Measuring Schedule Performance
                                     NASA Project Management Challenge 2011
                                                              8 - 10 February 2011
                                                                       Tony Harvey




                                         Los Angeles  Washington, D.C.  Boston  Chantilly  Huntsville  Dayton  Santa Barbara
          Albuquerque  Colorado Springs  Ft. Meade  Ft. Monmouth  Goddard Space Flight Center  Ogden  Patuxent River  Silver Spring  Washington Navy Yard
 Cleveland  Dahlgren  Denver  Johnson Space Center  Montgomery  New Orleans  Oklahoma City  San Antonio  San Diego  Tampa  Tacoma  Vandenberg AFB




PRT-57, 21 Nov 2010                                                Approved For Public Release
Acknowledgements

     NASA JSC, Constellation Mission Operations Project funded the
             concept development and tool development

     Terri Blatt for her support in applying the technique to the MOP
             PP&C environment

     Greg Hay for keeping monthly revisions of the MOP schedule and
             providing them for use in testing the schedule comparison tool

     Mike Stelly for his help with the presentation content




PRT-57, 21 Nov 2010                  Approved For Public Release                      2
Overview
     What is Schedule Performance?

     Purpose: develop methods/techniques to analyze schedule
             performance over time

     Development to date consists of two pieces:
             Performance Metrics and Toolset for analyzing data

     Toolset takes two schedules and extracts appropriate data
                     MS Project-based schedules
                     Prototype stage of development
                        Batch program that created an Excel style tab-delimited text output
                        Excel macros to format the spreadsheet for easy viewing
                        Prototype Desktop program for immediate display and optional saving to an Excel
                         file




PRT-57, 21 Nov 2010                              Approved For Public Release                               3
What is Schedule Performance?
                                and Why do we need more metrics?
        The collection of project cost performance measures based on
               actual resource cost is often made difficult by inaccurate or missing
               resource cost data

        Yet even basic schedules includes quantitative data, which can be
               used in measuring schedule performance. This includes:
                     Task start and end dates
                     Task durations
                     Task completion assessment

        The VALUE expressed in all schedules is in the TIME COST
               (duration) of the tasks

                Using two schedules in a comparison process provides
                     A statement of planned activity, in the earlier schedule
                     A statement of performed activity, in the later schedule

        Schedule Performance is simply “measuring a project’s ability to
               complete its planned activities in a given timeframe”
PRT-57, 21 Nov 2010                              Approved For Public Release           4
Schedule Performance,
                                                                                Definition of Terms
         Paralleling the traditional earned value approach to performance
                 measurements we can define terms for measuring our schedule
                 performance against the plan as follows:
                         Planned Duration Of Work Scheduled (PDWS)
                              Original planned duration of activities
                         Planned Duration of Work Performed (PDWP)
                              Earned duration of completed activities
                         Actual Duration of Work Performed (ADWP)
                              Actual duration of completed activities

  Schedule 1


                                                                                          Original plan is for 10
                                                                                             days, therefore
                                                                                               PDWS=10


  Schedule 2


                                    Completed 100% of the 10                              Activity took 12 days to
                                   day planned activity, therefore                         complete, therefore
                                            PDWP=10                                              ADWP=12


PRT-57, 21 Nov 2010                                         Approved For Public Release                              5
Schedule Earned Value
                                                                                               Metrics
         Based on the performance measures a number of metrics can be
                 calculated
                          Schedule Variance for Duration (SVd): PDWP - PDWS
                               The difference between earned duration and planned duration
                               Negative values imply a schedule slip

                          Schedule Performance Index for Duration (SPId): PDWP/PDWS
                               Schedule efficiency factor representing the relationship between the earned
                                duration and the planned duration
                               Values less than 1.0 indicate a performance shortfall

                          Schedule Cost Performance Index (SCPI) : PDWP/ADWP
                               A Schedule cost efficiency factor representing the relationship between the
                                earned duration and the actual duration
                               Values less than 1.0 indicate a cost (duration) overrun

