Issues During Construction Time Extensions/Delay Claims Change Orders  Changed Conditions Suspension, Delay or Interruption Liquidated Damages Progress Reporting
Issues During Construction  The key to understanding project management is knowing and anticipating issues and problems arising during the construction process The key to a successful project is knowing how to deal with issues and problems when they arise or Knowing how to possibly “head off” certain issues and problems before they arise
Time Extensions/Delay Claims The contractor requests a time extension to the contract completion date Based on delays out of the control of the contractor Delays caused by owner or architect Design problem Owner modification Acts of God Weather (“adverse weather conditions not reasonably anticipatable”) Labor & Materials  Strike Late material delivery
Time Extensions/Delay Claims Time extensions are added to the original duration as stated in the contract Example: 62 day extension added to an original duration of 1050 days = project must be completed in 1112 calendar days The  Date of Substantial Completion  of the Work or designated portion thereof is the Date certified by the Owner’s representative when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended.
Change Orders Any alteration to the documents constitutes a change to the contract. AKA: “Modification” to the contract A change order is considered a “mini-contract” Handled in the same way as a bid, but no competition Scope of work and technical documents are forwarded to contractor  Contractor then submits a price quotation to complete the work Owner will either accept or negotiate price on change order Contractor usually increases costs on CO due to job disruption and additional overhead to complete paperwork
Changed Conditions When subsurface and site topographical conditions are not as expected Even after soil boring reports and geotechnical tests Engineering reports give information: To the A/E to help design foundation for building/structure To contractor in estimating work to excavate and move earth to satisfy the contract If the conditions are not representative of the reports, the contractor can claim a “changed condition” Often called the “concealed condition” If the Owner accepts the changed condition, the extended scope of work represented will be included in the contract as a change order.
Suspension, Delay or Interruption The Contracting officer may order the Contractor in writing to suspend, delay or interrupt all or any part of the work for such period of time he may determined be appropriate for the convenience of the Owner. Owner has right (according to contract) to stop construction on project for whatever reason they deem necessary Contractor has right to be compensated for demobilization-remobilization cycle or inflated costs on material and labor at time of restart Amount of adjustment is typically contested by contractor and often leads to arbitration/litigation to resolve the issue
Liquidated Damages Projects have completion dates for a reason!! The project is intended to serve a purpose or function The date of completion is tied to the date the project is needed for occupancy and utilization If contractor does not meet project completion date (or milestones), then contractor pays owner damages as a result of a beech of contract Damages (monetary amount) are determined in contract: Dollar amount per day is paid for each day past the completion date (stipulated sum) - $50 to $50,000 per day Usually found in the  Special Conditions of the Contract Owner must show proof of actual damage Cannot specify an arbitrary amount ($20k per day) to scare the contractor into completing the work on time
Liquidated Damages Example: Project: Strip Shopping Center  Projected monthly rental value:  $30,000 Contract date of completion:  October 1 Actual date of completion:  October 15 The owner has lost $15k in potential rental moneys and therefore is “damaged” by the contractor.  Legally, the owner can sue the contractor for the damaged amount, but the contract was written with a Liquidated Damage clause, which allows for more immediate recourse for recovering lost revenue.
Progress Reporting Contracts require that general contractor must submit a schedule of activity and periodic updates to the schedule to reflect ACTUAL PROGRESS. Contractors satisfy this requirement by completing: Progress meetings and minutes Daily reports Diaries Progress photos Monthly reports
Progress Reporting Progress Meetings and Minutes A means of face-to-face communication concerning project progress Meetings are held weekly or biweekly Usually present at the meeting: GC project manager Owner’s rep (architect or construction manager) Top trades/subcontractor’s rep (project manager or foreman) Opportunity to confront immediate issues and concerns Schedule coordination between GC and trades Has a formal agenda, structure and leader Meeting Minutes Must be detailed and organized Typically contractor is responsible for documenting minutes Notes should be distributed to all that are concerned with the issues Page 312 in book for example of minutes
Progress Reporting Daily Reports Report that is kept by superintendent Documents day-to-day activities and conditions on the job site Uses a pre-printed form that details: Date and sequential report numbering (each report gets a number) Project name and number Name of superintendent (or other filing report) Weather conditions including temperature Descriptions of activities Deliveries Visitors  What trades/subcontractors were present on site Large equipment present on site Report is used internally to document progress and update schedule Can be used in dispute resolution
Progress Reporting Dairies Like a daily report, but contains more information and detail regarding a particular activity or task Offers more opinion and attitudes on the job  Usually kept in a spiral bound notebook Information is handwritten with accompanying signature and date Items usually found in diary: Phone conversation notes Problems and issues that arise on site Personal conversations with anyone involved with the project Any other pertinent information  Can be used in dispute resolution; dairies are public record in the project
Progress Reporting Progress Photos Photos or videos taken at various levels of the project as a means of documentation for the project Time-lapse photography included capturing construction methods and process Adds information regarding the project that reports and written summaries can not document Conditions of site Quality of installation Progress over time Critical activity sequences (following critical path) Progress Photography has become a normal occurrence on jobsite  Use of digital cameras is key to sharing information electronically  Can also be used to resolve issues with design team rapidly without having A/E making site visit
Progress Reporting Monthly Reports Report that is submitted to owner and architect documenting project progress over the preceding month Typically submitted with monthly requisition  Used for distribution to owner’s “upper management” for comments and discussion No set format (unlike daily report form) Owner and contractor discuss format submission during pre-construction planning stage
Progress Reporting Monthly Reports Report includes: Narrative of project progress to date List of subcontractors and trades Cash flow actuals and projected Updated schedule (with all activity information from daily reports) detailing critical path Safety report  including accidents documented and visits from OSHA Contract modifications log Construction change requests  Change orders pending and approved for previous month Submittal and shop drawing log
NEXT LECTURE LECTURE 10 Materials Management and Quality Control

