Agenda
• Project Time
Management
• Project Cost Management
• Mid Term
ATEC 2340
Project Management for Arts & Technology - I
Project Management Body of Knowledge (PMBOK)
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Project Time Management
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Before we begin…
Project Time Management = Project Scheduling
Because, 95 % of the time when people think about project management, they
think about schedule.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Importance of Project Schedules…
• Managers often cite delivering projects on time as one of their biggest
challenges.
• Schedule issues are the main reason for conflicts on projects, especially during
the second half of projects.
• Time has the least amount of flexibility; it passes no matter what happens on
a project.
*The Standish Group, “Latest Standish Group CHAOS Report Shows Project Success Rates Have Improved by 50%,”
(www.standishgroup.com) (March 25, 2003
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Project Time Management: The Big Picture
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Project Time Management Processes
• Activity definition: Identifying the specific activities that the project team
members and stakeholders must perform to produce the project deliverables.
• Activity sequencing: Identifying and documenting the relationships between
project activities.
• Activity resource estimating: Estimating how many resources a project team
should use to perform project activities.
• Activity duration estimating: Estimating the number of work periods that are
needed to complete individual activities.
• Schedule development: Analyzing activity sequences, activity resource
estimates, and activity duration estimates to create the project schedule.
• Schedule control: Controlling and managing changes to the project schedule.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Activity Definition
• Activity List:
– An activity list is a tabulation of activities to be included on a project schedule.
– All activities necessary and sufficient to produce the product deliverables
– Defined in sufficient detail to promote understanding by project team
• Activity Attributes:
Activity attributes provide more information about each activity, such as
predecessors, successors, logical relationships, leads and lags, resource
requirements, constraints, imposed dates, and assumptions related to the
activity.
– Activity identifier and code
– Activity description
– Assumption and constraints
– Predecessor and Successor Activities
– Resource Requirements
– Team Member Responsible for Performing the Work
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Milestones
• A milestone is a significant event that normally has no duration.
• It often takes several activities and a lot of work to complete a milestone.
• Milestones are useful tools for setting schedule goals and monitoring
progress.
• Examples include completion and customer sign-off on key documents and
completion of specific products.
ATEC 2340
Project Management for Arts & Technology - I
Project Time Management: The Big Picture
ATEC 2340
Project Management for Arts & Technology - I
Activity Sequencing
• Identifies the dependencies among the schedule activities and orders the
activities accordingly
– A task has a dependency if it involves an activity, resource or work
product which is subsequently required by another task
• Tasks may have dependencies because they require the same resource
A B
Activity A is a predecessor
of activity B
Activity B is a successor of
activity A
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Precedence Relationships
• Finish to Start
– Initiation of the successor activity depends upon completion of the
predecessor activity
• Finish to Finish
– The completion of the successor activity depends upon the completion of
the predecessor activity
• Start to start
– The initiation of the successor activity depends upon the initiation of the
predecessor activity
• Start to finish
– The completion of the successor activity depends upon the initiation of
the predecessor activity
ATEC 2340
Project Management for Arts & Technology - I
Precedence Relationships
ATEC 2340.001.F16 Sagar Wadhwani http://www.stellman-greene.com
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Three types of Dependencies
• Mandatory Dependencies
– Inherent to the schedule activities (e.g. software must be developed
before it can be tested)
• Discretionary Dependencies
– Dependencies at the discretion of the project team (e.g. acceptance test
with marketing before accounting)
• External Dependencies
– Involves a relationship between a project activity and a non-project
activity (e.g. Windows Vista Delivered)
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Network Diagram
• Network diagrams are the preferred technique for showing activity
sequencing.
• A network diagram is a schematic display of the logical relationships among,
or sequencing of, project activities.
• Two main formats are the arrow and precedence diagramming methods.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
A Sample Network Diagram
ATEC 2340
Project Management for Arts & Technology - I
Project Time Management: The Big Picture
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Activity Resource Estimating
• Before estimating activity durations, you must have a good idea of the
quantity and type of resources that will be assigned to each activity.
• Consider important issues in estimating resources:
– How difficult will it be to complete specific activities on this project?
