METHOD STATEMENTSMETHOD STATEMENTS
Method Statements
More and more contractors are being asked
by their clients to produce a method
statement.
As part of their Health and Safety
documentation or for larger projects, under
the CDM Regulations.
A Method Statement is a document detailing
how a particular task or activity will be carried
out.
Method Statements
It should detail:
the possible dangers/risks associated
with your particular part of the project;
and the methods of control to be
established;
to show how the work will be
managed safely.
Method Statements
A method statement is:
a written safe system of work
or series of safe systems of work
Method Statements are agreed between:
a client and principal contractor
a principal contractor and contractor
They are produced where work with a
foreseeable high hazard content is to be
undertaken.
Method Statements
A method statement should specify the
activities to be undertaken on a stage-
by-stage basis.
All the precautions necessary to protect
site operators.
the client's employees and members of
the public who could be affected by site
activities.
Method Statements
May be produced and agreed
between:
a client and principal
contractor for a range of high
risk activities prior to
commencement of work.
Method Statements
What goes into a MS?
There is no standard format for a
method statement.
The following aspects may need
consideration:
working systems to be used;
Method Statements
arrangements for access e.g. to roofs;
methods for safeguarding existing
structures;
structural stability precautions, e.g.
temporary shoring arrangements;
Method Statements
arrangements for protecting the safety
of members of the public;
plant and equipment to be used;
health protection arrangements, such
as the use of local exhaust ventilation
and respiratory protection, where
hazardous dusts and fumes could be
created;
Method Statements
procedures to prevent local pollution;
segregation of specific areas;
and procedures to ensure compliance with legal
requirements under, for instance, Control of
Noise at Work Regulations;
Or Work at Height Regulations;
Control of Lead at Work Regulations;
and Construction (Design and Management)
Regulations-CDM.
Method Statements
The method statement may also incorporate
information and specific requirements laid down
by organizations such as:
clients
enforcement officers
the police
local fire authority
Manufacturers
suppliers of plant
equipment and substances and health and
safety specialists
Method Statements
In certain cases
the method statement may identify
training needs for those carrying out the
work
and the use of competent persons
or specially-trained operators for certain
activities.
Method Statements
What are Method Statements?
A method statement is a method of control that
is used after a risk assessment of an operation
has been carried out.
the method statement is always ‘Site Specific’,
and is used to control the operation,
and to ensure that all concerned are aware of
the hazards associated with the work.
and the safety precautions needed to be taken.
Method Statements
In addition,
construction method statements are used on
site.
Method statements must be written by a
competent person familiar with the work
processes.
Method statements should also contain
information concerning the order and method of
construction with reference to work procedures.
Method Statements
On some sites they are in fact a
contractual requirement.
Requiring submission of a MS to the
Principal contractor.
And to the client or engineer for approval
prior to the commencement of works.

More Related Content

PPTX
Health and Safety Policies
PDF
'DRISHTI' Chapter 8: Scaffolding (स्कैफ़ोल्डिंग)
PPT
Scaffolding
PDF
DOCX
WORK PERMIT REGISTER Form # HSEQ - WPR Rev 2.docx
DOCX
8 lifting operations with mobile crane risk assessment templates
PDF
Rigging and lifting
PDF
Methodstatement welding
Health and Safety Policies
'DRISHTI' Chapter 8: Scaffolding (स्कैफ़ोल्डिंग)
Scaffolding
WORK PERMIT REGISTER Form # HSEQ - WPR Rev 2.docx
8 lifting operations with mobile crane risk assessment templates
Rigging and lifting
Methodstatement welding

What's hot (20)

PPTX
Construction safety management
PPT
HSE-INDUCTION-TRAINING.ppt
PDF
Risk Assessment (Master).pdf
PPTX
Construction safety
PDF
12 construction safety
PDF
Construction Safety Training
PPT
Confined Space.ppt
PDF
Working at height slides
PDF
03-hira-for-welding-work-_compress.pdf
PPTX
Permit to Work Training
PDF
Risk assessment for testing & commissioning of cranes
PDF
Fire Risk Assessment Presentation
PDF
Scaffold safe work method statement
PPT
Construction Site Health & Safety
PDF
Safe Working during Monsoon- Construction Safety
PPT
NGI-Excavation Hazards
PDF
Construction hazards and_safety_by_isti
PPTX
construction site safety and management
PDF
Working at heights training powerpoint
DOCX
HEALTH, SAFETY AND ENVIRONMENTAL MANUAL
Construction safety management
HSE-INDUCTION-TRAINING.ppt
Risk Assessment (Master).pdf
Construction safety
12 construction safety
Construction Safety Training
Confined Space.ppt
Working at height slides
03-hira-for-welding-work-_compress.pdf
Permit to Work Training
Risk assessment for testing & commissioning of cranes
Fire Risk Assessment Presentation
Scaffold safe work method statement
Construction Site Health & Safety
Safe Working during Monsoon- Construction Safety
NGI-Excavation Hazards
Construction hazards and_safety_by_isti
construction site safety and management
Working at heights training powerpoint
HEALTH, SAFETY AND ENVIRONMENTAL MANUAL
Ad

