Accelerate Performance
Achieving Superior Energy Performance
through Performance-based
Procurement
Adam McMillen
Director of Energy Consulting
Seventhwave
Agenda
Why performance based procurement
Industry momentum
How project support and energy
analysis is different (and more highly
valued)
How proposals are evaluated Jennifer Scheib
Research Engineer
NREL
Photos courtesy of University of Chicago
12
Creating a better contract
Simplicity Results Value Alignment
Accelerate performance
Accelerate performance
Accelerate performance
Accelerate performance
Accelerate performance
46 kBtu/ft2/yr
52 kBtu/ft2/yr
54 kBtu/ft2/yr
51 kBtu/ft2/yr
• RSF uses 50% less energy than if it
were built to current commercial
codes
• RSF increases space at NREL by
60% but only increases energy use
by 6%
NREL/25931
Owner Sets Vision
http://www.newbuildings.org/sites/default/files/Energy_Performance_of_LEED-NC_Buildings-Final_3-4-08b.pdf
Owner Sets Energy Target
• Creating a list of what the building could accomplish.
– Critical: Project success hinges on this element
– Highly Desirable: What the owner wants
– If Possible: The wish list
HIGHLY
DESIRABLE
MISSION
CRITICAL
IF
POSSIBLE
HIGHLY
DESIRABLE
IF
POSSIBLE
Owner Defines Desires
• Attain safe work
performance
• LEED Platinum
• ENERGY STAR “Plus”
$64M fixed price HIGHLY
DESIRABLE
MISSION CRITICAL
IF
POSSIBLE
• 800 staff capacity
• 25 kBtu/sf/year
• Architectural integrity
• Honor future staff needs
• Measurable ASHRAE 90.1
• Support culture and
amenities
• Expandable building
• Ergonomics
• Flexible workspace
• Support future
technologies
• Documentation to produce
a “How to” manual
• “PR” campaign
implemented in real-time
• Allow secure collaboration
with outsiders
• Building information
modeling
• Substantial Completion by
2010
HIGHLY DESIRABLE
• Net zero energy
• Most energy efficient
building in the world
• LEED Platinum Plus
• ASHRAE 90.1 + 50%
• Visual displays of current
energy efficiency
• Support public tours
• Achieve national and global
recognition and awards
• Support personnel
turnover
IF POSSIBLE
PV System
Natural
Ventilation
Thermal Mass
UFAD
Outdoor Air
Pre-cool
Transpired
Collectors
Radiant Cooling
Radiant Heating
Workplace
Daylighting
(60-ft)
Enhanced
Envelope
Thermal
Bridging
Electrical lighting
Design Teams Respond
Competition Rendering
Final Building
Gaining
momentum
Department of
Energy initiative to
scale performance-
based procurement
100 buildings
three years
Extended partnerships and stakeholder group forming now.
TEAM
Seventhwave
National Renewable Energy
Laboratory
Institute for Sustainable Energy
UTILITY PARTNERS
ComEd
Eversource
United Illuminating
OWNER PARTNERS
University of Chicago
Lend Lease
Photos courtesy of University of Chicago
Accelerate performance
Photos courtesy of University of Chicago
Bring more context to target EUI
Photos courtesy of University of Chicago
RFP and contract language
PROJECT GOAL LIST: Project goals help design teams prioritize their focus on the MEP and building performance design.
Goals are categorized in three main sections:
Mission critical goals - required by contract and critical to success
Highly desirable goals - not required by contract and have influence on the recommended design
If possible goals - influence recommended design and are considered highly beneficial if included in the solution
• Maximum energy target of 45 KBTU/gsf annually; lower is preferred
• LEED NC version 4, Silver Certification
• Superior occupant comfort
• 100% of occupied spaces physically or visually connected to nature
• Living Building Challenge (LBC) 3.0 Feasibility Study
MISSION CRITICAL
HIGHLY DESIRABLE
IF POSSIBLE • Living Building full certification
• Net Zero Energy Design
• Maximum energy target of 35 kBtu/gsf annually; lower is preferred
• Best in class Energy Star equipment or best in class energy efficient equipment
• Passive design strategies (i.e. daylighting, passive solar heating, etc.)
