Agile Project Management:
A simple guide to creating a project burn-down chart
Author: PM Majik
Copyright 2020. All rights reserved. www.pmmajik.com
Contents
1.0 Purpose of this presentation
2.0 What is a burn down chart
3.0 How to create a project burn down chart
3.1 Create data table
3.2 Define tasks
3.3 Enter time estimate for tasks
3.4 Create estimated effort
3.5 Track daily progress
3.6 Actual effort
3.7 Create project burndown chart
4.0 Summary
5.0 Agile resources (including link to download burn down chart template)
6.0 PMO resources
Copyright 2020. All rights reserved. www.pmmajik.com
1.0 Purpose of this presentation
The purpose of this presentation is to provide an overview of working with Remote
Project Teams and the different considerations to make it a success.
This will help to build a framework for success on your own projects that involve remote
project team members.
Remember these are general guidelines. You should use them to help tailor a project
change control process that meets the need of your organisation.
Additional Resource
https://www.pmmajik.com/remote-project-management-guide-to-working-from-hom
e/
Copyright 2020. All rights reserved. www.pmmajik.com
2.0 What is a burn down chart?
Copyright 2020. All rights reserved. www.pmmajik.com
• A popular method of reporting progress when using Agile Project Management is the use of
burn-down charts.
• Wikipedia defines a burn-down chart as:
“A burn down chart is a graphical representation of work left to do versus time. The
outstanding work (or backlog) is often on the vertical axis, with time along the horizontal.
This is a simple yet powerful method. It is very easy to quickly understand if work is ahead,
behind or on schedule.
• A burn-down chart is a graphical representation of the completion of something against a
defined baseline. Put another way it is work left against time.
• This is typically achieved by plotting the activity on the x axis of a chart against time on the y
axis. The chart will read from left to right with the starting position as the first plot.
• As time progresses the progress against the baseline is captured. The data is then plotted
so that it is easy to see progress against the defined baseline.
3.0 How to create a project burndown chart
In this presentation I want to provide a
simple 7 step guide to how you can
build a project burn-down chart using
Excel.
In order to illustrate this I am going to
use the example of an Agile Sprint.
Sprint Example
•5 day duration
•8 tasks
•80 available hours
Copyright 2020. All rights reserved. www.pmmajik.com
1. Create data table
2. Define tasks
3. Enter time estimate for tasks
4. Create estimated effort
5. Track daily progress
6. Actual effort
7. Create project burndown chart
3.1 Create data table
All reporting requires an input, typically data. This date must be stored in a structured
way so that it can be efficiently processed and used.
The date table for the sprint needs to contain the following:
•Daily hours used by task
•Daily total hours used
•Baseline hours by day (the available hours known as ideal hours
Copyright 2020. All rights reserved. www.pmmajik.com
3.2 Define tasks
Each task that is to be included in the sprint should be entered into the table. It is
important to use consistent naming so that each task is clear and links back to the item in
the Product Backlog (this contains all of the features / requirements of the project).
Note: there can be many items in the Sprint that link to a single item in the Product
Backlog. This is because the tasks in the sprint represent the decomposition of the item
in the Product backlog to allow the tasks to be allocated.
In the example I have simply entered them as Task 1 to Task 8
Copyright 2020. All rights reserved. www.pmmajik.com
3.3 Enter the estimates for the tasks
As part of the sprint planning, the team should have estimated how much each task will
take. The sprint is then adjusted so that the total effort estimated for the sprint is equal to
the sprint budget (this is the available hours taking number of resources multiplied by
available working hours).
The estimate for each task is then captured in the table. This is important as it is used to
create the baseline.
Copyright 2020. All rights reserved. www.pmmajik.com
3.4 Create the estimated effort
This will represent the ideal baseline for using the available hours over the sprint. So in
the simplest for this is the available hours divided by number of days. In this example, 80
hours over 5 days equating to 16 hours a day.
In order to create the project burn-down chart, the data needs to be captured as a daily
running total starting with 80 hours than 64 hours left at end of day 1 (80 – 16), 48 hours
left at end of day 2, etc
Copyright 2020. All rights reserved. www.pmmajik.com
3.5 Track daily progress
The daily progress is then captured in the table against each task. It is important to
remember that the value captured for each day is the estimated effort to complete the
task, not the actual effort
Copyright 2020. All rights reserved. www.pmmajik.com
3.6 Actual effort
The total remaining effort needs to be captured at the end of each day. This is the total
(sum) of all of the estimated time remaining at the end of each day.
Copyright 2020. All rights reserved. www.pmmajik.com
3.7 Create project burndown chart
When the data is available, the project burn-down chart can be created. This is relatively
simple using the line chart option available within Excel.
Copyright 2020. All rights reserved. www.pmmajik.com
Highlight the summary table that contains the daily total for baseline effort and estimated
effort. You should also capture the heading of time period (Day 0, Day 1, etc).
From the insert option in Excel select the Bar Chart option and this will create a burn-
down chart for your data.
4.0 Summary
It is very simple to create a project burn-down chart as long as you know what data you
are tracking. The result is very powerful.
Remember the 7 steps:
1.Create data table
2.Define tasks
3.Enter time estimate for tasks
4.Create estimated effort
5.Track daily progress
6.Actual effort
7.Create project burndown chart
Copyright 2020. All rights reserved. www.pmmajik.com
Additional Resources
https://www.pmmajik.com/agile-simple-guide-to-creating-a-project-burn-down-chart/
https://www.pmmajik.com/agile-project-burn-chart-overview/
5.0 Resources
If you want more information, visit www.pmmajik.com where you will find lots of project
and PMO resources including the a copy of the template used in this tutorial (download
link is near the bottom of the blog post listed below).
https://www.pmmajik.com/agile-simple-
guide-to-creating-a-project-burn-down-chart/
Agile Template Framework
This powerful, yet simple to use framework contains 13
modules with guides, templates and video tutorials to
implement an Agile approach for your project.
https://pmmajik.com/members/agile-template-
framework-info/
Copyright 2020. All rights reserved. www.pmmajik.com
6.0 PMO Resources
If you want more information, visit www.pmmajik.com where you will find lots of project
and PMO resources including the FREE guide, 7 Steps to Set-Up a PMO.
Visit http://www.pmmajik.com/set-pmo/
PM Majik Website
On the PM Majik website you will find over 400 articles that contain practical and
pragmatic tips and insights for designing, mobilising and managing a PMO. New
articles are added weekly. Topic requests are encouraged from the community.
Copyright 2020. All rights reserved. www.pmmajik.com

