An Introduction to an
Effective Earned
Value Management
System
By Scot Butcher & Martin Eveleigh
1
Webinar 1 of 3:
Earned Value
Building Blocks
2
Objectives.
Introduce the concept that Earned Value Management is a
‘system of collective processes’
and
That the metrics it provides are simply mathematical
outputs to help support informed decisions
Introductions
• Scot Butcher
• 30 years working in defence
acquisition and support
• Started out life as a mechanical
engineer but quickly moved to
management of projects
• Last 18 years have been spent in
and around project controls
• First experience of EVM was in
2003
• Experienced IBR participant and
chair
• Martin Eveleigh
• 40+ years working in the Defence
Sector both in the UK and USA
• Mechanical/Electrical Engineer,
but moved to
Programme Management in 1993
• Author of a US
DoD Validated Earned
Value Management System
Description (EVMSD)
• Holds an MSc in Programme &
Project Management
• Experience in enabling and leading
IBRs
3
Why these webinars?
• There is clear confusion between Project Controls, Earned Value Management
and Earned Value Analysis.
• There is an acknowledged and widespread obsession with Earned Value metrics
and its analysis without a firm understanding of the system required to underpin
it.
• There is a false belief that if you are planning discrete activities, that you can/are
performing EVM
• Therefore, these webinars are aimed at dispelling myths and advising what it
takes to establish an appropriate, pragmatic Earned Value Management System
4SB
Content of the 3 webinars
1. Basics and myth busting:
• Incessant ‘false focus’ - the Earned Value Management ‘Iceberg’.
• The relationship between Project Controls (PC), Earned Value Management System (EVMS) and Earned Value
Analysis (EVA).
• The understanding and importance of the Performance Measurement Baseline (PMB).
2. What’s needed……..and importantly what’s not!:
• Explain the attributes of an effective EVMS with/without compliance to EIA748.
• Discuss were Earned Value Analysis is beneficial and where not!
3. Assurance reviews:
• System Demonstration Review (SDR)
• Surveillance Review (SR)
• Integrated Baseline Review (IBR)
• Annual Estimate at Completion Review (AEAC)
5SB
The Earned Value
Iceberg
6SB
• Incessant ‘false focus’ - the Earned Value Management
‘Iceberg’.
• The relationship between Project Controls (PC), Earned
Value Management System (EVMS) and Earned Value
Analysis (EVA).
• The understanding and importance of the Performance
Measurement Baseline (PMB).
The Visible Iceberg
Schedule
Performance
Index (SPI)
Cost
Performance
Index (CPI)
7SB
The Invisible Iceberg!
SPI
CPI
SV
CV
1. You need to:
Set up and continuously
operate an effective
Earned Value
Management
System
2. In order to:
Enable accurate
collection, correct
interpretation and
effectively use
the data
EAC
BAC
CPR
TCPI
ETC
IEAC
ACWP(AC)
RAM
EVT
BCWP(EV)
BCWS(PV)
Obj%Complete
WBS
OBS
PMB
MR
WP
CA
IBR
CAM
LoE
0/100
SDR
Organisation
Planning
& Budgeting
Accounting
Revisions
Analysis
SB
Myth #1
Earned Value Management is
all about calculating CPI & SPI
9SB
The biggest Myth of all!
10
‘Project Controls
and
Earned Value Management
are different’
ME
• Incessant ‘false focus’ - the Earned Value Management
‘Iceberg’.
• The relationship between Project Controls (PC), Earned
Value Management System (EVMS) and Earned Value
Analysis (EVA).
• The understanding and importance of the Performance
Measurement Baseline (PMB).
How does EVM/EVA reconcile with Project
Controls?
11
Project Control System (PCS)
Earned Value Management System (EVMS)
Earned Value Analysis (EVA)
People
Process
Data
Tools
Organisation
Planning,
Resourcing &
Budgeting
Change Control
Analysis
& Reporting
Assurance
Organisation
Planning &
Budgeting
Accounting
Analysis
Revisions
Material &
Subcontract Mngt
Surveillance
Substantiating &
Reporting Performance
to-date
Performance Prediction
& Focus on Estimate
to/at Complete
Models, Guides &
Advice
Project
Control
System
Description
(PCSD)
Earned
Value Mngt
System
Description
(EVMSD)
ME
It’s all in the ‘Rules’!
12
Project Control System
(PCS)
Earned Value Management
System
(EVMS)
• Common Elements/Processes
• Common Role Players
• Common Data Sets
• Common Training
• Common Tools
• Common Assurance
• Specific Compliance
ME
Myth #2
Project Controls
and
Earned Value Management
are different
13ME
Myth #3
An effective EVMS, by
definition, needs to be 100%
compliant with an industry
standard*
* Often EIA748 or APM Guidance 14ME
The Performance
Measurement Baseline
(PMB)
15SB
• Incessant ‘false focus’ - the Earned Value Management
‘Iceberg’.
• The relationship between Project Controls (PC), Earned
Value Management System (EVMS) and Earned Value
Analysis (EVA).
• The understanding and importance of the Performance
Measurement Baseline (PMB).
APM Definition of a Baseline
16SB
The project baseline (often referred to as the performance
measurement baseline or PMB) is an approved plan for the
project, against which project performance is measured to
facilitate management decision making and action. The
setting of the baseline cannot be achieved until the scope is
defined and agreed, as the baseline must encompass the
entire project scope, schedule and cost.
APM: Planning, Scheduling, Monitoring & Control
Edition 1, 2015
APM Definition of a Baseline
17SB
The project baseline (often referred to as the performance
measurement baseline or PMB) is an approved plan for the
project, against which project performance is measured to
facilitate management decision making and action. The
setting of the baseline cannot be achieved until the scope is
defined and agreed, as the baseline must encompass the
entire project scope, schedule and cost.
APM: Planning, Scheduling, Monitoring & Control
Edition 1, 2015
The Performance Measurement Baseline (PMB)
• Aligned to Requirements
• Estimated
• Time-phased
• Resourced
• Substantiated
• Agreed
• Baselined
• Change Controlled
• Forecasted
18SB
Project Control System (PCS)
Earned Value Management System (EVMS)
Earned Value Analysis (EVA)
People
Process
Data
Tools
Organisation
Planning,
Resourcing&
Budgeting
Change Control
Analysis
& Reporting
Assurance
Organisation
Planning &
Budgeting
Accounting
Analysis
Revisions
Material &
Subcontract Mngt
Surveillance
Substantiating &
Reporting Performance
to-date
Performance Prediction
& Focus on Estimate
to/at Complete
£100K
£200K
£300K
£400K
1 2 3 4 5 6 7 8 9 10 11 12
BAC
BCWS
BCWP
ACWP
PMB
The Performance Measurement Baseline
(PMB)
Work Packages
Planning
Packages
Control Account
Budgets
Distributed
Budget (DB)
Undistributed
Budget
(UB)
Performance
Measurement
Baseline (PMB)
Management
Reserve (MR)
Contract
Budgeted
Baseline (CBB)
Profit
Contract Price
19
Business
Owned
Project
Owned
Integrated
Master
Schedule
(IMS)
Cost & Schedule
Alignment
SB
Myth #4
Because I have a discrete
schedule I am doing EVM
20SB
Myth #5
EVM will save my project…and
any other project I deploy it on
21SB

