Coromatic Academy
Open Compute Project, Critical Facilities Operations Framework
Functions: Integration
Rev 2020-08-10
Information classification: Public
Contents
• Overview of functions
• Lessons learned / customer experiences
• Final notes
INTEGRATION
OCP Critical Facilities Operations Framework
Site Operations
Integration
Terms &
Conditions
OCP CFOPS Delivery model
Incidents
Work Orders & Projects
On-site Access
Service Levels
Organization
KPI Monitoring
& Reporting
Lifecycle &
Financial
Mgmt
On-site
services
Security &
Access
Maintenance
In / outdoor
FM
Site
assistance
Site Inspection
Audits and
Compliance
Site Management
Delivery Support
Service Level
Mgmt
Lifecycle &
Financial
Mgmt
WO & Project
Mgmt
Monitoring &
Reporting
Governance
and BCP
Advisory and
Benchmarking
Supply Chain
and Sourcing
Service Desk
24/7
Incident Mgmt
Team &
Suppliers
Capacity
Mgmt &
Optimization
Document
Mgmt
Compliance
Mgmt
Service
Improvements
Asset List
Border List
Customer
Managed
Operating
Center
Source: OCP CFOPS 2019 v1.4
Integration
MindMap Overview Summary
Integration of processes and governance through Transition
The delivery requires integration of the parties’ processes and governance structures to
minimize risks and to secure continuous improvements.
During the transition phase, the customer and the supplier align and integrate their
processes, functions, systems and organizations to enable efficient operations.
The starting point should be the current site strategy set by the customer.
Transition project
To ensure transparency and minimized risks, the transition should be run as a clearly
defined project that is led and quality assured by highly skilled and experienced transition
specialists.
In some instances, team members from the previous customer organization join a new
supplier, while in other situations the organizations are kept as-is.
Risk-based approach to ensure commonly understood Statement of Work
Through a risk-based transition methodology the parties collaborate and ensure there is a
commonly understood Statement of Work (SOW) which clarifies what services are
included in the baseline and what services are available via separate service requests.
Based on: OCP CFOPS 2019 v1.4
Lessons learned / Customer experiences
Based on: OCP CFOPS 2019 v1.4
Integration
MindMap Overview Summary
Integration of processes and governance through Transition
The delivery requires integration of the parties’ processes and governance structures to
minimize risks and to secure continuous improvements.
During the transition phase, the customer and the supplier align and integrate their
processes, functions, systems and organizations to enable efficient operations.
The starting point should be the current site strategy set by the customer.
Transition project
To ensure transparency and minimized risks, the transition should be run as a clearly
defined project that is led and quality assured by highly skilled and experienced transition
specialists.
In some instances, team members from the previous customer organization join a new
supplier, while in other situations the organizations are kept as-is.
Risk-based approach to ensure commonly understood Statement of Work
Through a risk-based transition methodology the parties collaborate and ensure there is a
commonly understood Statement of Work (SOW) which clarifies what services are
included in the baseline and what services are available via separate service requests.
Based on: OCP CFOPS 2019 v1.4
Output Comment
Statement of Work incl. service levels with penalties for Site Services
(SOW with SLA)
This is the main document clarifying scope and expectations for the Services Agreement.
The SOW has a focus on services and technologies in scope, but also covers other topics, e.g. pricing, duration. It can cover
anything from pure play Site Management to a full-blown Site Operations – or anything in between.
Service levels are defined to ensure a proper prioritization of efforts. These should reflect the Site Strategy to ensure alignment
with customer needs. The service levels to be managed can be any combination of KPIs and they may address the commitments
by Site Management or by other stakeholders, depending on roles and responsibilities.
The SOW should have appendices or refer to separate documentation for Border Lists, Asset Lists, Service Levels, Organization
(demand and supply) and refer to what Terms & Conditions apply.
It is approved by both the Customer and the supplier and handled through the Document Management. It is stored in the
Reference Library (“Agreements incl. Border lists”).
Asset Lists for in-scope site supply systems (AL)
Current Asset Lists for in-scope supply systems should be produced and validated by both parties to ensure it matches the
planned scope of the SOW and to minimize risks of stakeholder expectation gaps.
It is handled through the Document Management process and stored in the Reference Library (“Asset lists incl. EOL”).
Border Lists for in-scope site services (BL)
Current Border Lists for in-scope services should be produced and validated by both parties to ensure it matches the planned