More Related Content

PDF
Scrum With Ms Project
PPTX
ProMT
PPTX
Ms project presentation
PPTX
44259126 ms-project-presentation
PPTX
dokumen.tips_ms-project-presentation.pptx
PPTX
ms-project-presentation.pptx
PDF
Team Contract
PPTX
MS Project Presentation
Scrum With Ms Project
ProMT
Ms project presentation
44259126 ms-project-presentation
dokumen.tips_ms-project-presentation.pptx
ms-project-presentation.pptx
Team Contract
MS Project Presentation

Similar to agile-simple-guide-to-creating-project-burndown-chart-201025172824.ppt (20)

PDF
Odoo project management_casestudy
PDF
Construction Project Schedule Template- Residential Building
DOCX
Critical Path MethodIntroductionOnce you have the network diag.docx
PPTX
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
DOCX
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DOCX
DescriptionThe Aires Corporation is highly desirous of implementi.docx
PDF
Project 2007 full handout
DOC
Cmgt 410 cmgt410 cmgt 410 education for service uopstudy.com
DOCX
Project NameCommunication PlanOverviewEffective and .docx
DOC
Brief tutorial on gantt charts
PDF
Project Share Feature List - MS Project Services
PPTX
Modelingprogramstructure
DOCX
Mgmt404 project management whole course
DOCX
Mgmt404 project management whole course
DOCX
Mgmt404 project management whole course
DOCX
Mgmt404 project management whole course
DOCX
Mgmt404 project management whole course
DOCX
Mgmt404 project management whole course
DOCX
Mgmt404 project management whole course
Odoo project management_casestudy
Construction Project Schedule Template- Residential Building
Critical Path MethodIntroductionOnce you have the network diag.docx
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
Project 2007 full handout
Cmgt 410 cmgt410 cmgt 410 education for service uopstudy.com
Project NameCommunication PlanOverviewEffective and .docx
Brief tutorial on gantt charts
Project Share Feature List - MS Project Services
Modelingprogramstructure
Mgmt404 project management whole course
Mgmt404 project management whole course
Mgmt404 project management whole course
Mgmt404 project management whole course
Mgmt404 project management whole course
Mgmt404 project management whole course
Mgmt404 project management whole course
Ad

