Cathy Claunch
                  Sid Schmidt
PM Challenge   February, 2011
   Need to balance Agency portfolio within
    tight budgets
    ◦ Successful Programs
    ◦ Robust Institutional Base

   Are they really competing priorities?

   Is a competitive environment healthy?

   Can the Agency succeed with one or the
    other?


                                              2
11/12/2010 report from the Inspector General
 listed “Infrastructure and Facilities Management”
             as a top Agency challenge.


“NASA is the ninth largest Federal Government property
 holder, controlling a network of approximately 5,400
      buildings and structures that support Agency
  research, development, and flight activities. NASA’s
ability to effectively manage the necessary maintenance
   and renovation of this large and aging portfolio of
   facilities is a critical challenge facing the Agency.”


                                                            3
   Can the budget process help bridge the
    apparent competition for scarce resources?

   What is the content of these two budgets?

   What activities are underway to improve these
    efforts?

   How are these two entities linked? Can the
    synergy be improved?

                                                    4
Claunch.cathy
   Lengthy budget formulation process


   Small window of time for integration
    of program and institution budgets




                                           6
Appropriation Process Takes ~18 Months

      M     A      M      J     J      A      S     O      N      D     J    F    M     A      M      J/J    A      S     O

     FY11 Execution                                FY12 Execution
                                                            18 MONTHS

Start PPBE-13                                                                                                 FY13 Appropriation
                                                                             • Final budget
~March 2011                                                      PRESIDENT   approval
                                                                             • Budget message to
                                                                               Congress


                                                                             CONGRESS • Budget Resolution
                                                                                          • Authorization Acts
                                             OMB                                          • Appropriation Acts
                                              Review and
                                             integrate agency
                                             recommendations
                                              Markup and                                                    OMB
                                             reclama process                                                 • Midyear update /
                                             Secure final                                                      sequester report
                                             determinations by                                               • Apportionment of
                                             President                                                         appropriated funds


     AGENCIES
                                                                                                   • Operating Plans
    Internal determination of requirements
                                                                                                   • Implementation of   AGENCIES
        and authorities
                                                                                                      program
    Formation of budget recommendations
                                                                                                   • Obligations
                                                                                                   • Costs
                                                                                                   • Outlays
                                                                                                                                    7
Feb           March          April         May              June            July            Aug            Sept             Oct
                                                                            Agency Budget Final Budget
      Leadership Governance/Decisions                                          Reviews     Decisions


         President’s                                                                                                       Agency
           Budget                                                                                                          Request
          Request                                                                                                          to OMB

                                                                            Issues      Issues Agency Budgets
                                                                             Book        Book Decisions Amended
HQ    Office of the Chief Financial Officer                                             Update Made        as
                                                                                                        Necessary


                 Agency                                                 Program Program &
                Guidance                                                Budgets    Center
                                                                       Submitted Budgets
                                                           Program               Integrated
                                                            Budget
     Mission Directorates                                  Reviews


                           Program
                           Guidance

                                                                            Work actions as necessary based on decisions
     Programs/Projects &
     Centers


                                      Budget Development




                                                                                                                                           8
Claunch.cathy
   Agency budget is understandably mission
    oriented

   Center institutional component of budget
    ◦ Relatively small
    ◦ More than “overhead”




                                               10
NASA FY10 Budget by Theme




                            11
FY10 Cross-Agency Support Budget




                                   12
FY10 Center M&O Budget




   Science &
   Engineering                            Institutional
  Engineering Technical
   $244M, 51%              Programmatic
Center Investments
  Authority
                                             $1,679
   Ensure core science         $483
$65M, 13%
  $122M, 25%                                  78%
   and engineering             22%
Independent Research &
  Engineering Leadership
SMA Technicalare
   capabilities
Development Authority
  &
$52M, 11% to support
   available
Bid and Proposal Chief
  Program/Project
Safety and Mission at
   program activities
  Engineers
   a Center
Assurance Support


                                          13
                                                          13
FY10 CMO Institutional Budget                Center Director
                                      Center Multi-Media Support
                                              Equal Opportunity &
                                                          Diversity
                                       Other Center Management
                                        Strategic Communications
                                                     Chief Counsel
                                                     Procurement
                                                Human Resources
                                           Financial Management
                                              Occupational Health
                                                          Logistics




Utilities
Operations
Inactive Buildings & Structures
Roads & Grounds Maintenance
Scheduled (proactive) Maintenance
Unscheduled (reactive) Maintenance
New Capability
Other Facilities Services
                                                              14
Facility Management
Claunch.cathy
Profiles Vary Widely By Center
FY 2004   Center G&A – with CoF          • Focus on budget year
                                         knowing that out-year
                                         budgets could be adjusted in
FY 2005   Center G&A – no CoF            next cycle
                                         • Some Centers anticipating
                                         reduced workforce
FY 2006        Center G&A

