Page 1 of 9
DASHERKANDI SEWAGE TREATMENT
PLANT PROJECT
Employer: Dhaka Water Supply & Sewerage
Authority
DSTP-HCC-MS-02
Method Statement for Excavation
Work
THE EMPLOYER:
DHAKA WASA
THE CONSULTANTS:
HANKUK ENGINEERING
CONSULTANTS
THE CONTRACTOR:
HYDROCHINA
Page 2 of 9
Rev.
No.
Date Amendment Record Prepared By Approved By
0 22/04/2018
First Version Provided by
HydroChina
Nabin
1 27/05/2018
Second Version Provided
by HydroChina
Nabin
2 10/06/2018
Third Version Provided by
HydroChina
Nabin
Page 3 of 9
Table of Content
1. Purpose and Scope ....................................................4
2. Reference Document ..................................................4
3. Organization Responsibility.......................................4
4. Resource .....................................................................5
4.1 Main construction equipment ...................................................5
4.2 Manpower..................................................................................5
4.3 Soil and improved sub-grade testing equipments...................6
5. Excavation Method .....................................................6
5.1 Process of Excavation work...................................................... 6
5.2 Survey and setting out.............................................................. 7
5.3 Excavation work........................................................................7
5.4 Filling for foundation..................................................................8
6. Health and Safety ........................................................8
7. Quality Plan .................................................................9
Page 4 of 9
1. Purpose & Scope
This plan provided for structure of DSTP excavation and associated work to
ensure compliance with contract specification and BNBC 2006.
The plant is located in low lying area and sand filling work to an average
elevation is already completed. As the construction drawing, all of the
excavation and backfilling work of the structure of DSTP will be on the filling
sand layer. This procedure provides a standardized framework for the control
of excavation, earthwork, storage and filling of filling sand for foundation
treatment.
2. Reference Document
1) Volume 2 & 4: technical proposal & technical specification.
2) Bangladesh National Building Code 2006.
3. OrganizationResponsibility
The organization of site includes Construction Manager, Site Manager, Site
Engineer and Site Safety Officer for the structure excavation and associated
work.
Construction Manager gives instructions to Site Manager to ensure that all
safety requirements are comply all the times.
Site Manager Reports to the Construction Manager will be in-charge of the
construction. He will coordinate all concerned parties and ensure site works are
completing in time and with proper quality.
Site Engineer reports to the Site Manager will be in charge of the construction
quality. In order to contact with them on site instantly, the detailed information
about them will be provided as follow.
Page 5 of 9
Site Safety Officer who create and maintain safe working conditions in all
operations.
Table 3.1: Organization chart for excavation work
S/
N
Name Position Mobile
1 Liu Aihua Construction Manager 01829879756
2 Qiu Dong Site Manager 01774177589
3 Liu Zhi Site Engineer 01783775739
4 Chen Song Site Safety officer 01701394908
4. Resource
4.1Main Construction Equipment
Main equipment’s utilized in this work are as following.
Table 4.1: Equipment’s list for excavation work
NO. Description Quantity Remarks
1 Excavator 2
2 Plate Compactor 1
3 Wheel loader 2
4 Heavy truck 4
5 Small truck 1
4.2Manpower
The estimated manpower is tabulated as follow, which will be subject to revision
based on actual requirements during implementation.
Table 4.2: Manpower list for excavation work
S/N Description Number Required Remarks
1 Construction Manager 1
2 Site Manager 1
3 Site Engineer 1
Page 6 of 9
4 Excavator operator 2
5 Wheel loader operator 2
6 Truck operator 5
7 Site Safety Officer 1
8 Compactor operator 1
9 Technician of survey 1
10 Repairman 2
11 Electrician 2
12 labor 10
4.3 Soil and Improved Sub-grade testing
1. Digital moisture measuring meter
2. One set of standard proctor test equipment (mould,hammer,cans etc.)
3. One set field density measuring device (measuring jar, sand etc.)
4. One no. electric oven (250’c, 720 litre)
5. One no. electric oven (250’C, 720 litre)
5 Excavation Method
5.1 Process of Excavation work and backfilling
Survey and setting out
Excavation
Structure construction
Backfilling
Figure-5.1 Excavation process
Page 7 of 9
5.2 Survey and Setting Out
Prior to commencement work, a level survey will be carried out to confirm the
information included on the contract drawing and to provide an accurate record
of the existing ground levels (E.G.L) for the calculation of quantities.
Before the trench excavation, the alignment of structure shall be surveyed and
set out accurately and submit the report to the consultant and approved by them.
5.3 Excavation Work
1) Excavator will be used for excavation and dump trucks will be used to
transport the excavated material to the suitable place for temporary storage.
The excavated material will be backfilled after the structure work completed.
2) The excavation will be done according to the location of survey and setting
out, professional construction personnel will be arranged to in charge of the
work.
3) The excavation will be done in which method that the excavate level shall
be controlled time to time to avoid over excavate happened.
4) After reaching the designed formation level, consultant’s representative
shall be requested in writing to inspect and approve the formation prior to
the commencement of any subsequent activities.
5) If water is encountered, dewatering measures, such ditches drainage
should be applied. Dewatering should be conducted carefully when it is in
the vicinity of the buildings or structures so as to avoid the damage of
buildings or structures. Great care shall be taken to minimize noise, vibration
and dust pollution, which can cause nuisance and damage.
6) For slop protection of the foundation excavation suitable method will be
adopt to prevent slope instability.
a) For most of the structures in DSTP which have enough space, slop
excavation method will be adopted and the slop will be control.
b) The inlet pump station of DSTP will use steel sheet pile for foundation
protection due to its excavation depth is very deep.
Page 8 of 9
c) Some other structure or pipeline at site can’t use the method of open
excavation the sheet pile may be used as required of the site condition.
5.4 Filling for Foundation
1) Before placement of the fill, the existing ground surface shall be stripped of
all organic growth, timber, rubbish and debris. After stripping, the ground
surface shall be compacted.
2) Filling should be done from both sides of pipe line in such a way that, the
pipes may not shove away. Include the filling material quality around the
pipe for 0.5 m.
3) Excavated foundations will be back-filled with excavated material and the
material is filling sand. Roller (15t) will be used as required to compact the
excavated material which will be compacted layer by layer as require depth.
Watering the backfilled sand as required after filling work completed for self-
compaction.
6 Safety and Health
Every excavation shall be provided with safe means of ingress and exit kept
available at all times.
1) Safety equipment as necessary
2) Safety induction for New Employees
3) Inspection of Machinery everyday
4) Safety tool box talks to be convened and attended by all personnel to do
the work prior to starting which will be given instruction the hazards and
safe systems of work.
5) Strictly following the approved HSE plan is necessary.
6) Guard rail of 1m height should be provided.
Page 9 of 9
7 Quality Plan
HydroChina intends to implement its quality control in accordance with the
approved Quality Plan of the project. The quality of our activities will be set to
conform to our commitment to provide a level of service and operational
standard that complies with Project technical specification.

