Project Summary
Team: Reckless 7
Institute of Information Technology
University of Dhaka
25th
November, 2016
2
Contents
Project Summary............................................................................................................................. 3
Executive Summary........................................................................................................................ 3
Project Team and Staffing .............................................................................................................. 3
Project Deliverables (Planned vs. Actual) ...................................................................................... 4
Project Major Activities and Milestones......................................................................................... 5
Transition to Operations ................................................................................................................. 7
Recommendations........................................................................................................................... 7
3
Project Summary
Team Reckless 7 recently completed the ResearchColab Project which has been deployed
successfully. This marks the end of a difficult but successful project for the Reckless 7
group.
The main objective of this document is to provide an overall view of the project and discuss
main learnings of the project. Another objective is to provide indicators for assessing the
success of the project and provide recommendations for use in similar projects in future.
Finally, the main goal of this document is to formally close the project summarizing all
required information.
Executive Summary
The project is for a web application called ResearchColab.com which offers review and data
sharing service and a discussion platform for researchers. To avail these services, users need
to register as either a researcher or a reviewer. A researcher will post a review request and the
reviewers will bid for it. The poster will then see the list of interested reviewers and choose
the most suitable candidate and have a one to one communication with the person in order to
hire him for the paper review. Researches can also post data on the website that can be used
in further researches. The data can either be free or paid. A discussion system will also help
the researchers to discuss research related topics in the discussion room.
Project Team and Staffing
The ResearchColab project consisted of a skilled and knowledgeable team. The chart below
provides information about the project team members:
Name Assigned task Contact
Md. Adiluzzaman Adil Project Management adil@researchcolab.com
Minhas Kamal System Analysis minhas@researchcolab.com
Kishan Kumar Ganguly Development kishan@researchcolab.com
Md. Rakib Hossain Quality Assurance rakib@researchcolab.com
Mostaque Ahmed Documentation mostaque@researchcolab.com
A.H.M. Azimul Haque Communication &
Collaboration
azimul@researchcolab.com
Israt Fatema Shantu Documentation shantu@researchcolab.com
ResearchColab project team members utilized standard project management methodologies
to successfully complete the project. The project team was a matrixed organization with full
support from functional managers and senior leadership. Effective communication, detailed
planning, stakeholder involvement, project management tools, and organizational structure
all played key roles in the project’s success.
Staffing lessons from previous projects were used in building the project team. Rather than
allocate too many resources, as some past projects have done, the team was staffed with one
4
resource per development area. The project sponsor made clear to the project manager that if
any additional resources were required, they must be requested through standard channels
and the impact on project cost and schedule would need to be defined.
Project Deliverables (Planned vs. Actual)
The ResearchColab project has been completed successfully. There were planned
deliverables for each phase of this project as well as for the completed product. This section
highlights the planned deliverables and compares them to actual deliverables as they
occurred.
Planned
Deliverable
Actual Deliverable Summary
Project
Management
Reports.
The team provided the entire project plan. It
contains which development process to follow, how
to coordinate between team members, which
development tools to follow.
This deliverable was
completed as
planned
SRS & Design
document
The analyst team provided the architecture of the
software and UX design is described in this report.
This deliverable was
completed as
planned
Configuration
Manual
The documentation team provided with a
configuration manual that describes about how to
configure the tools and what environment is
required for running the software.
This deliverable was
completed as
planned
Executable code
module
The development team has deployed the actual web
application to be used.
This deliverable was
completed as
planned
In summary all documented project deliverables have been met by the MicroFiber project
team. All stakeholders have submitted their feedback and acknowledge that there are no
deliverables which were missed or omitted for this project.
5
Project Major Activities and Milestones
Main Activity
Planne
d
Time
(days)
Actual
Time
(days)
Time
Deviation
(days)
Major Reason for deviation
Starting Project and Defining Scope
and Objectives
15 15 0
Developing Project Charter 4 4 0
Receiving Project Charter Approval 5 5 0
Project Plan Development 4 6 2
Additional time needed on risk
identification and deciding performance
indicators
