Connectivity in the Road Sector
Faces Strategic Challenges

Low competitiveness of road infrastructure v. SEA
region
Current policies are not creating a sustainable modern
highway system
Development of high-capacity expressway network is
lagging demand

Rising funding allocation needs to expand even further

Road program delivery needs more efficiency and
accountability

Change in business model needed
                                                         2
Proposed Support for DGH and BPJT


Road Network Planning (Bipran, BPJT)

• - Long-term Masterplan for Road Infrastructure
• - Investment pipeline to improve connectivity in MP3EI
  corridors

Improved delivery of national road programs
(Bintek, Wilayah-Balai)
• - Longer road life, whole life costing
• Asset management devolved to balai
                                                           3
MP3EI Economic Corridors
                  – 12,000 km National Arterial Roads


                  1                                                 4
                                           3
                                                                                                     6

                                       2
      Economic Corridor
      Mega Hub
                                                   5
      Hub
      Potential Area for Development




The Recommended Six (6) Economic Corridors :                               Logistics is part of the supply
                                                                           chain (supply chain):
  1     Eastern Sumatera-North West Java       4       Western Sulawesi    1. procurement activities
                                                                           2. storage
  2     Northern Java                          5       East Java-Bali-NT   3. delivery / transportation
                                                                               and service
  3     Kalimantan                             6       Papua

                                                                                Source: Coord. Ministry of Economic 4   4
Road Connectivity
              – Estimated Current and Target Service Levels

           Normalized Trip Times on Economic Corridor
                      Arterial Roads- 2011
                                       Trip time hr/100 km*
                    0,0      1,0      2,0      3,0       4,0   5,0    6,0

    Trans-Sumatra
1




                                                     Target Service level
       Trans-Java                                     1-1.5 hr/100 km
2




      Kalimantan
3




         Sulawesi
4




         Bali-NTT
5




    Papua-Maluku
6




                          Road Trip Time    Nautical Add-on    * Corridor distance
                                                               shorter than Arterial
                                                                                       5
                                                               road distance
DGH Masterplan for Road Infrastructure 2010-14
     Incremental Widening to Minimum Width Standard

                          Road Length, km             • Budget IDR 7 trillion/yr
               -     2.000 4.000 6.000 8.000 10.000
                                                      • Covers 47% of network in 5 yr
     Sumatra               3.690                      • Increments to 4.5, 6 or 7 m width
        Java       1.430                              But comes at high cost:

  Kalimantan                                          • No distance saving, little speed
                     2.780
                                                        improvement
    Sulawesi             3.160
                                       Total Length   • Investment repeated in 5-10 yrs
        NTT        987                 Improved       • High cost = 40-60% of full
                                       length           construction for 20-yr life
Maluku-Papua       1.905
                                                      • Defers achieving modern asset
                                                      • Compounds land issues
                                                                                           6
DGH Support on Road Network Planning
Proposed outputs:

• Long-term 50-yr strategy to plan optimal road infrastructure
  for sustaining development

• 20-yr pipeline of investment projects in each economic
  corridor, staged to optimise benefits and spread funding
  requirements

• Journey time used to define connectivity and infrastructure
  plan outcomes

• Expressway network defined as backbone of trans-regional
  connectivity, with staged implementation

• Modernise arterial road network gradually through full
  renewal of roadway and alignment
                                                                 7
TRANS KALIMANTAN NATIONAL ROAD PROGRAM
       Improving connectivity:
       Kalimantan Economic Corridor                                                                        Simanggaris
                                                                                                                        Nunukan



                                                                                                      Malinau

      Corridor plan evaluates options when
                                                                                                            Tj. Selor
      generating project pipeline and
      investment profile for Economic
                              Aruk

      Corridor:                             Enttikong
                                                        Ng Badau
                                                                         Putusibau
      staged over 5, 10,
      15 & 20 year periods
                            Pontianak       Tayan
                                                                                                                        Samarinda



                                                                                                                 Balikpapan
                                                                                     Palangkaraya