scope of the SOW and to minimize risks of stakeholder expectation gaps.
It is handled through the Document Management process and stored in the Reference Library (“Agreements incl. Border lists”).
Organization with roles, meeting frequencies and templates etc.
This is part of the Document Management repository for Site Policies, where Organization including third party stakeholder
dependencies are used to capture demand and supply of services via an operating model and a governance model.
It is handled through the Document Management process and stored in the Site Policies (“Organization”).
Terms & Conditions that regulate the SOW (T&C)
The SOW relies on being part of a larger context. This could be generally accepted standard agreement in the market or directly
negotiated terms and conditions between the parties (with or without an underlying Framework Agreement).
Handled in Document Mgmt process and stored in Reference Library (“Agreements incl. Border lists”).
SOW: Key outputs
Based on: OCP CFOPS 2019 v1.4
Integration
MindMap Overview Summary
Integration of processes and governance through Transition
The delivery requires integration of the parties’ processes and governance structures to
minimize risks and to secure continuous improvements.
During the transition phase, the customer and the supplier align and integrate their
processes, functions, systems and organizations to enable efficient operations.
The starting point should be the current site strategy set by the customer.
Transition project
To ensure transparency and minimized risks, the transition should be run as a clearly
defined project that is led and quality assured by highly skilled and experienced transition
specialists.
In some instances, team members from the previous customer organization join a new
supplier, while in other situations the organizations are kept as-is.
Risk-based approach to ensure commonly understood Statement of Work
Through a risk-based transition methodology the parties collaborate and ensure there is a
commonly understood Statement of Work (SOW) which clarifies what services are
included in the baseline and what services are available via separate service requests.
Based on: OCP CFOPS 2019 v1.4
Processes and site systems: Key outputs
Based on: OCP CFOPS 2019 v1.4
Output Comment
Incident Management It is critical that Incident Management is handled correctly between all involved stakeholders, including third parties.
Work Orders & Project Management
To ensure that Border List accountabilities are fulfilled by the process to order and approve site works it needs to be integrated and documented
between the stakeholders involved.
Monitoring & Reporting with standard KPI reports
The process and its supporting systems (automated or manual) should be in place to collect, share and report relevant data in a timely manner.
This also includes frequency and contents for recurring operational level meetings and reports
Lifecycle & Financial Management
By ensuring that Site Systems Lifecycle Management, Financial Management and Tender & Selection sub-processes are integrated between
demand and supply, the general cost levels and quality KPIs get identified.
Parts of Security & Access: Authorize &
Authenticate for On-site Access
The activities of authentication and authorization should not be confused when integrating access control to sites in scope:
 Authorization is to decide who has permit to access to a site. (provided by the customer)
 Authentication confirms a person’s identity
(provided by customer, Supplier or a third party)
 Access to site is only allowed for authenticated authorized persons
(provided by customer, Supplier or a third party)
Other access controls exist, e.g. against items not allowed on site, etc.
Supporting systems for the processes Site systems, e.g. technical alarms, and other systems required to enable the processes.
Lessons learned / Customer experiences
“We have led transition projects for critical facilities
in multiple countries during the past five years.
Our biggest lesson we have learnt is never to expect
a transition project to be run for a shorter period
than four months.
If you are forced to run it for a shorter period than
that, you should also plan for a second project to
sort out unresolved issues within 12 months…”
Final notes
Critical Success Factors during Transition
1. Customer must be willing to invest in transition
– Secure true stakeholder commitment
– Close collaboration between parties – full transparency under NDA
2. Plan based on actual current state, not “expected current state”
– Risk-based approach for prioritization of processes and activities – be honest!
– Weekly updates and risk/issue resolution meetings
3. Use expert knowledge to minimize risk
– Transition Manager skilled in Transition and Operations
– Keep experience and site knowledge in handover
4. Allow for time – but be fierce on meeting project deadlines
– 1-3 months to plan*
– 3-9 months to execute*
* N.B. For up to 10 sites and takeover of employees
Questions?
coromatic.com
17. Process: ocp cfops integration