                                     Profiles Vary Widely By Center
          CMO - Center G&A,
FY 2007   Facilities & IT Service
            Pools, Eng & SMA         Existing G&A Out-yr budgets
           Technical Authority       transferred to CMO as fixed
                                     budget
FY 2008   CMO – Added Indirect
          portion of remaining
              Service Pools         Profiles Consistent Across Agency
                                    • Reallocated budget among
FY 2009           CMO               Centers
                                    •Reallocated some funds (FY09)
                                    from Corporate G&A
                                                                          16
   During recent years, the institutional budget
    portfolio has seen several process changes all
    seeking to improve efficiencies

     ◦ Baseline Services Level Review

     ◦ Institutional Gap Review

     ◦ Corporate Portfolio Management Review




                                                     17
   Goal:
    ◦ Define content of Center Management & Ops budget for
      ease of explanation to stakeholders
    ◦ Minimize or eliminate the variation in service levels
      provided across the Agency
    ◦ Minimize or eliminate variation in charging practices

   Conclusions
    ◦ City Management functions – goals met
    ◦ Technical Capability functions – more work to be done


                                                              18
   Began as review of facilities require decision as
    Shuttle Program ended
    ◦ Continue operations – fund with next Program with
      requirement? Mothball – until needed by future Program?
      Abandon – not needed in foreseeable future?
   Acknowledges need to maintain minimum critical skills
    for the Agency during a changing environment
   Review of all facilities and technical capabilities –
    focus is Human Spaceflight (ESMD/SOMD)
    ◦ What will be needed by future programs?
   Excellent example of ongoing debate that links
    infrastructure, capabilities, and Programmatic
    requirements

                                                                19
   NASA Agency management proposed that a
    process be instituted to manage Agency
    strategic capabilities as corporate portfolios

     ◦ Study underway

     ◦ Promotes increased collaboration across NASA




                                                      20
Claunch.cathy
   Mission Directorate example

   Center example

   Civil Service budgeting




                                  22
Claunch.cathy
   A healthy institutional base enables
    Programmatic success

   Tension between two competing budget
    entities can be healthy – if kept in check

   Real-life budget pressures require both to
    be efficiently managed



                                                 24

More Related Content

PDF
Sally.godfrey
PDF
Thomas.a.greathouse.r
PPT
R simpson elee
PDF
Gary.humphreys
PPTX
Amer.tahani
PDF
Humphreys.gary
PPTX
Harvey.tony
PPTX
Blythe ortiz7120 5e handbooks 2 15-2012 final
Sally.godfrey
Thomas.a.greathouse.r
R simpson elee
Gary.humphreys
Amer.tahani
Humphreys.gary
Harvey.tony
Blythe ortiz7120 5e handbooks 2 15-2012 final

What's hot (20)

PDF
Law.richard
PPTX
Noneman.steven
PDF
Zimmerman barbier
PPTX
Borchardt.heidemarie
PDF
Ken poole
PDF
Thomas.coonce
PDF
Louis.cioletti
PPTX
Jerald kerby
PPTX
Ed mangopanelpm challengefinal
PPTX
Mahmood porter
PDF
William.miller.pmc2010
PPTX
Backup darren elliott
PDF
Randall.taylor
PDF
Osterkamp jeff
PPT
Woods.edwards.pm challenge bpr presentation 2012 v1
PDF
K.pagel.beene
PDF
Sandra smalley
PPTX
Val.lunz
PDF
Healy edward
PPT
Backup jim cassidy
Law.richard
Noneman.steven
Zimmerman barbier
Borchardt.heidemarie
Ken poole
Thomas.coonce
Louis.cioletti
Jerald kerby
Ed mangopanelpm challengefinal
Mahmood porter
William.miller.pmc2010
Backup darren elliott
Randall.taylor
Osterkamp jeff
Woods.edwards.pm challenge bpr presentation 2012 v1
K.pagel.beene
Sandra smalley
Val.lunz
Healy edward
Backup jim cassidy
Ad

Viewers also liked (11)

PDF
Charles.leising
PDF
Noor
PDF
John.baniszewski
PPTX
Newman.steve
PPTX
Zavala.ed
PDF
Rothenberg.joe
PDF
Anil.rekha
PDF
Manzer fred
PPTX
Denver PMI Symposium 2009
PDF
Performance Based Management Handbook
PDF
Applying the checklist manifesto for project management success
Charles.leising
Noor
John.baniszewski
Newman.steve
Zavala.ed
Rothenberg.joe
Anil.rekha
Manzer fred
Denver PMI Symposium 2009
Performance Based Management Handbook
Applying the checklist manifesto for project management success
Ad

