Method Statement for Execution of the Civil Works for the 
Refurbishment of the Agricultural Laboratory of the University of 
Liberia 
· Receipt of Contract 
When the contract is awarded to City construction Inc. the following will be executed in a 
suitable and shortest time as per steps laid down below. 
The works that will be carried comprise of the following: 
· Carry out Pre-demolition and Refurbishment survey to identify all walls as shown in 
dotted line and concrete shell to be clean within the existing structure to be used as 
Main Laboratory Building. 
· Demolition of walls, clearing and storing debris for future use if necessary and 
preparation of site. 
· Excavation of new foundations. 
· Use of equipment to construct the existing and new buildings sub and superstructure. 
· Scaffolding 
· Consultants shall supervise these works, produce verification reports and carry out the 
necessary checking of materials and testing of concrete when required. 
1
Table of Contents 
□ General 
□ Pre-Construction 
□ Site Management 
□ Personnel 
□ Scaffolding 
□ Dust and Debris 
□ Working Hours 
□ Equipment for work 
□ Security and Warehouse 
2
 General 
This method statement has been prepared on the basis of the tender information as issued 
and gives an indication of our general approach to the construction and management of 
the project. 
We have included our intentions for managing and supporting the project and the 
particular approaches that will be taken for certain key aspects. 
 Pre-construction 
Prior to commencement of site works, an external survey will be carried out to confirm 
the existing site levels, extent of any existing services and the condition of the existing 
environs. 
These will be plotted on a drawing and a photographic record will be taken, which will be 
maintained as a record throughout the stages of the contract. 
 Site Establishment Managements 
The site establishment will be managed by the site supervisor who will be stationed at site until 
the project is completed. He will take steps for ensuring that all resources, man and materials 
are available at site in time. All of our site staff will be governed by rules and procedure of City 
Construction Inc.which will include the following: 
· Working conditions 
· Health and safety(All of our site staff will be tested before the work commencement of 
contract when awarded) 
· Conduct at site 
· Facilities at site 
● Reporting of site activities to head office on regular basis. 
Personnel 
All personnel will be inducted prior to gaining access to the site. They will be informed of the 
specific site rules required in the preliminaries relating to this project as well as City 
Construction Inc. site rules and their own companies method statement 
Listed below are key personnel that will be present on site: 
3
· Project Engineer (Civil Engineer) 
· Site Supervisor ( Civil Engineer) 
· Laborers 
· First Aiders (Nurse) 
· Employer Representative 
 Scaffolding 
Scaffoldings where required, will be independent to suit the nature; location and type of the 
particular operations. All scaffolding will be securely tied to the structure and will include 
suitable ladder access. Scaffolding will be provided, erected and maintained in accordance with 
all current statutory regulations. No person other than certified competent scaffolders will be 
permitted to erect, alter, adapt or dismantle any scaffolding. 
 Dust and Debris 
The site will be kept clean and tidy at all times and will accord with any statutory requirements. 
Particular attention will be given to preventing the contamination of existing water courses. 
 Working hour 
There will be one hour of break during every working day for lunch. All employees of ours will be 
identified with a tag symbolizing our company name and location with numbers on it. 
Time arrangement 8.00 am – 5.00pm Monday – Saturday (12noon-1:00pm lunch time) 
 Equipments for work 
These are equipments that will be used to execute the project when the contract is awarded to 
us. 
Excavator fitted with shears selector grab 
Demolition tracked machine fitted with controlled attachments tractor and towable water 
bower and jet spray for dust suppression 
4
4 utility mobiles for elevating demolished materials 
4 tankers for sucking of oil and fuel 
1 Water pumps 
 Security and Warehouse 
All necessary registers, diary, time book method statement, health and safety plan will be kept 
on site under the control of the project engineer and can be inspected at any time. All accidents 
are to be reported to and entered in the site accident book. 
A supply of spare hard hats, overalls, gloves, and goggles masks, all of these materials will be 
store on site. 
City Construction Inc. will ensure a high standard of health safety carried out at all times on site. 
All operatives on site must wear full PPE accordance with the health safety requirements 
including safety boots, hard hats and a high visibility vets or coat as standard. 
No smoking on site policy will be adhered to at all times; smoking will only take place in the site 
designated area. 
There will be private guards appointed to ensure that all properties and lives are well taken care 
of on site at all time. 
A temporary warehouse will be built when the contract is awarded to us before the start date of 
the contract for storage of materials that should not be exposing to water and etc. 
5
CONCLUSION 
The above method statement has been developed specifically to demonstrate our 
understanding of the project requirements and the detailed methodology required to carry 
out a project of this nature, in the most viable and safe manner to achieve a completed 
project to the satisfaction of all parties involved. 
6
CONCLUSION 
The above method statement has been developed specifically to demonstrate our 
understanding of the project requirements and the detailed methodology required to carry 
out a project of this nature, in the most viable and safe manner to achieve a completed 
project to the satisfaction of all parties involved. 
6