More Related Content

PDF
An introduction to an effective earned value management system (EVMS) webinar...
PDF
An introduction to an effective earned value management system (EVMS) webinar...
PPTX
Cost management
PDF
Earned value management with Examples | Control Cost | PMBOK | PMP
PPT
Using Earned Value Management Concepts to Improve Commercial Project Performance
PDF
The Benefits of using Earned Value Management
PPTX
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
PDF
A brief on project cost management
An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...
Cost management
Earned value management with Examples | Control Cost | PMBOK | PMP
Using Earned Value Management Concepts to Improve Commercial Project Performance
The Benefits of using Earned Value Management
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
A brief on project cost management

What's hot (19)

PDF
Kpi basics construction _building material_industry 2009
PPTX
Project Cost Management - PMP preparation course
PPTX
Project Cost Management
PPTX
Project cost & control
PPTX
PMBoK, discussion #5: Project Cost Management
PPTX
Project Cost Management
PPTX
Cost Management
PPT
Project Control- Overview Presentation Tafseer
PPT
Ch 9 project monitoring & control updated
PDF
Project cost control system in SAP
PDF
Annual Results and Impact Evaluation Workshop for RBF - Day Three - Measureme...
PPTX
PMP Training - 07 project cost management
PPT
Evm intro. slide deck 13 may 2018
PDF
PMP_Project Cost Management
PPTX
Project cost control
PDF
4. project cost management
PDF
Cost management basics for Construction Engineers
PPT
09. Project Cost Management
PPT
Project Cost Management
Kpi basics construction _building material_industry 2009
Project Cost Management - PMP preparation course
Project Cost Management
Project cost & control
PMBoK, discussion #5: Project Cost Management
Project Cost Management
Cost Management
Project Control- Overview Presentation Tafseer
Ch 9 project monitoring & control updated
Project cost control system in SAP
Annual Results and Impact Evaluation Workshop for RBF - Day Three - Measureme...
PMP Training - 07 project cost management
Evm intro. slide deck 13 may 2018
PMP_Project Cost Management
Project cost control
4. project cost management
Cost management basics for Construction Engineers
09. Project Cost Management
Project Cost Management
Ad

