SlideShare a Scribd company logo
Basic System Scaffold
KNOWLEDGE BASED
SOLUTIONS
CUPLOK
PROPRIETARY SCAFFOLDING
Ring scaffold node or connection point Kwikstage scaffold node
KWIKSTAGE
PROPRIETARY SCAFFOLDING
Rapid scaffold node or connection point Cuplok scaffold node or connection point
Strong winds tore a sheeted scaffolding system from this building.
The Cuplok Scaffold System is a
fully galvanized multi purpose steel
scaffold for general access and
supporting vertical loads.
The principal feature of the cuplok
modular system is the unique
method of connecting ledgers &
transoms to the standard.
In one single action without the use
of any loose component such as
nuts, bolts, wedges.
INSPECTION
Before commencing the erection of any Cuplok Scaffold, great care
should be taken to see that the ground is suitable.
On soft or made-up ground the scaffold should be erected on timber sole
plates of appropriate size. Bricks or blocks should not be used.
The scaffold should be started on the highest part of the ground – this will
make levelling easier as the scaffolding progresses horizontally.
Always check whether or not an inside board platform of one, two or three
boards will be required. If so this will determine the distance of the
scaffold from the building.
SCAFFOLD STABILITY
The scaffold must be suitably tied to a sound structure, all ties must be inserted
as each required level and spacing is reached.
Attachment must be to the components specified. The scaffolder can attach, in
order of preference:
At any position along a fully fastened ledger above head level.
At any position along a fully fastened guardrail at waist level where the scaffold
extends at least one lift above the level at which the scaffolder is working.
At any position along a fully fastened ledger supporting the platform on which
the scaffolder is working (only recommended when it is not possible to attach
above head or waist level)
To transoms, in the lift above which are fixed at both ends.
NEVER CLIP TO:
• Cuplok Standards (Verticals)
• Transoms below foot level
• Ledgers or Transoms which have not been fully fastened.
• Weak anchoring points
STRENGTH
Cuplok independent tied access scaffolds built up to 2.5m bays have a
capability of 3kN (300kg) per square meter.
For other applications, such as birdcage, mobile towers and staircases the
loadings may vary, and advice should be sought from the MIM
(manufacturers instruction manual)
PLATFORM LOADINGS - WORKING LIFTS
2m lift access scaffolds: 1.5kN/m2
1.5m bricklayers scaffold
for 1 platform: 3.0kN/m2
or 2 platforms: 1 at 3.0kN/m2
& 1 at 1.5kN/m2
COMPONENTS
COMPONENTS
COMPONENTS
ASSEMBLY
ASSEMBLY
Layout out the ledger and transoms for the
first bay in their approximate positions.
Then insert an adjustable base jack into
each of the first pair of standards.
ASSEMBLY CONT.…
Connect the standards with a transom in
the lowest cup joint by inserting the blades
into the cups.
Level the transom.
Always start the scaffold with a three meter
standard on the outside and a two meter
standard on the inside.
joints are staggered.
ASSEMBLY CONT.….
With one person still holding the first pair of
standards, the second person inserts a
jack into the third standard and connects it
to the first pair with a ledger.
The upper cup can then be dropped
temporarily into the locking position.
The structure is now self supporting and
the fourth standard can now be connected
by a further ledger and transom and the
bay levelled.
Once the base lift has been completely
levelled, your spirit level will no longer be
required.
USING THE OMEGA BATTEN SYSTEM
The same erection procedure is adopted for the Omega Batten System as for
the Scaffold Board System, except that the Omega top hat type transom Is
used in place of the tubular transom.
No intermediate board supports will be required.
The first bay of Cuplok is completed by locating the upper ledgers and
transoms.
It is now a simple matter to extend the scaffold structure by connecting
ledgers, transoms and standards to the existing bay.
The top fixing cups can now be secured with a hammer. The scaffold should
USING THE OMEGA BATTEN SYSTEM
USING THE OMEGA BATTEN SYSTEM CONT.….