                      If PDWS=10, PDWP=10, and ADWP=12, then
                      Schedule Variance (SVd): PDWP – PDWS = 10 - 10 = 0
                          - Interpretation: The scheduled task is earning value on schedule
                      Schedule Performance Index (SPId): PDWP/PDWS = 10 / 10 = 1.0
                      - Interpretation: The scheduled task has earned value perfectly against its planned value
                      Schedule Cost Performance Index (SCPI): PDWP/ADWP = 10/12 = .833
                      - Interpretation: The scheduled task took longer (cost more) to complete than originally planned

PRT-57, 21 Nov 2010                                             Approved For Public Release                              6
Project Level Measures,
                                                                                 A Simple Example
       Schedule 1




                                                   Task 1                  Task 2               Task 3      Task 4         Overall Project
                                                   PDWS: 10                PDWS: 10             PDWS: 8     PDWS: 2        PDWS: 30
                                                   PDWP: 10                PDWP: 8              PDWP: 7     PDWP: 0        PDWP: 25
                                                   ADWP: 12                ADWP: 10             ADWP: 8     ADWP: 2        ADWP: 32
       Schedule 2




                      Schedule Variance (SVd): PDWP – PDWS = 25-30 = -5
                      - Interpretation: The cumulative effect of all schedule tasks analyzed are 5 days behind schedule
                        (not to be interpreted as the overall project is 5 days behind schedule)
                      Schedule Performance Index (SPId): PDWP/PDWS = 25/30 = .83
                      - Interpretation: The project has currently earned 83% of the duration that it had planned to-date
                      Schedule Cost Performance Index (SCPI): PDWP/ADWP = 25/32 = .78
                      - Interpretation: Tasks are taking longer to complete than originally planned



PRT-57, 21 Nov 2010                                               Approved For Public Release                                                7
Why Create a Schedule Comparison
                                         Tool from Scratch?

            There are no existing tools that create these performance measures

            We were motivated to build a tool that could be used for comparing
             ANY two schedule instances from the same project

            Performance measures can be output in a user friendly format (Excel)
             or directly to a database

            Comparing the current schedule against the original schedule provides
             performance measures for the project up to the current schedule’s
             status date (Data Date)

            Using schedules with monthly Data Date intervals will provide
             performance measures for that month interval

            Monthly performance measures can be used for performance trending

            Performance Indices can be used for duration projections and schedule
             confidence level analyses

PRT-57, 21 Nov 2010                    Approved For Public Release                   8
Creating a
             Schedule Comparison
                     Tool


PRT-57, 21 Nov 2010                9
Key Requirements for our
                                                 Schedule Comparison Tool
      Use any two revisions of a project’s schedule

      Create output that “aligns” the two schedules at the task level
                     Tasks are aligned by Task Name

      Create Performance Measures for each task

      Create Performance Measures for the project

      Retain the schedule hierarchical structure
                     Schedules are by their nature organized in a hierarchical structure of
                      summary tasks and regular tasks

      Create Performance Measures at each Summary task level
                     Allows performance measures to be used to reflect the task
                      organization, as modeled in the schedule hierarchy (project teams?,
                      project phases?)

      Create data capable of being stored in a database

PRT-57, 21 Nov 2010                          Approved For Public Release                       10
Real World Data
                                                                 Summary
                                                                 Performance
                                                                 Metrics




                                                                                Task
   Schedule 1                                                                   Performance
                                         Schedule 2
   Structure                                                                    Metrics
                      Schedule 1         Task Data
                                                                                                        Projected
                      Task Data                                                                         Durations
                                                                                                        using SCPI


                                       Project
                                       Performance
                                       Indexes




                                                 Interpretation of Project Metrics
                                                 •All currently analyzed tasks are cumulatively behind schedule
                                                 by 61.32 days.
                                                 •Analyzed tasks have earned 92.1% of the duration they should
                                                 have earned
                                                 •Tasks are being accomplished at a 65.5% efficiency rate



PRT-57, 21 Nov 2010                Approved For Public Release                                                       11
Current Issues &
                                                                        Future Development
   Current Issues
                     Metrics and process
                        SPId tends toward 1 as task nears completion
                            May exceed 1 if task finishes early