– What is the organization’s history in doing similar activities?
– Are the required resources available?
ATEC 2340
Project Management for Arts & Technology - I
Project Time Management: The Big Picture
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Activity Duration Estimating
• Duration includes the actual amount of time worked on an activity plus the
elapsed time.
• Effort is the number of workdays or work hours required to complete a task.
• Effort does not normally equal duration.
• People doing the work should help create estimates, and an expert should
review them.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Developing the Schedule
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Schedule Development
• Uses results of the other time management processes to determine the start
and end dates of the project.
• Ultimate goal is to create a realistic project schedule that provides a basis for
monitoring project progress for the time dimension of the project.
• Important tools and techniques include Gantt charts, critical path analysis,
critical chain scheduling, and PERT analysis.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Gantt Charts
Gantt charts provide a standard format for displaying project schedule
information by listing project activities and their corresponding start and finish
dates in a calendar format.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
A Sample Gantt Chart
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Adding Milestones to Gantt Charts
• Many people like to focus on meeting milestones, especially for large projects.
• Milestones emphasize important events or accomplishments in projects.
• You typically create milestone by entering tasks that have a zero duration, or
you can mark any task as a milestone.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Schedule Control
• Perform reality checks on schedules.
• Allow for contingencies.
• Don’t plan for everyone to work at 100 percent capacity all the time.
• Hold progress meetings with stakeholders and be clear and honest in
communicating schedule issues.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Reality Checks on Scheduling
• Review the draft schedule or estimated completion date in the project
charter.
• Prepare a more detailed schedule with the project team.
• Make sure the schedule is realistic and followed.
• Alert top management well in advance if there are schedule problems.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Using Software to assist in Time Management
• Software for facilitating communication helps people exchange schedule-
related information.
• Decision support models help analyze trade-offs that can be made.
• Project management software can help in various time management areas.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Project Cost Management
ATEC 2340
Project Management for Arts & Technology - I
Project Management Body of Knowledge (PMBOK)
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Project Cost Management
• Cost is a resource sacrificed or foregone to achieve a specific objective or
something given up in exchange
– Costs are usually measured in monetary units like dollars
• Project cost management includes the processes required to ensure that the
project is completed within an approved budget
– Project managers must make sure their projects are well defined, have
accurate time and cost estimates and have a realistic budget that they
were involved in approving
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Project Cost Management Process
1. Plan Cost Management
• Establish the policies and procedures for planning and managing
project costs.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Project Cost Management Process
1. Plan Cost Management
2. Estimate Costs
• Develop an estimate or approximation of the monetary resources
needed to complete project activities.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Project Cost Management Process
1. Plan Cost Management
2. Estimate Costs
3. Determine Budget
• Combining the total estimated costs of individual activities – plus
contingency – to develop a cost baseline, also known as approved
budget.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Project Cost Management Process
1. Plan Cost Management
2. Estimate Costs
3. Determine Budget
4. Control Costs
• Monitor and manage costs, as based on status of activities.
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Plan Cost Management
Inputs:
• Project Management Documents to date
• Enterprise & Environmental Factors
• Organizational Process & Policies
Tools and Techniques:
• Expert Judgement
• Financial Strategies such as Purchasing, renting, leasing, Internal or
external funding or investments
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Estimate Costs
Inputs:
• Cost Management Plan
• Scope baseline
• Project schedule
Tools and Techniques:
• Expert judgement
• Analogous estimating - Similar project
• Bottom-up or Rolled-up - Estimate individual activities and roll up
• Three point estimating - Most likely, Optimistic, Pessimistic/worst case
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Determine Budget
Inputs:
• Cost management plan
• Scope
• Schedule
• Activity cost estimates
• Resource calendars
• Agreements
• Organizational rules and tools
ATEC
ARTS & TECHNOLOGY
ATEC 2340
Project Management for Arts & Technology - I
Determine Budget
Tools and Techniques:
• Expert Judgement
• Cost Aggregation – take details and roll up
• Reserve analysis – estimates of contingency
• Analogous estimates – similar projects
• Funding limits and estimated costs
Atec 2340 lecture7
Atec 2340 lecture7