Viewers also liked (20)

DOC
Building work method statement cm - ms- bw - 001
DOCX
Method statement piping works
DOCX
Method statement painting
DOC
Method statement for structural concrete repair rev.0
PDF
Pipe and-fittings
PDF
Ms for-mechanical-piping-system-installation-work
PDF
ERECTION METHOD STATEMENT
DOC
Method statement for repair of concrete surface
DOC
Concrete method rev02
DOC
Piling work method statement cm- ms- bw - 002
DOC
Excavation method rectified 13-11-2010
DOC
Method painting works emulsion paint
PDF
01 Construction Code of Practice - Method of Statement
DOC
METHOD STATEMENT
DOC
Engineering constructionmethodsguidelinescbs(2)
PDF
Method of Statement - Pavement works
DOCX
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
PDF
Method aluminum door & window
PPTX
Concrete repair
PDF
Umrtl1 cp1b-stbs-cws-mst-00023-e-method statement for construction of ba son ...
Building work method statement cm - ms- bw - 001
Method statement piping works
Method statement painting
Method statement for structural concrete repair rev.0
Pipe and-fittings
Ms for-mechanical-piping-system-installation-work
ERECTION METHOD STATEMENT
Method statement for repair of concrete surface
Concrete method rev02
Piling work method statement cm- ms- bw - 002
Excavation method rectified 13-11-2010
Method painting works emulsion paint
01 Construction Code of Practice - Method of Statement
METHOD STATEMENT
Engineering constructionmethodsguidelinescbs(2)
Method of Statement - Pavement works
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Method aluminum door & window
Concrete repair
Umrtl1 cp1b-stbs-cws-mst-00023-e-method statement for construction of ba son ...
Ad

Similar to 072 Method Statement (20)

PPTX
Process Safety
PDF
14 Tips for Process Safety Management
PPS
presentation thesis kanios hse 0.5
PPTX
Management of Change 22.4.15
PDF
First engineering contracting
PPTX
DPCAC-PSM-Feb-2020-1.pptx
PDF
Firstcool electromechanical works llc
PDF
Advanced Well Control Systems_ Preventing Blowouts and Accidents with Javier ...
PDF
Advanced Well Control Systems_ Preventing Blowouts and Accidents with Javier ...
PDF
Advanced Well Control Systems_ Preventing Blowouts and Accidents with Javier ...
PDF
Advanced Well Control Systems_ Preventing Blowouts and Accidents with Javier ...
PPTX
Hsse policy group 5 final
PPTX
PERMIT-TO-WORK-TRAINING-15645566978.pptx
PDF
Mitigate Hidden Business Risk: Improving Safety by Pre-screening and Qualifyi...
PDF
PPT
PPTX
Process safety managment
PDF
Analisis de Riesgo en Tuberias_11-20.pdf
PPTX
Event infrastructure
PDF
DCR Safety Solutions
 
Process Safety
14 Tips for Process Safety Management
presentation thesis kanios hse 0.5
Management of Change 22.4.15
First engineering contracting
DPCAC-PSM-Feb-2020-1.pptx
Firstcool electromechanical works llc
Advanced Well Control Systems_ Preventing Blowouts and Accidents with Javier ...
Advanced Well Control Systems_ Preventing Blowouts and Accidents with Javier ...
Advanced Well Control Systems_ Preventing Blowouts and Accidents with Javier ...
Advanced Well Control Systems_ Preventing Blowouts and Accidents with Javier ...
Hsse policy group 5 final
PERMIT-TO-WORK-TRAINING-15645566978.pptx
Mitigate Hidden Business Risk: Improving Safety by Pre-screening and Qualifyi...
Process safety managment
Analisis de Riesgo en Tuberias_11-20.pdf
Event infrastructure
DCR Safety Solutions
 

More from Dr Fereidoun Dejahang (20)