More from ASHUTOSH TRIVEDI (9)

PPTX
Docker Introduction How to create Image.pptx
PPTX
CircullarLinkedList notes for data sturcture
PPTX
Manual Testing Test Case To Learn Part-2.pptx
PPTX
Collection in java to store multiple values.pptx
PPTX
Arrays are used in java to holding more.pptx
PDF
ServletConfig & ServletContext
PPTX
Identifier
PPTX
Type cast operator
PPTX
JAVA Literals
Docker Introduction How to create Image.pptx
CircullarLinkedList notes for data sturcture
Manual Testing Test Case To Learn Part-2.pptx
Collection in java to store multiple values.pptx
Arrays are used in java to holding more.pptx
ServletConfig & ServletContext
Identifier
Type cast operator
JAVA Literals
Ad

Recently uploaded (20)

PDF
TR - Agricultural Crops Production NC III.pdf
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PPTX
Cell Types and Its function , kingdom of life
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PDF
Pre independence Education in Inndia.pdf
PDF
O7-L3 Supply Chain Operations - ICLT Program
PDF
Sports Quiz easy sports quiz sports quiz
PPTX
Institutional Correction lecture only . . .
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PPTX
Pharma ospi slides which help in ospi learning
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
RMMM.pdf make it easy to upload and study
PDF
Classroom Observation Tools for Teachers
TR - Agricultural Crops Production NC III.pdf
O5-L3 Freight Transport Ops (International) V1.pdf
Cell Types and Its function , kingdom of life
Microbial disease of the cardiovascular and lymphatic systems
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
Module 4: Burden of Disease Tutorial Slides S2 2025
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Renaissance Architecture: A Journey from Faith to Humanism
Pre independence Education in Inndia.pdf
O7-L3 Supply Chain Operations - ICLT Program
Sports Quiz easy sports quiz sports quiz
Institutional Correction lecture only . . .
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
Pharma ospi slides which help in ospi learning
Supply Chain Operations Speaking Notes -ICLT Program
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
RMMM.pdf make it easy to upload and study
Classroom Observation Tools for Teachers