More Related Content

PPT
ACH 216 Lecture 09 (Issues During Project)
PPT
ACH 216 Lecture 08 (Scheduling)
PDF
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
DOC
Project End Report - Project Management template
DOCX
Ivy summary
PPT
ACH 216 Lecture 12 (Closeut & Turnover)
PDF
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
PPT
Common Interest Repair Issues
ACH 216 Lecture 09 (Issues During Project)
ACH 216 Lecture 08 (Scheduling)
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
Project End Report - Project Management template
Ivy summary
ACH 216 Lecture 12 (Closeut & Turnover)
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Common Interest Repair Issues

What's hot (20)

DOC
Project closure template v3.0
PPTX
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
PPT
Owner Big Picture Repair Legal Issues
PPTX
Project closure
DOCX
Project status report template v2.0
DOC
Activity definition-and-sequencing-worksheet-1.2
PPT
Renovate Repair Legal Issues Owner View
PDF
Construction Contract Issues for Owners of Residences
PPTX
Activity logic relationships and constraints
PDF
Construction Contracts Common Interest Developments
DOC
Prince 2, project managment Document End project report
DOC
Prince 2: project managment Document, End stage report
PDF
Vendor Contract Issues for Boards of Common Interest Developments
PDF
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
PPTX
Stages In Construction
PDF
Rev207 matrixexcelfile
DOC
Project scope statement template v2.3
DOC
Work breakdown-structure-table-template
Project closure template v3.0
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Owner Big Picture Repair Legal Issues
Project closure
Project status report template v2.0
Activity definition-and-sequencing-worksheet-1.2
Renovate Repair Legal Issues Owner View
Construction Contract Issues for Owners of Residences
Activity logic relationships and constraints
Construction Contracts Common Interest Developments
Prince 2, project managment Document End project report
Prince 2: project managment Document, End stage report
Vendor Contract Issues for Boards of Common Interest Developments
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Stages In Construction
Rev207 matrixexcelfile
Project scope statement template v2.3
Work breakdown-structure-table-template
Ad

Viewers also liked (20)