Similar to An introduction to an effective earned value management system (EVMS) webinar series part 1, 29 September 2020 (20)

PDF
Earned Value Management Essentials
PDF
Earned Value Managed Services
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PPTX
Presentation Relating to Earned Value
PDF
Back to basics - Earned Value Management for beginners webinar
PPTX
project control using earned value analysis - Part 01
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
S12 Earned Value Management
PDF
Project monitoring and controlling with earned value management
PDF
Basic Concepts of Earned Value Management.pdf
PPTX
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PDF
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
PDF
Earned Value Management Essentials
PDF
Knowing the Project Health using Earned Value Management (EVM)
PDF
Earned Value Management
PDF
Odoo experience 2015 earned value management
DOCX
1Earned Value Management at NASA An Integrated, Light.docx
PPT
Evm power point 25 august 2015 prams co (2)
PPT
Evm power point 25 august 2015 prams co (2)
Earned Value Management Essentials
Earned Value Managed Services
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
Presentation Relating to Earned Value
Back to basics - Earned Value Management for beginners webinar
project control using earned value analysis - Part 01
Projects Control Using Earned Value Techniques - Part One
S12 Earned Value Management
Project monitoring and controlling with earned value management
Basic Concepts of Earned Value Management.pdf
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
Earned Value Management Essentials
Knowing the Project Health using Earned Value Management (EVM)
Earned Value Management
Odoo experience 2015 earned value management
1Earned Value Management at NASA An Integrated, Light.docx
Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)
Ad

More from Association for Project Management (20)

PDF
How using AI in construction planning boosts efficiency and production
PDF
APM North East Network: Micro P3 Express – A framework for all small projects
PDF
Leveraging Projects and PMOs to drive Sustainability, 2 July 2025
PDF
Transforming Tomorrow Managing Change in the Public Sector.pdf
PPTX
1155 Teri Okoro.pptx APM People Interest Network Presents: A People-Centric A...
PPTX
1100 Kate Howes.pptx The Value of Education and Training: Developing a Learni...
PPTX
0815 Matt Gitsham APM Conf 2025-Professor of Sustainable Development and Acad...
PPTX
1510 Rami Deen Turning Fools Gold to Sustainable Gold v0.9.pptx
PPTX
1100 Suzanne Maxted & Ellie Cady APM Sustainability Interest Network presents...
PPTX
1510 day 2 Hall 5 Arun Khuttan Building a project business case using the UN ...
PPTX
1155 Helen Clayton_Tasha Clark - ESG Slides - Final - APM Conference 25.pptx
PPTX
1100 Mark & Andrew APM Enabling Change IN Slides.pptx
PPTX
0945 APM presentation from Gabrielle Walker.pptx
PDF
How you can use behavioural insights on your projects and pitfalls to be awar...
PPTX
Sadie B Okiji - Head of projects, NHS Sussex
PPTX
Cyara Buchuck-Wilsenach.pptx Embedding DEI into Sustainable Project Managemen...
PPTX
APM 2025 Tayyab Jamil Slide Deck_Rethinking Technology Projects For Sustaina...
PPTX
1155 Robbie Warwick - Chaos to Clarity V1.0.pptx
PPTX
Daniel O’Neill Director of Project Delivery, Tevalis and Felicity Peart Count...
PPTX
1155 APM Conference 2025 - How to Embed Sustainability into the Entire Projec...
How using AI in construction planning boosts efficiency and production
APM North East Network: Micro P3 Express – A framework for all small projects
Leveraging Projects and PMOs to drive Sustainability, 2 July 2025
Transforming Tomorrow Managing Change in the Public Sector.pdf
1155 Teri Okoro.pptx APM People Interest Network Presents: A People-Centric A...
1100 Kate Howes.pptx The Value of Education and Training: Developing a Learni...
0815 Matt Gitsham APM Conf 2025-Professor of Sustainable Development and Acad...
1510 Rami Deen Turning Fools Gold to Sustainable Gold v0.9.pptx
1100 Suzanne Maxted & Ellie Cady APM Sustainability Interest Network presents...
1510 day 2 Hall 5 Arun Khuttan Building a project business case using the UN ...
1155 Helen Clayton_Tasha Clark - ESG Slides - Final - APM Conference 25.pptx
1100 Mark & Andrew APM Enabling Change IN Slides.pptx
0945 APM presentation from Gabrielle Walker.pptx
How you can use behavioural insights on your projects and pitfalls to be awar...
Sadie B Okiji - Head of projects, NHS Sussex
Cyara Buchuck-Wilsenach.pptx Embedding DEI into Sustainable Project Managemen...
APM 2025 Tayyab Jamil Slide Deck_Rethinking Technology Projects For Sustaina...
1155 Robbie Warwick - Chaos to Clarity V1.0.pptx
Daniel O’Neill Director of Project Delivery, Tevalis and Felicity Peart Count...
1155 APM Conference 2025 - How to Embed Sustainability into the Entire Projec...