More Related Content

DOCX
Method statement tank base concrete pouring
PDF
Method of Statement - Road furniture works
DOC
Method statement for repair of concrete surface
PPTX
Pipeline integrity documentation
PPTX
5 "S" A brief presentation by shihab
DOCX
Method statement honycomb repairing
DOC
Static load test method statement cm - ms- bw - 003
PDF
Ms for-mechanical-piping-system-installation-work
Method statement tank base concrete pouring
Method of Statement - Road furniture works
Method statement for repair of concrete surface
Pipeline integrity documentation
5 "S" A brief presentation by shihab
Method statement honycomb repairing
Static load test method statement cm - ms- bw - 003
Ms for-mechanical-piping-system-installation-work

What's hot (20)

PPTX
civil engineering-Contracts
PPTX
Safety precautions during demolition
PPTX
Spun pile
PDF
Bar bending schedule (2)
PDF
Bridge construction methodology
DOC
Engineering constructionmethodsguidelinescbs(2)
PDF
Procurement in construction
PPT
Backfilling 2014a-Lecture4
PPT
Stages in Construction
DOCX
Job layout per
PPTX
Highway failure & their maintenance ppt
PPTX
G+3 APARTMENT BUILDING PROJECT REPORT
PDF
Method of Statement - Pavement works
DOC
Excavation method rectified 13-11-2010
PPTX
Chapter 5 formwork
PPTX
Rate analysis in civil engineering
PPTX
Setting out construction works 01
PPT
Tender evaluation procedure
DOCX
Civil engineering internship report
PPTX
Demolition methods and its sequence
civil engineering-Contracts
Safety precautions during demolition
Spun pile
Bar bending schedule (2)
Bridge construction methodology
Engineering constructionmethodsguidelinescbs(2)
Procurement in construction
Backfilling 2014a-Lecture4
Stages in Construction
Job layout per
Highway failure & their maintenance ppt
G+3 APARTMENT BUILDING PROJECT REPORT
Method of Statement - Pavement works
Excavation method rectified 13-11-2010
Chapter 5 formwork
Rate analysis in civil engineering
Setting out construction works 01
Tender evaluation procedure
Civil engineering internship report
Demolition methods and its sequence
Ad

Similar to Method statement for structure excavation (20)