• Achieve ‘retreat-like’ feel using biophilic design principles
• Low recycled air content
• Strong HVAC response to quickly changing occupancy (limit precooling with air)
• Usable daylight in all occupied spaces
• Geothermal system
• Design features that create an interactive sustainable learning experience
• Exceed LEED NC version 4, Silver Certification
• Guidance for calculating the EUI
• Modeling schedule and expectations
• Substantiation dashboard
NREL/17833
Modeling Resources
Owner Sets EUI Target Adjustments
Floor
Area (ft2)z
Number of People
640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800
170,000 31.8 32.35 32.85 33.35 33.85 34.34 34.84 35.34 35.84 36.33 36.83 37.33 37.83 38.33 38.82 39.32 39.82
180,000 30.09 30.56 31.03 31.50 31.97 32.44 32.91 33.38 33.85 34.32 34.79 35.26 35.73 36.20 36.67 37.14 37.61
190,000 28.50 28.95 29.39 29.84 30.28 30.73 31.17 31.62 32.06 32.51 32.96 33.40 33.85 34.29 34.74 35.18 35.63
200,000 27.08 27.50 27.92 28.35 28.77 29.19 29.62 30.04 30.46 30.88 31.31 31.73 32.15 32.58 33.00 33.42 33.85
210,000 25.79 26.19 26.59 27.00 27.40 27.80 28.21 28.61 29.01 29.41 29.82 30.22 30.62 31.03 31.43 31.83 32.23
220,000 24.62 25.00 25.38 25.77 26.15 26.54 26.92 27.31 27.69 28.08 28.46 28.85 29.23 29.62 30.00 30.38 30.77
230,000 23.55 23.91 24.28 24.65 25.02 25.38 25.75 26.12 26.49 26.86 27.22 27.59 27.96 28.33 28.70 29.06 29.43
240,000 22.56 22.92 23.27 23.62 23.97 24.33 24.68 25.03 25.38 25.74 26.09 26.44 26.79 27.15 27.50 27.85 28.21
250,000 21.66 22.00 22.34 22.68 23.02 23.35 23.69 24.03 24.37 24.71 25.05 25.38 25.72 26.06 26.40 26.74 27.08
260,000 20.83 21.15 21.48 21.80 22.13 22.46 22.78 23.11 23.43 23.76 24.08 24.41 24.73 25.06 25.38 25.71 26.04
270,000 20.06 20.37 20.68 21.00 21.31 21.62 21.94 22.25 22.56 22.88 23.19 23.50 23.82 24.13 24.44 24.76 25.07
280,000 19.34 19.64 19.95 20.25 20.55 20.85 21.15 21.46 21.76 22.06 22.36 22.66 22.97 23.27 23.57 23.87 24.18
290,000 18.67 18.97 19.26 19.55 19.84 20.13 20.42 20.72 21.01 21.30 21.59 21.88 22.18 22.47 22.76 23.05 23.34
300,000 18.05 18.33 18.62 18.90 19.18 19.46 19.74 20.03 20.31 20.59 20.87 21.15 21.44 21.72 22.00 22.28 22.56
310,000 17.47 17.74 18.01 18.29 18.56 18.83 19.11 19.38 19.65 19.93 20.20 20.47 20.74 21.02 21.29 21.56 21.84
320,000 16.92 17.19 17.45 17.72 17.98 18.25 18.51 18.77 19.04 19.30 19.57 19.83 20.10 20.36 20.63 20.89 21.15
Owner Provides Calculation Guidelines
Provided central plant assumptions
• COP=3 for chilled water
• 90% boiler efficiency
Benchmarked plug and data center loads
• Provided peak uses and occupancy schedule by
plug load type
• Allowed design team to recommend and
account for more efficient equipment
Explicitly defined net zero energy
46 kBtu/ft2/yr
52 kBtu/ft2/yr
54 kBtu/ft2/yr
51 kBtu/ft2/yr
How do the models look?
0.0
5.0
10.0
15.0
20.0
25.0
Lights Misc space heating space cooling heat reject pumps vent fans DhW
ModeledEUIbyenduse
Team Comparison - Energy by End Use
ECWv1 ECWv2 Team Av1 Team Av2 Team B Team C Team D
Design A Design B
Design C Design D
-5
15
35
55
75
95
115
135
155
175
Moreenergyuse---------->
Final Competition Designs – EUI
Evaluate submittals
Team
Risk –
Confidence
performance
meets intent
Energy Target
Daylight, Views,
Connection to
Nature
Comfort and
HVAC Response
Maintainability Innovation
A
B
C
D
Modelers Follow a Meaningful Schedule
Proposal
Calculation demonstrating the EUI of the proposed
design
Design Development
Projected annual energy consumption of all
equipment
Construction Documents
Updated projected annual energy consumption
Commissioning
Actual measurements of energy consumption
