Lecture - 5
2
The Critical Path Method (CPM)
3
Who develops the WBS?
A WBS is developed by the A/E at the end of the design phase.
and/or by the bidders during the proposal (procurement phase).
4
TYPES OF ACTIVITIES
1. Production Activities
Those that can be taken directly from plans and specifications
2. Procurement Activities
Procurement of material and equipment
3. Management Decision Activities
Activities that can be created by management to avoid certain situations
Delay Concrete
Company Vacation
5
Example
Draw the logic network and perform the CPM calculations for the schedule shown next.
Duration
IPA
Activity
5
-
A
8
A
B
6
A
C
9
B
D
6
B,C
E
3
C
F
1
D,E,F
G
6
In mathematical terms, the ES for activity j is as follows :
ESj =max( EFi )
where (EFi) represents the EF for all preceding activities.
Likewise, the EF time for activity j is as follows :
EF j= ESj + Dur j
where Dur j is the duration of activity j
Forward pass: The process of navigating through a network from start to end and calculating the
completion date for the project and the early dates for each activity
Forward pass calculations
7
A
5
G
1
C
6
D
9
B
8
E
6
F
3
22,23
5,11
5,13 13,22
13,19
11,14
0,5
Solution :
Duration
IPA
Activity
5
-
A
8
A
B
6
A
C
9
B
D
6
B,C
E
3
C
F
1
D,E,F
G
8
In mathematical terms, the late finish LF for activity j is as follows :
(
LFj =min(LSk
where (LSk) represents the late start date for all succeeding activities.
Likewise, the LS time for activity j (LS j) is as follows :
LS j= LFj - Dur j
where Dur j is the duration of activity
Backward pass: The process of navigating through a network from end to start and calculating the late dates for
each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the
amount of float each activity has.
Backward pass calculations
9
Solution :
A
5
G
1
C
6
D
9
B
8
E
6
F
3
22,23
5,11
5,13 13,22
13,19
11,14
0,5
22,23
13,22
19,22
16,22
5,13
10,16
0,5
CPM ( ES = LS , EF = LF , TF = FF = 0)
10
Types Of Floats
There are several types of float. The simplest and most important type of float is
Total Float (TF)
 Total float (TF): The maximum amount of time an activity can be delayed from its
early start without delaying the entire project.
TF = LS – ES
or
TF = LF - EF
or
TF = LF - Dur - ES
11
 Free Float: may be defined as the maximum amount of time an activity can be delayed
without delaying the early start of the succeeding activities
FFi = min(ESi+1) - EFi
where min (ESi+1) means the least (i.e., earliest) of the early start dates of succeeding activities
12
In the previous example we can find the free float and total float for each activity as the following :
Activity C’s free float, FF = 11 - 11 = 0 days
And
Activity C’s total float, TF =16 - 11= 5 days …… and so on.
FF
TF
LF
LS
EF
ES
Duration
Activity
0
0
5
0
5
0
5
A
0
0
13
5
13
5
8
B
0
5
16
10
11
5
6
C
0
0
22
13
22
13
9
D
3
3
22
16
19
13
6
E
8
8
22
19
14
11
3
F
0
0
23
22
23
22
1
G
 Critical activity
 Note : We must always realize that FF ≤ TF
13
Node Format
Activity Name
Activity ID
Duration
ES EF
LS LF
TF FF
14
Example
Activity Duration IPA
A 5 -
B 6 A
C 5 A
D 3 A
E 3 B
F 4 B, C
G 4 D
H 7 B,C,G
I 8 E, F
J 2 F
K 3 H, J
L 2 I, J
15
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
16
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
0, 5
0, 5
5, 11
5, 10
5, 8
11, 15
11, 14
8, 12
15, 17
15, 23
12, 19
23, 25
19, 22
25
25
23, 25
22, 25
15, 23
20, 22
15, 22
12, 15
11, 15
11, 15
5, 11
6, 11
8, 11
1
3
1
3
5
3 3
Graphic Solution
17
Activity ES EF LS LF TF FF
A 0 5 0 5 0 0
B 5 11 5 11 0 0
C 5 10 6 11 1 1
D 5 8 8 11 3 0
E 11 14 12 15 1 1
F 11 15 11 15 0 0
G 8 12 11 15 3 0
H 12 19 15 22 3 0
I 15 23 15 23 0 0
J 15 17 20 22 5 2
K 19 22 22 25 3 3
L 23 25 23 25 0 0
Tabular Solution
18
Comments on the Solution
 Near-critical activities may be as important as critical activities
 It is a good practice for the project manager not to give subordinates two sets of
dates
 PM has to choose one set of dates within the range of Early – Late
 Management may reserve a number of days as “management float” or “time contingency”
19
Float Discussion
 Total float –in general- belongs to a path rather than the activity itself
 If an activity uses “its” float, successors may lose some or all of “their” float
 Total float versus free float
20
 The question is: “who owns the float”?