PDF
Method statement of temporary office and fa
DOC
Column & beam
DOC
Concreting of super structure
PDF
Advanced Building Measurement
PPTX
A summer training at pwd b&r,hisar
PDF
Building Construction Report
PDF
final report last.pdf
DOCX
Building Industrial Training report for CIVIL ENGINEERING
PDF
Buildng construction report
PDF
SITE REPORT
PDF
1008 caissons-specification
PDF
Conceptual and geometric design of tunnel and quantity estimation
PDF
WAJ gen.specs 2007
PPTX
Earthwork
DOCX
Civil Engineering Measurment
PPTX
Site Organization (Construction management)
PPTX
Experiencing Construction
PDF
Deep Excavation Design and Construction _2023.pdf
DOCX
CE1 - Final Reviewed - 10 Feb 2016
PDF
Delhi metro presention
Method statement of temporary office and fa
Column & beam
Concreting of super structure
Advanced Building Measurement
A summer training at pwd b&r,hisar
Building Construction Report
final report last.pdf
Building Industrial Training report for CIVIL ENGINEERING
Buildng construction report
SITE REPORT
1008 caissons-specification
Conceptual and geometric design of tunnel and quantity estimation
WAJ gen.specs 2007
Earthwork
Civil Engineering Measurment
Site Organization (Construction management)
Experiencing Construction
Deep Excavation Design and Construction _2023.pdf
CE1 - Final Reviewed - 10 Feb 2016
Delhi metro presention
Ad

Recently uploaded (20)

PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPT
introduction to datamining and warehousing
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
bas. eng. economics group 4 presentation 1.pptx
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PPTX
Sustainable Sites - Green Building Construction
PPTX
OOP with Java - Java Introduction (Basics)
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
Current and future trends in Computer Vision.pptx
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
web development for engineering and engineering
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
introduction to datamining and warehousing
Lecture Notes Electrical Wiring System Components
bas. eng. economics group 4 presentation 1.pptx
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
Sustainable Sites - Green Building Construction
OOP with Java - Java Introduction (Basics)
Operating System & Kernel Study Guide-1 - converted.pdf
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Embodied AI: Ushering in the Next Era of Intelligent Systems
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
Model Code of Practice - Construction Work - 21102022 .pdf
Foundation to blockchain - A guide to Blockchain Tech
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
UNIT 4 Total Quality Management .pptx
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Current and future trends in Computer Vision.pptx
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
web development for engineering and engineering