Closeout
Recalculation using measurements of equipment
Contract signed
5 4 4 4 5 1 4 8 3 7 4 1 4 6 5 1 5 2 4 4 4 7 5 1 5 4 5 5 4 8 4 7 4 9 5 4 5 2 3 9 4 3 4 6 5 2 4 9 4 0 4 8 5 0 5 3 5 2
5 2 3 9 4 2 4 0 3 3 3 7 3 9 4 4 4 4 3 6 3 9 4 2 4 4 4 5 3 9 4 0 4 2 4 5 4 3 3 4 3 9 4 1 4 3 4 2 3 3 4 1 4 3 4 7 4 4
5 0 3 3 3 5 3 4 3 1 3 2 3 5 3 6 3 5 3 2 3 4 3 6 3 9 3 8 3 0 3 5 3 6 3 7 3 8 3 0 3 0 3 5 3 7 3 6 3 2 3 4 3 6 4 0 3 9
4 8 2 9 3 3 3 3 3 0 2 8 3 0 3 4 3 5 3 2 2 8 3 1 3 6 3 6 3 2 2 6 3 0 3 6 3 5 3 2 2 8 2 9 3 5 3 4 3 1 2 8 3 1 3 5 3 6
4 6 2 2 1 2 1 1 1 1 2 1 2 2 1 3 1 2 1 3 2 3 2 4 1 3 1 4 1 3 2 1 2 3 1 4 1 3 1 3 2 3 2 3 1 4 1 4 1 3 2 2 2 4 1 4 1 4
4 4 1 9 1 5 1 6 1 8 2 1 1 9 1 6 1 6 1 9 2 2 2 0 1 7 1 8 1 9 2 2 1 9 1 8 1 7 1 9 2 0 2 0 1 7 1 7 1 9 2 3 2 2 1 9 1 8
4 2 1 6 1 7 1 6 1 6 1 8 1 6 1 7 1 7 1 7 2 0 1 8 2 0 1 9 1 9 2 1 1 9 1 8 1 9 1 8 2 1 1 8 1 9 1 9 1 9 2 1 1 9 2 1 1 9
4 0 1 5 1 5 1 5 1 6 1 8 1 5 1 6 1 6 1 7 1 3 1 8 1 7 1 9 1 6 1 8 1 8 1 8 1 7 1 2 1 9 1 6 1 6 1 7 1 9 2 1 1 8 1 9 1 9
3 8 2 0 1 6 1 7 1 8 1 9 1 9 1 5 1 4 1 7 1 2 1 4 1 9 2 0 2 0 2 2 1 7 1 5 1 5 1 2 1 9 1 6 1 5 1 8 2 2 2 0 1 7 1 8 2 3
3 6 1 2 1 1 6 1 1 1 2 1 3 1 3 1 6 1 7 1 7 1 4 1 4 1 3 1 0 9 1 3 1 4 1 4 1 7 1 6 1 5 1 5 1 4 1 4 1 2 7 1 3 1 4
3 4 1 6 1 4 9 1 3 1 6 1 6 1 7 1 7 1 7 1 7 1 7 1 7 1 8 1 5 1 1 1 6 1 8 1 7 1 8 1 7 1 7 1 6 1 5 1 7 1 6 9 1 8 1 9
3 2 1 3 1 2 1 2 1 4 1 4 1 4 1 8 1 7 1 7 1 7 1 8 1 6 1 7 1 5 1 4 1 6 1 6 1 6 1 7 1 7 1 8 1 7 1 6 1 6 1 5 7 1 4 1 9
3 0 4 4 4 8 3 4 1 7 1 7 1 7 1 8 1 8 4 4 5 4 4 5 1 6 1 8 1 8 1 8 1 7 4 6 7 5 4 6
2 8 1 3 1 2 1 1 1 3 1 4 1 5 1 9 1 7 1 8 1 8 1 7 1 5 1 4 1 2 1 3 1 4 1 5 1 9 1 9 1 9 1 8 1 8 1 6 1 5 1 4 9 1 6 1 6
2 6 1 5 1 4 1 1 1 5 1 6 1 7 1 8 1 9 1 9 2 1 1 9 1 8 1 8 1 4 1 4 1 7 1 7 2 0 2 1 2 0 1 9 1 9 1 9 1 9 1 7 1 0 1 9 2 0
2 4 1 7 1 5 8 1 5 1 7 1 8 1 9 2 1 2 2 2 2 2 1 2 0 1 8 1 5 1 2 1 9 1 9 2 1 2 2 2 2 2 2 2 2 2 1 2 1 1 7 9 2 1 2 1
2 2 1 4 1 6 7 1 6 1 6 2 0 1 7 2 0 2 3 1 9 1 8 1 8 1 6 1 3 1 2 1 6 2 2 2 0 1 8 2 4 2 2 1 9 2 1 1 7 1 5 7 2 1 1 9
2 0 2 1 1 9 1 0 2 1 2 2 2 1 2 3 2 5 2 5 2 6 2 4 2 5 2 4 1 8 4 2 2 3 2 4 2 3 2 3 2 5 2 5 2 5 2 5 2 3 2 2 1 2 2 5 2 5
1 8 2 2 2 2 1 1 1 9 2 3 2 4 2 7 2 7 2 7 2 8 2 7 2 7 2 6 2 1 1 7 2 5 2 5 2 6 2 5 2 7 2 8 2 6 2 7 2 7 2 3 1 1 2 5 2 7
1 6 2 6 2 4 2 2 2 4 2 5 2 7 2 9 3 0 2 8 2 9 3 0 2 9 2 7 2 4 2 5 2 6 2 8 2 9 2 8 2 9 2 9 2 9 2 8 2 7 2 7 1 2 2 8 3 0
1 4 1 7 1 5 1 5 2 0 1 9 1 7 3 1 3 2 3 1 3 2 3 0 1 7 1 9 1 8 1 7 1 7 2 0 2 9 2 9 3 0 3 1 3 1 2 0 1 8 1 8 9 2 1 1 8
1 2 3 0 2 7 2 7 2 4 2 9 3 1 3 5 3 4 3 5 3 7 3 5 3 2 2 8 3 0 2 7 2 7 3 1 3 5 3 5 3 3 3 3 3 6 3 2 3 1 2 7 1 4 2 9 3 1
1 0 3 4 3 0 2 8 2 9 3 5 3 6 3 6 3 5 3 8 3 8 3 7 4 1 3 8 3 1 3 0 3 3 3 7 3 2 3 2 3 8 3 7 3 6 3 6 3 6 3 5 2 1 3 5 3 9
8 3 4 3 2 1 5 2 6 3 4 3 4 3 5 3 5 4 1 4 4 4 2 3 6 3 7 2 7 1 8 3 2 3 4 3 3 3 3 3 6 3 9 3 7 3 5 3 7 3 0 1 4 3 6 4 2
6 3 2 2 9 1 7 2 9 3 1 3 2 3 1 3 9 4 9 4 4 3 4 3 4 3 6 2 3 1 7 3 0 3 0 3 1 3 5 4 7 4 4 3 3 3 1 3 3 2 9 1 3 3 5 3 7
4 5 7 5 4 5 7 5 9 5 7 5 7 5 5 5 6 5 8 5 5 5 8 5 9 5 7 5 8 5 7 5 7 5 0 5 0 5 5 5 1 5 1 5 1 4 9 5 3 6 3 5 7 5 7 5 2
2 6 2 7 5 7 9 6 8 5 6 6 2 7 5 7 8 7 1 5 8 6 1 7 3 7 9 7 0 6 0 6 0 6 9 7 6 6 7 6 2 6 0 6 6 7 6 6 9 5 7 6 6 7 5 7 8
2 4 6 8 1 0 1 2 1 4 1 6 1 8 2 0 2 2 2 4 2 6 2 8 3 0 3 2 3 4 3 6 3 8 4 0 4 2 4 4 4 6 4 8 5 0 5 2 5 4 5 6
Owner and Modelers Verify Performance
• Attract early adopters
• Achievable path to scale
net zero buildings at little
to no cost premium
• Support cities, states and
owners with aggressive
energy goals
• Transform the
procurement paradigm
Accelerate Performance
A new construction initiative for superior energy performance
2 billion ft2 are new construction each year.