DOCX
27 j20 my news punch -dr f dejahang 27-01-2020
DOCX
28 dej my news punch rev 28-12-2019
DOCX
16 fd my news punch rev 16-12-2019
PPT
029 fast-tracking projects
PPT
028 fast-tracking projects & cost overrun
PPT
027 fast-tracked projects-materials
PPT
026 fast react-productivity improvement
PPT
025 enterprise resources management
PPT
022 b construction productivity-write
PPT
022 a construction productivity (2)
PPT
021 construction productivity (1)
PPTX
019 competencies-managers
PPT
018 company productivity
PPT
017 communication
PPT
016 communication in construction sector
PPTX
015 changes-process model
PPTX
014 changes-cost overrun measurement
PPTX
013 changes in construction projects
PPT
012 bussiness planning process
PPT
011 business performance management
27 j20 my news punch -dr f dejahang 27-01-2020
28 dej my news punch rev 28-12-2019
16 fd my news punch rev 16-12-2019
029 fast-tracking projects
028 fast-tracking projects & cost overrun
027 fast-tracked projects-materials
026 fast react-productivity improvement
025 enterprise resources management
022 b construction productivity-write
022 a construction productivity (2)
021 construction productivity (1)
019 competencies-managers
018 company productivity
017 communication
016 communication in construction sector
015 changes-process model
014 changes-cost overrun measurement
013 changes in construction projects
012 bussiness planning process
011 business performance management

Recently uploaded (20)

PPTX
Construction Project Organization Group 2.pptx
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
composite construction of structures.pdf
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
OOP with Java - Java Introduction (Basics)
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PDF
Well-logging-methods_new................
PPTX
web development for engineering and engineering
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPT
Project quality management in manufacturing
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
DOCX
573137875-Attendance-Management-System-original
Construction Project Organization Group 2.pptx
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
composite construction of structures.pdf
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
OOP with Java - Java Introduction (Basics)
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Strings in CPP - Strings in C++ are sequences of characters used to store and...
Operating System & Kernel Study Guide-1 - converted.pdf
Well-logging-methods_new................
web development for engineering and engineering
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Foundation to blockchain - A guide to Blockchain Tech
Project quality management in manufacturing
bas. eng. economics group 4 presentation 1.pptx
UNIT-1 - COAL BASED THERMAL POWER PLANTS
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
573137875-Attendance-Management-System-original

072 Method Statement

  • 2. Method Statements More and more contractors are being asked by their clients to produce a method statement. As part of their Health and Safety documentation or for larger projects, under the CDM Regulations. A Method Statement is a document detailing how a particular task or activity will be carried out.
  • 3. Method Statements It should detail: the possible dangers/risks associated with your particular part of the project; and the methods of control to be established; to show how the work will be managed safely.
  • 4. Method Statements A method statement is: a written safe system of work or series of safe systems of work Method Statements are agreed between: a client and principal contractor a principal contractor and contractor They are produced where work with a foreseeable high hazard content is to be undertaken.
  • 5. Method Statements A method statement should specify the activities to be undertaken on a stage- by-stage basis. All the precautions necessary to protect site operators. the client's employees and members of the public who could be affected by site activities.
  • 6. Method Statements May be produced and agreed between: a client and principal contractor for a range of high risk activities prior to commencement of work.
  • 7. Method Statements What goes into a MS? There is no standard format for a method statement. The following aspects may need consideration: working systems to be used;
  • 8. Method Statements arrangements for access e.g. to roofs; methods for safeguarding existing structures; structural stability precautions, e.g. temporary shoring arrangements;
  • 9. Method Statements arrangements for protecting the safety of members of the public; plant and equipment to be used; health protection arrangements, such as the use of local exhaust ventilation and respiratory protection, where hazardous dusts and fumes could be created;
  • 10. Method Statements procedures to prevent local pollution; segregation of specific areas; and procedures to ensure compliance with legal requirements under, for instance, Control of Noise at Work Regulations; Or Work at Height Regulations; Control of Lead at Work Regulations; and Construction (Design and Management) Regulations-CDM.
  • 11. Method Statements The method statement may also incorporate information and specific requirements laid down by organizations such as: clients enforcement officers the police local fire authority Manufacturers suppliers of plant equipment and substances and health and safety specialists
  • 12. Method Statements In certain cases the method statement may identify training needs for those carrying out the work and the use of competent persons or specially-trained operators for certain activities.
  • 13. Method Statements What are Method Statements? A method statement is a method of control that is used after a risk assessment of an operation has been carried out. the method statement is always ‘Site Specific’, and is used to control the operation, and to ensure that all concerned are aware of the hazards associated with the work. and the safety precautions needed to be taken.
  • 14. Method Statements In addition, construction method statements are used on site. Method statements must be written by a competent person familiar with the work processes. Method statements should also contain information concerning the order and method of construction with reference to work procedures.
  • 15. Method Statements On some sites they are in fact a contractual requirement. Requiring submission of a MS to the Principal contractor. And to the client or engineer for approval prior to the commencement of works.