 Float distribution attempts
 Review the contract – what if it is not mentioned?
 Float with resource leveling
 Shifting activities within their float may affect:
 Start / finish dates of succeeding activities
 Resource usage: Labor and equipment (crews)
 Materials: delivery, storage
 Cash flow
21
Lags in Node Networks
 A lag is a minimum compulsory waiting period between the start/finish of an
activity and the start/finish of the successor
 A lead is a negative lag
 The lag is added in the CPM’s forward pass calculations and subtracted in the
backward pass
22
Examples:
 Concrete curing (before formwork stripping or reshoring)
 Asphalt curing (before striping)
 Waiting for a permit to be issued
 Waiting for the delivery of a custom material or equipment
23
Example
Activity Duration IPA Lag
A 5 -
B 3 -
C 6 -
D 7 A
E 7 A
B 4
F 4 A,B,C
G 5 E
F 3
H 6 D
G 2
I 3 D,G
24
C
6
B
3
A
5
G
5
F
4
E
7
D
7
H
6
I
3
4
3
2
PS PF
27
0
0 27
0, 5 5, 12
0, 3
0, 6
7, 14
6, 10
14, 19
21, 27
19, 22
21, 27
24, 27
14, 19
14, 21
7, 14
7, 11
2, 7
0, 3
1, 7
Graphic Solution
25
Activity ES EF LS LF TF FF
A 0 5 2 7 2 0
B 0 3 0 3 0 0
C 0 6 1 7 1 0
D 5 12 14 21 9 7
E 7 14 7 14 0 0
F 6 10 7 11 1 1
G 14 19 14 19 0 0
H 21 27 21 27 0 0
I 19 22 24 27 5 5
Tabular Solution
26
Effect of Imposed Finish Date
 Imposed Finish Date is the project’s completion date, as specified in the contract or
stipulated by the owner
 When compared to the calculated finish date:
 Calculated finish date < imposed finish date
• You are in good shape
• What happens if you enter the imposed date?
 Calculated finish date > imposed finish date
• Negative float appears when you enter the imposed date
• You need to accelerate / crash the schedule
27
Examples with Imposed Finish Dates
Repeat Example 3 with imposed finish date of 28 days
Repeat Example 3 with imposed finish date of 22 days
28
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
0, 5
0, 5
5, 11
5, 10
5, 8
11, 15
11, 14
8, 12
15, 17
15, 23
12, 19
23, 25
19, 22
25
25
23, 25
22, 25
15, 23
20, 22
15, 22
12, 15
11, 15
11, 15
5, 11
6, 11
8, 11
1
3
1
3
5
3 3
With out Imposed finished date
29
Imposed Finish Date > Calculated Finish Date
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
0, 5
3, 8
5, 11
5, 10
5, 8
11, 15
11, 14
8, 12
15, 17
15, 23
12, 19
23, 25
19, 22
25
28
26, 28
25, 28
18, 26
23, 25
18, 25
15, 18
14, 18
14, 18
8, 14
9, 14
11, 14
3 4
6 6 6 6
8
4
3 3
3
3
30
A
5
D
3
B
6
C
5
G
4
E
3
F
4
H
7
I
8
J
2
K
3
L
2
PF
0, 5
-3, 2
5, 11
5, 10
5, 8
11, 15
11, 14
8, 12
15, 17
15, 23
12, 19
23, 25
19, 22
25
22
20, 22
19, 22
12, 20
17, 19
12, 19
9, 12
8, 12
8, 12
2, 8
3, 8
5, 8
-3
-3
-3
-2 -3
-3
-2 2
0 0 0 0
Imposed Finish Date < Calculated Finish Date
31
 Negative float is a situation that occurs when performing an activity even
on its early dates, fails to meet the project’s imposed finish date or other
constraint
 It may occur in one of two cases:
Before construction starts
During construction (after normal start)
Negative Float
32
Event Times in Arrow Networks
 The early event time, TE, is the largest (latest) date obtained to reach an event (going from
start to finish).