                        SPId subject to how scheduler determines “% complete” field
                        SCPId is used for new duration estimate
                            SCPI (PDWP/ADWP) can be zero when task is in progress

                     Tool
                        Uses task names as the identifier to compare tasks
                            Renamed tasks are not comparable unless new name “contains” old name

                        Changes in schedule hierarchy makes analysis difficult
                            Tool option allows looking one level deeper

                        Added tasks are ignored
                        Deleted tasks are excluded from performance metrics


   Future Development
                     Data capture for trending analysis
                     Extraction of task “confidence measures” (low, mode, high duration)

PRT-57, 21 Nov 2010                              Approved For Public Release                        12
Conclusions
        Strengths
                     Does not require resource cost data for performance measures
                     Allows ANY two revisions of a schedule to be compared
                     Creates Task, Summary Task and Project-level performance measures
                     Summary Task performance indices identify items needing attention

        Weaknesses
                     Relies on project percent complete measures from the schedules
                     New (projected) duration estimation function needs refining

        Conclusion
                     Useful performance measures can be obtained from basic schedule data
                     Performance indices are useful focusing functions
                     Schedule comparison provides an earned value (duration) perspective
                      without an EVMS




PRT-57, 21 Nov 2010                           Approved For Public Release                    13

More Related Content

PPTX
Mahmood porter
PDF
Sally.godfrey
PDF
Thomas.a.greathouse.r
PDF
Law.richard
PPTX
Claunch.cathy
PPTX
Ed mangopanelpm challengefinal
PDF
Harrison.g.poole.k
PDF
Louis.cioletti
Mahmood porter
Sally.godfrey
Thomas.a.greathouse.r
Law.richard
Claunch.cathy
Ed mangopanelpm challengefinal
Harrison.g.poole.k
Louis.cioletti

What's hot (20)

PPTX
Borchardt.heidemarie
PPTX
Amer.tahani
PPTX
Backup darren elliott
PDF
Osterkamp jeff
PPTX
Noneman.steven
PDF
Thomas.coonce
PPTX
Simon.dekker.vance kotrla
PPTX
Symons
PDF
Gary.humphreys
PPT
Backup jim cassidy
PPT
R simpson elee
PPT
Gonzales.matthew
PDF
Humphreys.gary
PPTX
Lukas
PDF
Ken poole
PDF
Sandra smalley
PPTX
Harvey elliott
PPTX
Blythe ortiz7120 5e handbooks 2 15-2012 final
PPT
Woods.edwards.pm challenge bpr presentation 2012 v1
PPT
Esker.linda
Borchardt.heidemarie
Amer.tahani
Backup darren elliott
Osterkamp jeff
Noneman.steven
Thomas.coonce
Simon.dekker.vance kotrla
Symons
Gary.humphreys
Backup jim cassidy
R simpson elee
Gonzales.matthew
Humphreys.gary
Lukas
Ken poole
Sandra smalley
Harvey elliott
Blythe ortiz7120 5e handbooks 2 15-2012 final
Woods.edwards.pm challenge bpr presentation 2012 v1
Esker.linda
Ad

Viewers also liked (7)

PPTX
B sherwood dmc_cleese
PPTX
Olson,john$isecg overview olson pmc v go
PDF
Ivatury.raju
PDF
Calfee
PPTX
Lengyel.david
PPT
Baize,lionel pm challenge cnes
PDF
Stephen.book
B sherwood dmc_cleese
Olson,john$isecg overview olson pmc v go
Ivatury.raju
Calfee
Lengyel.david
Baize,lionel pm challenge cnes
Stephen.book
Ad

Similar to Harvey.tony (20)