An historic opportunity
Source: U.S Energy Information Administration
3
Thank you
Adam McMillen, PE, LEED AP BD+C
amcmillen@seventhwave.org
312.852.1360
Jennifer Scheib
Jennifer.Scheib@nrel.gov
303.275.4323
www.seventhwave.org/accelerateperformance

More Related Content

PDF
DSD-INT 2016 Urban water modelling - Meijer
PDF
Centenes, desenes, unitats per a cicle inicial
PPTX
Good Enough Analytics
PDF
Dr. azad hama sharif
ODP
Image scalar hw_algorithm
PDF
Evaluation of chem lab software.
PDF
The use of waveform cross correlation for creation of an accurate catalogue o...
PDF
Historical IBM quarterly dividend rates and payable and records dates.
DSD-INT 2016 Urban water modelling - Meijer
Centenes, desenes, unitats per a cicle inicial
Good Enough Analytics
Dr. azad hama sharif
Image scalar hw_algorithm
Evaluation of chem lab software.
The use of waveform cross correlation for creation of an accurate catalogue o...
Historical IBM quarterly dividend rates and payable and records dates.

What's hot (18)

PDF
Satta Matka
DOC
Fichas escalonadas
DOCX
Fichas escalonadas
DOCX
Fichas escalonadas
DOCX
Fichas escalonadas
PDF
Copy of z table
PDF
Future of Planning Use Cases
PDF
Geneve Monitoring event - InfluxDb and Loud ML presentation
PDF
1 kaarten
PDF
The practical guide of Infrastructure CI
PPTX
Creating an effective dashboards slideshare
PPTX
MULTIPLICACIONES PARA PRACTICAR CÁLCULO MENTAL
PDF
PDF
TABLATURAS FLAMENCO: Don cortes-maya
PPT
Ppt 1stelj Getallen
PDF
merdian layout-5K hubbell - T4
XLS
Reporte Notas
RTF
Master tabel pengetahuan dan sikap (uji validitas)
Satta Matka
Fichas escalonadas
Fichas escalonadas
Fichas escalonadas
Fichas escalonadas
Copy of z table
Future of Planning Use Cases
Geneve Monitoring event - InfluxDb and Loud ML presentation
1 kaarten
The practical guide of Infrastructure CI
Creating an effective dashboards slideshare
MULTIPLICACIONES PARA PRACTICAR CÁLCULO MENTAL
TABLATURAS FLAMENCO: Don cortes-maya
Ppt 1stelj Getallen
merdian layout-5K hubbell - T4
Reporte Notas
Master tabel pengetahuan dan sikap (uji validitas)
Ad

Viewers also liked (20)

PDF
04.15.15 energy design assistance program tracker 2
PDF
Daimler Trucks of North America
PDF
Energy Modeling of Dedicated Outdoor Air System, DOAS, for a Small Commercial...
PDF
A User's Perspective on IES Modeling
PDF
Besf building renewal_021815
PDF
Stay Ahead of Advancing Energy Codes with the Advanced Buildings New Construc...
PDF
150312 updating history_deep_retrofits
PDF
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
PDF
Allies for efficiency training chemeketa final locked
PDF
08.06.15 training occupant_engagement
PDF
Envelope Design Training
PDF
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
PDF
Cowhorn Vineyard + Garden Tasting Room
PDF
Energy and comfort modeling for the net zero rocky mountain institute headqua...
PDF
High Performing Collaboration
PDF
Efficient and Affordable: Applying the Passive House Standard to Low-income, ...
PDF
3.17.15 commercial solar_design_training
PDF
Building enclosure design presentation 2
PDF
Building enclosure design presentation 1
PDF
Combined Heat and Power Engineering and Installation in the Pacific NW
04.15.15 energy design assistance program tracker 2
Daimler Trucks of North America
Energy Modeling of Dedicated Outdoor Air System, DOAS, for a Small Commercial...
A User's Perspective on IES Modeling
Besf building renewal_021815
Stay Ahead of Advancing Energy Codes with the Advanced Buildings New Construc...
150312 updating history_deep_retrofits
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
Allies for efficiency training chemeketa final locked
08.06.15 training occupant_engagement
Envelope Design Training
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
Cowhorn Vineyard + Garden Tasting Room
Energy and comfort modeling for the net zero rocky mountain institute headqua...
High Performing Collaboration
Efficient and Affordable: Applying the Passive House Standard to Low-income, ...