Recently uploaded (20)

PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PPTX
UNIT III MENTAL HEALTH NURSING ASSESSMENT
PPTX
Orientation - ARALprogram of Deped to the Parents.pptx
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Complications of Minimal Access Surgery at WLH
PPTX
Lesson notes of climatology university.
PDF
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
RMMM.pdf make it easy to upload and study
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PPTX
Cell Types and Its function , kingdom of life
PPTX
Final Presentation General Medicine 03-08-2024.pptx
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
Practical Manual AGRO-233 Principles and Practices of Natural Farming
UNIT III MENTAL HEALTH NURSING ASSESSMENT
Orientation - ARALprogram of Deped to the Parents.pptx
Final Presentation General Medicine 03-08-2024.pptx
Complications of Minimal Access Surgery at WLH
Lesson notes of climatology university.
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
RMMM.pdf make it easy to upload and study
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
A powerpoint presentation on the Revised K-10 Science Shaping Paper
Chinmaya Tiranga quiz Grand Finale.pdf
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
Cell Types and Its function , kingdom of life
Final Presentation General Medicine 03-08-2024.pptx

An introduction to an effective earned value management system (EVMS) webinar series part 1, 29 September 2020

  • 1. An Introduction to an Effective Earned Value Management System By Scot Butcher & Martin Eveleigh 1
  • 2. Webinar 1 of 3: Earned Value Building Blocks 2 Objectives. Introduce the concept that Earned Value Management is a ‘system of collective processes’ and That the metrics it provides are simply mathematical outputs to help support informed decisions
  • 3. Introductions • Scot Butcher • 30 years working in defence acquisition and support • Started out life as a mechanical engineer but quickly moved to management of projects • Last 18 years have been spent in and around project controls • First experience of EVM was in 2003 • Experienced IBR participant and chair • Martin Eveleigh • 40+ years working in the Defence Sector both in the UK and USA • Mechanical/Electrical Engineer, but moved to Programme Management in 1993 • Author of a US DoD Validated Earned Value Management System Description (EVMSD) • Holds an MSc in Programme & Project Management • Experience in enabling and leading IBRs 3
  • 4. Why these webinars? • There is clear confusion between Project Controls, Earned Value Management and Earned Value Analysis. • There is an acknowledged and widespread obsession with Earned Value metrics and its analysis without a firm understanding of the system required to underpin it. • There is a false belief that if you are planning discrete activities, that you can/are performing EVM • Therefore, these webinars are aimed at dispelling myths and advising what it takes to establish an appropriate, pragmatic Earned Value Management System 4SB
  • 5. Content of the 3 webinars 1. Basics and myth busting: • Incessant ‘false focus’ - the Earned Value Management ‘Iceberg’. • The relationship between Project Controls (PC), Earned Value Management System (EVMS) and Earned Value Analysis (EVA). • The understanding and importance of the Performance Measurement Baseline (PMB). 2. What’s needed……..and importantly what’s not!: • Explain the attributes of an effective EVMS with/without compliance to EIA748. • Discuss were Earned Value Analysis is beneficial and where not! 3. Assurance reviews: • System Demonstration Review (SDR) • Surveillance Review (SR) • Integrated Baseline Review (IBR) • Annual Estimate at Completion Review (AEAC) 5SB
  • 6. The Earned Value Iceberg 6SB • Incessant ‘false focus’ - the Earned Value Management ‘Iceberg’. • The relationship between Project Controls (PC), Earned Value Management System (EVMS) and Earned Value Analysis (EVA). • The understanding and importance of the Performance Measurement Baseline (PMB).
  • 7. The Visible Iceberg Schedule Performance Index (SPI) Cost Performance Index (CPI) 7SB