Similar to Claunch.cathy (20)

PPTX
SPAN IFMIS Project in Indonesia
PPTX
Global Trends in the Design and Implementation of Financial Management Inform...
PDF
Federal Budget Process Overview
PDF
Smith.donnie
PDF
Chevron Section1 V1
PPT
An Introduction to the Australian Mid-Term Expenditure Framework (MTEF) and P...
PDF
Dc budget process2012-020212
PDF
Program Management Dashboards
PDF
Nonprofit Boards And Effective Governance
PPTX
App Budget Process And Schedule Diagram
PDF
Didier Keters director sector head ut.tran.log - ing -3-pl industry trends
PDF
Ortiz.james
PDF
Developing asset management plans
PDF
Analysis Of Plans
SPAN IFMIS Project in Indonesia
Global Trends in the Design and Implementation of Financial Management Inform...
Federal Budget Process Overview
Smith.donnie
Chevron Section1 V1
An Introduction to the Australian Mid-Term Expenditure Framework (MTEF) and P...
Dc budget process2012-020212
Program Management Dashboards
Nonprofit Boards And Effective Governance
App Budget Process And Schedule Diagram
Didier Keters director sector head ut.tran.log - ing -3-pl industry trends
Ortiz.james
Developing asset management plans
Analysis Of Plans

More from NASAPMC (20)

PDF
Bejmuk bo
PDF
Baniszewski john
PDF
Yew manson
PDF
Wood frank
PDF
Wood frank
PDF
Wessen randi (cd)
PDF
Vellinga joe
PDF
Trahan stuart
PDF
Stock gahm
PDF
Snow lee
PDF
Smalley sandra
PDF
Seftas krage
PDF
Sampietro marco
PDF
Rudolphi mike
PDF
Roberts karlene
PDF
Rackley mike
PDF
Paradis william
PDF
O'keefe william
PDF
Muller ralf
PDF
Mulenburg jerry
Bejmuk bo
Baniszewski john
Yew manson
Wood frank
Wood frank
Wessen randi (cd)
Vellinga joe
Trahan stuart
Stock gahm
Snow lee
Smalley sandra
Seftas krage
Sampietro marco
Rudolphi mike
Roberts karlene
Rackley mike
Paradis william
O'keefe william
Muller ralf
Mulenburg jerry

Recently uploaded (20)

PDF
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
PDF
NewMind AI Weekly Chronicles - August'25 Week I
PDF
Unlocking AI with Model Context Protocol (MCP)
PPTX
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
PDF
Network Security Unit 5.pdf for BCA BBA.
PDF
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PDF
Spectral efficient network and resource selection model in 5G networks
PPTX
MYSQL Presentation for SQL database connectivity
PDF
NewMind AI Monthly Chronicles - July 2025
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PPTX
A Presentation on Artificial Intelligence
PDF
Empathic Computing: Creating Shared Understanding
PPTX
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
PPTX
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
PDF
Encapsulation_ Review paper, used for researhc scholars
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PDF
cuic standard and advanced reporting.pdf
PPTX
Cloud computing and distributed systems.
PDF
Modernizing your data center with Dell and AMD
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
NewMind AI Weekly Chronicles - August'25 Week I
Unlocking AI with Model Context Protocol (MCP)
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
Network Security Unit 5.pdf for BCA BBA.
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
“AI and Expert System Decision Support & Business Intelligence Systems”
Spectral efficient network and resource selection model in 5G networks
MYSQL Presentation for SQL database connectivity
NewMind AI Monthly Chronicles - July 2025
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
A Presentation on Artificial Intelligence
Empathic Computing: Creating Shared Understanding
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
Encapsulation_ Review paper, used for researhc scholars
Digital-Transformation-Roadmap-for-Companies.pptx
cuic standard and advanced reporting.pdf
Cloud computing and distributed systems.
Modernizing your data center with Dell and AMD