3.17.15 commercial solar_design_training
Building enclosure design presentation 2
Building enclosure design presentation 1
Combined Heat and Power Engineering and Installation in the Pacific NW
Ad

Similar to Accelerate performance (20)

PDF
Your App Metrics Are Telling You How To Make Them Better: The Digits Data Report
PDF
Election 2016: Mobile Activity in the U.S. on Election Day
PDF
SophiaConf 2018 - Q. Nguyen (Amadeus)
PDF
Tableau for statistical graphic and data visualization
PPTX
División por dos cifras
PDF
Anytime Dynamic A*
PPT
Gone Shopping: detailed retail mapping
PPTX
4.4 M. Ángeles Rol
PDF
Irreversible: The Public Relations Big Data Revolution
PDF
Will renewable electrification of energy solve air pollution? Not quite! - Ma...
PPTX
Final Presentation
DOCX
Quadro valor lugar milhões
PDF
Atlanta SQL Saturday
PDF
Horses for Courses: Deep Learning Beyond Niche Applications
PDF
Sudoku Solving with Computational Intelligence
PDF
[ACM-ICPC] Sort
PPTX
Rethinking Supply Chain Analytics
PDF
Eficiency and Low Cost: Pro Tips for you to save 50% of your money with Googl...
PDF
Don't Forget This!
PDF
plantilla sistema numeracion
Your App Metrics Are Telling You How To Make Them Better: The Digits Data Report
Election 2016: Mobile Activity in the U.S. on Election Day
SophiaConf 2018 - Q. Nguyen (Amadeus)
Tableau for statistical graphic and data visualization
División por dos cifras
Anytime Dynamic A*
Gone Shopping: detailed retail mapping
4.4 M. Ángeles Rol
Irreversible: The Public Relations Big Data Revolution
Will renewable electrification of energy solve air pollution? Not quite! - Ma...
Final Presentation
Quadro valor lugar milhões
Atlanta SQL Saturday
Horses for Courses: Deep Learning Beyond Niche Applications
Sudoku Solving with Computational Intelligence
[ACM-ICPC] Sort
Rethinking Supply Chain Analytics
Eficiency and Low Cost: Pro Tips for you to save 50% of your money with Googl...
Don't Forget This!
plantilla sistema numeracion

Recently uploaded (20)

PPTX
"One Earth Celebrating World Environment Day"
PPTX
Conformity-and-Deviance module 7 ucsp grade 12
PPTX
RadiationSafetyPt120252026nucchemis.pptx
PPTX
Microbial-Pathogens-and-Parasites-Their-Impact-on-Plant-Health.pptx
PDF
The European Green Deal (EU Green Deal)
DOCX
Double Membrane Roofs for Bio CNG Plants Stores biogas.docx
PDF
Tree Biomechanics, a concise presentation
PDF
Effects of rice-husk biochar and aluminum sulfate application on rice grain q...
PPT
Environmental pollution for educational study
PPTX
Lecture-05-Audio-lingual. Method & Appro
PDF
1748933543SJA_41_2_826-834 SJA Ihsan ullha.pdf
DOCX
Double Membrane Roofs for Agricultural Waste Biogas Digesters Turns various f...
PDF
Effective factors on adoption of intercropping and it’s role on development o...
DOCX
Double Membrane Roofs for Biogas Tanks Securely store produced biogas.docx
PPTX
Minor Species of nutmeg, cinnamon and clove
PPTX
AUTO IRRIGATION USING GRID SYSTEM123.pptx
PPTX
NSTP1 NSTP1NSTP1NSTP1NSTP1NSTP1NSTP1NSTP
PPTX
Environmental pollutants for natural res
PPTX
Biodiversity of nature in environmental studies.pptx
PPTX
Pollution, it's Types and Impacts on Global context.pptx
"One Earth Celebrating World Environment Day"
Conformity-and-Deviance module 7 ucsp grade 12
RadiationSafetyPt120252026nucchemis.pptx
Microbial-Pathogens-and-Parasites-Their-Impact-on-Plant-Health.pptx
The European Green Deal (EU Green Deal)
Double Membrane Roofs for Bio CNG Plants Stores biogas.docx
Tree Biomechanics, a concise presentation
Effects of rice-husk biochar and aluminum sulfate application on rice grain q...
Environmental pollution for educational study
Lecture-05-Audio-lingual. Method & Appro
1748933543SJA_41_2_826-834 SJA Ihsan ullha.pdf
Double Membrane Roofs for Agricultural Waste Biogas Digesters Turns various f...
Effective factors on adoption of intercropping and it’s role on development o...