Project Plan Approval 2 2 0
Requirement Specification 4 4 0
Design 4 3 -1
Some component logics were reusable
across the whole architecture
Development 5 5 0
Testing 3 3 0
Installing Live System 2 4 2
Time deviation due to installation
problem in the production environment
Update Documents 2 3 0
Additional time spent on finding
traceability of documents and fixing
these
Gain Formal Acceptance and Close
Project
1 1 0
Project End 51 55 4
6
Project Cost
The budgeted cost for the Researchcolab.com Project was set at 7,23,500/=BDT. This cost
was broken out by project phase in the following chart with actual costs compared to the
planned/budgeted cost.
Project Phase Budgeted Cost Actual Cost Comments
 Project staffing 63,000/= BDT 65,000/= BDT Staffing cost were
over budget due to
Schedule pressure
 Logistic 11,500/= BDT 10000/= BDT Logistics were over
budget due to under
estimation
 Utility 7,000/=BDT 6000/= BDT Utility costs came in
under budget
 Miscellaneous 2,000/=BDT 5000/= BDT Miscellaneous cost
was over budget
 Laptop 2,80,000/=BDT 2,80,000/=BDT costs were on budget
 Desktop 1,20,000/=BDT 1,20,000/=BDT costs were on budget
 Premises 2,40,000/=BDT 2,20,000/=BDT costs were on budget
Total actual costs of the Researchcolab.com Project amounted to 706,000/=BDT. The
Researchcolab.com project was not only successful in meeting all of its objectives and
deliverables, but by completing under budget, it also allowed project team to allocate
17500/=BDT to other important initiatives.
Project Schedule
The Researchcolab.com Project schedule called for a four-month project with initiation
beginning on September 29, 2016 and project closeout ending on November 26, 2016. There
were initial concerns by the project team that the schedule would potentially slip due to
limited number of resources and time to the project. The below chart shows each phase of the
project lifecycle, the planned schedule dates, and the actual completion dates of each phase.
Project Phase Scheduled
Completion
Actual Completion Comments
Initiation September 29, 2016 September 29, 2016 Completed on time
Planning October 30, 2016 October 30, 2016 Completed on time
Design November 8, 2016 November 8, 2016 Completed on time
Build November 12, 2016 November 20, 2016 Not Completed on time
Testing November 15, 2016 November 22, 2016 Completed on time
Trial Build/Install November 22, 20xx November 25, 2016 Not Completed on time
Transition to Ops November 22, 2016 November 26, 2016 Not Completed on time
Project Closure November 26, 2016 TBD Progressing on time
7
The Researchcolab.com Project successfully completed most of the phase on time which can be
attributed to effective planning and communication as well as sponsor support of this important
initiative.
During the initiation and planning phases there was concern among the team members that there
were inadequate resources assigned to this project. However, due to team members experience,
additional resources were not needed and the assigned staff was adequate to complete all work
packages in the planned timeframes.
The only project phase which encountered schedule problems were the build and trail builds
phase.
Transition to Operations
Transition of a project to an operational environment can be a challenging task for many
organizations. The ResearchColab project was successfully transitioned to operations as a
direct result of effective communication and detailed planning. The inclusion of the effective
members as stakeholders ensured a collective approach to the creation of an improved
product which could be transitioned smoothly to a manufacturing environment.
Future projects can benefit by involving operations staff early in the project planning phase
and soliciting input from operations team members on important considerations for the
project from an operational perspective. The project team was not only successful in
communicating and planning with operations staff but they leveraged these strengths to
determine expectations of what operations required as part of the transition. In this case, the
project team was able to develop complete technical data packages and process specifications
for operations to use in the manufacturing of the product. This resulted in an almost
seamless transition of product lines on the development floor. If the operations staff had not
been included as stakeholders nor participated in the project planning, it is likely this step
would have been overlooked and the project would have encountered delays and additional
costs.
Recommendations
The ResearchColab Project was an example of a carefully planned and successfully executed
project for Reckless 7. However, it is not without its recommendations or lessons learned.
Recommendation #1:
Involve operations personnel during the initiation phase for new product development
projects so they are involved during every step of the planning and execution process. This
is imperative in establishing familiarity with the product and processes as well as establishing
expectations of what operations will require during transition.
8
Recommendation #2:
Researching previous project archives was extremely beneficial in establishing budgets and
schedules for project phases. As a result of studying documentation from similar past
projects the project team was able to accurately determine budgets, work packages required,
and resource allocation.
Recommendation #3:
The most challenging part was the planning of the budget and timeline. Although the project
team successfully met the budget constrain, the schedule was a bit off track. Its
recommended to be careful the next time.