PPT
Fundamentals of scheduling
PDF
16 Essential Project KPIs
PPTX
project planning
PDF
Ms Project Workshop
PDF
Performing against the wall - SPI after completion
PPT
Wbs & Project Scheduling
PPT
WBS PROJECT
PDF
Ms Project 2010
PDF
CCP_SEC3_Planning and Scheduling
PPTX
Improving project performance presentation
PPT
Ms Project 2007(Basic)
PPTX
Chapter - 27.pptx
PDF
Building a Credible Performance Measurement Baseline in Two Days
PPTX
MARKS IN YOUR POCKET PMP for PMP Preparation
PPTX
10 me667 chap4 project scheduling
PPTX
Project Management
PPTX
PROJECT SCHEDULE
PPTX
project time management
PPTX
Project scheduling
PPTX
Building a Credible Performance Measurement Baseline (v3)
Fundamentals of scheduling
16 Essential Project KPIs
project planning
Ms Project Workshop
Performing against the wall - SPI after completion
Wbs & Project Scheduling
WBS PROJECT
Ms Project 2010
CCP_SEC3_Planning and Scheduling
Improving project performance presentation
Ms Project 2007(Basic)
Chapter - 27.pptx
Building a Credible Performance Measurement Baseline in Two Days
MARKS IN YOUR POCKET PMP for PMP Preparation
10 me667 chap4 project scheduling
Project Management
PROJECT SCHEDULE
project time management
Project scheduling
Building a Credible Performance Measurement Baseline (v3)

More from NASAPMC (20)

PDF
Bejmuk bo
PDF
Baniszewski john
PDF
Yew manson
PDF
Wood frank
PDF
Wood frank
PDF
Wessen randi (cd)
PDF
Vellinga joe
PDF
Trahan stuart
PDF
Stock gahm
PDF
Snow lee
PDF
Smalley sandra
PDF
Seftas krage
PDF
Sampietro marco
PDF
Rudolphi mike
PDF
Roberts karlene
PDF
Rackley mike
PDF
Paradis william
PDF
O'keefe william
PDF
Muller ralf
PDF
Mulenburg jerry
Bejmuk bo
Baniszewski john
Yew manson
Wood frank
Wood frank
Wessen randi (cd)
Vellinga joe
Trahan stuart
Stock gahm
Snow lee
Smalley sandra
Seftas krage
Sampietro marco
Rudolphi mike
Roberts karlene
Rackley mike
Paradis william
O'keefe william
Muller ralf
Mulenburg jerry

Recently uploaded (20)

PDF
Encapsulation_ Review paper, used for researhc scholars
PPTX
Big Data Technologies - Introduction.pptx
PDF
Electronic commerce courselecture one. Pdf
PDF
Reach Out and Touch Someone: Haptics and Empathic Computing
PDF
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Encapsulation theory and applications.pdf
PDF
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PPTX
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PDF
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PDF
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PDF
Modernizing your data center with Dell and AMD
PDF
Empathic Computing: Creating Shared Understanding
PDF
Chapter 3 Spatial Domain Image Processing.pdf
DOCX
The AUB Centre for AI in Media Proposal.docx
Encapsulation_ Review paper, used for researhc scholars
Big Data Technologies - Introduction.pptx
Electronic commerce courselecture one. Pdf
Reach Out and Touch Someone: Haptics and Empathic Computing
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Encapsulation theory and applications.pdf
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
Diabetes mellitus diagnosis method based random forest with bat algorithm
Mobile App Security Testing_ A Comprehensive Guide.pdf
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
Advanced methodologies resolving dimensionality complications for autism neur...
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
Modernizing your data center with Dell and AMD
Empathic Computing: Creating Shared Understanding
Chapter 3 Spatial Domain Image Processing.pdf
The AUB Centre for AI in Media Proposal.docx