Now be secured by the ties/anchors or
equivalent methods at the earliest
opportunity
USING THE OMEGA BATTEN SYSTEM CONT.….
The working platform can now be constructed.
To ensure safe erection, alteration and dismantling of the scaffolding it is
important that the procedures outlined in the Guidance Note SG4:10 is
followed.
In summary, a minimum of three boards should be placed from below for
erectors and single guard rails should be installed as work progresses along
each lift (double guard rails and toe boards will be required to complete).
Scaffolders' should safely clip on to ledgers or guard rails at any height or
above, Full body harnesses should be worn and lanyards attached.
USING THE OMEGA BATTEN SYSTEM CONT.….
Intermediate transoms are secured at
strategic points (1.2m and 1.5m support
frequency) across the ledgers to support
38mm scaffold boards.
The scaffold boards and toe boards can
now be positioned.
Two standard ledgers can be located 0.5
and 1.0 meters above the working platform
to form the double guardrails.
USING THE OMEGA BATTEN SYSTEM CONT.….
Additional lifts can now be constructed
simply by adding further standards on to
the spigots of the lower lift, and connecting
them with ledgers and transoms.
When swivel face braces are used, these
are located at the cup joints and should
span from lift level to lift level (see face
bracing overleaf).
CUPLOK COMPONENTS
Standards
Cuplok Standards are made from a high
grade steel tube and are identified by a red
flash at the bottom.
Top cups have 4 lugs.
Earlier stocks were made from a different
grade steel and carry slightly less load.
For all normal access scaffold either type is
suitable.
LEDGERS/TRANSOMS
Cuplok tubular ledgers are also used for transoms or guardrails and are fully
interchangeable.
Cuplok tubular ledgers are used with standard boards.
Omega transoms are used with timber or steel battens.
Intermediate Transoms used to provide intermediate support to scaffold boards.
Also used at board ends.
They are fitted with a wedge operated lock to prevent accidental sliding in use.
BASE JACKS
Cuplok Universal jacks must always be
used in conjunction with Head/Base plates,
Sitting on scaffold board or other suitable
sole plates as in normal scaffolding
practice.
The jack must always be fitted so that the
unthreaded portion is inside the standard to
prevent the minimum overlap in the tube
being reduced.
SCAFFOLD BOARDS
All standard scaffold boards are suitable for
use with Cuplok when laid over tubular
transoms.
They safely span distances between 1.2m
and 1.5m for most types, but care must be
taken to check the embossed bands at the
end to determine the max permissible
span.
Intermediate transoms must be used to
limit the span and also to give support to
the ends.
SCAFFOLD BOARDS
Cuplok Battens, both steel and timber, are
suitable for spans up to 2.5m without
intermediate support for loadings of up to
3kN/m2.
Toe boards, Can be provided by scaffold
boards, timber or steel battens using the
appropriate clips from the Cuplok range.
The broad principles applied to tubular
scaffolding also apply to the use of
Cuplok with scaffold boards:
Provided adequate number of transoms
supporting Scaffolding Boards
SCAFFOLD BOARDS
GUARDRAILS
The standard heights for guard rails
(approx. 0.5m to 1.0m) are predetermined
by the Cuplok System.
Brick guard panels may be used with
Cuplok.
Double guard rails and toe boards must
always be provided.
SPIGOT PINS
Only required where resistance to uplift is
required and would be required when
scaffold projects above last tie, or when
using hop-up brackets, or with crane
handled assemblies.
Spigot pins should be used to lock the
standards against uplift at all joints down to
the last tied lift below the hop-ups.
On a scaffold where the brackets will be
moved, spigot pins should be used
throughout at time of erection to minimize
risk of omission during modifying of
platform levels.
CORNERS AND RETURNS
Rigid corners are formed in Cuplok by
using a 1.3m square corner bay.
For scaffolds with scaffold boards, check
the Cuplok return devices (or tube and
fittings) are used to connect the two runs at
each level.