Strategic Options
                                                                              Banjarmasin
(1) Widen existing road
                          Jalan yang belum terbangun digambarkan dengan garis putus-putus
                                                                                                    Road standard
(2) Realign and rebuild – “road renewal”;                                                                 Expressway
                                                                                                          >= 7 m
(3) Highway on future expressway location                                                                 6m
                                                                                                          4.5 – 6 m
                                                                                                          Not Connected
(4) Expressway in new location                                                                            Sea Port
Improving Connectivity:
  Trans-Sumatra - Corridor Plan for Staged Development of
        Capacity in Parallel Facilities over long-term 20-yr period
ARTERIAL NATIONAL ROAD WIDTH
Width m 14                                                                                                        2019
    Road Width
                 10                      2024
                                                                                                                                                            2014
                  7
                  6
                  5                                                                                                                                              2010
                      101          102            103      104    105      106         107         108     109         110         111         112         113

                 B Aceh
                   B Aceh                                Medan
                                                          Medan                                      Pekanbaru
                                                                                                       Pekanba                                         Lampung
                                                                                                                                               Palembg Lampung

Length km      644                                         694                                             754                                 443                       0
Total distance 2536                                        1892                                            1198                                443



                      EXPRESSWAY
                      Dual C'way


                                                                                                                                                                 Renstra period color code
                                                                                                                                                                 Baseline
                                                                                                                                                                 2010-2014
                                                                                                                                                                 2015-2019
                                                                                                                                                                 2020-2024
                                                                                                                                                                 2025-2029
                                         101       102     103    104     105    106         107     108   109        110    111         112         113
                                         B Aceh                   Medan                                     Pekanba                      Palembg Lampung

                                                  2029                           2019                                 2024                     2019
                      Length km   460                             564                                      610                           380                0
                      Distance km 2014                            1554                                     990                           380




                                                                                                                                                                               9
Corridor Plan Output - Trans-Sumatra Example:
                               Linkage of Development Outcomes and Financing Plan
                                              – Long-term 20-yr Period


                          Connectivity:                                                        80          Financing Plan




                                                            5-Year Spending estimate (IDR T)
                   Travel Time from South to                                                   70
                                                                                                                                          1,5
                             North                                                             60
                                                                                                                             7
                                                                                               50
                   70
                   60                                                                          40
                                                                                                                                   58,6
TRAVEL TIME (hr)




                   50                                                                          30                     47,9
                                                                                                                                                           0
                   40                                                                          20
                                                                                                                                                    20,2
                   30                              B Aceh                                      10
                                                                                                          2,6              1,7 3          3,6
                                                                                                                3 3                             3          0
                   20                              Medan                                       0    1,8
                                                   Pekanb
                   10                                                                                     R1          R2           R3               R4
                                                   Palem                                                              RENSTRA PERIOD
                    0                              Boukh
                        2010 2015 2020 2025 2030                                       Rd Presv           Rd Widening        Exwy GOI     Exwy PrivSec




                                                                                                                                                               10
Accelerating Expressway Development
• Development expected                               3500

                                                     3000
  to accelerate – but land                           2500




                                  Total length, km
  and private finance risks                          2000

  will dictate                                       1500

• Need broader financing                             1000

                                                      500
  modality, better use of                               0
  available public funds                                 1980   1990   2000   2010    2020   2030
                                                        Operational    Implementing      Planned


IndII Support:
• Assist delivery of Trans-Sumatra & East Java expressways
• Define “expressway” classification in Road Law
• Update long-term plan for expressway network
• Advice on viability gap funding & PPP modalities
• Support project preparation with VGF
• Management: Strengthen BPJT, consider expressway authority
                                                                                               11
Funding Forecasts to Achieve Connectivity Goals
                                          and Modernisation of Road Network
• Long range forecasts of                                                                        Total Highway Expenditure to Meet Connectivity
  funding requirements built                                                                              Goals - Long-term Plan to 2029
  from the investment pipeline                                                               90
                                                                                             80
• Supports scenario planning




                                                                  Annual Expenditure IDR t
                                                                                             70
                                                                                                                                                 Plan forecast
                                                                                                                                                                             Exw-PS
                                                                                             60
  - pace of development                                                                                                                                                      Exw-GOI
                                                                                             50
  - public-private share                                                                     40
                                                                                                                                                                             Devel-DGH
                                                                                             30
• Modernising whole network                                                                  20                                                                              Presvn - DGH
  in 15 yr requires allocations                                                              10
                                                                                              0                                                                              Mgt - DGH
  to double                                                                                    2005                               2010        2015    2020     2025


