
DevSecOps What Why and How
PPT
Introduction to the Web API
PPTX
DevSecOps
Software testing and quality assurance
Getting Started With Cypress
HP ALM
Configuration Management
Tech Talk #5 : Code Analysis SonarQube - Lương Trọng Nghĩa
An Introduction To Automated API Testing
Track code quality with SonarQube - short version
Api testing
Jira overview
Performance testing presentation
Test planning
API Testing With Katalon Studio
Official "push" and real-time capabilities for Symfony and API Platform (Merc...
JIRA-An intro
QA interview questions and answers
QA Center Of Excellence (TCoE)
Test Case Management Tools
DevSecOps What Why and How
Introduction to the Web API
DevSecOps
Ad

Viewers also liked (20)

PDF
Software Project Management: Testing Document
PDF
Project Proposal: Bengali Braille to Text Translation
PDF
Software Project Management: Release Notes
PDF
Software Project Management: Configuration Management
PDF
Proposal: A Study on Business Communucation System of KAZ Software
PDF
Software Requirements Specification on Bengali Braille to Text Translator
PDF
Software Project Management: Project Planning
PDF
Software Project Management: Project Summary
PDF
Software Project Management: Budget
PPTX
Software Project Management Presentation Final
PDF
Software Project Management: Project Initiation
PPTX
Software Project Proposal: Bengali Braille to Text Translation
PDF
Software Project Management: Risk Management
PDF
Software Project Management: Project Charter
PDF
Software Project Management: Business Case
PDF
Final Internship Report
PPT
How the change control process affects project quality
PDF
Letter of Endorsement Sample
PDF
Report Acknowledgement Sample
PDF
Software Requirements Specification on Student Information System (SRS on SIS)
Software Project Management: Testing Document
Project Proposal: Bengali Braille to Text Translation
Software Project Management: Release Notes
Software Project Management: Configuration Management
Proposal: A Study on Business Communucation System of KAZ Software
Software Requirements Specification on Bengali Braille to Text Translator
Software Project Management: Project Planning
Software Project Management: Project Summary
Software Project Management: Budget
Software Project Management Presentation Final
Software Project Management: Project Initiation
Software Project Proposal: Bengali Braille to Text Translation
Software Project Management: Risk Management
Software Project Management: Project Charter
Software Project Management: Business Case
Final Internship Report
How the change control process affects project quality
Letter of Endorsement Sample
Report Acknowledgement Sample
Software Requirements Specification on Student Information System (SRS on SIS)
Ad

Similar to Software Project Management: Change Control (20)

PPTX
Assisit with devlopment.pptx
PDF
PMP Change Request Process
DOC
Project change request template v2.0
PDF
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
PDF
Change management in Software Engineering
DOC
Change controlform
PPTX
ITIL # Lecture 3
PDF
Change Control Process Identification Evaluation Engineering Fulfillment Requ...
PPTX
Software configuration management
DOCX
Change management plan_template
DOCX
CHANGE MANAGEMENT PLAN TEMPLATEIntroductionStart the developme.docx
PPTX
Change Management - UC Berkeley Extension
PPT
Numara change & approval mgmt
PPT
SFHDI presents: Numara Software - Change & Approval Management
PPTX
Change Request Template for 192.168.pptx
PDF
9 Trng6_Change_Management_CIT.pdf
DOC
Change request form_template
PPT
IT Change Control Process
PPSX
Requirement Management
PDF
Change Plan Template and Example
Assisit with devlopment.pptx
PMP Change Request Process
Project change request template v2.0
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
Change management in Software Engineering
Change controlform
ITIL # Lecture 3
Change Control Process Identification Evaluation Engineering Fulfillment Requ...
Software configuration management
Change management plan_template
CHANGE MANAGEMENT PLAN TEMPLATEIntroductionStart the developme.docx
Change Management - UC Berkeley Extension
Numara change & approval mgmt
SFHDI presents: Numara Software - Change & Approval Management
Change Request Template for 192.168.pptx
9 Trng6_Change_Management_CIT.pdf
Change request form_template
IT Change Control Process
Requirement Management
Change Plan Template and Example