For scaffolds fitted with battens an Omega
Return Transom is used. In both cases
attention must be given to providing proper
toe boards and this may involve cutting
boards to suit the various dimensions of
the corners.
Further information is contained in the
Cuplok Users Manual.
HOP-UP BRACKETS
The maximum permitted loading on hop-up
brackets is as follows:
1 board: 3kN/m2
2 board: 1.5kN/m2
3 board: 0.75kN/m2
DIAGONAL BRACING
Face Bracing
• One bay of bracing to the full height is required every 8 bays (20m).
• On short runs up to 4 bays (10m), one braced bay should be provided.
• Over 10m at least two bays of bracing are required.
•As only one blade can be located at each node point, parallel bracing is
used.
•Braces must go from platform level to platform level.
•Note that the bottom brace is always fitted in a 1.0 or 1.5m lift and
should be of the appropriate size.
LEDGER BRACE AND PLAN BRACING
The Cuplok node connection is extremely rigid and ledger bracing is not normally
required.
On very high scaffolds it may be specified to increase the load capacity but all
such work should be referred to an BS/EN design standard.
Plan bracing is also uncommon and should be the subject of consideration by
the design.
When the hop-up level occurs between tied levels, ledger bracing must be used
at each lift down to the next tie.
SG4:05 ‘PREVENTING FALLS IN SCAFFOLDING’
The publication of the NASC Guidance Note, “Preventing falls in Scaffolding
and False work” (SG4:05-2006), was an important move forward in preventing
falls by scaffolds.
However, the scope of the document extends to steel tube and fittings
scaffolds, and not to system scaffolds in respect of anchor points.
The document (commended by the Health and safety Executive) recommends
that one should follow the System Scaffold Manufacturers advice as to suitable
anchor points for safety harness lanyards.
FALLS FROM HEIGHT
Falls account for more than half of the fatal accidents in construction.
The aim of the Regulations is to prevent falls from any height, but
there are specific steps to be taken for work over 2-4 meters high.
Above this height, where work cannot be done safely from the ground, the first
objective is to provide physical safeguards to prevent falls.
Where possible, means of access and working places should be of sound
construction and capable of safely supporting both people and the materials
needed for the work.
Guard rails and toe boards or an equivalent standard of protection should be
provided at any edge from which people could fall.
FALLING OBJECTS
Where necessary to protect people at work and others, take steps to prevent
materials or objects from falling;
Where it is not reasonably practicable to prevent falling materials, take
precautions to prevent people from being struck, e.g. covered walkways.
Do not throw any materials or objects down from a height if they could strike
someone.
Store materials and equipment safely.
SAFETY COMPLIANCE
All Access Scaffolds must comply with the general requirements of the following:
Construction (Health, Safety & Welfare) Regulations 1996
Code of Practice BSEN12811 (new guidelines)
Code of Practice BS5973 (withdrawn June 2004)
However, Cuplok, as a proprietary system, is not based upon scaffold tube and
fittings, and certain requirements in BS5973 may not be relevant. In these cases,
if there is conflict, MIM or Cuplok user guide should be used.