More Related Content

PDF
Software Project Management: Project Planning
PDF
Software Project Management: Project Initiation
PDF
Introduction To Jira
PPTX
Know the project kickoff meeting and project execution plan
PPT
What Is A Sprint Planning Meeting
PPTX
Jira overview
PPT
Agile Scrum Methodology
PDF
Agile Methodology
Software Project Management: Project Planning
Software Project Management: Project Initiation
Introduction To Jira
Know the project kickoff meeting and project execution plan
What Is A Sprint Planning Meeting
Jira overview
Agile Scrum Methodology
Agile Methodology

What's hot (20)

PPTX
Product backlog
PDF
Software Project Management: Business Case
PDF
Project scope and requirements management
PDF
Jira Agile
PDF
Project scope management
PDF
Agile software development
DOCX
Low level design template (1)
PDF
Waterfall vs Agile : A Beginner's Guide in Project Management
PPTX
Release Planning. For Agile Teams. A Quick Overview
PPT
Project Status Report
PDF
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
PPT
Scrum ppt
PDF
Software Project Management: Project Charter
PDF
Jira as a Project Management Tool
ODP
Scrum in 15 Minutes
PPTX
Scrum ceromonies
PPT
Scrum In 15 Minutes
PPT
What Is Agile Scrum
PPTX
Agile methodology
Product backlog
Software Project Management: Business Case
Project scope and requirements management
Jira Agile
Project scope management
Agile software development
Low level design template (1)
Waterfall vs Agile : A Beginner's Guide in Project Management
Release Planning. For Agile Teams. A Quick Overview
Project Status Report
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
Scrum ppt
Software Project Management: Project Charter
Jira as a Project Management Tool
Scrum in 15 Minutes
Scrum ceromonies
Scrum In 15 Minutes
What Is Agile Scrum
Agile methodology
Ad

Viewers also liked (20)

PDF
Software Project Management: Budget
PDF
Letter of Endorsement Sample
PDF
Numerical Method Analysis: Algebraic and Transcendental Equations (Non-Linear)
PDF
Software Project Management: Testing Document
PPTX
Software Project Management Presentation Final
PPTX
Software Project Proposal: Bengali Braille to Text Translation
PDF
Project Proposal: Bengali Braille to Text Translation
PDF
Software Project Management: Release Notes
PDF
Software Project Management: Configuration Management
PDF
Proposal: A Study on Business Communucation System of KAZ Software
PDF
Software Requirements Specification on Bengali Braille to Text Translator
PDF
Software Project Management: Change Control
PDF
Software Project Management: Risk Management
PDF
Final Internship Report
PDF
Software Requirements Specification on Student Information System (SRS on SIS)
PDF
Report Acknowledgement Sample
PPTX
Software Project Presentation: Leaf Me Alone
PPTX
Case Study- Software as a Service (SaaS)
PDF
Numerical Method Analysis: Algebraic and Transcendental Equations (Linear)
PPTX
Amazing Math Tips & Tricks
Software Project Management: Budget
Letter of Endorsement Sample
Numerical Method Analysis: Algebraic and Transcendental Equations (Non-Linear)
Software Project Management: Testing Document
Software Project Management Presentation Final
Software Project Proposal: Bengali Braille to Text Translation
Project Proposal: Bengali Braille to Text Translation
Software Project Management: Release Notes
Software Project Management: Configuration Management
Proposal: A Study on Business Communucation System of KAZ Software
Software Requirements Specification on Bengali Braille to Text Translator
Software Project Management: Change Control
Software Project Management: Risk Management
Final Internship Report
Software Requirements Specification on Student Information System (SRS on SIS)
Report Acknowledgement Sample
Software Project Presentation: Leaf Me Alone
Case Study- Software as a Service (SaaS)
Numerical Method Analysis: Algebraic and Transcendental Equations (Linear)
Amazing Math Tips & Tricks
Ad

Similar to Software Project Management: Project Summary (20)