More from Minhas Kamal (12)

PPTX
Digital Image Processing
PPTX
Deep Learning - Exploring The Magical World of Neural Network
PPTX
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
PPTX
Artificial Intelligence - Staring at The Grand Universe of AI (1)
PDF
Final Project Report- Bengali Braille to Text Translator
PDF
Abstract- Bengali Braille to Text Translator
PDF
Software Project Management: Software Architecture
PDF
Software Project Management: Software Requirement Specification
PPTX
Software Design: User Interface Design
PPTX
Business Communication System: KAZ Software
PPTX
Final Internship Presentation
PDF
Letter of Transmittal
Digital Image Processing
Deep Learning - Exploring The Magical World of Neural Network
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
Artificial Intelligence - Staring at The Grand Universe of AI (1)
Final Project Report- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text Translator
Software Project Management: Software Architecture
Software Project Management: Software Requirement Specification
Software Design: User Interface Design
Business Communication System: KAZ Software
Final Internship Presentation
Letter of Transmittal

Recently uploaded (20)

PPTX
Oracle E-Business Suite: A Comprehensive Guide for Modern Enterprises
PDF
Nekopoi APK 2025 free lastest update
PDF
System and Network Administration Chapter 2
PPTX
ManageIQ - Sprint 268 Review - Slide Deck
PDF
medical staffing services at VALiNTRY
PPTX
L1 - Introduction to python Backend.pptx
PDF
Softaken Excel to vCard Converter Software.pdf
PDF
How to Choose the Right IT Partner for Your Business in Malaysia
PDF
2025 Textile ERP Trends: SAP, Odoo & Oracle
PPTX
Operating system designcfffgfgggggggvggggggggg
PDF
Which alternative to Crystal Reports is best for small or large businesses.pdf
PDF
Design an Analysis of Algorithms II-SECS-1021-03
PDF
Audit Checklist Design Aligning with ISO, IATF, and Industry Standards — Omne...
PDF
Addressing The Cult of Project Management Tools-Why Disconnected Work is Hold...
PDF
Internet Downloader Manager (IDM) Crack 6.42 Build 42 Updates Latest 2025
PPTX
Agentic AI Use Case- Contract Lifecycle Management (CLM).pptx
PDF
T3DD25 TYPO3 Content Blocks - Deep Dive by André Kraus
PDF
Upgrade and Innovation Strategies for SAP ERP Customers
PPTX
Online Work Permit System for Fast Permit Processing
PPTX
Agentic AI : A Practical Guide. Undersating, Implementing and Scaling Autono...
Oracle E-Business Suite: A Comprehensive Guide for Modern Enterprises
Nekopoi APK 2025 free lastest update
System and Network Administration Chapter 2
ManageIQ - Sprint 268 Review - Slide Deck
medical staffing services at VALiNTRY
L1 - Introduction to python Backend.pptx
Softaken Excel to vCard Converter Software.pdf
How to Choose the Right IT Partner for Your Business in Malaysia
2025 Textile ERP Trends: SAP, Odoo & Oracle
Operating system designcfffgfgggggggvggggggggg
Which alternative to Crystal Reports is best for small or large businesses.pdf
Design an Analysis of Algorithms II-SECS-1021-03
Audit Checklist Design Aligning with ISO, IATF, and Industry Standards — Omne...
Addressing The Cult of Project Management Tools-Why Disconnected Work is Hold...
Internet Downloader Manager (IDM) Crack 6.42 Build 42 Updates Latest 2025
Agentic AI Use Case- Contract Lifecycle Management (CLM).pptx
T3DD25 TYPO3 Content Blocks - Deep Dive by André Kraus
Upgrade and Innovation Strategies for SAP ERP Customers
Online Work Permit System for Fast Permit Processing
Agentic AI : A Practical Guide. Undersating, Implementing and Scaling Autono...