Basic system scaffold

More Related Content

PPTX
Basic Scaffolding Awareness
PPTX
Scaffolding safety at construction site
PPT
Scaffolding safety training.ppt
PDF
Eta Scaffold Training
PPT
PPTX
Erection of scaffolding
PPTX
SCAFFOLDING Safety Training
PPT
Scaffolding awareness presentation
Basic Scaffolding Awareness
Scaffolding safety at construction site
Scaffolding safety training.ppt
Eta Scaffold Training
Erection of scaffolding
SCAFFOLDING Safety Training
Scaffolding awareness presentation

What's hot (20)

PPT
Liftingproedure
PDF
scaffolding safety.pdf
PPT
Scaffold classes and duties (cals)
PPTX
Excavation & trenching
PPTX
Safety in Erection of Steel Structures
PPT
Scaffolding
PDF
Risk assessment for testing & commissioning of cranes
PPTX
Wire rope
PDF
Crane safety and_awareness_presentation_ttp
PPTX
Mewp training
PDF
Lifting tools
PPT
Scaffolding2. CO3.ppt
PDF
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
PPT
Excavations ppt
PDF
Scaffold safe work method statement
PDF
Scaffolding checklist
PPTX
Health And Safety Induction Training
DOCX
8 lifting operations with mobile crane risk assessment templates
PPTX
Fall arrest systems
DOCX
Lifting Safety
Liftingproedure
scaffolding safety.pdf
Scaffold classes and duties (cals)
Excavation & trenching
Safety in Erection of Steel Structures
Scaffolding
Risk assessment for testing & commissioning of cranes
Wire rope
Crane safety and_awareness_presentation_ttp
Mewp training
Lifting tools
Scaffolding2. CO3.ppt
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Excavations ppt
Scaffold safe work method statement
Scaffolding checklist
Health And Safety Induction Training
8 lifting operations with mobile crane risk assessment templates
Fall arrest systems
Lifting Safety
Ad

Viewers also liked (11)

PDF
Erectile Dysfunction Treatment Without Medication or Operation
PDF
Supported scaffold safety
PPT
Memos, Letters and Email Correspondence
PPT
Scaffold ladder
PPTX
Business letter
PPTX
Email Etiquette: Tips For Better Communication
PPT
Email Etiquette
PPT
Scaffolding
PDF
Email Writing Skills
PPT
Writing Letters by Ganta Kishore Kumar
PPTX
Business Letters
Erectile Dysfunction Treatment Without Medication or Operation
Supported scaffold safety
Memos, Letters and Email Correspondence
Scaffold ladder
Business letter
Email Etiquette: Tips For Better Communication
Email Etiquette
Scaffolding
Email Writing Skills
Writing Letters by Ganta Kishore Kumar
Business Letters
Ad

Similar to Basic system scaffold (20)

PPTX
CBMSQUARE PVT LIMITED shd2idh2ih2hsk1js1j
PDF
DOC-20231115-WA0057..pdf
PDF
Muscat scaffolding Cuplock System
PPT
HSE-BMS-018 Scaffolding Safety.......ppt
PPTX
Scaffolding Safety HSE Presentation  HSE Formats.pptx
PPT
HSE-BMS-018 Scaffolding Safety training.ppt
PPTX
Scaffold Competent Person Presentation 2
PPTX
MHTA- Scaffolding Inspector Training.pptx
PDF
Scaffolding 090512061510-phpapp01
PDF
kupdf.net_scaffolding-ppt.pdf
PDF
Scaffolding cuplock standards manufacturers
PPT
Scaffolding
PPT
Scaffolding
PDF
Triangle Engineering
PDF
HSE-9523-TECSM02-Safe-Scaffolding-01 06-SEP-2022.pdf
PPT
SCAFFOLDING safety training PRESENTATION .ppt
PPTX
6..Scaffolding_8ff89334-6060-4f89-816a-1b85d14313a1.pptx
PPTX
Scaffolding automation preparation and engineering ppt.pptx
PDF
Scaffolding- Everything You Need to Know
PPTX
Scaffolding by chakamba j
CBMSQUARE PVT LIMITED shd2idh2ih2hsk1js1j
DOC-20231115-WA0057..pdf
Muscat scaffolding Cuplock System
HSE-BMS-018 Scaffolding Safety.......ppt
Scaffolding Safety HSE Presentation  HSE Formats.pptx
HSE-BMS-018 Scaffolding Safety training.ppt
Scaffold Competent Person Presentation 2
MHTA- Scaffolding Inspector Training.pptx
Scaffolding 090512061510-phpapp01
kupdf.net_scaffolding-ppt.pdf
Scaffolding cuplock standards manufacturers
Scaffolding
Scaffolding
Triangle Engineering
HSE-9523-TECSM02-Safe-Scaffolding-01 06-SEP-2022.pdf
SCAFFOLDING safety training PRESENTATION .ppt
6..Scaffolding_8ff89334-6060-4f89-816a-1b85d14313a1.pptx
Scaffolding automation preparation and engineering ppt.pptx
Scaffolding- Everything You Need to Know
Scaffolding by chakamba j

Recently uploaded (20)

PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPTX
UNIT 4 Total Quality Management .pptx
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PDF
Well-logging-methods_new................