More Related Content

PPTX
16. Process: ocp cfops delivery support
PPTX
4. Process: ocp cfops monitoring and reporting
DOCX
17. ocp cfops.integration.guideline.2019.1
PPTX
12. Process: ocp cfops indoor outdoor fm
DOCX
4. ocp cfops.monitoring reporting.guideline.2019.5
PPTX
8. Process: ocp cfops document mgmt
PPTX
9. Process: ocp cfops team and suppliers mgmt
PPTX
15. Process: ocp cfops: site assistance
16. Process: ocp cfops delivery support
4. Process: ocp cfops monitoring and reporting
17. ocp cfops.integration.guideline.2019.1
12. Process: ocp cfops indoor outdoor fm
4. ocp cfops.monitoring reporting.guideline.2019.5
8. Process: ocp cfops document mgmt
9. Process: ocp cfops team and suppliers mgmt
15. Process: ocp cfops: site assistance

What's hot (20)

PPTX
5. Process: ocp cfops work orders and project mgmt
PPTX
1. Process: ocp cfops incident mgmt
PPTX
3. Process: ocp cfops lifecycle and financial mgmt
PPT
Ocp framework.mind map.2019v1.4
PPTX
11. Process: ocp cfops maintenance
PPTX
2. Process: ocp cfops service level mgmt
PPTX
7. Process: ocp cfops compliance mgmt
PPTX
14. Process: ocp cfops audits and compliance reviews
PPTX
13. Process: ocp cfops site inspections
PPTX
6. Process: ocp cfops capacity mgmt and optimization
PPTX
10. Process: ocp cfops security and access
DOCX
8. ocp cfops.document mgmt.guideline.2019.2
PPTX
0. ocp cfops flyby
PDF
Insurance Lead Management
PPT
IAB Europe Metrics & KPIs Brand Advertiser Bulletin
PDF
Shared Services_Compliance_credential
PPTX
Visionwaves Knowledge Days - in control dashboards
PDF
Revisiting the Four Pillars Supporting an Effective BSA/AML Compliance Program
PDF
RealWinWin Wholesale Rebate Administration Services
PPTX
Service Management: Unify and streamline warranty, parts, support & service p...
5. Process: ocp cfops work orders and project mgmt
1. Process: ocp cfops incident mgmt
3. Process: ocp cfops lifecycle and financial mgmt
Ocp framework.mind map.2019v1.4
11. Process: ocp cfops maintenance
2. Process: ocp cfops service level mgmt
7. Process: ocp cfops compliance mgmt
14. Process: ocp cfops audits and compliance reviews
13. Process: ocp cfops site inspections
6. Process: ocp cfops capacity mgmt and optimization
10. Process: ocp cfops security and access
8. ocp cfops.document mgmt.guideline.2019.2
0. ocp cfops flyby
Insurance Lead Management
IAB Europe Metrics & KPIs Brand Advertiser Bulletin
Shared Services_Compliance_credential
Visionwaves Knowledge Days - in control dashboards
Revisiting the Four Pillars Supporting an Effective BSA/AML Compliance Program
RealWinWin Wholesale Rebate Administration Services
Service Management: Unify and streamline warranty, parts, support & service p...
Ad

Similar to 17. Process: ocp cfops integration (20)

PPTX
Managing outsource IT contracts - Transition management
PPT
Managing IT Transition
DOCX
Ocp cfops-framework.2019v1.4
PPT
Contract an obligation
PDF
Hitchhikers guide to_data_center_facility_ops
PPTX
1+ a strategy for the post merger network
PDF
Governance - Project Management Office Professional Services
PDF
Start With The End In Mind
PPTX
Chap013.pptx
PDF
Handling risk
PPT
Randleman Presentation
PDF
A model for optimizing process efficiency in multi stream data keying environ...
PDF
Outsourcing Best Practices - Process Efficiency
PDF
Outsourcing and Managed Services - Developing a Common Language Between Suppl...
PPT
6 Steps to Transition Govt ICT effectiveness
PPTX
SharePoint: A Case Study at Harvesters Food Bank
PDF
Project Scoping Powerpoint Presentation Slides
PPTX
Applied Project Management Strategies Upholding Public Transparency & Account...
PDF
IT Service Transformations
PPTX
SharePoint Post Deployment Stress Management NZSPC
Managing outsource IT contracts - Transition management
Managing IT Transition
Ocp cfops-framework.2019v1.4
Contract an obligation
Hitchhikers guide to_data_center_facility_ops
1+ a strategy for the post merger network
Governance - Project Management Office Professional Services
Start With The End In Mind
Chap013.pptx
Handling risk
Randleman Presentation
A model for optimizing process efficiency in multi stream data keying environ...
Outsourcing Best Practices - Process Efficiency
Outsourcing and Managed Services - Developing a Common Language Between Suppl...
6 Steps to Transition Govt ICT effectiveness
SharePoint: A Case Study at Harvesters Food Bank
Project Scoping Powerpoint Presentation Slides
Applied Project Management Strategies Upholding Public Transparency & Account...
IT Service Transformations
SharePoint Post Deployment Stress Management NZSPC
Ad

Recently uploaded (20)

PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PDF
Well-logging-methods_new................
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Construction Project Organization Group 2.pptx
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Geodesy 1.pptx...............................................
PPTX
OOP with Java - Java Introduction (Basics)
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
Welding lecture in detail for understanding
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
PPT on Performance Review to get promotions
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
web development for engineering and engineering
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
Digital Logic Computer Design lecture notes
Automation-in-Manufacturing-Chapter-Introduction.pdf
Well-logging-methods_new................
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Construction Project Organization Group 2.pptx
Mechanical Engineering MATERIALS Selection
Geodesy 1.pptx...............................................
OOP with Java - Java Introduction (Basics)
Model Code of Practice - Construction Work - 21102022 .pdf
Welding lecture in detail for understanding
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Internet of Things (IOT) - A guide to understanding
PPT on Performance Review to get promotions
UNIT 4 Total Quality Management .pptx
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
web development for engineering and engineering
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
R24 SURVEYING LAB MANUAL for civil enggi
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Digital Logic Computer Design lecture notes

17. Process: ocp cfops integration

  • 1. Coromatic Academy Open Compute Project, Critical Facilities Operations Framework Functions: Integration Rev 2020-08-10 Information classification: Public
  • 2. Contents • Overview of functions • Lessons learned / customer experiences • Final notes
  • 3. INTEGRATION OCP Critical Facilities Operations Framework
  • 4. Site Operations Integration Terms & Conditions OCP CFOPS Delivery model Incidents Work Orders & Projects On-site Access Service Levels Organization KPI Monitoring & Reporting Lifecycle & Financial Mgmt On-site services Security & Access Maintenance In / outdoor FM Site assistance Site Inspection Audits and Compliance Site Management Delivery Support Service Level Mgmt Lifecycle & Financial Mgmt WO & Project Mgmt Monitoring & Reporting Governance and BCP Advisory and Benchmarking Supply Chain and Sourcing Service Desk 24/7 Incident Mgmt Team & Suppliers Capacity Mgmt & Optimization Document Mgmt Compliance Mgmt Service Improvements Asset List Border List Customer Managed Operating Center Source: OCP CFOPS 2019 v1.4
  • 5. Integration MindMap Overview Summary Integration of processes and governance through Transition The delivery requires integration of the parties’ processes and governance structures to minimize risks and to secure continuous improvements. During the transition phase, the customer and the supplier align and integrate their processes, functions, systems and organizations to enable efficient operations. The starting point should be the current site strategy set by the customer. Transition project To ensure transparency and minimized risks, the transition should be run as a clearly defined project that is led and quality assured by highly skilled and experienced transition specialists. In some instances, team members from the previous customer organization join a new supplier, while in other situations the organizations are kept as-is. Risk-based approach to ensure commonly understood Statement of Work Through a risk-based transition methodology the parties collaborate and ensure there is a commonly understood Statement of Work (SOW) which clarifies what services are included in the baseline and what services are available via separate service requests. Based on: OCP CFOPS 2019 v1.4
  • 6. Lessons learned / Customer experiences Based on: OCP CFOPS 2019 v1.4
  • 7. Integration MindMap Overview Summary Integration of processes and governance through Transition The delivery requires integration of the parties’ processes and governance structures to minimize risks and to secure continuous improvements. During the transition phase, the customer and the supplier align and integrate their processes, functions, systems and organizations to enable efficient operations. The starting point should be the current site strategy set by the customer. Transition project To ensure transparency and minimized risks, the transition should be run as a clearly defined project that is led and quality assured by highly skilled and experienced transition specialists. In some instances, team members from the previous customer organization join a new supplier, while in other situations the organizations are kept as-is. Risk-based approach to ensure commonly understood Statement of Work Through a risk-based transition methodology the parties collaborate and ensure there is a commonly understood Statement of Work (SOW) which clarifies what services are included in the baseline and what services are available via separate service requests. Based on: OCP CFOPS 2019 v1.4