More Related Content

DOCX
Method statement piping works
PDF
Method of Statement - Road furniture works
PPT
072 Method Statement
DOC
Piling work method statement cm- ms- bw - 002
PDF
Method statement of temporary office and fa
DOCX
Method statement for structure excavation
DOC
Building work method statement cm - ms- bw - 001
PDF
Method statement for civil works
Method statement piping works
Method of Statement - Road furniture works
072 Method Statement
Piling work method statement cm- ms- bw - 002
Method statement of temporary office and fa
Method statement for structure excavation
Building work method statement cm - ms- bw - 001
Method statement for civil works

What's hot (20)

PPTX
Crane Operation - Lifting
PDF
Method of Statement - Pavement works
DOC
Excavation method rectified 13-11-2010
PDF
Construction Presentations 2019
PDF
Oil & Gas Plant Construction, Project Execution Plan
DOCX
22 casting of concrete columns risk assessment templates
PDF
Project Execution Plan for Bridge Construction
PDF
Lifting steam drum 72 ton by winch
DOCX
Method statement tank base concrete pouring
PPTX
CH: 8 Safety measures
DOCX
29 Workplace Temporary Lighting Risk Assessment Templates.docx
DOC
Method statement for repair of concrete surface
PPTX
Basic Rigging
PDF
Scaffold safe work method statement
DOCX
VISITOR SAFETY INDUCTION Form # HSEQ - VSI Rev 2 - S.docx
PDF
Use of IS Code for safety
DOC
Concreting of super structure
PDF
risk assessment - pile cap.pdf
PPT
Rope suspended platform- Safety
Crane Operation - Lifting
Method of Statement - Pavement works
Excavation method rectified 13-11-2010
Construction Presentations 2019
Oil & Gas Plant Construction, Project Execution Plan
22 casting of concrete columns risk assessment templates
Project Execution Plan for Bridge Construction
Lifting steam drum 72 ton by winch
Method statement tank base concrete pouring
CH: 8 Safety measures
29 Workplace Temporary Lighting Risk Assessment Templates.docx
Method statement for repair of concrete surface
Basic Rigging
Scaffold safe work method statement
VISITOR SAFETY INDUCTION Form # HSEQ - VSI Rev 2 - S.docx
Use of IS Code for safety
Concreting of super structure
risk assessment - pile cap.pdf
Rope suspended platform- Safety
Ad

Viewers also liked (13)

PPT
Construction plan 29.08. 14
DOC
Concrete method rev02
PDF
Pca rectangular concrete tanks (1)
PDF
Method Statement Cleaning and Treating New Commercial Systems
PDF
ERECTION METHOD STATEMENT
PDF
Rectangular tank example_latest
PDF
Introduction & under ground water tank problem
PPT
Quality Control & Quality Assurance of MS pipeline
DOC
Method painting works emulsion paint
PDF
Ms for-mechanical-piping-system-installation-work
DOCX
Method statement painting
PDF
Estimating and-costing book
DOCX
Methods of Dewatering
Construction plan 29.08. 14
Concrete method rev02
Pca rectangular concrete tanks (1)
Method Statement Cleaning and Treating New Commercial Systems
ERECTION METHOD STATEMENT
Rectangular tank example_latest
Introduction & under ground water tank problem
Quality Control & Quality Assurance of MS pipeline
Method painting works emulsion paint
Ms for-mechanical-piping-system-installation-work
Method statement painting
Estimating and-costing book
Methods of Dewatering
Ad

Similar to METHOD STATEMENT (20)

PDF
Constructionmethodologyandprojectmanagementreport
PDF
Job Layout
PPTX
Subsea fibre optics Submarine cable laying.pptx
PPT
rustomji urbania- technical presentation (r2) (1).ppt
PPTX
Process Hazards analysis presentation for beginners
PDF
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
DOCX
CEM455 CONSTRUCTION Final Project
DOCX
Monthly Environmental Inspection
PDF
Industrial training report.pdf
PDF
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PPTX
Checklist for Safety and Health Program.pptx
PDF
Building Construction 1: Project 1
PDF
Building Construction Assignment 1
PPTX
Site organization and networking techniques
PPTX
17. environmental and safety consideration and choice of materials
DOCX
ajay jain FINAL REPORT
PDF
Phases of Construction & Erection for Wind Power Project_03 09 2019
DOCX
start.docx
PDF
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
PPTX
RAMRAJ field practice about civilengineering.pptx
Constructionmethodologyandprojectmanagementreport
Job Layout
Subsea fibre optics Submarine cable laying.pptx
rustomji urbania- technical presentation (r2) (1).ppt
Process Hazards analysis presentation for beginners
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
CEM455 CONSTRUCTION Final Project
Monthly Environmental Inspection
Industrial training report.pdf
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
Checklist for Safety and Health Program.pptx
Building Construction 1: Project 1
Building Construction Assignment 1
Site organization and networking techniques
17. environmental and safety consideration and choice of materials
ajay jain FINAL REPORT
Phases of Construction & Erection for Wind Power Project_03 09 2019
start.docx
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
RAMRAJ field practice about civilengineering.pptx