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
Digital Logic Computer Design lecture notes
PPTX
Welding lecture in detail for understanding
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
Sustainable Sites - Green Building Construction
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
CH1 Production IntroductoryConcepts.pptx
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
bas. eng. economics group 4 presentation 1.pptx
CYBER-CRIMES AND SECURITY A guide to understanding
Operating System & Kernel Study Guide-1 - converted.pdf
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
UNIT 4 Total Quality Management .pptx
Mechanical Engineering MATERIALS Selection
Strings in CPP - Strings in C++ are sequences of characters used to store and...
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
Well-logging-methods_new................
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Model Code of Practice - Construction Work - 21102022 .pdf
Digital Logic Computer Design lecture notes
Welding lecture in detail for understanding
Internet of Things (IOT) - A guide to understanding
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Sustainable Sites - Green Building Construction
Lesson 3_Tessellation.pptx finite Mathematics

Basic system scaffold

  • 3. PROPRIETARY SCAFFOLDING Ring scaffold node or connection point Kwikstage scaffold node
  • 5. PROPRIETARY SCAFFOLDING Rapid scaffold node or connection point Cuplok scaffold node or connection point
  • 6. Strong winds tore a sheeted scaffolding system from this building.
  • 7. The Cuplok Scaffold System is a fully galvanized multi purpose steel scaffold for general access and supporting vertical loads.
  • 8. The principal feature of the cuplok modular system is the unique method of connecting ledgers & transoms to the standard. In one single action without the use of any loose component such as nuts, bolts, wedges.
  • 9. INSPECTION Before commencing the erection of any Cuplok Scaffold, great care should be taken to see that the ground is suitable. On soft or made-up ground the scaffold should be erected on timber sole plates of appropriate size. Bricks or blocks should not be used. The scaffold should be started on the highest part of the ground – this will make levelling easier as the scaffolding progresses horizontally. Always check whether or not an inside board platform of one, two or three boards will be required. If so this will determine the distance of the scaffold from the building.
  • 10. SCAFFOLD STABILITY The scaffold must be suitably tied to a sound structure, all ties must be inserted as each required level and spacing is reached. Attachment must be to the components specified. The scaffolder can attach, in order of preference: At any position along a fully fastened ledger above head level. At any position along a fully fastened guardrail at waist level where the scaffold extends at least one lift above the level at which the scaffolder is working. At any position along a fully fastened ledger supporting the platform on which the scaffolder is working (only recommended when it is not possible to attach above head or waist level) To transoms, in the lift above which are fixed at both ends.
  • 11. NEVER CLIP TO: • Cuplok Standards (Verticals) • Transoms below foot level • Ledgers or Transoms which have not been fully fastened. • Weak anchoring points
  • 12. STRENGTH Cuplok independent tied access scaffolds built up to 2.5m bays have a capability of 3kN (300kg) per square meter. For other applications, such as birdcage, mobile towers and staircases the loadings may vary, and advice should be sought from the MIM (manufacturers instruction manual)
  • 13. PLATFORM LOADINGS - WORKING LIFTS 2m lift access scaffolds: 1.5kN/m2 1.5m bricklayers scaffold for 1 platform: 3.0kN/m2 or 2 platforms: 1 at 3.0kN/m2 & 1 at 1.5kN/m2
  • 18. ASSEMBLY Layout out the ledger and transoms for the first bay in their approximate positions. Then insert an adjustable base jack into each of the first pair of standards.
  • 19. ASSEMBLY CONT.… Connect the standards with a transom in the lowest cup joint by inserting the blades into the cups. Level the transom. Always start the scaffold with a three meter standard on the outside and a two meter standard on the inside. joints are staggered.