  • 8. Output Comment Statement of Work incl. service levels with penalties for Site Services (SOW with SLA) This is the main document clarifying scope and expectations for the Services Agreement. The SOW has a focus on services and technologies in scope, but also covers other topics, e.g. pricing, duration. It can cover anything from pure play Site Management to a full-blown Site Operations – or anything in between. Service levels are defined to ensure a proper prioritization of efforts. These should reflect the Site Strategy to ensure alignment with customer needs. The service levels to be managed can be any combination of KPIs and they may address the commitments by Site Management or by other stakeholders, depending on roles and responsibilities. The SOW should have appendices or refer to separate documentation for Border Lists, Asset Lists, Service Levels, Organization (demand and supply) and refer to what Terms & Conditions apply. It is approved by both the Customer and the supplier and handled through the Document Management. It is stored in the Reference Library (“Agreements incl. Border lists”). Asset Lists for in-scope site supply systems (AL) Current Asset Lists for in-scope supply systems should be produced and validated by both parties to ensure it matches the planned scope of the SOW and to minimize risks of stakeholder expectation gaps. It is handled through the Document Management process and stored in the Reference Library (“Asset lists incl. EOL”). Border Lists for in-scope site services (BL) Current Border Lists for in-scope services should be produced and validated by both parties to ensure it matches the planned scope of the SOW and to minimize risks of stakeholder expectation gaps. It is handled through the Document Management process and stored in the Reference Library (“Agreements incl. Border lists”). Organization with roles, meeting frequencies and templates etc. This is part of the Document Management repository for Site Policies, where Organization including third party stakeholder dependencies are used to capture demand and supply of services via an operating model and a governance model. It is handled through the Document Management process and stored in the Site Policies (“Organization”). Terms & Conditions that regulate the SOW (T&C) The SOW relies on being part of a larger context. This could be generally accepted standard agreement in the market or directly negotiated terms and conditions between the parties (with or without an underlying Framework Agreement). Handled in Document Mgmt process and stored in Reference Library (“Agreements incl. Border lists”). SOW: Key outputs Based on: OCP CFOPS 2019 v1.4
  • 9. Integration MindMap Overview Summary Integration of processes and governance through Transition The delivery requires integration of the parties’ processes and governance structures to minimize risks and to secure continuous improvements. During the transition phase, the customer and the supplier align and integrate their processes, functions, systems and organizations to enable efficient operations. The starting point should be the current site strategy set by the customer. Transition project To ensure transparency and minimized risks, the transition should be run as a clearly defined project that is led and quality assured by highly skilled and experienced transition specialists. In some instances, team members from the previous customer organization join a new supplier, while in other situations the organizations are kept as-is. Risk-based approach to ensure commonly understood Statement of Work Through a risk-based transition methodology the parties collaborate and ensure there is a commonly understood Statement of Work (SOW) which clarifies what services are included in the baseline and what services are available via separate service requests. Based on: OCP CFOPS 2019 v1.4
  • 10. Processes and site systems: Key outputs Based on: OCP CFOPS 2019 v1.4 Output Comment Incident Management It is critical that Incident Management is handled correctly between all involved stakeholders, including third parties. Work Orders & Project Management To ensure that Border List accountabilities are fulfilled by the process to order and approve site works it needs to be integrated and documented between the stakeholders involved. Monitoring & Reporting with standard KPI reports The process and its supporting systems (automated or manual) should be in place to collect, share and report relevant data in a timely manner. This also includes frequency and contents for recurring operational level meetings and reports Lifecycle & Financial Management By ensuring that Site Systems Lifecycle Management, Financial Management and Tender & Selection sub-processes are integrated between demand and supply, the general cost levels and quality KPIs get identified. Parts of Security & Access: Authorize & Authenticate for On-site Access The activities of authentication and authorization should not be confused when integrating access control to sites in scope:  Authorization is to decide who has permit to access to a site. (provided by the customer)  Authentication confirms a person’s identity (provided by customer, Supplier or a third party)  Access to site is only allowed for authenticated authorized persons (provided by customer, Supplier or a third party) Other access controls exist, e.g. against items not allowed on site, etc. Supporting systems for the processes Site systems, e.g. technical alarms, and other systems required to enable the processes.
  • 11. Lessons learned / Customer experiences “We have led transition projects for critical facilities in multiple countries during the past five years. Our biggest lesson we have learnt is never to expect a transition project to be run for a shorter period than four months. If you are forced to run it for a shorter period than that, you should also plan for a second project to sort out unresolved issues within 12 months…”
  • 12. Final notes Critical Success Factors during Transition 1. Customer must be willing to invest in transition – Secure true stakeholder commitment – Close collaboration between parties – full transparency under NDA 2. Plan based on actual current state, not “expected current state” – Risk-based approach for prioritization of processes and activities – be honest! – Weekly updates and risk/issue resolution meetings 3. Use expert knowledge to minimize risk – Transition Manager skilled in Transition and Operations – Keep experience and site knowledge in handover 4. Allow for time – but be fierce on meeting project deadlines – 1-3 months to plan* – 3-9 months to execute* * N.B. For up to 10 sites and takeover of employees

Editor's Notes

  • #15: Clear market leader in turnkey data centers and other critical facilities Highly skilled and experienced workforce operating out of 20 locations Unrivalled experience as a full-service provider of turnkey critical facilities solutions Proven international delivery capabilities Strong Nordic customer base across a wide range of industries