Software Project Management: Change Control

  • 1. 1 ResearchColab Change Control Team: Reckless 7 Institute of Information Technology University of Dhaka 25th November, 2016
  • 2. 2 Contents Introduction.................................................................................................................................................3 Change Request Process Flow ...................................................................................................................3 Change Control Board ...............................................................................................................................4 Change Request Template: ........................................................................................................................5 Change Log..................................................................................................................................................6
  • 3. 3 Introduction The Change Management Plan of our project documents and tracks the necessary information required to effectively manage project change from project inception to delivery. The Change Management Plan has been created during the Planning Phase of the project and is included in the planning document. Change Request Process Flow Step Description Generate Change Request A submitter completes a CR request and sends the completed request to the Change Manager Log Change Request Status The Change Manager enters the CR into the CR Log. The CR’s status is updated throughout the CR process as needed. Evaluate Change Request Project personnel review the CR and provide an estimated level of effort to process, and develop a proposed solution for the suggested change Authorize Approval to move forward with incorporating the suggested change into the project Implement If approved, make the necessary adjustments to carry out the requested change and communicate CR status to the submitter and other stakeholders Change requests are evaluated and assigned one or more of the following change types: Scope Time Change affecting time Duration Change affecting duration Cost Change affecting time Resources Change affecting resources Deliverables Change affecting deliverables Product Change affecting product Processes product Quality Change affecting quality Type Description Scope Change affecting scope Time Change affecting time Duration Change affecting time Cost Change affecting cost Resources Change affecting resources Deliverables Change affecting deliverables Product Change affecting product Processes Change affecting Processes Quality Change affecting Quality
  • 4. 4 Change requests are evaluated and assigned one of the following status types: Status Description Open Entered/Open but not yet approved or assigned Work in Progress CR approved, assigned, and work is progressing In review CR approved, assigned, and work is progressing Testing CR work has been reviewed and is being tested Closed CR work is complete, has passed all tests, and updates have been released. Change Control Board Name Position CCB Role Md. Adiluzzaman Adil Project Manager CCB Manager Kishan kumar Ganguly Md. Rakib Hossain Software Architect & Developer CCB Member Minhas Kamal A.H.M. Azimul Haque Designer & Developer CCB Member Mostaque Ahmed Israt Fatema Shantu Documentation CCB Member
  • 5. 5 Change Request Template: We have used the following form template for change request: Change Request Project: Date: Change Requestor: Change No: Change Category (Check all that apply): □ Schedule □ Cost □ Scope □ Requirements/Deliverables □ Testing/Quality □ Resources Does this Change Affect (Check all that apply): □ Corrective Action □ Preventative Action □ Defect Repair □ Updates □ Other Describe the Change Being Requested: Describe the Reason for the Change: Describe all Alternatives Considered: Describe any Technical Changes Required to Implement this Change: Describe Risks to be Considered for this Change: Estimate Resources and Costs Needed to Implement this Change: Describe the Implications to Quality: Disposition: □ Approve □ Reject □ Defer Justification of Approval, Rejection, or Deferral: Change Board Approval: Name Signature Date
  • 6. 6 Change Log Change Log Project: Network Upgrade Project Date: 04/01/20xx Change No. Change Type Description of Change Requestor Date Submitted Date Approved Status Comments CR001 Equipment This change request calls for the purchase of wlan routers. Minhas Kamal 07/08/16 08/08/16 Denied This request was denied by the change control board because there is not adequate funding available for the purchase of new routers and because the request is outside of the project's scope. CR002 Schedule This change request calls for delaying the existing schedule by one week to ensure all applications are backed up which was not considered in the original project plan. Kishan Kumar Ganguly 03/11/16 08/11/16 Approved This request was approved to ensure the security and continuity of all applications. One week will be added to the project schedule and the project manager will communicate the impact of this change to all stakeholders.