 The late event time, TL, is the smallest (earliest) date obtained to reach an event (going from
finish to start).
Example
Perform the CPM calculations, including the event times, for the arrow network shown below.
33
10 30
40
20 60
C
E
B
50
D
F
70
A
G
H
10
5
7
8
9
4
5
8
d1
d2
Arrow network for example
34
The preceding logic is similar to that of the forward and backward passes: When you are going forward, pick
the largest number. When you are going backward, pick the smallest number.
i j
Act. Name
Dur.
TEi
TLi
TEj
TLj
CPM
35
10 30
40
20 60
C
E
B
50
D
F
70
A
G
H
10
5
7
8
9
4
5
8
d1
d2
10
10
7
0
0
15
10
10
19
19
24
27
27
27
(0,10)
(0,10)
(5,10)
(0,5)
(0,7)
(8,15)
(10,18)
(11,19)
(10,19)
(10,19)
(7,11)
(15,19)
(19,24)
(22,27)
(19,27)
(19,27)
36
Definitions
Activity, or task: A basic unit of work as part of the total project that is easily measured and
controlled. It is time- and resource consuming.
Backward pass: The process of navigating through a network from end to start and calculating the
late dates for each activity. The late dates (along with the early dates) determine the critical
activities, the critical path, and the amount of float each activity has.
Critical activity: An activity on the critical path. Any delay in the start or finish of a critical activity will
result in a delay in the entire project.
Critical path: The longest path in a network, from start to finish, including lags and constraints.
.
37
Early dates: The early start date and early finish date of an activity.
Early finish (EF): The earliest date on which an activity can finish within project constraints.
Early start (ES): The earliest date on which an activity can start within project constraints.
Event: A point in time marking a start or an end of an activity. In contrast to an activity, an event does not consume time or
resources.
Forward pass: The process of navigating through a network from start to end and calculating the completion date for the
project and the early dates for each activity.
Late dates: The late start date and late finish date of an activity.
Late finish (LF): The latest date on which an activity can finish without extending the project duration.
Late start (LS): The latest date on which an activity can start without extending the project duration.