                                     Expanding Level of Service                                                                         Economic Corridor avg trip time
                                 30000                                                                                            4,0
                                                                                                      Avg Trip Time (hr/100 km)
    Network length at LoS (km)




                                                                                                                                  3,0
                                 20000
                                         Exway                                                                                    2,0
                                 10000   LOS-A                                                                                    1,0
                                                                                                                                  0,0
                                    0                                                                                                2000      2010     2020    2030      2040
                                     2005 2010 2015 2020 2025

                                                                                                                                                                                         12
IndII Support for DGH - 1

Enhance Planning of National Road Development:
- Expedite national connectivity and mobility
- Reform road development planning process
- Efficient deployment of expanded private and public funds
- Accelerate development of expressway network


• Build comprehensive process for planning road network
  development with expenditure forecasts and pipeline of projects
• Prepare long-range capacity expansion profiles for six economic
  corridors, include pipeline of projects and financing plan
• Develop an optimal 20-yr strategy for financing development of the
  expressway and arterial road networks
• Assist BPJT to build capacity for processing the enlarged expressway
  development program, and transactions with viability gap funding
DGH Support for Network Planning:
 Activity packaging

Package 1: Connectivity in Eastern Indonesia
   • Preparation of 20-yr investment plans for 4 MP3EI
     corridors (Kalimantan, Sulawesi, NTT, Maluku-Papua)
   • Prepare 5-year pipeline of capacity expansion projects on
     arterial road network & budget estimates
   • Planning procedures upgraded to include strategy on
     capacity expansion and road renewal

Package 2: Connectivity in Sumatra and Java
   • Advisory support on expressway package preparation for E
     Java and Sumatra corridors, including financing
   • Classification and updating of expressway plan
   • Capacity & policy support to Bipran and BPJT
   • Preparation of 20-yr investment plans for MP3EI corridors
                                                             14
IndII Support for DGH - 2

Improve efficiency national road program delivery:
- Reduced life-cycle costs, improved performance and life of road assets
- Improved design and delivery of projects;
- Improved management of road and bridge assets; and
- Improved transparency and accountablity for performance


• Implement new design guide – longer life pavements
• Prepare road renewal project pipeline for heavily trafficked
  corridors in East Sumatra and Java (Balais 3, 4 and 5)
• Build balai capacity for managing national road network - devolved
  road management process, new system and.
• Assist 1-3 Balais with preparation of 3-year programs 2013-15 using
  new system;
• Apply new project design methods, contract preparation and
  supervision in selected heavy traffic corridors.
Approach for Support to DGH and MPW

• Facilitate delivery of DGH program:
   • Working with Directorates to design and implement program
   • Demonstrating applications and reforms through outputs
   • Supporting MTEF budget preparations in 2012, 2013 & 2014
• Progressive engagement:
   • Hold-points for review after initial stage and annual stages
• Governance:
   •   Building reliable data & information database for shared use
   •   Deploy strategic KPI for travel time, asset age and activity costs
   •   Launch public disclosure – possibly under CoST Initiative
   •   Support MPW administrative reform measures
Terima kasih




               17

More Related Content

PDF
Ind ii2 national roads program proposal to dgh 09jul12 plus concepts
PDF
Freight and public transport planning initiatives conference 24 november 2011
PPT
Trb09 ped strategy-zvaniga
PPTX
COTA NE AA Public Meeting Presentation
PDF
Nov 2010 mha report
PDF
HSR (Phase1 Report) Executive Summary
PDF
CPEC OverView
PPTX
Rail Directions Workshop: ARTC
Ind ii2 national roads program proposal to dgh 09jul12 plus concepts
Freight and public transport planning initiatives conference 24 november 2011
Trb09 ped strategy-zvaniga
COTA NE AA Public Meeting Presentation
Nov 2010 mha report
HSR (Phase1 Report) Executive Summary
CPEC OverView
Rail Directions Workshop: ARTC

What's hot (12)