PDF
Experimental investigation on concrete by replacing crusher dust as fine aggr...
PDF
AN EXPERIMENTAL INVESTIGATION OF MODIFIED CONCRETE USING FLY ASH AND STONE DUST
PDF
AN EXPERIMENTAL STUDY ON PROPERTIES OF THE CONCRETE FOR REPLACEMENT OF SAND B...
DOCX
Cover letter
PDF
Experimental Investigation on the Concrete as a Partial Replacement of Fine a...
PPT
Stone crusher
PDF
Improved Concrete Properties Using Quarry Dust as Replacement for Natural Sand
PDF
Ur-Energy 2015 Year End Webcast and Teleconference
PPT
Branded Content / Marcelo Cortazio
PPTX
Relationship philosophy presentation
PPTX
Presentación de Gian Fulgoni en IAB Conecta 2012
DOC
David kenneth waldman's_2012_cv_mayv31
PDF
Mobile Consumer Report 2013 por Nielsen
PDF
J-Day Kraków: Listen to the sounds of your application
PDF
An Introduction To Onva
PDF
50 * Anios
PPS
love life and appreciate love
PDF
Ccc@Eccbr08 Iis Hanft
PPT
Internship presentation on Feb 22
PDF
Comparing Performance of Decision Diagrams vs. Case Retrieval Nets
Experimental investigation on concrete by replacing crusher dust as fine aggr...
AN EXPERIMENTAL INVESTIGATION OF MODIFIED CONCRETE USING FLY ASH AND STONE DUST
AN EXPERIMENTAL STUDY ON PROPERTIES OF THE CONCRETE FOR REPLACEMENT OF SAND B...
Cover letter
Experimental Investigation on the Concrete as a Partial Replacement of Fine a...
Stone crusher
Improved Concrete Properties Using Quarry Dust as Replacement for Natural Sand
Ur-Energy 2015 Year End Webcast and Teleconference
Branded Content / Marcelo Cortazio
Relationship philosophy presentation
Presentación de Gian Fulgoni en IAB Conecta 2012
David kenneth waldman's_2012_cv_mayv31
Mobile Consumer Report 2013 por Nielsen
J-Day Kraków: Listen to the sounds of your application
An Introduction To Onva
50 * Anios
love life and appreciate love
Ccc@Eccbr08 Iis Hanft
Internship presentation on Feb 22
Comparing Performance of Decision Diagrams vs. Case Retrieval Nets
Ad

Similar to ACH 216 Lecture 09 (Issues During Project) (20)

PPTX
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
PPT
Making Changes on the Construction Project
PDF
Construction Work Schedule Proposal PowerPoint Presentation Slides
PPT
Construction Administration Seminar
PPT
ACH 216 Lecture 12 (Closeut & Turnover)
PDF
Construction Bid Proposal Template PowerPoint Presentation Slides
PPT
ACH 216 Lecture 06 (Pre Construction Planning)
PPTX
Independent Engineer roles and responsibilities
PPT
ACH 216 Lecture 07 (Project Funding)
PDF
glossary-of-construction-terms.pdf
PPTX
Time management in fidic red book 2017(prmg080 project)
PPTX
C. Site managment chapter 5.pptx
PDF
Construction Process Proposal PowerPoint Presentation Slides
PPTX
FIDIC-Relevant to Time Management
PPTX
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
PPT
ACH 216 Lecture 02 (Project Format)
PDF
Construction Costing Proposal PowerPoint Presentation Slides
PPS
PM : Request for Information
PPT
Architectural Professional Practice - Construction Documents
PDF
Construction terminologies
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Making Changes on the Construction Project
Construction Work Schedule Proposal PowerPoint Presentation Slides
Construction Administration Seminar
ACH 216 Lecture 12 (Closeut & Turnover)
Construction Bid Proposal Template PowerPoint Presentation Slides
ACH 216 Lecture 06 (Pre Construction Planning)
Independent Engineer roles and responsibilities
ACH 216 Lecture 07 (Project Funding)
glossary-of-construction-terms.pdf
Time management in fidic red book 2017(prmg080 project)
C. Site managment chapter 5.pptx
Construction Process Proposal PowerPoint Presentation Slides
FIDIC-Relevant to Time Management
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
ACH 216 Lecture 02 (Project Format)
Construction Costing Proposal PowerPoint Presentation Slides
PM : Request for Information
Architectural Professional Practice - Construction Documents
Construction terminologies