38
A
B
C
Improper Proper
A
B
C
PF
(a) Do not end a network with more than one node

More Related Content

PPT
Pert cpm
PPT
Pert cpm
PPTX
Pert and CPM
PPT
Critical Path Method
PPTX
Cpm and pert
PPTX
Critical path method (CPM).pptx
PDF
Lecture - Project, Planning and Control.pdf
PPT
Critical path method (cpm)
Pert cpm
Pert cpm
Pert and CPM
Critical Path Method
Cpm and pert
Critical path method (CPM).pptx
Lecture - Project, Planning and Control.pdf
Critical path method (cpm)

Similar to Lecture 5.pdf (20)

PPTX
Cpm pert
PPT
Cpm n pert lecture 1
PPTX
Networktechniques
PPT
Chapter 12(cpm pert)
PPT
Operation research's CPM techniques
PPTX
Unit 3 PERT.pptx in related to supply chain
PPT
Productions & Operations Management Chapter 03
DOCX
MP assignment for printing
PDF
Planning & Scheduling in Oil and Gas by PM Prodigy.pdf
PPTX
CPM.pptx
PDF
Chapter 6 Scheduling CPM PERT Classes.pdf
PPT
Project Scheduling.ppt
PPTX
Pb602 operation management chapter 7
PPT
chapter 6.ppt
PPTX
SCHEDULING IN PROJECT MANAGEMENT PROJECT SCHEDULE MANAGEMENT
PPT
Management Science : Project SchedulingPert_cpm.ppt
PPT
Critical Path Analysis
PPT
Chapter-2 Solved examples.ppt
PPTX
PDF
Critical path presentation for timely project completion
Cpm pert
Cpm n pert lecture 1
Networktechniques
Chapter 12(cpm pert)
Operation research's CPM techniques
Unit 3 PERT.pptx in related to supply chain
Productions & Operations Management Chapter 03
MP assignment for printing
Planning & Scheduling in Oil and Gas by PM Prodigy.pdf
CPM.pptx
Chapter 6 Scheduling CPM PERT Classes.pdf
Project Scheduling.ppt
Pb602 operation management chapter 7
chapter 6.ppt
SCHEDULING IN PROJECT MANAGEMENT PROJECT SCHEDULE MANAGEMENT
Management Science : Project SchedulingPert_cpm.ppt
Critical Path Analysis
Chapter-2 Solved examples.ppt
Critical path presentation for timely project completion
Ad

Recently uploaded (20)

PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PPTX
Pharma ospi slides which help in ospi learning
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PPTX
Cell Structure & Organelles in detailed.
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
Computing-Curriculum for Schools in Ghana
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
master seminar digital applications in india
PPTX
Orientation - ARALprogram of Deped to the Parents.pptx
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
Final Presentation General Medicine 03-08-2024.pptx
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
Microbial disease of the cardiovascular and lymphatic systems
2.FourierTransform-ShortQuestionswithAnswers.pdf
Pharma ospi slides which help in ospi learning
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Cell Structure & Organelles in detailed.
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
Final Presentation General Medicine 03-08-2024.pptx
Anesthesia in Laparoscopic Surgery in India
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
Weekly quiz Compilation Jan -July 25.pdf
Computing-Curriculum for Schools in Ghana
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
master seminar digital applications in india
Orientation - ARALprogram of Deped to the Parents.pptx
Chinmaya Tiranga quiz Grand Finale.pdf
Ad

Lecture 5.pdf

  • 2. 2 The Critical Path Method (CPM)
  • 3. 3 Who develops the WBS? A WBS is developed by the A/E at the end of the design phase. and/or by the bidders during the proposal (procurement phase).
  • 4. 4 TYPES OF ACTIVITIES 1. Production Activities Those that can be taken directly from plans and specifications 2. Procurement Activities Procurement of material and equipment 3. Management Decision Activities Activities that can be created by management to avoid certain situations Delay Concrete Company Vacation
  • 5. 5 Example Draw the logic network and perform the CPM calculations for the schedule shown next. Duration IPA Activity 5 - A 8 A B 6 A C 9 B D 6 B,C E 3 C F 1 D,E,F G