More Related Content

PPTX
4370 Week Two: History and Overview
PPTX
Atec 4370 lecture3
PPTX
Atec 2340 lecture6
PPTX
ATEC 2340/4370 Lecture 4
PDF
Best Practices: Project Documentation and Construction Management
PDF
Promo_Epc project rule of credit and progress measurement
PDF
Proposed Project Office Strategy
PPTX
Pmp – pmbok 5th edition chapter4 project integration management final
4370 Week Two: History and Overview
Atec 4370 lecture3
Atec 2340 lecture6
ATEC 2340/4370 Lecture 4
Best Practices: Project Documentation and Construction Management
Promo_Epc project rule of credit and progress measurement
Proposed Project Office Strategy
Pmp – pmbok 5th edition chapter4 project integration management final

What's hot (18)

PPTX
Managing & Supervising Projects, Consultants & Contractors
PDF
Project management
PDF
Construction Project Management
PPTX
The Program Management Framework—What's New?
PPTX
Project Management
PPT
Lecture 1
PPT
Episode 23 : PROJECT TIME MANAGEMENT
PPT
Software Project Management( lecture 1)
PPT
Capello Pw 2011
PDF
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
PPT
Project Management
DOCX
Pm chapter 7
PPTX
Project planning and scheduling
PPT
Episode 23 : PROJECT TIME MANAGEMENT
PPTX
4.project integrationmanagement
PDF
JC-Real-Time-Operational-Readiness
PDF
Consultancy brochure_Europe (final)
PDF
Project Management Project 1
Managing & Supervising Projects, Consultants & Contractors
Project management
Construction Project Management
The Program Management Framework—What's New?
Project Management
Lecture 1
Episode 23 : PROJECT TIME MANAGEMENT
Software Project Management( lecture 1)
Capello Pw 2011
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
Project Management
Pm chapter 7
Project planning and scheduling
Episode 23 : PROJECT TIME MANAGEMENT
4.project integrationmanagement
JC-Real-Time-Operational-Readiness
Consultancy brochure_Europe (final)
Project Management Project 1
Ad

Similar to Atec 2340 lecture7 (20)

PPTX
Time management pressent
PPTX
Time management
PPT
Project time management
PPTX
Itpm ch6 project schedule management notes
PDF
Lecture -19 & 20.ppt.pdf
PPT
Project time management
PPT
105 project time management
DOCX
Project TimeIST4055Chapter 6Now that you have the Sc.docx
PPTX
Introduction to Software Project Management: Key Concepts, Objectives, Challe...
PPTX
PMNM101 Lesson 2 2022.pptx
PPTX
PMP Training - 06 project time management2
PDF
A brief on project time management
PPTX
Pmp session 3
PPTX
4) PTM & PCM .pptx
PPTX
Project time management involves the processes required to ensure timely comp...
PPTX
978285452340_06.pptx
PDF
SPM chapter 06 - Activity Planning by Bob Hughes
PPTX
Unit-3 Activity planning and Scheduling.pptx
DOCX
MGT 3302, Introduction to Project Management 1 Cou.docx
PPTX
Software Project Management UNIT 3 Activity planning
Time management pressent
Time management
Project time management
Itpm ch6 project schedule management notes
Lecture -19 & 20.ppt.pdf
Project time management
105 project time management
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Introduction to Software Project Management: Key Concepts, Objectives, Challe...
PMNM101 Lesson 2 2022.pptx
PMP Training - 06 project time management2
A brief on project time management
Pmp session 3
4) PTM & PCM .pptx
Project time management involves the processes required to ensure timely comp...
978285452340_06.pptx
SPM chapter 06 - Activity Planning by Bob Hughes
Unit-3 Activity planning and Scheduling.pptx
MGT 3302, Introduction to Project Management 1 Cou.docx
Software Project Management UNIT 3 Activity planning
Ad

Recently uploaded (20)

PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PDF
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PDF
Empathic Computing: Creating Shared Understanding
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PPTX
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PDF
MIND Revenue Release Quarter 2 2025 Press Release
PPTX
Understanding_Digital_Forensics_Presentation.pptx
PDF
Spectral efficient network and resource selection model in 5G networks
PDF
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
PDF
Machine learning based COVID-19 study performance prediction
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PPTX
Programs and apps: productivity, graphics, security and other tools
PPTX
Big Data Technologies - Introduction.pptx
PDF
Electronic commerce courselecture one. Pdf
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
Per capita expenditure prediction using model stacking based on satellite ima...
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
Empathic Computing: Creating Shared Understanding
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
MIND Revenue Release Quarter 2 2025 Press Release
Understanding_Digital_Forensics_Presentation.pptx
Spectral efficient network and resource selection model in 5G networks
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
Machine learning based COVID-19 study performance prediction
Advanced methodologies resolving dimensionality complications for autism neur...
Programs and apps: productivity, graphics, security and other tools
Big Data Technologies - Introduction.pptx
Electronic commerce courselecture one. Pdf
Building Integrated photovoltaic BIPV_UPV.pdf

Atec 2340 lecture7

  • 1. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I
  • 2. ATEC 2340 Project Management for Arts & Technology - I Agenda • Project Time Management • Project Cost Management • Mid Term
  • 3. ATEC 2340 Project Management for Arts & Technology - I Project Management Body of Knowledge (PMBOK)
  • 4. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Project Time Management
  • 5. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Before we begin… Project Time Management = Project Scheduling Because, 95 % of the time when people think about project management, they think about schedule.
  • 6. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Importance of Project Schedules… • Managers often cite delivering projects on time as one of their biggest challenges. • Schedule issues are the main reason for conflicts on projects, especially during the second half of projects. • Time has the least amount of flexibility; it passes no matter what happens on a project. *The Standish Group, “Latest Standish Group CHAOS Report Shows Project Success Rates Have Improved by 50%,” (www.standishgroup.com) (March 25, 2003
  • 7. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Project Time Management: The Big Picture
  • 8. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Project Time Management Processes • Activity definition: Identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables. • Activity sequencing: Identifying and documenting the relationships between project activities. • Activity resource estimating: Estimating how many resources a project team should use to perform project activities. • Activity duration estimating: Estimating the number of work periods that are needed to complete individual activities. • Schedule development: Analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule. • Schedule control: Controlling and managing changes to the project schedule.
  • 9. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Activity Definition • Activity List: – An activity list is a tabulation of activities to be included on a project schedule. – All activities necessary and sufficient to produce the product deliverables – Defined in sufficient detail to promote understanding by project team • Activity Attributes: Activity attributes provide more information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity. – Activity identifier and code – Activity description – Assumption and constraints – Predecessor and Successor Activities – Resource Requirements – Team Member Responsible for Performing the Work
  • 10. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Milestones • A milestone is a significant event that normally has no duration. • It often takes several activities and a lot of work to complete a milestone. • Milestones are useful tools for setting schedule goals and monitoring progress. • Examples include completion and customer sign-off on key documents and completion of specific products.
  • 11. ATEC 2340 Project Management for Arts & Technology - I Project Time Management: The Big Picture
  • 12. ATEC 2340 Project Management for Arts & Technology - I Activity Sequencing • Identifies the dependencies among the schedule activities and orders the activities accordingly – A task has a dependency if it involves an activity, resource or work product which is subsequently required by another task • Tasks may have dependencies because they require the same resource A B Activity A is a predecessor of activity B Activity B is a successor of activity A
  • 13. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Precedence Relationships • Finish to Start – Initiation of the successor activity depends upon completion of the predecessor activity • Finish to Finish – The completion of the successor activity depends upon the completion of the predecessor activity • Start to start – The initiation of the successor activity depends upon the initiation of the predecessor activity • Start to finish – The completion of the successor activity depends upon the initiation of the predecessor activity
  • 14. ATEC 2340 Project Management for Arts & Technology - I Precedence Relationships ATEC 2340.001.F16 Sagar Wadhwani http://www.stellman-greene.com
  • 15. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Three types of Dependencies • Mandatory Dependencies – Inherent to the schedule activities (e.g. software must be developed before it can be tested) • Discretionary Dependencies – Dependencies at the discretion of the project team (e.g. acceptance test with marketing before accounting) • External Dependencies – Involves a relationship between a project activity and a non-project activity (e.g. Windows Vista Delivered)