More from Anne Arundel Community College (20)

PPTX
Green team iceland presentation with audio
PPTX
ACH 122 Lecture 05a (Brick Masonry)
PPTX
ACH 122 Lecture 02 (Sustainability Leed)
PPT
ACH 122 Lecture 04a (Excavation & Foundations P1)
PPT
ACH 218 Lecture 04 (Marketing In Construction) Part 2
PPT
ACH 218 Lecture 04 (Marketing In Construction) Part 1
PPT
ACH 218 Lecture 03 (Organizational Structure) Part1
PPT
ACH 218 Lecture 03 (Organizational Structure) Part1
PPT
ACH 122 Lecture 01 (Bldg Codes)
PPT
ACH 122 Lecture 01 (Bldg Codes)
PPT
ACH 122 Lecture 01 (Bldg Codes)
PPT
ACH 245 Lecture 02 (Intro To Cad 2010)
PPT
ACH 245 Lecture 03 (Drawing 2010)
PPT
Ach 245 Lecture 01 (Fundamentals) Vista
PPT
ACH 121 Lecture 14 (Finishes)
PPT
ACH 121 Lecture 13 (Special Construction)
PPT
ACH 216 Lecture 11 (Safety)
PPT
ACH 216 Lecture 10 (Materials Mgmt & Quality Assurance)
PPT
ACH 121 Lecture 11a (Thermal & Moisture Protection)
PPT
ACH 121 Lecture 11b (Thermal & Moisture Protection)
Green team iceland presentation with audio
ACH 122 Lecture 05a (Brick Masonry)
ACH 122 Lecture 02 (Sustainability Leed)
ACH 122 Lecture 04a (Excavation & Foundations P1)
ACH 218 Lecture 04 (Marketing In Construction) Part 2
ACH 218 Lecture 04 (Marketing In Construction) Part 1
ACH 218 Lecture 03 (Organizational Structure) Part1
ACH 218 Lecture 03 (Organizational Structure) Part1
ACH 122 Lecture 01 (Bldg Codes)
ACH 122 Lecture 01 (Bldg Codes)
ACH 122 Lecture 01 (Bldg Codes)
ACH 245 Lecture 02 (Intro To Cad 2010)
ACH 245 Lecture 03 (Drawing 2010)
Ach 245 Lecture 01 (Fundamentals) Vista
ACH 121 Lecture 14 (Finishes)
ACH 121 Lecture 13 (Special Construction)
ACH 216 Lecture 11 (Safety)
ACH 216 Lecture 10 (Materials Mgmt & Quality Assurance)
ACH 121 Lecture 11a (Thermal & Moisture Protection)
ACH 121 Lecture 11b (Thermal & Moisture Protection)

Recently uploaded (20)