agile-simple-guide-to-creating-project-burndown-chart-201025172824.ppt

  • 1. Agile Project Management: A simple guide to creating a project burn-down chart Author: PM Majik Copyright 2020. All rights reserved. www.pmmajik.com
  • 2. Contents 1.0 Purpose of this presentation 2.0 What is a burn down chart 3.0 How to create a project burn down chart 3.1 Create data table 3.2 Define tasks 3.3 Enter time estimate for tasks 3.4 Create estimated effort 3.5 Track daily progress 3.6 Actual effort 3.7 Create project burndown chart 4.0 Summary 5.0 Agile resources (including link to download burn down chart template) 6.0 PMO resources Copyright 2020. All rights reserved. www.pmmajik.com
  • 3. 1.0 Purpose of this presentation The purpose of this presentation is to provide an overview of working with Remote Project Teams and the different considerations to make it a success. This will help to build a framework for success on your own projects that involve remote project team members. Remember these are general guidelines. You should use them to help tailor a project change control process that meets the need of your organisation. Additional Resource https://www.pmmajik.com/remote-project-management-guide-to-working-from-hom e/ Copyright 2020. All rights reserved. www.pmmajik.com
  • 4. 2.0 What is a burn down chart? Copyright 2020. All rights reserved. www.pmmajik.com • A popular method of reporting progress when using Agile Project Management is the use of burn-down charts. • Wikipedia defines a burn-down chart as: “A burn down chart is a graphical representation of work left to do versus time. The outstanding work (or backlog) is often on the vertical axis, with time along the horizontal. This is a simple yet powerful method. It is very easy to quickly understand if work is ahead, behind or on schedule. • A burn-down chart is a graphical representation of the completion of something against a defined baseline. Put another way it is work left against time. • This is typically achieved by plotting the activity on the x axis of a chart against time on the y axis. The chart will read from left to right with the starting position as the first plot. • As time progresses the progress against the baseline is captured. The data is then plotted so that it is easy to see progress against the defined baseline.
  • 5. 3.0 How to create a project burndown chart In this presentation I want to provide a simple 7 step guide to how you can build a project burn-down chart using Excel. In order to illustrate this I am going to use the example of an Agile Sprint. Sprint Example •5 day duration •8 tasks •80 available hours Copyright 2020. All rights reserved. www.pmmajik.com 1. Create data table 2. Define tasks 3. Enter time estimate for tasks 4. Create estimated effort 5. Track daily progress 6. Actual effort 7. Create project burndown chart
  • 6. 3.1 Create data table All reporting requires an input, typically data. This date must be stored in a structured way so that it can be efficiently processed and used. The date table for the sprint needs to contain the following: •Daily hours used by task •Daily total hours used •Baseline hours by day (the available hours known as ideal hours Copyright 2020. All rights reserved. www.pmmajik.com
  • 7. 3.2 Define tasks Each task that is to be included in the sprint should be entered into the table. It is important to use consistent naming so that each task is clear and links back to the item in the Product Backlog (this contains all of the features / requirements of the project). Note: there can be many items in the Sprint that link to a single item in the Product Backlog. This is because the tasks in the sprint represent the decomposition of the item in the Product backlog to allow the tasks to be allocated. In the example I have simply entered them as Task 1 to Task 8 Copyright 2020. All rights reserved. www.pmmajik.com
  • 8. 3.3 Enter the estimates for the tasks As part of the sprint planning, the team should have estimated how much each task will take. The sprint is then adjusted so that the total effort estimated for the sprint is equal to the sprint budget (this is the available hours taking number of resources multiplied by available working hours). The estimate for each task is then captured in the table. This is important as it is used to create the baseline. Copyright 2020. All rights reserved. www.pmmajik.com
  • 9. 3.4 Create the estimated effort This will represent the ideal baseline for using the available hours over the sprint. So in the simplest for this is the available hours divided by number of days. In this example, 80 hours over 5 days equating to 16 hours a day. In order to create the project burn-down chart, the data needs to be captured as a daily running total starting with 80 hours than 64 hours left at end of day 1 (80 – 16), 48 hours left at end of day 2, etc Copyright 2020. All rights reserved. www.pmmajik.com
  • 10. 3.5 Track daily progress The daily progress is then captured in the table against each task. It is important to remember that the value captured for each day is the estimated effort to complete the task, not the actual effort Copyright 2020. All rights reserved. www.pmmajik.com
  • 11. 3.6 Actual effort The total remaining effort needs to be captured at the end of each day. This is the total (sum) of all of the estimated time remaining at the end of each day. Copyright 2020. All rights reserved. www.pmmajik.com
  • 12. 3.7 Create project burndown chart When the data is available, the project burn-down chart can be created. This is relatively simple using the line chart option available within Excel. Copyright 2020. All rights reserved. www.pmmajik.com Highlight the summary table that contains the daily total for baseline effort and estimated effort. You should also capture the heading of time period (Day 0, Day 1, etc). From the insert option in Excel select the Bar Chart option and this will create a burn- down chart for your data.
  • 13. 4.0 Summary It is very simple to create a project burn-down chart as long as you know what data you are tracking. The result is very powerful. Remember the 7 steps: 1.Create data table 2.Define tasks 3.Enter time estimate for tasks 4.Create estimated effort 5.Track daily progress 6.Actual effort 7.Create project burndown chart Copyright 2020. All rights reserved. www.pmmajik.com Additional Resources https://www.pmmajik.com/agile-simple-guide-to-creating-a-project-burn-down-chart/ https://www.pmmajik.com/agile-project-burn-chart-overview/
  • 14. 5.0 Resources If you want more information, visit www.pmmajik.com where you will find lots of project and PMO resources including the a copy of the template used in this tutorial (download link is near the bottom of the blog post listed below). https://www.pmmajik.com/agile-simple- guide-to-creating-a-project-burn-down-chart/ Agile Template Framework This powerful, yet simple to use framework contains 13 modules with guides, templates and video tutorials to implement an Agile approach for your project. https://pmmajik.com/members/agile-template- framework-info/ Copyright 2020. All rights reserved. www.pmmajik.com
  • 15. 6.0 PMO Resources If you want more information, visit www.pmmajik.com where you will find lots of project and PMO resources including the FREE guide, 7 Steps to Set-Up a PMO. Visit http://www.pmmajik.com/set-pmo/ PM Majik Website On the PM Majik website you will find over 400 articles that contain practical and pragmatic tips and insights for designing, mobilising and managing a PMO. New articles are added weekly. Topic requests are encouraged from the community. Copyright 2020. All rights reserved. www.pmmajik.com