PDF
Project Brief Summary PowerPoint Presentation Slides
DOCX
Hello Class- This is a very rough draft of the assignment. I have
PPTX
Projects2016_Franks_PreparingFortheParty-Project Close
DOCX
COMP6214 Project 2.docx
PPT
15 Deliv template
DOCX
Running Head Project Overview Statement1Project Overview Stat.docx
PPTX
Module 4 Project management by ranjan v.pptx
PPTX
Software Requiremnet analysis module 2.pptx
PDF
C. Burcham - Project Closure Report
PPT
Software Engineering (Project Scheduling)
PPT
lecture8-190719030939.ppthjtyuiytiytiyti
PPTX
Project Scheduling
PDF
Project Management Controlling And Monitoring PowerPoint Presentation Slides
PPTX
Untitled presentation that says about nigelous
PDF
Project Management Controlling And Monitoring Powerpoint Presentation Slides
PPTX
You_Exec_-_Ultimate_Project_Management_Toolbox_Free.pptx
PPTX
Software Project Requirement and Team Requirement Model
PPTX
Planning with numbers
DOCX
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docx
PPT
Sas Presentation
Project Brief Summary PowerPoint Presentation Slides
Hello Class- This is a very rough draft of the assignment. I have
Projects2016_Franks_PreparingFortheParty-Project Close
COMP6214 Project 2.docx
15 Deliv template
Running Head Project Overview Statement1Project Overview Stat.docx
Module 4 Project management by ranjan v.pptx
Software Requiremnet analysis module 2.pptx
C. Burcham - Project Closure Report
Software Engineering (Project Scheduling)
lecture8-190719030939.ppthjtyuiytiytiyti
Project Scheduling
Project Management Controlling And Monitoring PowerPoint Presentation Slides
Untitled presentation that says about nigelous
Project Management Controlling And Monitoring Powerpoint Presentation Slides
You_Exec_-_Ultimate_Project_Management_Toolbox_Free.pptx
Software Project Requirement and Team Requirement Model
Planning with numbers
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docx
Sas Presentation

More from Minhas Kamal (12)

PPTX
Digital Image Processing
PPTX
Deep Learning - Exploring The Magical World of Neural Network
PPTX
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
PPTX
Artificial Intelligence - Staring at The Grand Universe of AI (1)
PDF
Final Project Report- Bengali Braille to Text Translator
PDF
Abstract- Bengali Braille to Text Translator
PDF
Software Project Management: Software Architecture
PDF
Software Project Management: Software Requirement Specification
PPTX
Software Design: User Interface Design
PPTX
Business Communication System: KAZ Software
PPTX
Final Internship Presentation
PDF
Letter of Transmittal
Digital Image Processing
Deep Learning - Exploring The Magical World of Neural Network
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
Artificial Intelligence - Staring at The Grand Universe of AI (1)
Final Project Report- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text Translator
Software Project Management: Software Architecture
Software Project Management: Software Requirement Specification
Software Design: User Interface Design
Business Communication System: KAZ Software
Final Internship Presentation
Letter of Transmittal

Recently uploaded (20)

PDF
2025 Textile ERP Trends: SAP, Odoo & Oracle
PDF
wealthsignaloriginal-com-DS-text-... (1).pdf
PPTX
Agentic AI Use Case- Contract Lifecycle Management (CLM).pptx
PDF
Softaken Excel to vCard Converter Software.pdf
PPTX
Lecture 3: Operating Systems Introduction to Computer Hardware Systems
PDF
Wondershare Filmora 15 Crack With Activation Key [2025
PDF
How to Migrate SBCGlobal Email to Yahoo Easily
PPTX
VVF-Customer-Presentation2025-Ver1.9.pptx
PDF
PTS Company Brochure 2025 (1).pdf.......
PPTX
Embracing Complexity in Serverless! GOTO Serverless Bengaluru
PPTX
history of c programming in notes for students .pptx
PDF
Nekopoi APK 2025 free lastest update
PPTX
Transform Your Business with a Software ERP System
PDF
SAP S4 Hana Brochure 3 (PTS SYSTEMS AND SOLUTIONS)
PDF
Navsoft: AI-Powered Business Solutions & Custom Software Development
PDF
Upgrade and Innovation Strategies for SAP ERP Customers
PPTX
ai tools demonstartion for schools and inter college
PDF
Internet Downloader Manager (IDM) Crack 6.42 Build 42 Updates Latest 2025
PPTX
Agentic AI : A Practical Guide. Undersating, Implementing and Scaling Autono...
PDF
medical staffing services at VALiNTRY
2025 Textile ERP Trends: SAP, Odoo & Oracle
wealthsignaloriginal-com-DS-text-... (1).pdf
Agentic AI Use Case- Contract Lifecycle Management (CLM).pptx
Softaken Excel to vCard Converter Software.pdf
Lecture 3: Operating Systems Introduction to Computer Hardware Systems
Wondershare Filmora 15 Crack With Activation Key [2025
How to Migrate SBCGlobal Email to Yahoo Easily
VVF-Customer-Presentation2025-Ver1.9.pptx
PTS Company Brochure 2025 (1).pdf.......
Embracing Complexity in Serverless! GOTO Serverless Bengaluru
history of c programming in notes for students .pptx
Nekopoi APK 2025 free lastest update
Transform Your Business with a Software ERP System
SAP S4 Hana Brochure 3 (PTS SYSTEMS AND SOLUTIONS)
Navsoft: AI-Powered Business Solutions & Custom Software Development
Upgrade and Innovation Strategies for SAP ERP Customers
ai tools demonstartion for schools and inter college
Internet Downloader Manager (IDM) Crack 6.42 Build 42 Updates Latest 2025
Agentic AI : A Practical Guide. Undersating, Implementing and Scaling Autono...
medical staffing services at VALiNTRY