  • 6. 6 In mathematical terms, the ES for activity j is as follows : ESj =max( EFi ) where (EFi) represents the EF for all preceding activities. Likewise, the EF time for activity j is as follows : EF j= ESj + Dur j where Dur j is the duration of activity j Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity Forward pass calculations
  • 8. 8 In mathematical terms, the late finish LF for activity j is as follows : ( LFj =min(LSk where (LSk) represents the late start date for all succeeding activities. Likewise, the LS time for activity j (LS j) is as follows : LS j= LFj - Dur j where Dur j is the duration of activity Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has. Backward pass calculations
  • 10. 10 Types Of Floats There are several types of float. The simplest and most important type of float is Total Float (TF)  Total float (TF): The maximum amount of time an activity can be delayed from its early start without delaying the entire project. TF = LS – ES or TF = LF - EF or TF = LF - Dur - ES
  • 11. 11  Free Float: may be defined as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities FFi = min(ESi+1) - EFi where min (ESi+1) means the least (i.e., earliest) of the early start dates of succeeding activities
  • 12. 12 In the previous example we can find the free float and total float for each activity as the following : Activity C’s free float, FF = 11 - 11 = 0 days And Activity C’s total float, TF =16 - 11= 5 days …… and so on. FF TF LF LS EF ES Duration Activity 0 0 5 0 5 0 5 A 0 0 13 5 13 5 8 B 0 5 16 10 11 5 6 C 0 0 22 13 22 13 9 D 3 3 22 16 19 13 6 E 8 8 22 19 14 11 3 F 0 0 23 22 23 22 1 G  Critical activity  Note : We must always realize that FF ≤ TF
  • 13. 13 Node Format Activity Name Activity ID Duration ES EF LS LF TF FF
  • 14. 14 Example Activity Duration IPA A 5 - B 6 A C 5 A D 3 A E 3 B F 4 B, C G 4 D H 7 B,C,G I 8 E, F J 2 F K 3 H, J L 2 I, J
  • 16. 16 A 5 D 3 B 6 C 5 G 4 E 3 F 4 H 7 I 8 J 2 K 3 L 2 PF 0, 5 0, 5 5, 11 5, 10 5, 8 11, 15 11, 14 8, 12 15, 17 15, 23 12, 19 23, 25 19, 22 25 25 23, 25 22, 25 15, 23 20, 22 15, 22 12, 15 11, 15 11, 15 5, 11 6, 11 8, 11 1 3 1 3 5 3 3 Graphic Solution
  • 17. 17 Activity ES EF LS LF TF FF A 0 5 0 5 0 0 B 5 11 5 11 0 0 C 5 10 6 11 1 1 D 5 8 8 11 3 0 E 11 14 12 15 1 1 F 11 15 11 15 0 0 G 8 12 11 15 3 0 H 12 19 15 22 3 0 I 15 23 15 23 0 0 J 15 17 20 22 5 2 K 19 22 22 25 3 3 L 23 25 23 25 0 0 Tabular Solution
  • 18. 18 Comments on the Solution  Near-critical activities may be as important as critical activities  It is a good practice for the project manager not to give subordinates two sets of dates  PM has to choose one set of dates within the range of Early – Late  Management may reserve a number of days as “management float” or “time contingency”
  • 19. 19 Float Discussion  Total float –in general- belongs to a path rather than the activity itself  If an activity uses “its” float, successors may lose some or all of “their” float  Total float versus free float
  • 20. 20  The question is: “who owns the float”?  Float distribution attempts  Review the contract – what if it is not mentioned?  Float with resource leveling  Shifting activities within their float may affect:  Start / finish dates of succeeding activities  Resource usage: Labor and equipment (crews)  Materials: delivery, storage  Cash flow
  • 21. 21 Lags in Node Networks  A lag is a minimum compulsory waiting period between the start/finish of an activity and the start/finish of the successor  A lead is a negative lag  The lag is added in the CPM’s forward pass calculations and subtracted in the backward pass
  • 22. 22 Examples:  Concrete curing (before formwork stripping or reshoring)  Asphalt curing (before striping)  Waiting for a permit to be issued  Waiting for the delivery of a custom material or equipment
  • 23. 23 Example Activity Duration IPA Lag A 5 - B 3 - C 6 - D 7 A E 7 A B 4 F 4 A,B,C G 5 E F 3 H 6 D G 2 I 3 D,G
  • 24. 24 C 6 B 3 A 5 G 5 F 4 E 7 D 7 H 6 I 3 4 3 2 PS PF 27 0 0 27 0, 5 5, 12 0, 3 0, 6 7, 14 6, 10 14, 19 21, 27 19, 22 21, 27 24, 27 14, 19 14, 21 7, 14 7, 11 2, 7 0, 3 1, 7 Graphic Solution