PPTX
Tenders & Contracts Works _ Services Afzal.pptx
PPTX
Wisp Textiles: Where Comfort Meets Everyday Style
PDF
Urban Design Final Project-Site Analysis
PDF
UNIT 1 Introduction fnfbbfhfhfbdhdbdto Java.pptx.pdf
PDF
GREEN BUILDING MATERIALS FOR SUISTAINABLE ARCHITECTURE AND BUILDING STUDY
PDF
Design Thinking - Module 1 - Introduction To Design Thinking - Dr. Rohan Dasg...
PPT
Machine printing techniques and plangi dyeing
PPTX
YV PROFILE PROJECTS PROFILE PRES. DESIGN
PDF
BRANDBOOK-Presidential Award Scheme-Kenya-2023
PDF
YOW2022-BNE-MinimalViableArchitecture.pdf
PDF
Trusted Executive Protection Services in Ontario — Discreet & Professional.pdf
PDF
Emailing DDDX-MBCaEiB.pdf DDD_Europe_2022_Intro_to_Context_Mapping_pdf-165590...
PPTX
6- Architecture design complete (1).pptx
PPTX
DOC-20250430-WA0014._20250714_235747_0000.pptx
PPTX
Complete Guide to Microsoft PowerPoint 2019 – Features, Tools, and Tips"
PPTX
rapid fire quiz in your house is your india.pptx
PPTX
Entrepreneur intro, origin, process, method
PPT
UNIT I- Yarn, types, explanation, process
PDF
Integrated-2D-and-3D-Animation-Bridging-Dimensions-for-Impactful-Storytelling...
PPTX
Special finishes, classification and types, explanation
Tenders & Contracts Works _ Services Afzal.pptx
Wisp Textiles: Where Comfort Meets Everyday Style
Urban Design Final Project-Site Analysis
UNIT 1 Introduction fnfbbfhfhfbdhdbdto Java.pptx.pdf
GREEN BUILDING MATERIALS FOR SUISTAINABLE ARCHITECTURE AND BUILDING STUDY
Design Thinking - Module 1 - Introduction To Design Thinking - Dr. Rohan Dasg...
Machine printing techniques and plangi dyeing
YV PROFILE PROJECTS PROFILE PRES. DESIGN
BRANDBOOK-Presidential Award Scheme-Kenya-2023
YOW2022-BNE-MinimalViableArchitecture.pdf
Trusted Executive Protection Services in Ontario — Discreet & Professional.pdf
Emailing DDDX-MBCaEiB.pdf DDD_Europe_2022_Intro_to_Context_Mapping_pdf-165590...
6- Architecture design complete (1).pptx
DOC-20250430-WA0014._20250714_235747_0000.pptx
Complete Guide to Microsoft PowerPoint 2019 – Features, Tools, and Tips"
rapid fire quiz in your house is your india.pptx
Entrepreneur intro, origin, process, method
UNIT I- Yarn, types, explanation, process
Integrated-2D-and-3D-Animation-Bridging-Dimensions-for-Impactful-Storytelling...
Special finishes, classification and types, explanation

ACH 216 Lecture 09 (Issues During Project)

