Project Management
(AOA) and (AON) Network Construction and
Critical Path Calculations
(Using Four Methods)
Dr. Mahmoud Abbas Mahmoud
Assistant Professor
(AOA) and (AON) Network Construction and
Critical Path Calculations
(Using Four Methods)
EXAMPLE:
Construct the (AOA) and (AON) networks for the project whose activities,
their durations and their precedence relationships are as given in the table,
also find:
i) [ES, EF, LS, LF, Slack] for all activities.
ii) Critical path(s).
iii) Project completion time.
Activity
Predecessor
Activity
Duration
(days)
A - 2
B A 8
C A 10
D B 6
E B 3
F C 3
G C 7
H D, F 5
I E 2
J G 8
Solution (1):
(AOA) network
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Yes
B (2 – 3) 8 2 10 8 16 6 No
C (2 – 4) 10 2 12 2 12 0* Yes
D (3 – 5) 6 10 16 16 22 6 No
E (3 – 6) 3 10 13 22 25 12 No
F (4 – 5) 3 12 15 19 22 7 No
G (4 – 7) 7 12 19 12 19 0* Yes
H (5 – 8) 5 16 21 22 27 6 No
I (6 – 8) 2 13 15 25 27 12 No
J (7 – 8) 8 19 27 19 27 0* Yes
Therefore:
Critical path: A --- C --- G --- J
Project completion time = 27 days
Solution (2):
(AOA) network (calculations in node)
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Yes
B (2 – 3) 8 2 10 8 16 6 No
C (2 – 4) 10 2 12 2 12 0* Yes
D (3 – 5) 6 10 16 16 22 6 No
E (3 – 6) 3 10 13 22 25 12 No
F (4 – 5) 3 12 15 19 22 7 No
G (4 – 7) 7 12 19 12 19 0* Yes
H (5 – 8) 5 16 21 22 27 6 No
I (6 – 8) 2 13 15 25 27 12 No
J (7 – 8) 8 19 27 19 27 0* Yes
Note: (LC = LF) & (EC = EF)
Therefore:
Critical path: A --- C --- G --- J
Project completion time = 27 days
Solution (3):
(AOA) network (calculations on arrow)
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Yes
B (2 – 3) 8 2 10 8 16 6 No
C (2 – 4) 10 2 12 2 12 0* Yes
D (3 – 5) 6 10 16 16 22 6 No
E (3 – 6) 3 10 13 22 25 12 No
F (4 – 5) 3 12 15 19 22 7 No
G (4 – 7) 7 12 19 12 19 0* Yes
H (5 – 8) 5 16 21 22 27 6 No
I (6 – 8) 2 13 15 25 27 12 No
J (7 – 8) 8 19 27 19 27 0* Yes
Therefore:
Critical path: A --- C --- G --- J
Project completion time = 27 days
Solution (4):
(AON) network
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Yes
B (2 – 3) 8 2 10 8 16 6 No
C (2 – 4) 10 2 12 2 12 0* Yes
D (3 – 5) 6 10 16 16 22 6 No
E (3 – 6) 3 10 13 22 25 12 No
F (4 – 5) 3 12 15 19 22 7 No
G (4 – 7) 7 12 19 12 19 0* Yes
H (5 – 8) 5 16 21 22 27 6 No
I (6 – 8) 2 13 15 25 27 12 No
J (7 – 8) 8 19 27 19 27 0* Yes
Therefore:
Critical path: A --- C --- G --- J
Project completion time = 27 days

More Related Content

PPSX
(Aoa) and (aon) networks
PDF
Article Review-Writing Sample
PDF
Managing to Learn Mentoring A3 Thinking
PDF
Solution manual for operations management processes and supply chains 10th ed...
PDF
Obligations and-contracts reviewer
PPTX
Competitive Advantage of H&M
PPTX
Project Management Techniques ( CPM & PERT Techniques )
PPTX
Ppt on project appraisal
(Aoa) and (aon) networks
Article Review-Writing Sample
Managing to Learn Mentoring A3 Thinking
Solution manual for operations management processes and supply chains 10th ed...
Obligations and-contracts reviewer
Competitive Advantage of H&M
Project Management Techniques ( CPM & PERT Techniques )
Ppt on project appraisal

What's hot (20)

PDF
Critical path method(cpm)
PPTX
Critical Path Ppt
PDF
time cost trade off
DOC
Network diagram problems
PPTX
Critical Path Method
PPTX
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
PPT
The Network Diagram and Critical Path
PPTX
Pert & cpm project management
PPTX
Pert analysis
PPTX
Network analysis by PERT and CPM
PPT
Chapter 12(cpm pert)
PPTX
Project scheduling
PPT
crashing of project
PDF
Integer programming
PPTX
PERT and CPM
PPTX
Project Management - Critical path method
PPT
Construction scheduling & Cost control
PPTX
Project Management PERT and CPM
PPT
Project Management: NETWORK ANALYSIS - CPM and PERT
PPTX
CPM, Network Analysis A-O-A, A-O-N, Resource management
Critical path method(cpm)
Critical Path Ppt
time cost trade off
Network diagram problems
Critical Path Method
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
The Network Diagram and Critical Path
Pert & cpm project management
Pert analysis
Network analysis by PERT and CPM
Chapter 12(cpm pert)
Project scheduling
crashing of project
Integer programming
PERT and CPM
Project Management - Critical path method
Construction scheduling & Cost control
Project Management PERT and CPM
Project Management: NETWORK ANALYSIS - CPM and PERT
CPM, Network Analysis A-O-A, A-O-N, Resource management
Ad

Similar to (AOA) and (AON) Network construction and critical path calculations (using four methods) (20)