DOC
MANISH KUMAR GUPTA.docx
DOC
Yogesh_Resume
PDF
Regional Transportation Alliance presentation on Regional Transit and BOSS
PDF
Comesa investment teaser 2011
PPSX
Indian port growth story satya pal 04.02.2011
PDF
Logistic Services - Between Trust And Control V1 2
PDF
Gosford city centre TMAP
PDF
Lunsford Group E. Africa Railway Project 01 2010
PDF
B I P N O F A Requirements R2
PDF
Tourism planning
PDF
Space Systems Loral
PPTX
2040 RTP Leadership Symposium 8.24.12
MANISH KUMAR GUPTA.docx
Yogesh_Resume
Regional Transportation Alliance presentation on Regional Transit and BOSS
Comesa investment teaser 2011
Indian port growth story satya pal 04.02.2011
Logistic Services - Between Trust And Control V1 2
Gosford city centre TMAP
Lunsford Group E. Africa Railway Project 01 2010
B I P N O F A Requirements R2
Tourism planning
Space Systems Loral
2040 RTP Leadership Symposium 8.24.12
Ad

Viewers also liked (20)

PPTX
Rob Bain - Toll Road Forecasting
PDF
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
PDF
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
PDF
Going Global: A Road Map for Bringing the World to Your Classroom
PDF
Management Presentation 2016_Update 1Q-16_v20
PPTX
Toll road business opportunity in Jakarta & West Java
PDF
Sistem pengelolaan jalan tol wilayah suramadu
PPTX
Elitery The First Tier III Certified data center in South East Asia by Uptime...
PDF
Analisa Resiko Pembangunan Jalan Tol Benoa- Bandara-Nusa Dua
PDF
Rest Stop Area KM 88 Tol Cipularang
PPT
Tol
PPTX
Smart Roadside Initiative
PPTX
Development of multimodal transport in north java corridor
PPSX
Planning for a Multimodal Transport Hub: Case Study - Sealdah Interchange, Ko...
PPSX
Site analysis - Transit hub
PPTX
[Urban Management Program City Paper : Bandung City, Indonesia]
PDF
Press Release Jalan Tol Kertosono – Mojokerto Oktober 2010
PPSX
Literature case study - ARTIC
PPTX
Proyek Infrastruktur Pembangunan Jalan Tol Bali Mandara
PPTX
Hunter Mill Road and Sunset Hills Road Study
Rob Bain - Toll Road Forecasting
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
LTC, Annual Forum, For Whom the Road Should Toll: The Future of Toll Roads an...
Going Global: A Road Map for Bringing the World to Your Classroom
Management Presentation 2016_Update 1Q-16_v20
Toll road business opportunity in Jakarta & West Java
Sistem pengelolaan jalan tol wilayah suramadu
Elitery The First Tier III Certified data center in South East Asia by Uptime...
Analisa Resiko Pembangunan Jalan Tol Benoa- Bandara-Nusa Dua
Rest Stop Area KM 88 Tol Cipularang
Tol
Smart Roadside Initiative
Development of multimodal transport in north java corridor
Planning for a Multimodal Transport Hub: Case Study - Sealdah Interchange, Ko...
Site analysis - Transit hub
[Urban Management Program City Paper : Bandung City, Indonesia]
Press Release Jalan Tol Kertosono – Mojokerto Oktober 2010
Literature case study - ARTIC
Proyek Infrastruktur Pembangunan Jalan Tol Bali Mandara
Hunter Mill Road and Sunset Hills Road Study
Ad

Similar to Presentation on dgh program to ind ii board 2012 04 (20)

PPT
The Need For Rail And Ports Integration Pmaesa
PDF
Working in synergy with neighbouring countries to seamlessly transport coal o...
PPT
Barry dowsett bo p freight & logistics forum 16 nov 2012
PPT
Economic cooperation
PDF
Department of Transport update on transport corridors
PDF
Priorities infrastructure retreat- web
PPTX
ECR Privatization 2
PPTX
SPACE HIGHWAY PROJECT- EXECUTIVE SUMMARY.pptx
PPTX
Malaysia Logistics
PPT
Upgrading and Extending Passenger Services
PPTX
IMPACT OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
PPTX
Service analytics: A proposal to LTA Singapore for on-demand bus trials
PDF
Simatupang human capital development in the asean logistics connectivity
PPT
DRC Presentation.ppt
PPT
Railway_Transporatation_Outlook_2021_concept
PDF
Ministry of Transport Report
PDF
#MP2013 Presentation of the Hon. Minister of Transport, Senator Idris Umar
PPTX
Cycle 2 Environmental and Social Equity Presentation
PPTX
Indian Railways - Freight corridor details
The Need For Rail And Ports Integration Pmaesa
Working in synergy with neighbouring countries to seamlessly transport coal o...
Barry dowsett bo p freight & logistics forum 16 nov 2012
Economic cooperation
Department of Transport update on transport corridors
Priorities infrastructure retreat- web
ECR Privatization 2
SPACE HIGHWAY PROJECT- EXECUTIVE SUMMARY.pptx
Malaysia Logistics
Upgrading and Extending Passenger Services
IMPACT OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
Service analytics: A proposal to LTA Singapore for on-demand bus trials
Simatupang human capital development in the asean logistics connectivity
DRC Presentation.ppt
Railway_Transporatation_Outlook_2021_concept
Ministry of Transport Report
#MP2013 Presentation of the Hon. Minister of Transport, Senator Idris Umar
Cycle 2 Environmental and Social Equity Presentation
Indian Railways - Freight corridor details