Method statement for structure excavation

  • 1. Page 1 of 9 DASHERKANDI SEWAGE TREATMENT PLANT PROJECT Employer: Dhaka Water Supply & Sewerage Authority DSTP-HCC-MS-02 Method Statement for Excavation Work THE EMPLOYER: DHAKA WASA THE CONSULTANTS: HANKUK ENGINEERING CONSULTANTS THE CONTRACTOR: HYDROCHINA
  • 2. Page 2 of 9 Rev. No. Date Amendment Record Prepared By Approved By 0 22/04/2018 First Version Provided by HydroChina Nabin 1 27/05/2018 Second Version Provided by HydroChina Nabin 2 10/06/2018 Third Version Provided by HydroChina Nabin
  • 3. Page 3 of 9 Table of Content 1. Purpose and Scope ....................................................4 2. Reference Document ..................................................4 3. Organization Responsibility.......................................4 4. Resource .....................................................................5 4.1 Main construction equipment ...................................................5 4.2 Manpower..................................................................................5 4.3 Soil and improved sub-grade testing equipments...................6 5. Excavation Method .....................................................6 5.1 Process of Excavation work...................................................... 6 5.2 Survey and setting out.............................................................. 7 5.3 Excavation work........................................................................7 5.4 Filling for foundation..................................................................8 6. Health and Safety ........................................................8 7. Quality Plan .................................................................9
  • 4. Page 4 of 9 1. Purpose & Scope This plan provided for structure of DSTP excavation and associated work to ensure compliance with contract specification and BNBC 2006. The plant is located in low lying area and sand filling work to an average elevation is already completed. As the construction drawing, all of the excavation and backfilling work of the structure of DSTP will be on the filling sand layer. This procedure provides a standardized framework for the control of excavation, earthwork, storage and filling of filling sand for foundation treatment. 2. Reference Document 1) Volume 2 & 4: technical proposal & technical specification. 2) Bangladesh National Building Code 2006. 3. OrganizationResponsibility The organization of site includes Construction Manager, Site Manager, Site Engineer and Site Safety Officer for the structure excavation and associated work. Construction Manager gives instructions to Site Manager to ensure that all safety requirements are comply all the times. Site Manager Reports to the Construction Manager will be in-charge of the construction. He will coordinate all concerned parties and ensure site works are completing in time and with proper quality. Site Engineer reports to the Site Manager will be in charge of the construction quality. In order to contact with them on site instantly, the detailed information about them will be provided as follow.
  • 5. Page 5 of 9 Site Safety Officer who create and maintain safe working conditions in all operations. Table 3.1: Organization chart for excavation work S/ N Name Position Mobile 1 Liu Aihua Construction Manager 01829879756 2 Qiu Dong Site Manager 01774177589 3 Liu Zhi Site Engineer 01783775739 4 Chen Song Site Safety officer 01701394908 4. Resource 4.1Main Construction Equipment Main equipment’s utilized in this work are as following. Table 4.1: Equipment’s list for excavation work NO. Description Quantity Remarks 1 Excavator 2 2 Plate Compactor 1 3 Wheel loader 2 4 Heavy truck 4 5 Small truck 1 4.2Manpower The estimated manpower is tabulated as follow, which will be subject to revision based on actual requirements during implementation. Table 4.2: Manpower list for excavation work S/N Description Number Required Remarks 1 Construction Manager 1 2 Site Manager 1 3 Site Engineer 1
  • 6. Page 6 of 9 4 Excavator operator 2 5 Wheel loader operator 2 6 Truck operator 5 7 Site Safety Officer 1 8 Compactor operator 1 9 Technician of survey 1 10 Repairman 2 11 Electrician 2 12 labor 10 4.3 Soil and Improved Sub-grade testing 1. Digital moisture measuring meter 2. One set of standard proctor test equipment (mould,hammer,cans etc.) 3. One set field density measuring device (measuring jar, sand etc.) 4. One no. electric oven (250’c, 720 litre) 5. One no. electric oven (250’C, 720 litre) 5 Excavation Method 5.1 Process of Excavation work and backfilling Survey and setting out Excavation Structure construction Backfilling Figure-5.1 Excavation process
  • 7. Page 7 of 9 5.2 Survey and Setting Out Prior to commencement work, a level survey will be carried out to confirm the information included on the contract drawing and to provide an accurate record of the existing ground levels (E.G.L) for the calculation of quantities. Before the trench excavation, the alignment of structure shall be surveyed and set out accurately and submit the report to the consultant and approved by them. 5.3 Excavation Work 1) Excavator will be used for excavation and dump trucks will be used to transport the excavated material to the suitable place for temporary storage. The excavated material will be backfilled after the structure work completed. 2) The excavation will be done according to the location of survey and setting out, professional construction personnel will be arranged to in charge of the work. 3) The excavation will be done in which method that the excavate level shall be controlled time to time to avoid over excavate happened. 4) After reaching the designed formation level, consultant’s representative shall be requested in writing to inspect and approve the formation prior to the commencement of any subsequent activities. 5) If water is encountered, dewatering measures, such ditches drainage should be applied. Dewatering should be conducted carefully when it is in the vicinity of the buildings or structures so as to avoid the damage of buildings or structures. Great care shall be taken to minimize noise, vibration and dust pollution, which can cause nuisance and damage. 6) For slop protection of the foundation excavation suitable method will be adopt to prevent slope instability. a) For most of the structures in DSTP which have enough space, slop excavation method will be adopted and the slop will be control. b) The inlet pump station of DSTP will use steel sheet pile for foundation protection due to its excavation depth is very deep.
  • 8. Page 8 of 9 c) Some other structure or pipeline at site can’t use the method of open excavation the sheet pile may be used as required of the site condition. 5.4 Filling for Foundation 1) Before placement of the fill, the existing ground surface shall be stripped of all organic growth, timber, rubbish and debris. After stripping, the ground surface shall be compacted. 2) Filling should be done from both sides of pipe line in such a way that, the pipes may not shove away. Include the filling material quality around the pipe for 0.5 m. 3) Excavated foundations will be back-filled with excavated material and the material is filling sand. Roller (15t) will be used as required to compact the excavated material which will be compacted layer by layer as require depth. Watering the backfilled sand as required after filling work completed for self- compaction. 6 Safety and Health Every excavation shall be provided with safe means of ingress and exit kept available at all times. 1) Safety equipment as necessary 2) Safety induction for New Employees 3) Inspection of Machinery everyday 4) Safety tool box talks to be convened and attended by all personnel to do the work prior to starting which will be given instruction the hazards and safe systems of work. 5) Strictly following the approved HSE plan is necessary. 6) Guard rail of 1m height should be provided.
  • 9. Page 9 of 9 7 Quality Plan HydroChina intends to implement its quality control in accordance with the approved Quality Plan of the project. The quality of our activities will be set to conform to our commitment to provide a level of service and operational standard that complies with Project technical specification.