  • 1. Project Management & Control Project Funding (LECTURE 7) Scheduling (LECTURE 8) Issues During Construction (LECTURE 9) Materials Management and Quality Control (LECTURE 10)
  • 2. Issues During Construction Time Extensions/Delay Claims Change Orders Changed Conditions Suspension, Delay or Interruption Liquidated Damages Progress Reporting
  • 3. Issues During Construction The key to understanding project management is knowing and anticipating issues and problems arising during the construction process The key to a successful project is knowing how to deal with issues and problems when they arise or Knowing how to possibly “head off” certain issues and problems before they arise
  • 4. Time Extensions/Delay Claims The contractor requests a time extension to the contract completion date Based on delays out of the control of the contractor Delays caused by owner or architect Design problem Owner modification Acts of God Weather (“adverse weather conditions not reasonably anticipatable”) Labor & Materials Strike Late material delivery
  • 5. Time Extensions/Delay Claims Time extensions are added to the original duration as stated in the contract Example: 62 day extension added to an original duration of 1050 days = project must be completed in 1112 calendar days The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Owner’s representative when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended.
  • 6. Change Orders Any alteration to the documents constitutes a change to the contract. AKA: “Modification” to the contract A change order is considered a “mini-contract” Handled in the same way as a bid, but no competition Scope of work and technical documents are forwarded to contractor Contractor then submits a price quotation to complete the work Owner will either accept or negotiate price on change order Contractor usually increases costs on CO due to job disruption and additional overhead to complete paperwork
  • 7. Changed Conditions When subsurface and site topographical conditions are not as expected Even after soil boring reports and geotechnical tests Engineering reports give information: To the A/E to help design foundation for building/structure To contractor in estimating work to excavate and move earth to satisfy the contract If the conditions are not representative of the reports, the contractor can claim a “changed condition” Often called the “concealed condition” If the Owner accepts the changed condition, the extended scope of work represented will be included in the contract as a change order.
  • 8. Suspension, Delay or Interruption The Contracting officer may order the Contractor in writing to suspend, delay or interrupt all or any part of the work for such period of time he may determined be appropriate for the convenience of the Owner. Owner has right (according to contract) to stop construction on project for whatever reason they deem necessary Contractor has right to be compensated for demobilization-remobilization cycle or inflated costs on material and labor at time of restart Amount of adjustment is typically contested by contractor and often leads to arbitration/litigation to resolve the issue
  • 9. Liquidated Damages Projects have completion dates for a reason!! The project is intended to serve a purpose or function The date of completion is tied to the date the project is needed for occupancy and utilization If contractor does not meet project completion date (or milestones), then contractor pays owner damages as a result of a beech of contract Damages (monetary amount) are determined in contract: Dollar amount per day is paid for each day past the completion date (stipulated sum) - $50 to $50,000 per day Usually found in the Special Conditions of the Contract Owner must show proof of actual damage Cannot specify an arbitrary amount ($20k per day) to scare the contractor into completing the work on time
  • 10. Liquidated Damages Example: Project: Strip Shopping Center Projected monthly rental value: $30,000 Contract date of completion: October 1 Actual date of completion: October 15 The owner has lost $15k in potential rental moneys and therefore is “damaged” by the contractor. Legally, the owner can sue the contractor for the damaged amount, but the contract was written with a Liquidated Damage clause, which allows for more immediate recourse for recovering lost revenue.
  • 11. Progress Reporting Contracts require that general contractor must submit a schedule of activity and periodic updates to the schedule to reflect ACTUAL PROGRESS. Contractors satisfy this requirement by completing: Progress meetings and minutes Daily reports Diaries Progress photos Monthly reports
  • 12. Progress Reporting Progress Meetings and Minutes A means of face-to-face communication concerning project progress Meetings are held weekly or biweekly Usually present at the meeting: GC project manager Owner’s rep (architect or construction manager) Top trades/subcontractor’s rep (project manager or foreman) Opportunity to confront immediate issues and concerns Schedule coordination between GC and trades Has a formal agenda, structure and leader Meeting Minutes Must be detailed and organized Typically contractor is responsible for documenting minutes Notes should be distributed to all that are concerned with the issues Page 312 in book for example of minutes
  • 13. Progress Reporting Daily Reports Report that is kept by superintendent Documents day-to-day activities and conditions on the job site Uses a pre-printed form that details: Date and sequential report numbering (each report gets a number) Project name and number Name of superintendent (or other filing report) Weather conditions including temperature Descriptions of activities Deliveries Visitors What trades/subcontractors were present on site Large equipment present on site Report is used internally to document progress and update schedule Can be used in dispute resolution
  • 14. Progress Reporting Dairies Like a daily report, but contains more information and detail regarding a particular activity or task Offers more opinion and attitudes on the job Usually kept in a spiral bound notebook Information is handwritten with accompanying signature and date Items usually found in diary: Phone conversation notes Problems and issues that arise on site Personal conversations with anyone involved with the project Any other pertinent information Can be used in dispute resolution; dairies are public record in the project
  • 15. Progress Reporting Progress Photos Photos or videos taken at various levels of the project as a means of documentation for the project Time-lapse photography included capturing construction methods and process Adds information regarding the project that reports and written summaries can not document Conditions of site Quality of installation Progress over time Critical activity sequences (following critical path) Progress Photography has become a normal occurrence on jobsite Use of digital cameras is key to sharing information electronically Can also be used to resolve issues with design team rapidly without having A/E making site visit
  • 16. Progress Reporting Monthly Reports Report that is submitted to owner and architect documenting project progress over the preceding month Typically submitted with monthly requisition Used for distribution to owner’s “upper management” for comments and discussion No set format (unlike daily report form) Owner and contractor discuss format submission during pre-construction planning stage
  • 17. Progress Reporting Monthly Reports Report includes: Narrative of project progress to date List of subcontractors and trades Cash flow actuals and projected Updated schedule (with all activity information from daily reports) detailing critical path Safety report including accidents documented and visits from OSHA Contract modifications log Construction change requests Change orders pending and approved for previous month Submittal and shop drawing log
  • 18. NEXT LECTURE LECTURE 10 Materials Management and Quality Control