  • 20. ASSEMBLY CONT.…. With one person still holding the first pair of standards, the second person inserts a jack into the third standard and connects it to the first pair with a ledger. The upper cup can then be dropped temporarily into the locking position. The structure is now self supporting and the fourth standard can now be connected by a further ledger and transom and the bay levelled. Once the base lift has been completely levelled, your spirit level will no longer be required.
  • 21. USING THE OMEGA BATTEN SYSTEM The same erection procedure is adopted for the Omega Batten System as for the Scaffold Board System, except that the Omega top hat type transom Is used in place of the tubular transom. No intermediate board supports will be required. The first bay of Cuplok is completed by locating the upper ledgers and transoms. It is now a simple matter to extend the scaffold structure by connecting ledgers, transoms and standards to the existing bay. The top fixing cups can now be secured with a hammer. The scaffold should
  • 22. USING THE OMEGA BATTEN SYSTEM
  • 23. USING THE OMEGA BATTEN SYSTEM CONT.…. Now be secured by the ties/anchors or equivalent methods at the earliest opportunity
  • 24. USING THE OMEGA BATTEN SYSTEM CONT.…. The working platform can now be constructed. To ensure safe erection, alteration and dismantling of the scaffolding it is important that the procedures outlined in the Guidance Note SG4:10 is followed. In summary, a minimum of three boards should be placed from below for erectors and single guard rails should be installed as work progresses along each lift (double guard rails and toe boards will be required to complete). Scaffolders' should safely clip on to ledgers or guard rails at any height or above, Full body harnesses should be worn and lanyards attached.
  • 25. USING THE OMEGA BATTEN SYSTEM CONT.…. Intermediate transoms are secured at strategic points (1.2m and 1.5m support frequency) across the ledgers to support 38mm scaffold boards. The scaffold boards and toe boards can now be positioned. Two standard ledgers can be located 0.5 and 1.0 meters above the working platform to form the double guardrails.
  • 26. USING THE OMEGA BATTEN SYSTEM CONT.…. Additional lifts can now be constructed simply by adding further standards on to the spigots of the lower lift, and connecting them with ledgers and transoms. When swivel face braces are used, these are located at the cup joints and should span from lift level to lift level (see face bracing overleaf).
  • 27. CUPLOK COMPONENTS Standards Cuplok Standards are made from a high grade steel tube and are identified by a red flash at the bottom. Top cups have 4 lugs. Earlier stocks were made from a different grade steel and carry slightly less load. For all normal access scaffold either type is suitable.
  • 28. LEDGERS/TRANSOMS Cuplok tubular ledgers are also used for transoms or guardrails and are fully interchangeable. Cuplok tubular ledgers are used with standard boards. Omega transoms are used with timber or steel battens. Intermediate Transoms used to provide intermediate support to scaffold boards. Also used at board ends. They are fitted with a wedge operated lock to prevent accidental sliding in use.
  • 29. BASE JACKS Cuplok Universal jacks must always be used in conjunction with Head/Base plates, Sitting on scaffold board or other suitable sole plates as in normal scaffolding practice. The jack must always be fitted so that the unthreaded portion is inside the standard to prevent the minimum overlap in the tube being reduced.
  • 30. SCAFFOLD BOARDS All standard scaffold boards are suitable for use with Cuplok when laid over tubular transoms. They safely span distances between 1.2m and 1.5m for most types, but care must be taken to check the embossed bands at the end to determine the max permissible span. Intermediate transoms must be used to limit the span and also to give support to the ends.
  • 31. SCAFFOLD BOARDS Cuplok Battens, both steel and timber, are suitable for spans up to 2.5m without intermediate support for loadings of up to 3kN/m2. Toe boards, Can be provided by scaffold boards, timber or steel battens using the appropriate clips from the Cuplok range.