PPTX
CPM.pptx
PPTX
Building Success: Project Scheduling Essentials
DOCX
Scheduling Problems Complete the following problems covering pro.docx
PDF
Management Network Lec 3
PPT
Chapter 6 project management
PPTX
Critical path method (cpm)
PPT
Productions & Operations Management Chapter 03
PDF
Lecture - Project, Planning and Control.pdf
PDF
Lecture 5.pdf
PPTX
Additional ppt Time Management Slides.pptx
PDF
Chap 6.5 Define Schedule
PPT
Project Management Techniques
PPTX
Chapter 5 - PERT-CPM
PPT
606CPM1.ppt
PPTX
Hard Rock
PPT
Project management
PDF
8th Semester Civil Engineering Question Papers June/july 2018
PPTX
Lecture 4 Program Evaluation and Review Technique.pptx
PPTX
Cpm and pert
PDF
Project network math solution
CPM.pptx
Building Success: Project Scheduling Essentials
Scheduling Problems Complete the following problems covering pro.docx
Management Network Lec 3
Chapter 6 project management
Critical path method (cpm)
Productions & Operations Management Chapter 03
Lecture - Project, Planning and Control.pdf
Lecture 5.pdf
Additional ppt Time Management Slides.pptx
Chap 6.5 Define Schedule
Project Management Techniques
Chapter 5 - PERT-CPM
606CPM1.ppt
Hard Rock
Project management
8th Semester Civil Engineering Question Papers June/july 2018
Lecture 4 Program Evaluation and Review Technique.pptx
Cpm and pert
Project network math solution
Ad

More from Dr. Mahmoud Al-Naimi (20)

PDF
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
PDF
Certificate - Dr. Mahmoud AL-Naimi
PDF
ملاحظات مهمة عن تعجيل المشاريع
PDF
Resource allocation and smoothing
PDF
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
PDF
أسلوب تقييم ومراجعة المشروع (PERT)
PDF
Applications dr. mahmoud al-naimi
PDF
Product design and manufacture lecture 1
PPSX
Easy steps to critical path determination and floats calculations for projects
PPSX
Step by step network construction and (cpm) calculations
PPSX
Easy steps to network construction and critical path determination
PPTX
ألأستدامة والتصنيع الرشيق
PDF
Control charts for variables
PDF
Just in time (jit), lean, and toyota production system (tps)
PDF
Evolution of mrp type systems
PPTX
Computer in Design and Manufacturing
PDF
إنشاء ورسم المخططات الشبكية
PDF
Network construction
PDF
Production planning hierarchy
PDF
Material and capacity requirements planning (mrp and crp) part 2
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
Certificate - Dr. Mahmoud AL-Naimi
ملاحظات مهمة عن تعجيل المشاريع
Resource allocation and smoothing
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
أسلوب تقييم ومراجعة المشروع (PERT)
Applications dr. mahmoud al-naimi
Product design and manufacture lecture 1
Easy steps to critical path determination and floats calculations for projects
Step by step network construction and (cpm) calculations
Easy steps to network construction and critical path determination
ألأستدامة والتصنيع الرشيق
Control charts for variables
Just in time (jit), lean, and toyota production system (tps)
Evolution of mrp type systems
Computer in Design and Manufacturing
إنشاء ورسم المخططات الشبكية
Network construction
Production planning hierarchy
Material and capacity requirements planning (mrp and crp) part 2

Recently uploaded (20)

PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PPT
Mechanical Engineering MATERIALS Selection
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
OOP with Java - Java Introduction (Basics)
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Geodesy 1.pptx...............................................
PPT
Project quality management in manufacturing
PDF
Digital Logic Computer Design lecture notes
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
Internet of Things (IOT) - A guide to understanding
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
web development for engineering and engineering
PDF
Arduino robotics embedded978-1-4302-3184-4.pdf
PDF
Well-logging-methods_new................
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PDF
PPT on Performance Review to get promotions
PPTX
Sustainable Sites - Green Building Construction
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
Model Code of Practice - Construction Work - 21102022 .pdf
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
Mechanical Engineering MATERIALS Selection
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
OOP with Java - Java Introduction (Basics)
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Geodesy 1.pptx...............................................
Project quality management in manufacturing
Digital Logic Computer Design lecture notes
Foundation to blockchain - A guide to Blockchain Tech
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Internet of Things (IOT) - A guide to understanding
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
web development for engineering and engineering
Arduino robotics embedded978-1-4302-3184-4.pdf
Well-logging-methods_new................
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PPT on Performance Review to get promotions
Sustainable Sites - Green Building Construction
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx

(AOA) and (AON) Network construction and critical path calculations (using four methods)

  • 1. Project Management (AOA) and (AON) Network Construction and Critical Path Calculations (Using Four Methods) Dr. Mahmoud Abbas Mahmoud Assistant Professor
  • 2. (AOA) and (AON) Network Construction and Critical Path Calculations (Using Four Methods) EXAMPLE: Construct the (AOA) and (AON) networks for the project whose activities, their durations and their precedence relationships are as given in the table, also find: i) [ES, EF, LS, LF, Slack] for all activities. ii) Critical path(s). iii) Project completion time. Activity Predecessor Activity Duration (days) A - 2 B A 8 C A 10 D B 6 E B 3 F C 3 G C 7 H D, F 5 I E 2 J G 8
  • 3. Solution (1): (AOA) network Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days
  • 4. Solution (2): (AOA) network (calculations in node) Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Note: (LC = LF) & (EC = EF) Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days
  • 5. Solution (3): (AOA) network (calculations on arrow) Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days
  • 6. Solution (4): (AON) network Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days