  • 8. The Invisible Iceberg! SPI CPI SV CV 1. You need to: Set up and continuously operate an effective Earned Value Management System 2. In order to: Enable accurate collection, correct interpretation and effectively use the data EAC BAC CPR TCPI ETC IEAC ACWP(AC) RAM EVT BCWP(EV) BCWS(PV) Obj%Complete WBS OBS PMB MR WP CA IBR CAM LoE 0/100 SDR Organisation Planning & Budgeting Accounting Revisions Analysis SB
  • 9. Myth #1 Earned Value Management is all about calculating CPI & SPI 9SB
  • 10. The biggest Myth of all! 10 ‘Project Controls and Earned Value Management are different’ ME • Incessant ‘false focus’ - the Earned Value Management ‘Iceberg’. • The relationship between Project Controls (PC), Earned Value Management System (EVMS) and Earned Value Analysis (EVA). • The understanding and importance of the Performance Measurement Baseline (PMB).
  • 11. How does EVM/EVA reconcile with Project Controls? 11 Project Control System (PCS) Earned Value Management System (EVMS) Earned Value Analysis (EVA) People Process Data Tools Organisation Planning, Resourcing & Budgeting Change Control Analysis & Reporting Assurance Organisation Planning & Budgeting Accounting Analysis Revisions Material & Subcontract Mngt Surveillance Substantiating & Reporting Performance to-date Performance Prediction & Focus on Estimate to/at Complete Models, Guides & Advice Project Control System Description (PCSD) Earned Value Mngt System Description (EVMSD) ME
  • 12. It’s all in the ‘Rules’! 12 Project Control System (PCS) Earned Value Management System (EVMS) • Common Elements/Processes • Common Role Players • Common Data Sets • Common Training • Common Tools • Common Assurance • Specific Compliance ME
  • 13. Myth #2 Project Controls and Earned Value Management are different 13ME
  • 14. Myth #3 An effective EVMS, by definition, needs to be 100% compliant with an industry standard* * Often EIA748 or APM Guidance 14ME
  • 15. The Performance Measurement Baseline (PMB) 15SB • Incessant ‘false focus’ - the Earned Value Management ‘Iceberg’. • The relationship between Project Controls (PC), Earned Value Management System (EVMS) and Earned Value Analysis (EVA). • The understanding and importance of the Performance Measurement Baseline (PMB).
  • 16. APM Definition of a Baseline 16SB The project baseline (often referred to as the performance measurement baseline or PMB) is an approved plan for the project, against which project performance is measured to facilitate management decision making and action. The setting of the baseline cannot be achieved until the scope is defined and agreed, as the baseline must encompass the entire project scope, schedule and cost. APM: Planning, Scheduling, Monitoring & Control Edition 1, 2015
  • 17. APM Definition of a Baseline 17SB The project baseline (often referred to as the performance measurement baseline or PMB) is an approved plan for the project, against which project performance is measured to facilitate management decision making and action. The setting of the baseline cannot be achieved until the scope is defined and agreed, as the baseline must encompass the entire project scope, schedule and cost. APM: Planning, Scheduling, Monitoring & Control Edition 1, 2015
  • 18. The Performance Measurement Baseline (PMB) • Aligned to Requirements • Estimated • Time-phased • Resourced • Substantiated • Agreed • Baselined • Change Controlled • Forecasted 18SB Project Control System (PCS) Earned Value Management System (EVMS) Earned Value Analysis (EVA) People Process Data Tools Organisation Planning, Resourcing& Budgeting Change Control Analysis & Reporting Assurance Organisation Planning & Budgeting Accounting Analysis Revisions Material & Subcontract Mngt Surveillance Substantiating & Reporting Performance to-date Performance Prediction & Focus on Estimate to/at Complete £100K £200K £300K £400K 1 2 3 4 5 6 7 8 9 10 11 12 BAC BCWS BCWP ACWP PMB
  • 19. The Performance Measurement Baseline (PMB) Work Packages Planning Packages Control Account Budgets Distributed Budget (DB) Undistributed Budget (UB) Performance Measurement Baseline (PMB) Management Reserve (MR) Contract Budgeted Baseline (CBB) Profit Contract Price 19 Business Owned Project Owned Integrated Master Schedule (IMS) Cost & Schedule Alignment SB
  • 20. Myth #4 Because I have a discrete schedule I am doing EVM 20SB
  • 21. Myth #5 EVM will save my project…and any other project I deploy it on 21SB