Harvey.tony

  • 1. Measuring Schedule Performance NASA Project Management Challenge 2011 8 - 10 February 2011 Tony Harvey  Los Angeles  Washington, D.C.  Boston  Chantilly  Huntsville  Dayton  Santa Barbara  Albuquerque  Colorado Springs  Ft. Meade  Ft. Monmouth  Goddard Space Flight Center  Ogden  Patuxent River  Silver Spring  Washington Navy Yard  Cleveland  Dahlgren  Denver  Johnson Space Center  Montgomery  New Orleans  Oklahoma City  San Antonio  San Diego  Tampa  Tacoma  Vandenberg AFB PRT-57, 21 Nov 2010 Approved For Public Release
  • 2. Acknowledgements  NASA JSC, Constellation Mission Operations Project funded the concept development and tool development  Terri Blatt for her support in applying the technique to the MOP PP&C environment  Greg Hay for keeping monthly revisions of the MOP schedule and providing them for use in testing the schedule comparison tool  Mike Stelly for his help with the presentation content PRT-57, 21 Nov 2010 Approved For Public Release 2
  • 3. Overview  What is Schedule Performance?  Purpose: develop methods/techniques to analyze schedule performance over time  Development to date consists of two pieces: Performance Metrics and Toolset for analyzing data  Toolset takes two schedules and extracts appropriate data  MS Project-based schedules  Prototype stage of development  Batch program that created an Excel style tab-delimited text output  Excel macros to format the spreadsheet for easy viewing  Prototype Desktop program for immediate display and optional saving to an Excel file PRT-57, 21 Nov 2010 Approved For Public Release 3
  • 4. What is Schedule Performance? and Why do we need more metrics?  The collection of project cost performance measures based on actual resource cost is often made difficult by inaccurate or missing resource cost data  Yet even basic schedules includes quantitative data, which can be used in measuring schedule performance. This includes:  Task start and end dates  Task durations  Task completion assessment  The VALUE expressed in all schedules is in the TIME COST (duration) of the tasks  Using two schedules in a comparison process provides  A statement of planned activity, in the earlier schedule  A statement of performed activity, in the later schedule  Schedule Performance is simply “measuring a project’s ability to complete its planned activities in a given timeframe” PRT-57, 21 Nov 2010 Approved For Public Release 4
  • 5. Schedule Performance, Definition of Terms  Paralleling the traditional earned value approach to performance measurements we can define terms for measuring our schedule performance against the plan as follows:  Planned Duration Of Work Scheduled (PDWS)  Original planned duration of activities  Planned Duration of Work Performed (PDWP)  Earned duration of completed activities  Actual Duration of Work Performed (ADWP)  Actual duration of completed activities Schedule 1 Original plan is for 10 days, therefore PDWS=10 Schedule 2 Completed 100% of the 10 Activity took 12 days to day planned activity, therefore complete, therefore PDWP=10 ADWP=12 PRT-57, 21 Nov 2010 Approved For Public Release 5
  • 6. Schedule Earned Value Metrics  Based on the performance measures a number of metrics can be calculated  Schedule Variance for Duration (SVd): PDWP - PDWS  The difference between earned duration and planned duration  Negative values imply a schedule slip  Schedule Performance Index for Duration (SPId): PDWP/PDWS  Schedule efficiency factor representing the relationship between the earned duration and the planned duration  Values less than 1.0 indicate a performance shortfall  Schedule Cost Performance Index (SCPI) : PDWP/ADWP  A Schedule cost efficiency factor representing the relationship between the earned duration and the actual duration  Values less than 1.0 indicate a cost (duration) overrun If PDWS=10, PDWP=10, and ADWP=12, then Schedule Variance (SVd): PDWP – PDWS = 10 - 10 = 0 - Interpretation: The scheduled task is earning value on schedule Schedule Performance Index (SPId): PDWP/PDWS = 10 / 10 = 1.0 - Interpretation: The scheduled task has earned value perfectly against its planned value Schedule Cost Performance Index (SCPI): PDWP/ADWP = 10/12 = .833 - Interpretation: The scheduled task took longer (cost more) to complete than originally planned PRT-57, 21 Nov 2010 Approved For Public Release 6
  • 7. Project Level Measures, A Simple Example Schedule 1 Task 1 Task 2 Task 3 Task 4 Overall Project PDWS: 10 PDWS: 10 PDWS: 8 PDWS: 2 PDWS: 30 PDWP: 10 PDWP: 8 PDWP: 7 PDWP: 0 PDWP: 25 ADWP: 12 ADWP: 10 ADWP: 8 ADWP: 2 ADWP: 32 Schedule 2 Schedule Variance (SVd): PDWP – PDWS = 25-30 = -5 - Interpretation: The cumulative effect of all schedule tasks analyzed are 5 days behind schedule (not to be interpreted as the overall project is 5 days behind schedule) Schedule Performance Index (SPId): PDWP/PDWS = 25/30 = .83 - Interpretation: The project has currently earned 83% of the duration that it had planned to-date Schedule Cost Performance Index (SCPI): PDWP/ADWP = 25/32 = .78 - Interpretation: Tasks are taking longer to complete than originally planned PRT-57, 21 Nov 2010 Approved For Public Release 7