  • 25. 25 Activity ES EF LS LF TF FF A 0 5 2 7 2 0 B 0 3 0 3 0 0 C 0 6 1 7 1 0 D 5 12 14 21 9 7 E 7 14 7 14 0 0 F 6 10 7 11 1 1 G 14 19 14 19 0 0 H 21 27 21 27 0 0 I 19 22 24 27 5 5 Tabular Solution
  • 26. 26 Effect of Imposed Finish Date  Imposed Finish Date is the project’s completion date, as specified in the contract or stipulated by the owner  When compared to the calculated finish date:  Calculated finish date < imposed finish date • You are in good shape • What happens if you enter the imposed date?  Calculated finish date > imposed finish date • Negative float appears when you enter the imposed date • You need to accelerate / crash the schedule
  • 27. 27 Examples with Imposed Finish Dates Repeat Example 3 with imposed finish date of 28 days Repeat Example 3 with imposed finish date of 22 days
  • 28. 28 A 5 D 3 B 6 C 5 G 4 E 3 F 4 H 7 I 8 J 2 K 3 L 2 PF 0, 5 0, 5 5, 11 5, 10 5, 8 11, 15 11, 14 8, 12 15, 17 15, 23 12, 19 23, 25 19, 22 25 25 23, 25 22, 25 15, 23 20, 22 15, 22 12, 15 11, 15 11, 15 5, 11 6, 11 8, 11 1 3 1 3 5 3 3 With out Imposed finished date
  • 29. 29 Imposed Finish Date > Calculated Finish Date A 5 D 3 B 6 C 5 G 4 E 3 F 4 H 7 I 8 J 2 K 3 L 2 PF 0, 5 3, 8 5, 11 5, 10 5, 8 11, 15 11, 14 8, 12 15, 17 15, 23 12, 19 23, 25 19, 22 25 28 26, 28 25, 28 18, 26 23, 25 18, 25 15, 18 14, 18 14, 18 8, 14 9, 14 11, 14 3 4 6 6 6 6 8 4 3 3 3 3
  • 30. 30 A 5 D 3 B 6 C 5 G 4 E 3 F 4 H 7 I 8 J 2 K 3 L 2 PF 0, 5 -3, 2 5, 11 5, 10 5, 8 11, 15 11, 14 8, 12 15, 17 15, 23 12, 19 23, 25 19, 22 25 22 20, 22 19, 22 12, 20 17, 19 12, 19 9, 12 8, 12 8, 12 2, 8 3, 8 5, 8 -3 -3 -3 -2 -3 -3 -2 2 0 0 0 0 Imposed Finish Date < Calculated Finish Date
  • 31. 31  Negative float is a situation that occurs when performing an activity even on its early dates, fails to meet the project’s imposed finish date or other constraint  It may occur in one of two cases: Before construction starts During construction (after normal start) Negative Float
  • 32. 32 Event Times in Arrow Networks  The early event time, TE, is the largest (latest) date obtained to reach an event (going from start to finish).  The late event time, TL, is the smallest (earliest) date obtained to reach an event (going from finish to start). Example Perform the CPM calculations, including the event times, for the arrow network shown below.
  • 34. 34 The preceding logic is similar to that of the forward and backward passes: When you are going forward, pick the largest number. When you are going backward, pick the smallest number. i j Act. Name Dur. TEi TLi TEj TLj CPM
  • 36. 36 Definitions Activity, or task: A basic unit of work as part of the total project that is easily measured and controlled. It is time- and resource consuming. Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has. Critical activity: An activity on the critical path. Any delay in the start or finish of a critical activity will result in a delay in the entire project. Critical path: The longest path in a network, from start to finish, including lags and constraints. .
  • 37. 37 Early dates: The early start date and early finish date of an activity. Early finish (EF): The earliest date on which an activity can finish within project constraints. Early start (ES): The earliest date on which an activity can start within project constraints. Event: A point in time marking a start or an end of an activity. In contrast to an activity, an event does not consume time or resources. Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity. Late dates: The late start date and late finish date of an activity. Late finish (LF): The latest date on which an activity can finish without extending the project duration. Late start (LS): The latest date on which an activity can start without extending the project duration.
  • 38. 38 A B C Improper Proper A B C PF (a) Do not end a network with more than one node