Claunch.cathy

  • 1. Cathy Claunch Sid Schmidt PM Challenge February, 2011
  • 2. Need to balance Agency portfolio within tight budgets ◦ Successful Programs ◦ Robust Institutional Base  Are they really competing priorities?  Is a competitive environment healthy?  Can the Agency succeed with one or the other? 2
  • 3. 11/12/2010 report from the Inspector General listed “Infrastructure and Facilities Management” as a top Agency challenge. “NASA is the ninth largest Federal Government property holder, controlling a network of approximately 5,400 buildings and structures that support Agency research, development, and flight activities. NASA’s ability to effectively manage the necessary maintenance and renovation of this large and aging portfolio of facilities is a critical challenge facing the Agency.” 3
  • 4. Can the budget process help bridge the apparent competition for scarce resources?  What is the content of these two budgets?  What activities are underway to improve these efforts?  How are these two entities linked? Can the synergy be improved? 4
  • 6. Lengthy budget formulation process  Small window of time for integration of program and institution budgets 6
  • 7. Appropriation Process Takes ~18 Months M A M J J A S O N D J F M A M J/J A S O FY11 Execution FY12 Execution 18 MONTHS Start PPBE-13 FY13 Appropriation • Final budget ~March 2011 PRESIDENT approval • Budget message to Congress CONGRESS • Budget Resolution • Authorization Acts OMB • Appropriation Acts Review and integrate agency recommendations Markup and OMB reclama process • Midyear update / Secure final sequester report determinations by • Apportionment of President appropriated funds AGENCIES • Operating Plans Internal determination of requirements • Implementation of AGENCIES and authorities program Formation of budget recommendations • Obligations • Costs • Outlays 7
  • 8. Feb March April May June July Aug Sept Oct Agency Budget Final Budget Leadership Governance/Decisions Reviews Decisions President’s Agency Budget Request Request to OMB Issues Issues Agency Budgets Book Book Decisions Amended HQ Office of the Chief Financial Officer Update Made as Necessary Agency Program Program & Guidance Budgets Center Submitted Budgets Program Integrated Budget Mission Directorates Reviews Program Guidance Work actions as necessary based on decisions Programs/Projects & Centers Budget Development 8
  • 10. Agency budget is understandably mission oriented  Center institutional component of budget ◦ Relatively small ◦ More than “overhead” 10
  • 11. NASA FY10 Budget by Theme 11
  • 13. FY10 Center M&O Budget Science & Engineering Institutional Engineering Technical $244M, 51% Programmatic Center Investments Authority $1,679 Ensure core science $483 $65M, 13% $122M, 25% 78% and engineering 22% Independent Research & Engineering Leadership SMA Technicalare capabilities Development Authority & $52M, 11% to support available Bid and Proposal Chief Program/Project Safety and Mission at program activities Engineers a Center Assurance Support 13 13
  • 14. FY10 CMO Institutional Budget Center Director Center Multi-Media Support Equal Opportunity & Diversity Other Center Management Strategic Communications Chief Counsel Procurement Human Resources Financial Management Occupational Health Logistics Utilities Operations Inactive Buildings & Structures Roads & Grounds Maintenance Scheduled (proactive) Maintenance Unscheduled (reactive) Maintenance New Capability Other Facilities Services 14 Facility Management
  • 16. Profiles Vary Widely By Center FY 2004 Center G&A – with CoF • Focus on budget year knowing that out-year budgets could be adjusted in FY 2005 Center G&A – no CoF next cycle • Some Centers anticipating reduced workforce FY 2006 Center G&A Profiles Vary Widely By Center CMO - Center G&A, FY 2007 Facilities & IT Service Pools, Eng & SMA Existing G&A Out-yr budgets Technical Authority transferred to CMO as fixed budget FY 2008 CMO – Added Indirect portion of remaining Service Pools Profiles Consistent Across Agency • Reallocated budget among FY 2009 CMO Centers •Reallocated some funds (FY09) from Corporate G&A 16
  • 17. During recent years, the institutional budget portfolio has seen several process changes all seeking to improve efficiencies ◦ Baseline Services Level Review ◦ Institutional Gap Review ◦ Corporate Portfolio Management Review 17
  • 18. Goal: ◦ Define content of Center Management & Ops budget for ease of explanation to stakeholders ◦ Minimize or eliminate the variation in service levels provided across the Agency ◦ Minimize or eliminate variation in charging practices  Conclusions ◦ City Management functions – goals met ◦ Technical Capability functions – more work to be done 18
  • 19. Began as review of facilities require decision as Shuttle Program ended ◦ Continue operations – fund with next Program with requirement? Mothball – until needed by future Program? Abandon – not needed in foreseeable future?  Acknowledges need to maintain minimum critical skills for the Agency during a changing environment  Review of all facilities and technical capabilities – focus is Human Spaceflight (ESMD/SOMD) ◦ What will be needed by future programs?  Excellent example of ongoing debate that links infrastructure, capabilities, and Programmatic requirements 19
  • 20. NASA Agency management proposed that a process be instituted to manage Agency strategic capabilities as corporate portfolios ◦ Study underway ◦ Promotes increased collaboration across NASA 20
  • 22. Mission Directorate example  Center example  Civil Service budgeting 22
  • 24. A healthy institutional base enables Programmatic success  Tension between two competing budget entities can be healthy – if kept in check  Real-life budget pressures require both to be efficiently managed 24