More from Indonesia Infrastructure Initiative (20)

PPTX
Presentasi Sanitasi INDII
PPTX
Balikpapan Public Diplomacy 25 May 2015
PPT
World experience-in-railway-restructuring
PPT
Indonesian railways revitalisation bambang susantono, vice minister for tra...
PPTX
WS2 Infrastructure Issues
PPTX
Railway function in developing multimodal transportation in java
PDF
The role of ipc in developing multimodal transportation in java
PDF
Government strategy in developing multimodal transportation
PDF
The role of ferry in developing multimodal transportation
PDF
Development of multimodal transportation and inter regional connectivitiy
PPTX
Ws3 safe system approach (bahasa version)
PPTX
Ws3 safe system supporting vru (english version)
PPTX
Ws3 safe system supporting vru (bahasa version)
PPTX
Ws3 infrastructure related to pedestrian safety
PPTX
Ws3 gender and disability presentation
PPT
Workshop #2 safe system approach
PPTX
Workshop #2 safe system approach english
Presentasi Sanitasi INDII
Balikpapan Public Diplomacy 25 May 2015
World experience-in-railway-restructuring
Indonesian railways revitalisation bambang susantono, vice minister for tra...
WS2 Infrastructure Issues
Railway function in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in java
Government strategy in developing multimodal transportation
The role of ferry in developing multimodal transportation
Development of multimodal transportation and inter regional connectivitiy
Ws3 safe system approach (bahasa version)
Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (bahasa version)
Ws3 infrastructure related to pedestrian safety
Ws3 gender and disability presentation
Workshop #2 safe system approach
Workshop #2 safe system approach english

Recently uploaded (20)

PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
DOCX
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
PPTX
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
PPT
Lecture notes on Business Research Methods
PPTX
Project Management_ SMART Projects Class.pptx
PPTX
Slide gioi thieu VietinBank Quy 2 - 2025
PDF
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
PDF
income tax laws notes important pakistan
DOCX
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
PDF
Booking.com The Global AI Sentiment Report 2025
PDF
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
PDF
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
PDF
Daniels 2024 Inclusive, Sustainable Development
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
PDF
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
PDF
Charisse Litchman: A Maverick Making Neurological Care More Accessible
PDF
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
DOCX
Center Enamel Powering Innovation and Resilience in the Italian Chemical Indu...
DOCX
Hand book of Entrepreneurship 4 Chapters.docx
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
Lecture notes on Business Research Methods
Project Management_ SMART Projects Class.pptx
Slide gioi thieu VietinBank Quy 2 - 2025
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
income tax laws notes important pakistan
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
Booking.com The Global AI Sentiment Report 2025
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
Daniels 2024 Inclusive, Sustainable Development
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
Charisse Litchman: A Maverick Making Neurological Care More Accessible
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
Center Enamel Powering Innovation and Resilience in the Italian Chemical Indu...
Hand book of Entrepreneurship 4 Chapters.docx