Software Project Management: Project Summary

  • 1. 1 ResearchColab Project Summary Team: Reckless 7 Institute of Information Technology University of Dhaka 25th November, 2016
  • 2. 2 Contents Project Summary............................................................................................................................. 3 Executive Summary........................................................................................................................ 3 Project Team and Staffing .............................................................................................................. 3 Project Deliverables (Planned vs. Actual) ...................................................................................... 4 Project Major Activities and Milestones......................................................................................... 5 Transition to Operations ................................................................................................................. 7 Recommendations........................................................................................................................... 7
  • 3. 3 Project Summary Team Reckless 7 recently completed the ResearchColab Project which has been deployed successfully. This marks the end of a difficult but successful project for the Reckless 7 group. The main objective of this document is to provide an overall view of the project and discuss main learnings of the project. Another objective is to provide indicators for assessing the success of the project and provide recommendations for use in similar projects in future. Finally, the main goal of this document is to formally close the project summarizing all required information. Executive Summary The project is for a web application called ResearchColab.com which offers review and data sharing service and a discussion platform for researchers. To avail these services, users need to register as either a researcher or a reviewer. A researcher will post a review request and the reviewers will bid for it. The poster will then see the list of interested reviewers and choose the most suitable candidate and have a one to one communication with the person in order to hire him for the paper review. Researches can also post data on the website that can be used in further researches. The data can either be free or paid. A discussion system will also help the researchers to discuss research related topics in the discussion room. Project Team and Staffing The ResearchColab project consisted of a skilled and knowledgeable team. The chart below provides information about the project team members: Name Assigned task Contact Md. Adiluzzaman Adil Project Management adil@researchcolab.com Minhas Kamal System Analysis minhas@researchcolab.com Kishan Kumar Ganguly Development kishan@researchcolab.com Md. Rakib Hossain Quality Assurance rakib@researchcolab.com Mostaque Ahmed Documentation mostaque@researchcolab.com A.H.M. Azimul Haque Communication & Collaboration azimul@researchcolab.com Israt Fatema Shantu Documentation shantu@researchcolab.com ResearchColab project team members utilized standard project management methodologies to successfully complete the project. The project team was a matrixed organization with full support from functional managers and senior leadership. Effective communication, detailed planning, stakeholder involvement, project management tools, and organizational structure all played key roles in the project’s success. Staffing lessons from previous projects were used in building the project team. Rather than allocate too many resources, as some past projects have done, the team was staffed with one
  • 4. 4 resource per development area. The project sponsor made clear to the project manager that if any additional resources were required, they must be requested through standard channels and the impact on project cost and schedule would need to be defined. Project Deliverables (Planned vs. Actual) The ResearchColab project has been completed successfully. There were planned deliverables for each phase of this project as well as for the completed product. This section highlights the planned deliverables and compares them to actual deliverables as they occurred. Planned Deliverable Actual Deliverable Summary Project Management Reports. The team provided the entire project plan. It contains which development process to follow, how to coordinate between team members, which development tools to follow. This deliverable was completed as planned SRS & Design document The analyst team provided the architecture of the software and UX design is described in this report. This deliverable was completed as planned Configuration Manual The documentation team provided with a configuration manual that describes about how to configure the tools and what environment is required for running the software. This deliverable was completed as planned Executable code module The development team has deployed the actual web application to be used. This deliverable was completed as planned In summary all documented project deliverables have been met by the MicroFiber project team. All stakeholders have submitted their feedback and acknowledge that there are no deliverables which were missed or omitted for this project.