Double Membrane Roofs for Biogas Tanks Securely store produced biogas.docx
Minor Species of nutmeg, cinnamon and clove
AUTO IRRIGATION USING GRID SYSTEM123.pptx
NSTP1 NSTP1NSTP1NSTP1NSTP1NSTP1NSTP1NSTP
Environmental pollutants for natural res
Biodiversity of nature in environmental studies.pptx
Pollution, it's Types and Impacts on Global context.pptx

Accelerate performance

  • 1. Accelerate Performance Achieving Superior Energy Performance through Performance-based Procurement
  • 2. Adam McMillen Director of Energy Consulting Seventhwave Agenda Why performance based procurement Industry momentum How project support and energy analysis is different (and more highly valued) How proposals are evaluated Jennifer Scheib Research Engineer NREL
  • 3. Photos courtesy of University of Chicago 12
  • 4. Creating a better contract Simplicity Results Value Alignment
  • 10. 46 kBtu/ft2/yr 52 kBtu/ft2/yr 54 kBtu/ft2/yr 51 kBtu/ft2/yr
  • 11. • RSF uses 50% less energy than if it were built to current commercial codes • RSF increases space at NREL by 60% but only increases energy use by 6% NREL/25931 Owner Sets Vision
  • 13. • Creating a list of what the building could accomplish. – Critical: Project success hinges on this element – Highly Desirable: What the owner wants – If Possible: The wish list HIGHLY DESIRABLE MISSION CRITICAL IF POSSIBLE HIGHLY DESIRABLE IF POSSIBLE Owner Defines Desires
  • 14. • Attain safe work performance • LEED Platinum • ENERGY STAR “Plus” $64M fixed price HIGHLY DESIRABLE MISSION CRITICAL IF POSSIBLE • 800 staff capacity • 25 kBtu/sf/year • Architectural integrity • Honor future staff needs • Measurable ASHRAE 90.1 • Support culture and amenities • Expandable building • Ergonomics • Flexible workspace • Support future technologies • Documentation to produce a “How to” manual • “PR” campaign implemented in real-time • Allow secure collaboration with outsiders • Building information modeling • Substantial Completion by 2010 HIGHLY DESIRABLE • Net zero energy • Most energy efficient building in the world • LEED Platinum Plus • ASHRAE 90.1 + 50% • Visual displays of current energy efficiency • Support public tours • Achieve national and global recognition and awards • Support personnel turnover IF POSSIBLE
  • 15. PV System Natural Ventilation Thermal Mass UFAD Outdoor Air Pre-cool Transpired Collectors Radiant Cooling Radiant Heating Workplace Daylighting (60-ft) Enhanced Envelope Thermal Bridging Electrical lighting Design Teams Respond
  • 18. Department of Energy initiative to scale performance- based procurement 100 buildings three years
  • 19. Extended partnerships and stakeholder group forming now. TEAM Seventhwave National Renewable Energy Laboratory Institute for Sustainable Energy UTILITY PARTNERS ComEd Eversource United Illuminating OWNER PARTNERS University of Chicago Lend Lease Photos courtesy of University of Chicago
  • 21. Photos courtesy of University of Chicago Bring more context to target EUI
  • 22. Photos courtesy of University of Chicago RFP and contract language PROJECT GOAL LIST: Project goals help design teams prioritize their focus on the MEP and building performance design. Goals are categorized in three main sections: Mission critical goals - required by contract and critical to success Highly desirable goals - not required by contract and have influence on the recommended design If possible goals - influence recommended design and are considered highly beneficial if included in the solution • Maximum energy target of 45 KBTU/gsf annually; lower is preferred • LEED NC version 4, Silver Certification • Superior occupant comfort • 100% of occupied spaces physically or visually connected to nature • Living Building Challenge (LBC) 3.0 Feasibility Study MISSION CRITICAL HIGHLY DESIRABLE IF POSSIBLE • Living Building full certification • Net Zero Energy Design • Maximum energy target of 35 kBtu/gsf annually; lower is preferred • Best in class Energy Star equipment or best in class energy efficient equipment • Passive design strategies (i.e. daylighting, passive solar heating, etc.) • Achieve ‘retreat-like’ feel using biophilic design principles • Low recycled air content • Strong HVAC response to quickly changing occupancy (limit precooling with air) • Usable daylight in all occupied spaces • Geothermal system • Design features that create an interactive sustainable learning experience • Exceed LEED NC version 4, Silver Certification