  • 8. Why Create a Schedule Comparison Tool from Scratch?  There are no existing tools that create these performance measures  We were motivated to build a tool that could be used for comparing ANY two schedule instances from the same project  Performance measures can be output in a user friendly format (Excel) or directly to a database  Comparing the current schedule against the original schedule provides performance measures for the project up to the current schedule’s status date (Data Date)  Using schedules with monthly Data Date intervals will provide performance measures for that month interval  Monthly performance measures can be used for performance trending  Performance Indices can be used for duration projections and schedule confidence level analyses PRT-57, 21 Nov 2010 Approved For Public Release 8
  • 9. Creating a Schedule Comparison Tool PRT-57, 21 Nov 2010 9
  • 10. Key Requirements for our Schedule Comparison Tool  Use any two revisions of a project’s schedule  Create output that “aligns” the two schedules at the task level  Tasks are aligned by Task Name  Create Performance Measures for each task  Create Performance Measures for the project  Retain the schedule hierarchical structure  Schedules are by their nature organized in a hierarchical structure of summary tasks and regular tasks  Create Performance Measures at each Summary task level  Allows performance measures to be used to reflect the task organization, as modeled in the schedule hierarchy (project teams?, project phases?)  Create data capable of being stored in a database PRT-57, 21 Nov 2010 Approved For Public Release 10
  • 11. Real World Data Summary Performance Metrics Task Schedule 1 Performance Schedule 2 Structure Metrics Schedule 1 Task Data Projected Task Data Durations using SCPI Project Performance Indexes Interpretation of Project Metrics •All currently analyzed tasks are cumulatively behind schedule by 61.32 days. •Analyzed tasks have earned 92.1% of the duration they should have earned •Tasks are being accomplished at a 65.5% efficiency rate PRT-57, 21 Nov 2010 Approved For Public Release 11
  • 12. Current Issues & Future Development  Current Issues  Metrics and process  SPId tends toward 1 as task nears completion  May exceed 1 if task finishes early  SPId subject to how scheduler determines “% complete” field  SCPId is used for new duration estimate  SCPI (PDWP/ADWP) can be zero when task is in progress  Tool  Uses task names as the identifier to compare tasks  Renamed tasks are not comparable unless new name “contains” old name  Changes in schedule hierarchy makes analysis difficult  Tool option allows looking one level deeper  Added tasks are ignored  Deleted tasks are excluded from performance metrics  Future Development  Data capture for trending analysis  Extraction of task “confidence measures” (low, mode, high duration) PRT-57, 21 Nov 2010 Approved For Public Release 12
  • 13. Conclusions  Strengths  Does not require resource cost data for performance measures  Allows ANY two revisions of a schedule to be compared  Creates Task, Summary Task and Project-level performance measures  Summary Task performance indices identify items needing attention  Weaknesses  Relies on project percent complete measures from the schedules  New (projected) duration estimation function needs refining  Conclusion  Useful performance measures can be obtained from basic schedule data  Performance indices are useful focusing functions  Schedule comparison provides an earned value (duration) perspective without an EVMS PRT-57, 21 Nov 2010 Approved For Public Release 13

Editor's Notes

  • #5: Reasons forinaccurate or missing resource cost data.Prime and subcontract WBSs do not alignSubcontractors are not “required” to collect detailed level data“Prime” accounting process incapable collecting project oriented dataTIME COST – one day slip in a Critical Path task will cause a one day slip in the projectTime is also important when customer end dates cannot change e.g. If a launch to Mars is possible for only 3 weeks every 26 months, end date slips beyond launch opportunities can be very expensive
  • #9: Every schedule has an “as of” date, referred to as the “Data Date”Any two schedules can be compared to calculate the project’s schedule performance for the period between the two Data Dates
  • #12: Projected duration is simply the remaining duration divided by the SCPI added to the actual duration