  • 32. The broad principles applied to tubular scaffolding also apply to the use of Cuplok with scaffold boards: Provided adequate number of transoms supporting Scaffolding Boards SCAFFOLD BOARDS
  • 33. GUARDRAILS The standard heights for guard rails (approx. 0.5m to 1.0m) are predetermined by the Cuplok System. Brick guard panels may be used with Cuplok. Double guard rails and toe boards must always be provided.
  • 34. SPIGOT PINS Only required where resistance to uplift is required and would be required when scaffold projects above last tie, or when using hop-up brackets, or with crane handled assemblies. Spigot pins should be used to lock the standards against uplift at all joints down to the last tied lift below the hop-ups. On a scaffold where the brackets will be moved, spigot pins should be used throughout at time of erection to minimize risk of omission during modifying of platform levels.
  • 35. CORNERS AND RETURNS Rigid corners are formed in Cuplok by using a 1.3m square corner bay. For scaffolds with scaffold boards, check the Cuplok return devices (or tube and fittings) are used to connect the two runs at each level. For scaffolds fitted with battens an Omega Return Transom is used. In both cases attention must be given to providing proper toe boards and this may involve cutting boards to suit the various dimensions of the corners. Further information is contained in the Cuplok Users Manual.
  • 36. HOP-UP BRACKETS The maximum permitted loading on hop-up brackets is as follows: 1 board: 3kN/m2 2 board: 1.5kN/m2 3 board: 0.75kN/m2
  • 37. DIAGONAL BRACING Face Bracing • One bay of bracing to the full height is required every 8 bays (20m). • On short runs up to 4 bays (10m), one braced bay should be provided. • Over 10m at least two bays of bracing are required. •As only one blade can be located at each node point, parallel bracing is used. •Braces must go from platform level to platform level. •Note that the bottom brace is always fitted in a 1.0 or 1.5m lift and should be of the appropriate size.
  • 38. LEDGER BRACE AND PLAN BRACING The Cuplok node connection is extremely rigid and ledger bracing is not normally required. On very high scaffolds it may be specified to increase the load capacity but all such work should be referred to an BS/EN design standard. Plan bracing is also uncommon and should be the subject of consideration by the design. When the hop-up level occurs between tied levels, ledger bracing must be used at each lift down to the next tie.
  • 39. SG4:05 ‘PREVENTING FALLS IN SCAFFOLDING’ The publication of the NASC Guidance Note, “Preventing falls in Scaffolding and False work” (SG4:05-2006), was an important move forward in preventing falls by scaffolds. However, the scope of the document extends to steel tube and fittings scaffolds, and not to system scaffolds in respect of anchor points. The document (commended by the Health and safety Executive) recommends that one should follow the System Scaffold Manufacturers advice as to suitable anchor points for safety harness lanyards.
  • 40. FALLS FROM HEIGHT Falls account for more than half of the fatal accidents in construction. The aim of the Regulations is to prevent falls from any height, but there are specific steps to be taken for work over 2-4 meters high. Above this height, where work cannot be done safely from the ground, the first objective is to provide physical safeguards to prevent falls. Where possible, means of access and working places should be of sound construction and capable of safely supporting both people and the materials needed for the work. Guard rails and toe boards or an equivalent standard of protection should be provided at any edge from which people could fall.
  • 41. FALLING OBJECTS Where necessary to protect people at work and others, take steps to prevent materials or objects from falling; Where it is not reasonably practicable to prevent falling materials, take precautions to prevent people from being struck, e.g. covered walkways. Do not throw any materials or objects down from a height if they could strike someone. Store materials and equipment safely.
  • 42. SAFETY COMPLIANCE All Access Scaffolds must comply with the general requirements of the following: Construction (Health, Safety & Welfare) Regulations 1996 Code of Practice BSEN12811 (new guidelines) Code of Practice BS5973 (withdrawn June 2004) However, Cuplok, as a proprietary system, is not based upon scaffold tube and fittings, and certain requirements in BS5973 may not be relevant. In these cases, if there is conflict, MIM or Cuplok user guide should be used.