Presentation on dgh program to ind ii board 2012 04

  • 1. Investing in Connectivity: Proposed DGH Support for MP3EI April 2012
  • 2. Connectivity in the Road Sector Faces Strategic Challenges Low competitiveness of road infrastructure v. SEA region Current policies are not creating a sustainable modern highway system Development of high-capacity expressway network is lagging demand Rising funding allocation needs to expand even further Road program delivery needs more efficiency and accountability Change in business model needed 2
  • 3. Proposed Support for DGH and BPJT Road Network Planning (Bipran, BPJT) • - Long-term Masterplan for Road Infrastructure • - Investment pipeline to improve connectivity in MP3EI corridors Improved delivery of national road programs (Bintek, Wilayah-Balai) • - Longer road life, whole life costing • Asset management devolved to balai 3
  • 4. MP3EI Economic Corridors – 12,000 km National Arterial Roads 1 4 3 6 2 Economic Corridor Mega Hub 5 Hub Potential Area for Development The Recommended Six (6) Economic Corridors : Logistics is part of the supply chain (supply chain): 1 Eastern Sumatera-North West Java 4 Western Sulawesi 1. procurement activities 2. storage 2 Northern Java 5 East Java-Bali-NT 3. delivery / transportation and service 3 Kalimantan 6 Papua Source: Coord. Ministry of Economic 4 4
  • 5. Road Connectivity – Estimated Current and Target Service Levels Normalized Trip Times on Economic Corridor Arterial Roads- 2011 Trip time hr/100 km* 0,0 1,0 2,0 3,0 4,0 5,0 6,0 Trans-Sumatra 1 Target Service level Trans-Java 1-1.5 hr/100 km 2 Kalimantan 3 Sulawesi 4 Bali-NTT 5 Papua-Maluku 6 Road Trip Time Nautical Add-on * Corridor distance shorter than Arterial 5 road distance
  • 6. DGH Masterplan for Road Infrastructure 2010-14 Incremental Widening to Minimum Width Standard Road Length, km • Budget IDR 7 trillion/yr - 2.000 4.000 6.000 8.000 10.000 • Covers 47% of network in 5 yr Sumatra 3.690 • Increments to 4.5, 6 or 7 m width Java 1.430 But comes at high cost: Kalimantan • No distance saving, little speed 2.780 improvement Sulawesi 3.160 Total Length • Investment repeated in 5-10 yrs NTT 987 Improved • High cost = 40-60% of full length construction for 20-yr life Maluku-Papua 1.905 • Defers achieving modern asset • Compounds land issues 6
  • 7. DGH Support on Road Network Planning Proposed outputs: • Long-term 50-yr strategy to plan optimal road infrastructure for sustaining development • 20-yr pipeline of investment projects in each economic corridor, staged to optimise benefits and spread funding requirements • Journey time used to define connectivity and infrastructure plan outcomes • Expressway network defined as backbone of trans-regional connectivity, with staged implementation • Modernise arterial road network gradually through full renewal of roadway and alignment 7
  • 8. TRANS KALIMANTAN NATIONAL ROAD PROGRAM Improving connectivity: Kalimantan Economic Corridor Simanggaris Nunukan Malinau Corridor plan evaluates options when Tj. Selor generating project pipeline and investment profile for Economic Aruk Corridor: Enttikong Ng Badau Putusibau staged over 5, 10, 15 & 20 year periods Pontianak Tayan Samarinda Balikpapan Palangkaraya Strategic Options Banjarmasin (1) Widen existing road Jalan yang belum terbangun digambarkan dengan garis putus-putus Road standard (2) Realign and rebuild – “road renewal”; Expressway >= 7 m (3) Highway on future expressway location 6m 4.5 – 6 m Not Connected (4) Expressway in new location Sea Port
  • 9. Improving Connectivity: Trans-Sumatra - Corridor Plan for Staged Development of Capacity in Parallel Facilities over long-term 20-yr period ARTERIAL NATIONAL ROAD WIDTH Width m 14 2019 Road Width 10 2024 2014 7 6 5 2010 101 102 103 104 105 106 107 108 109 110 111 112 113 B Aceh B Aceh Medan Medan Pekanbaru Pekanba Lampung Palembg Lampung Length km 644 694 754 443 0 Total distance 2536 1892 1198 443 EXPRESSWAY Dual C'way Renstra period color code Baseline 2010-2014 2015-2019 2020-2024 2025-2029 101 102 103 104 105 106 107 108 109 110 111 112 113 B Aceh Medan Pekanba Palembg Lampung 2029 2019 2024 2019 Length km 460 564 610 380 0 Distance km 2014 1554 990 380 9
  • 10. Corridor Plan Output - Trans-Sumatra Example: Linkage of Development Outcomes and Financing Plan – Long-term 20-yr Period Connectivity: 80 Financing Plan 5-Year Spending estimate (IDR T) Travel Time from South to 70 1,5 North 60 7 50 70 60 40 58,6 TRAVEL TIME (hr) 50 30 47,9 0 40 20 20,2 30 B Aceh 10 2,6 1,7 3 3,6 3 3 3 0 20 Medan 0 1,8 Pekanb 10 R1 R2 R3 R4 Palem RENSTRA PERIOD 0 Boukh 2010 2015 2020 2025 2030 Rd Presv Rd Widening Exwy GOI Exwy PrivSec 10