  • 23. • Guidance for calculating the EUI • Modeling schedule and expectations • Substantiation dashboard NREL/17833 Modeling Resources
  • 24. Owner Sets EUI Target Adjustments Floor Area (ft2)z Number of People 640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 170,000 31.8 32.35 32.85 33.35 33.85 34.34 34.84 35.34 35.84 36.33 36.83 37.33 37.83 38.33 38.82 39.32 39.82 180,000 30.09 30.56 31.03 31.50 31.97 32.44 32.91 33.38 33.85 34.32 34.79 35.26 35.73 36.20 36.67 37.14 37.61 190,000 28.50 28.95 29.39 29.84 30.28 30.73 31.17 31.62 32.06 32.51 32.96 33.40 33.85 34.29 34.74 35.18 35.63 200,000 27.08 27.50 27.92 28.35 28.77 29.19 29.62 30.04 30.46 30.88 31.31 31.73 32.15 32.58 33.00 33.42 33.85 210,000 25.79 26.19 26.59 27.00 27.40 27.80 28.21 28.61 29.01 29.41 29.82 30.22 30.62 31.03 31.43 31.83 32.23 220,000 24.62 25.00 25.38 25.77 26.15 26.54 26.92 27.31 27.69 28.08 28.46 28.85 29.23 29.62 30.00 30.38 30.77 230,000 23.55 23.91 24.28 24.65 25.02 25.38 25.75 26.12 26.49 26.86 27.22 27.59 27.96 28.33 28.70 29.06 29.43 240,000 22.56 22.92 23.27 23.62 23.97 24.33 24.68 25.03 25.38 25.74 26.09 26.44 26.79 27.15 27.50 27.85 28.21 250,000 21.66 22.00 22.34 22.68 23.02 23.35 23.69 24.03 24.37 24.71 25.05 25.38 25.72 26.06 26.40 26.74 27.08 260,000 20.83 21.15 21.48 21.80 22.13 22.46 22.78 23.11 23.43 23.76 24.08 24.41 24.73 25.06 25.38 25.71 26.04 270,000 20.06 20.37 20.68 21.00 21.31 21.62 21.94 22.25 22.56 22.88 23.19 23.50 23.82 24.13 24.44 24.76 25.07 280,000 19.34 19.64 19.95 20.25 20.55 20.85 21.15 21.46 21.76 22.06 22.36 22.66 22.97 23.27 23.57 23.87 24.18 290,000 18.67 18.97 19.26 19.55 19.84 20.13 20.42 20.72 21.01 21.30 21.59 21.88 22.18 22.47 22.76 23.05 23.34 300,000 18.05 18.33 18.62 18.90 19.18 19.46 19.74 20.03 20.31 20.59 20.87 21.15 21.44 21.72 22.00 22.28 22.56 310,000 17.47 17.74 18.01 18.29 18.56 18.83 19.11 19.38 19.65 19.93 20.20 20.47 20.74 21.02 21.29 21.56 21.84 320,000 16.92 17.19 17.45 17.72 17.98 18.25 18.51 18.77 19.04 19.30 19.57 19.83 20.10 20.36 20.63 20.89 21.15
  • 25. Owner Provides Calculation Guidelines Provided central plant assumptions • COP=3 for chilled water • 90% boiler efficiency Benchmarked plug and data center loads • Provided peak uses and occupancy schedule by plug load type • Allowed design team to recommend and account for more efficient equipment Explicitly defined net zero energy
  • 26. 46 kBtu/ft2/yr 52 kBtu/ft2/yr 54 kBtu/ft2/yr 51 kBtu/ft2/yr
  • 27. How do the models look? 0.0 5.0 10.0 15.0 20.0 25.0 Lights Misc space heating space cooling heat reject pumps vent fans DhW ModeledEUIbyenduse Team Comparison - Energy by End Use ECWv1 ECWv2 Team Av1 Team Av2 Team B Team C Team D
  • 28. Design A Design B Design C Design D -5 15 35 55 75 95 115 135 155 175 Moreenergyuse----------> Final Competition Designs – EUI
  • 29. Evaluate submittals Team Risk – Confidence performance meets intent Energy Target Daylight, Views, Connection to Nature Comfort and HVAC Response Maintainability Innovation A B C D
  • 30. Modelers Follow a Meaningful Schedule Proposal Calculation demonstrating the EUI of the proposed design Design Development Projected annual energy consumption of all equipment Construction Documents Updated projected annual energy consumption Commissioning Actual measurements of energy consumption Closeout Recalculation using measurements of equipment Contract signed