  • 5. 5 Project Major Activities and Milestones Main Activity Planne d Time (days) Actual Time (days) Time Deviation (days) Major Reason for deviation Starting Project and Defining Scope and Objectives 15 15 0 Developing Project Charter 4 4 0 Receiving Project Charter Approval 5 5 0 Project Plan Development 4 6 2 Additional time needed on risk identification and deciding performance indicators Project Plan Approval 2 2 0 Requirement Specification 4 4 0 Design 4 3 -1 Some component logics were reusable across the whole architecture Development 5 5 0 Testing 3 3 0 Installing Live System 2 4 2 Time deviation due to installation problem in the production environment Update Documents 2 3 0 Additional time spent on finding traceability of documents and fixing these Gain Formal Acceptance and Close Project 1 1 0 Project End 51 55 4
  • 6. 6 Project Cost The budgeted cost for the Researchcolab.com Project was set at 7,23,500/=BDT. This cost was broken out by project phase in the following chart with actual costs compared to the planned/budgeted cost. Project Phase Budgeted Cost Actual Cost Comments  Project staffing 63,000/= BDT 65,000/= BDT Staffing cost were over budget due to Schedule pressure  Logistic 11,500/= BDT 10000/= BDT Logistics were over budget due to under estimation  Utility 7,000/=BDT 6000/= BDT Utility costs came in under budget  Miscellaneous 2,000/=BDT 5000/= BDT Miscellaneous cost was over budget  Laptop 2,80,000/=BDT 2,80,000/=BDT costs were on budget  Desktop 1,20,000/=BDT 1,20,000/=BDT costs were on budget  Premises 2,40,000/=BDT 2,20,000/=BDT costs were on budget Total actual costs of the Researchcolab.com Project amounted to 706,000/=BDT. The Researchcolab.com project was not only successful in meeting all of its objectives and deliverables, but by completing under budget, it also allowed project team to allocate 17500/=BDT to other important initiatives. Project Schedule The Researchcolab.com Project schedule called for a four-month project with initiation beginning on September 29, 2016 and project closeout ending on November 26, 2016. There were initial concerns by the project team that the schedule would potentially slip due to limited number of resources and time to the project. The below chart shows each phase of the project lifecycle, the planned schedule dates, and the actual completion dates of each phase. Project Phase Scheduled Completion Actual Completion Comments Initiation September 29, 2016 September 29, 2016 Completed on time Planning October 30, 2016 October 30, 2016 Completed on time Design November 8, 2016 November 8, 2016 Completed on time Build November 12, 2016 November 20, 2016 Not Completed on time Testing November 15, 2016 November 22, 2016 Completed on time Trial Build/Install November 22, 20xx November 25, 2016 Not Completed on time Transition to Ops November 22, 2016 November 26, 2016 Not Completed on time Project Closure November 26, 2016 TBD Progressing on time
  • 7. 7 The Researchcolab.com Project successfully completed most of the phase on time which can be attributed to effective planning and communication as well as sponsor support of this important initiative. During the initiation and planning phases there was concern among the team members that there were inadequate resources assigned to this project. However, due to team members experience, additional resources were not needed and the assigned staff was adequate to complete all work packages in the planned timeframes. The only project phase which encountered schedule problems were the build and trail builds phase. Transition to Operations Transition of a project to an operational environment can be a challenging task for many organizations. The ResearchColab project was successfully transitioned to operations as a direct result of effective communication and detailed planning. The inclusion of the effective members as stakeholders ensured a collective approach to the creation of an improved product which could be transitioned smoothly to a manufacturing environment. Future projects can benefit by involving operations staff early in the project planning phase and soliciting input from operations team members on important considerations for the project from an operational perspective. The project team was not only successful in communicating and planning with operations staff but they leveraged these strengths to determine expectations of what operations required as part of the transition. In this case, the project team was able to develop complete technical data packages and process specifications for operations to use in the manufacturing of the product. This resulted in an almost seamless transition of product lines on the development floor. If the operations staff had not been included as stakeholders nor participated in the project planning, it is likely this step would have been overlooked and the project would have encountered delays and additional costs. Recommendations The ResearchColab Project was an example of a carefully planned and successfully executed project for Reckless 7. However, it is not without its recommendations or lessons learned. Recommendation #1: Involve operations personnel during the initiation phase for new product development projects so they are involved during every step of the planning and execution process. This is imperative in establishing familiarity with the product and processes as well as establishing expectations of what operations will require during transition.
  • 8. 8 Recommendation #2: Researching previous project archives was extremely beneficial in establishing budgets and schedules for project phases. As a result of studying documentation from similar past projects the project team was able to accurately determine budgets, work packages required, and resource allocation. Recommendation #3: The most challenging part was the planning of the budget and timeline. Although the project team successfully met the budget constrain, the schedule was a bit off track. Its recommended to be careful the next time.