  • 16. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Network Diagram • Network diagrams are the preferred technique for showing activity sequencing. • A network diagram is a schematic display of the logical relationships among, or sequencing of, project activities. • Two main formats are the arrow and precedence diagramming methods.
  • 17. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I A Sample Network Diagram
  • 18. ATEC 2340 Project Management for Arts & Technology - I Project Time Management: The Big Picture
  • 19. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Activity Resource Estimating • Before estimating activity durations, you must have a good idea of the quantity and type of resources that will be assigned to each activity. • Consider important issues in estimating resources: – How difficult will it be to complete specific activities on this project? – What is the organization’s history in doing similar activities? – Are the required resources available?
  • 20. ATEC 2340 Project Management for Arts & Technology - I Project Time Management: The Big Picture
  • 21. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Activity Duration Estimating • Duration includes the actual amount of time worked on an activity plus the elapsed time. • Effort is the number of workdays or work hours required to complete a task. • Effort does not normally equal duration. • People doing the work should help create estimates, and an expert should review them.
  • 22. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Developing the Schedule
  • 23. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Schedule Development • Uses results of the other time management processes to determine the start and end dates of the project. • Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project. • Important tools and techniques include Gantt charts, critical path analysis, critical chain scheduling, and PERT analysis.
  • 24. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Gantt Charts Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.
  • 25. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I A Sample Gantt Chart
  • 26. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Adding Milestones to Gantt Charts • Many people like to focus on meeting milestones, especially for large projects. • Milestones emphasize important events or accomplishments in projects. • You typically create milestone by entering tasks that have a zero duration, or you can mark any task as a milestone.
  • 27. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Schedule Control • Perform reality checks on schedules. • Allow for contingencies. • Don’t plan for everyone to work at 100 percent capacity all the time. • Hold progress meetings with stakeholders and be clear and honest in communicating schedule issues.
  • 28. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Reality Checks on Scheduling • Review the draft schedule or estimated completion date in the project charter. • Prepare a more detailed schedule with the project team. • Make sure the schedule is realistic and followed. • Alert top management well in advance if there are schedule problems.
  • 29. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Using Software to assist in Time Management • Software for facilitating communication helps people exchange schedule- related information. • Decision support models help analyze trade-offs that can be made. • Project management software can help in various time management areas.
  • 30. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Project Cost Management
  • 31. ATEC 2340 Project Management for Arts & Technology - I Project Management Body of Knowledge (PMBOK)
  • 32. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Project Cost Management • Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange – Costs are usually measured in monetary units like dollars • Project cost management includes the processes required to ensure that the project is completed within an approved budget – Project managers must make sure their projects are well defined, have accurate time and cost estimates and have a realistic budget that they were involved in approving
  • 33. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Project Cost Management Process 1. Plan Cost Management • Establish the policies and procedures for planning and managing project costs.
  • 34. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Project Cost Management Process 1. Plan Cost Management 2. Estimate Costs • Develop an estimate or approximation of the monetary resources needed to complete project activities.
  • 35. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Project Cost Management Process 1. Plan Cost Management 2. Estimate Costs 3. Determine Budget • Combining the total estimated costs of individual activities – plus contingency – to develop a cost baseline, also known as approved budget.
  • 36. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Project Cost Management Process 1. Plan Cost Management 2. Estimate Costs 3. Determine Budget 4. Control Costs • Monitor and manage costs, as based on status of activities.
  • 37. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Plan Cost Management Inputs: • Project Management Documents to date • Enterprise & Environmental Factors • Organizational Process & Policies Tools and Techniques: • Expert Judgement • Financial Strategies such as Purchasing, renting, leasing, Internal or external funding or investments
  • 38. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Estimate Costs Inputs: • Cost Management Plan • Scope baseline • Project schedule Tools and Techniques: • Expert judgement • Analogous estimating - Similar project • Bottom-up or Rolled-up - Estimate individual activities and roll up • Three point estimating - Most likely, Optimistic, Pessimistic/worst case
  • 39. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Determine Budget Inputs: • Cost management plan • Scope • Schedule • Activity cost estimates • Resource calendars • Agreements • Organizational rules and tools
  • 40. ATEC ARTS & TECHNOLOGY ATEC 2340 Project Management for Arts & Technology - I Determine Budget Tools and Techniques: • Expert Judgement • Cost Aggregation – take details and roll up • Reserve analysis – estimates of contingency • Analogous estimates – similar projects • Funding limits and estimated costs