  • 31. 5 4 4 4 5 1 4 8 3 7 4 1 4 6 5 1 5 2 4 4 4 7 5 1 5 4 5 5 4 8 4 7 4 9 5 4 5 2 3 9 4 3 4 6 5 2 4 9 4 0 4 8 5 0 5 3 5 2 5 2 3 9 4 2 4 0 3 3 3 7 3 9 4 4 4 4 3 6 3 9 4 2 4 4 4 5 3 9 4 0 4 2 4 5 4 3 3 4 3 9 4 1 4 3 4 2 3 3 4 1 4 3 4 7 4 4 5 0 3 3 3 5 3 4 3 1 3 2 3 5 3 6 3 5 3 2 3 4 3 6 3 9 3 8 3 0 3 5 3 6 3 7 3 8 3 0 3 0 3 5 3 7 3 6 3 2 3 4 3 6 4 0 3 9 4 8 2 9 3 3 3 3 3 0 2 8 3 0 3 4 3 5 3 2 2 8 3 1 3 6 3 6 3 2 2 6 3 0 3 6 3 5 3 2 2 8 2 9 3 5 3 4 3 1 2 8 3 1 3 5 3 6 4 6 2 2 1 2 1 1 1 1 2 1 2 2 1 3 1 2 1 3 2 3 2 4 1 3 1 4 1 3 2 1 2 3 1 4 1 3 1 3 2 3 2 3 1 4 1 4 1 3 2 2 2 4 1 4 1 4 4 4 1 9 1 5 1 6 1 8 2 1 1 9 1 6 1 6 1 9 2 2 2 0 1 7 1 8 1 9 2 2 1 9 1 8 1 7 1 9 2 0 2 0 1 7 1 7 1 9 2 3 2 2 1 9 1 8 4 2 1 6 1 7 1 6 1 6 1 8 1 6 1 7 1 7 1 7 2 0 1 8 2 0 1 9 1 9 2 1 1 9 1 8 1 9 1 8 2 1 1 8 1 9 1 9 1 9 2 1 1 9 2 1 1 9 4 0 1 5 1 5 1 5 1 6 1 8 1 5 1 6 1 6 1 7 1 3 1 8 1 7 1 9 1 6 1 8 1 8 1 8 1 7 1 2 1 9 1 6 1 6 1 7 1 9 2 1 1 8 1 9 1 9 3 8 2 0 1 6 1 7 1 8 1 9 1 9 1 5 1 4 1 7 1 2 1 4 1 9 2 0 2 0 2 2 1 7 1 5 1 5 1 2 1 9 1 6 1 5 1 8 2 2 2 0 1 7 1 8 2 3 3 6 1 2 1 1 6 1 1 1 2 1 3 1 3 1 6 1 7 1 7 1 4 1 4 1 3 1 0 9 1 3 1 4 1 4 1 7 1 6 1 5 1 5 1 4 1 4 1 2 7 1 3 1 4 3 4 1 6 1 4 9 1 3 1 6 1 6 1 7 1 7 1 7 1 7 1 7 1 7 1 8 1 5 1 1 1 6 1 8 1 7 1 8 1 7 1 7 1 6 1 5 1 7 1 6 9 1 8 1 9 3 2 1 3 1 2 1 2 1 4 1 4 1 4 1 8 1 7 1 7 1 7 1 8 1 6 1 7 1 5 1 4 1 6 1 6 1 6 1 7 1 7 1 8 1 7 1 6 1 6 1 5 7 1 4 1 9 3 0 4 4 4 8 3 4 1 7 1 7 1 7 1 8 1 8 4 4 5 4 4 5 1 6 1 8 1 8 1 8 1 7 4 6 7 5 4 6 2 8 1 3 1 2 1 1 1 3 1 4 1 5 1 9 1 7 1 8 1 8 1 7 1 5 1 4 1 2 1 3 1 4 1 5 1 9 1 9 1 9 1 8 1 8 1 6 1 5 1 4 9 1 6 1 6 2 6 1 5 1 4 1 1 1 5 1 6 1 7 1 8 1 9 1 9 2 1 1 9 1 8 1 8 1 4 1 4 1 7 1 7 2 0 2 1 2 0 1 9 1 9 1 9 1 9 1 7 1 0 1 9 2 0 2 4 1 7 1 5 8 1 5 1 7 1 8 1 9 2 1 2 2 2 2 2 1 2 0 1 8 1 5 1 2 1 9 1 9 2 1 2 2 2 2 2 2 2 2 2 1 2 1 1 7 9 2 1 2 1 2 2 1 4 1 6 7 1 6 1 6 2 0 1 7 2 0 2 3 1 9 1 8 1 8 1 6 1 3 1 2 1 6 2 2 2 0 1 8 2 4 2 2 1 9 2 1 1 7 1 5 7 2 1 1 9 2 0 2 1 1 9 1 0 2 1 2 2 2 1 2 3 2 5 2 5 2 6 2 4 2 5 2 4 1 8 4 2 2 3 2 4 2 3 2 3 2 5 2 5 2 5 2 5 2 3 2 2 1 2 2 5 2 5 1 8 2 2 2 2 1 1 1 9 2 3 2 4 2 7 2 7 2 7 2 8 2 7 2 7 2 6 2 1 1 7 2 5 2 5 2 6 2 5 2 7 2 8 2 6 2 7 2 7 2 3 1 1 2 5 2 7 1 6 2 6 2 4 2 2 2 4 2 5 2 7 2 9 3 0 2 8 2 9 3 0 2 9 2 7 2 4 2 5 2 6 2 8 2 9 2 8 2 9 2 9 2 9 2 8 2 7 2 7 1 2 2 8 3 0 1 4 1 7 1 5 1 5 2 0 1 9 1 7 3 1 3 2 3 1 3 2 3 0 1 7 1 9 1 8 1 7 1 7 2 0 2 9 2 9 3 0 3 1 3 1 2 0 1 8 1 8 9 2 1 1 8 1 2 3 0 2 7 2 7 2 4 2 9 3 1 3 5 3 4 3 5 3 7 3 5 3 2 2 8 3 0 2 7 2 7 3 1 3 5 3 5 3 3 3 3 3 6 3 2 3 1 2 7 1 4 2 9 3 1 1 0 3 4 3 0 2 8 2 9 3 5 3 6 3 6 3 5 3 8 3 8 3 7 4 1 3 8 3 1 3 0 3 3 3 7 3 2 3 2 3 8 3 7 3 6 3 6 3 6 3 5 2 1 3 5 3 9 8 3 4 3 2 1 5 2 6 3 4 3 4 3 5 3 5 4 1 4 4 4 2 3 6 3 7 2 7 1 8 3 2 3 4 3 3 3 3 3 6 3 9 3 7 3 5 3 7 3 0 1 4 3 6 4 2 6 3 2 2 9 1 7 2 9 3 1 3 2 3 1 3 9 4 9 4 4 3 4 3 4 3 6 2 3 1 7 3 0 3 0 3 1 3 5 4 7 4 4 3 3 3 1 3 3 2 9 1 3 3 5 3 7 4 5 7 5 4 5 7 5 9 5 7 5 7 5 5 5 6 5 8 5 5 5 8 5 9 5 7 5 8 5 7 5 7 5 0 5 0 5 5 5 1 5 1 5 1 4 9 5 3 6 3 5 7 5 7 5 2 2 6 2 7 5 7 9 6 8 5 6 6 2 7 5 7 8 7 1 5 8 6 1 7 3 7 9 7 0 6 0 6 0 6 9 7 6 6 7 6 2 6 0 6 6 7 6 6 9 5 7 6 6 7 5 7 8 2 4 6 8 1 0 1 2 1 4 1 6 1 8 2 0 2 2 2 4 2 6 2 8 3 0 3 2 3 4 3 6 3 8 4 0 4 2 4 4 4 6 4 8 5 0 5 2 5 4 5 6
  • 32. Owner and Modelers Verify Performance
  • 33. • Attract early adopters • Achievable path to scale net zero buildings at little to no cost premium • Support cities, states and owners with aggressive energy goals • Transform the procurement paradigm Accelerate Performance A new construction initiative for superior energy performance
  • 34. 2 billion ft2 are new construction each year. An historic opportunity Source: U.S Energy Information Administration 3
  • 35. Thank you Adam McMillen, PE, LEED AP BD+C amcmillen@seventhwave.org 312.852.1360 Jennifer Scheib Jennifer.Scheib@nrel.gov 303.275.4323 www.seventhwave.org/accelerateperformance