  • 11. Accelerating Expressway Development • Development expected 3500 3000 to accelerate – but land 2500 Total length, km and private finance risks 2000 will dictate 1500 • Need broader financing 1000 500 modality, better use of 0 available public funds 1980 1990 2000 2010 2020 2030 Operational Implementing Planned IndII Support: • Assist delivery of Trans-Sumatra & East Java expressways • Define “expressway” classification in Road Law • Update long-term plan for expressway network • Advice on viability gap funding & PPP modalities • Support project preparation with VGF • Management: Strengthen BPJT, consider expressway authority 11
  • 12. Funding Forecasts to Achieve Connectivity Goals and Modernisation of Road Network • Long range forecasts of Total Highway Expenditure to Meet Connectivity funding requirements built Goals - Long-term Plan to 2029 from the investment pipeline 90 80 • Supports scenario planning Annual Expenditure IDR t 70 Plan forecast Exw-PS 60 - pace of development Exw-GOI 50 - public-private share 40 Devel-DGH 30 • Modernising whole network 20 Presvn - DGH in 15 yr requires allocations 10 0 Mgt - DGH to double 2005 2010 2015 2020 2025 Expanding Level of Service Economic Corridor avg trip time 30000 4,0 Avg Trip Time (hr/100 km) Network length at LoS (km) 3,0 20000 Exway 2,0 10000 LOS-A 1,0 0,0 0 2000 2010 2020 2030 2040 2005 2010 2015 2020 2025 12
  • 13. IndII Support for DGH - 1 Enhance Planning of National Road Development: - Expedite national connectivity and mobility - Reform road development planning process - Efficient deployment of expanded private and public funds - Accelerate development of expressway network • Build comprehensive process for planning road network development with expenditure forecasts and pipeline of projects • Prepare long-range capacity expansion profiles for six economic corridors, include pipeline of projects and financing plan • Develop an optimal 20-yr strategy for financing development of the expressway and arterial road networks • Assist BPJT to build capacity for processing the enlarged expressway development program, and transactions with viability gap funding
  • 14. DGH Support for Network Planning: Activity packaging Package 1: Connectivity in Eastern Indonesia • Preparation of 20-yr investment plans for 4 MP3EI corridors (Kalimantan, Sulawesi, NTT, Maluku-Papua) • Prepare 5-year pipeline of capacity expansion projects on arterial road network & budget estimates • Planning procedures upgraded to include strategy on capacity expansion and road renewal Package 2: Connectivity in Sumatra and Java • Advisory support on expressway package preparation for E Java and Sumatra corridors, including financing • Classification and updating of expressway plan • Capacity & policy support to Bipran and BPJT • Preparation of 20-yr investment plans for MP3EI corridors 14
  • 15. IndII Support for DGH - 2 Improve efficiency national road program delivery: - Reduced life-cycle costs, improved performance and life of road assets - Improved design and delivery of projects; - Improved management of road and bridge assets; and - Improved transparency and accountablity for performance • Implement new design guide – longer life pavements • Prepare road renewal project pipeline for heavily trafficked corridors in East Sumatra and Java (Balais 3, 4 and 5) • Build balai capacity for managing national road network - devolved road management process, new system and. • Assist 1-3 Balais with preparation of 3-year programs 2013-15 using new system; • Apply new project design methods, contract preparation and supervision in selected heavy traffic corridors.
  • 16. Approach for Support to DGH and MPW • Facilitate delivery of DGH program: • Working with Directorates to design and implement program • Demonstrating applications and reforms through outputs • Supporting MTEF budget preparations in 2012, 2013 & 2014 • Progressive engagement: • Hold-points for review after initial stage and annual stages • Governance: • Building reliable data & information database for shared use • Deploy strategic KPI for travel time, asset age and activity costs • Launch public disclosure – possibly under CoST Initiative • Support MPW administrative reform measures