METHOD STATEMENT

  • 1. Method Statement for Execution of the Civil Works for the Refurbishment of the Agricultural Laboratory of the University of Liberia · Receipt of Contract When the contract is awarded to City construction Inc. the following will be executed in a suitable and shortest time as per steps laid down below. The works that will be carried comprise of the following: · Carry out Pre-demolition and Refurbishment survey to identify all walls as shown in dotted line and concrete shell to be clean within the existing structure to be used as Main Laboratory Building. · Demolition of walls, clearing and storing debris for future use if necessary and preparation of site. · Excavation of new foundations. · Use of equipment to construct the existing and new buildings sub and superstructure. · Scaffolding · Consultants shall supervise these works, produce verification reports and carry out the necessary checking of materials and testing of concrete when required. 1
  • 2. Table of Contents □ General □ Pre-Construction □ Site Management □ Personnel □ Scaffolding □ Dust and Debris □ Working Hours □ Equipment for work □ Security and Warehouse 2
  • 3.  General This method statement has been prepared on the basis of the tender information as issued and gives an indication of our general approach to the construction and management of the project. We have included our intentions for managing and supporting the project and the particular approaches that will be taken for certain key aspects.  Pre-construction Prior to commencement of site works, an external survey will be carried out to confirm the existing site levels, extent of any existing services and the condition of the existing environs. These will be plotted on a drawing and a photographic record will be taken, which will be maintained as a record throughout the stages of the contract.  Site Establishment Managements The site establishment will be managed by the site supervisor who will be stationed at site until the project is completed. He will take steps for ensuring that all resources, man and materials are available at site in time. All of our site staff will be governed by rules and procedure of City Construction Inc.which will include the following: · Working conditions · Health and safety(All of our site staff will be tested before the work commencement of contract when awarded) · Conduct at site · Facilities at site ● Reporting of site activities to head office on regular basis. Personnel All personnel will be inducted prior to gaining access to the site. They will be informed of the specific site rules required in the preliminaries relating to this project as well as City Construction Inc. site rules and their own companies method statement Listed below are key personnel that will be present on site: 3
  • 4. · Project Engineer (Civil Engineer) · Site Supervisor ( Civil Engineer) · Laborers · First Aiders (Nurse) · Employer Representative  Scaffolding Scaffoldings where required, will be independent to suit the nature; location and type of the particular operations. All scaffolding will be securely tied to the structure and will include suitable ladder access. Scaffolding will be provided, erected and maintained in accordance with all current statutory regulations. No person other than certified competent scaffolders will be permitted to erect, alter, adapt or dismantle any scaffolding.  Dust and Debris The site will be kept clean and tidy at all times and will accord with any statutory requirements. Particular attention will be given to preventing the contamination of existing water courses.  Working hour There will be one hour of break during every working day for lunch. All employees of ours will be identified with a tag symbolizing our company name and location with numbers on it. Time arrangement 8.00 am – 5.00pm Monday – Saturday (12noon-1:00pm lunch time)  Equipments for work These are equipments that will be used to execute the project when the contract is awarded to us. Excavator fitted with shears selector grab Demolition tracked machine fitted with controlled attachments tractor and towable water bower and jet spray for dust suppression 4
  • 5. 4 utility mobiles for elevating demolished materials 4 tankers for sucking of oil and fuel 1 Water pumps  Security and Warehouse All necessary registers, diary, time book method statement, health and safety plan will be kept on site under the control of the project engineer and can be inspected at any time. All accidents are to be reported to and entered in the site accident book. A supply of spare hard hats, overalls, gloves, and goggles masks, all of these materials will be store on site. City Construction Inc. will ensure a high standard of health safety carried out at all times on site. All operatives on site must wear full PPE accordance with the health safety requirements including safety boots, hard hats and a high visibility vets or coat as standard. No smoking on site policy will be adhered to at all times; smoking will only take place in the site designated area. There will be private guards appointed to ensure that all properties and lives are well taken care of on site at all time. A temporary warehouse will be built when the contract is awarded to us before the start date of the contract for storage of materials that should not be exposing to water and etc. 5
  • 6. CONCLUSION The above method statement has been developed specifically to demonstrate our understanding of the project requirements and the detailed methodology required to carry out a project of this nature, in the most viable and safe manner to achieve a completed project to the satisfaction of all parties involved. 6
  • 7. CONCLUSION The above method statement has been developed specifically to demonstrate our understanding of the project requirements and the detailed methodology required to carry out a project of this nature, in the most viable and safe manner to achieve a completed project to the satisfaction of all parties involved. 6