Chapter 6 - Developing a Project Plan
6–2
Developing the Project Plan
• The Project Network
–A flow chart that graphically depicts the sequence,
interdependencies, and start and finish times of the
project job plan of activities that is the critical path
through the network.
• Provides the basis for scheduling labor and equipment.
• Enhances communication among project participants.
• Provides an estimate of the project’s duration.
• Provides a basis for budgeting cash flow.
• Identifies activities that are critical.
• Highlights activities that are “critical” and can not be delayed.
• Help managers get and stay on plan.
6–3
Constructing a Project Network
• Terminology
–Activity: an element of the
project that requires time.
–Merge Activity: an activity that
has two or more preceding
activities on which it depends.
–Parallel (Concurrent) Activities:
Activities that can occur
independently and, if desired,
not at the same time.
A
C
D
B
6–4
Constructing a Project Network (cont’d)
• Terminology
–Path: a sequence of connected, dependent activities.
–Critical path: the longest path through the activity
network that allows for the completion of all project-
related activities; the shortest expected time in which
the entire project can be completed. Delays on the
critical path will delay completion of the entire project.
A B D
(Assumes that minimum of A + B > minimum of C in length of times to complete activities.)
C
6–5
Constructing a Project Network (cont’d)
• Terminology
–Event: a point in time when an activity is started
or completed. It does not consume time.
–Burst Activity: an activity that has more than one
activity immediately following it (more than one
dependency arrow flowing from it).
• Two Approaches
–Activity-on-Node (AON)
• Uses a node to depict an activity.
–Activity-on-Arrow (AOA)
• Uses an arrow to depict an activity.
B
D
A C
6–6
Basic Rules to Follow in Developing
Project Networks
1. Networks typically flow from left to right.
2. An activity cannot begin until all preceding
connected activities are complete.
3. Arrows indicate precedence and flow
and can cross over each other.
4. Each activity must have a unique identify number
that is greater than any of its predecessor activities.
5. Looping is not allowed.
6. Conditional statements are not allowed.
7. Use common start and stop nodes.
6–7
Activity-on-Node Fundamentals
FIGURE 6.2
6–8
Activity-on-Node Fundamentals (cont’d)
FIGURE 6.2 (cont’d)
6–9
Network Information
TABLE 6.1
6–10
Koll Business Center—Partial Network
FIGURE 6.3
6–11
Koll Business Center—Complete Network
FIGURE 6.4
6–12
Network Computation Process
• Forward Pass—Earliest Times
–How soon can the activity start? (early start—ES)
–How soon can the activity finish? (early finish—EF)
–How soon can the project finish? (expected time—ET)
• Backward Pass—Latest Times
–How late can the activity start? (late start—LS)
–How late can the activity finish? (late finish—LF)
–Which activities represent the critical path?
–How long can activity be delayed? (slack or float—SL)
6–13
Network Information
TABLE 6.2
6–14
Activity-on-Node Network
FIGURE 6.5
6–15
Activity-on-Node Network Forward Pass
FIGURE 6.6
6–16
Forward Pass Computation
• Add activity times along each path in the
network (ES + Duration = EF).
• Carry the early finish (EF) to the next activity
where it becomes its early start (ES) unless…
• The next succeeding activity is a merge activity,
in which case the largest EF of all preceding
activities is selected.
6–17
Activity-on-Node Network Backward Pass
FIGURE 6.7
6–18
Backward Pass Computation
• Subtract activity times along each path in the
network (LF - Duration = LS).
• Carry the late start (LS) to the next activity
where it becomes its late finish (LF) unless
• The next succeeding activity is a burst activity, in
which case the smallest LF of all preceding
activities is selected.
6–19
Determining Free Slack (or Float)
• Free Slack (or Float)
–Is the amount of time an activity can be delayed after
the start of a longer parallel activity or activities.
–Is how long an activity can exceed its early finish date
without affecting early start dates of any successor(s).
–Allows flexibility in scheduling scarce resources.
• Sensitivity
–The likelihood the original critical path(s) will change
once the project is initiated.
–The critical path is the network path(s) that has (have)
the least slack in common.
6–20
Activity-on-Node Network with Slack
FIGURE 6.8
6–21
Free Slack Example
FIGURE 6.9
6–22
Illogical Loop
FIGURE 6.10
6–23
Extended Network Techniques
to Come Close to Reality
• Laddering
–Activities are broken into segments so the following
activity can begin sooner and not delay the work.
6–24
Example of Laddering Using
Finish-to-Start Relationship
FIGURE 6.13
6–25
Activity-on-Arrow Network Building Blocks
FIGURE A6.1
6–26
Activity-on-Arrow Network Fundamentals
FIGURE A6.2

More Related Content

PPT
PDF
Forecasting Methods
PPTX
Supply chain analytics essentials
PPT
5. project activity and risk planning
PPTX
SCM Outsourcing
PPTX
(Kmb202) HRM , unit 4, recent trends in Compensation Management
PPTX
Operations management forecasting
PPTX
Forecasting in Management- Methods,features,advantages,importance and process
Forecasting Methods
Supply chain analytics essentials
5. project activity and risk planning
SCM Outsourcing
(Kmb202) HRM , unit 4, recent trends in Compensation Management
Operations management forecasting
Forecasting in Management- Methods,features,advantages,importance and process

What's hot (20)

PPTX
Outsourcing of Supply Chain Management
PPTX
E procurement
PPT
Chapter 1. understanding the supply chain
PPT
Enterprise resource planning (erp) systems
PPTX
Demand forecasting in supply chain
PPTX
Vendor rating
DOCX
Demand forecast process and inventory management
PPTX
Procurement process
PPTX
Sourcing and Materials Management Presentation
PPT
Demand Forecasting
PPT
ERP Implementation Life Cycle
PPTX
Fundamentals of operations management
PPT
Strategic capacity planning for products and services
PPT
Chapter 1 understanding the supply chain
PPSX
Aggregate planning
PPTX
LOGISTICS AUDIT
PPTX
Aggregate production planning
PPTX
Operation research techniques
PPTX
Bullwhip effect ppt
PDF
Steps Of Strategic Procurement Process PowerPoint Presentation Slides
Outsourcing of Supply Chain Management
E procurement
Chapter 1. understanding the supply chain
Enterprise resource planning (erp) systems
Demand forecasting in supply chain
Vendor rating
Demand forecast process and inventory management
Procurement process
Sourcing and Materials Management Presentation
Demand Forecasting
ERP Implementation Life Cycle
Fundamentals of operations management
Strategic capacity planning for products and services
Chapter 1 understanding the supply chain
Aggregate planning
LOGISTICS AUDIT
Aggregate production planning
Operation research techniques
Bullwhip effect ppt
Steps Of Strategic Procurement Process PowerPoint Presentation Slides
Ad

Similar to Chapter 6 - Developing a Project Plan.pdf (20)

PPT
Project Management The Manegerial Process
PPTX
6. Developing Project Plan.pptx
PPT
PPT
Chap 6 Developing A Project Plan
PPT
PM Session 5
PPTX
CHAPTER 6.pptx
PPTX
Larson2024_Ch06_PowerPoint_Accessible.pptx
DOCX
Chapter SixDeveloping a Project Plan6-1Copyright © 2018
PPTX
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
PPTX
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
PDF
08_lecture_scheduling.pdf based on project management
PPTX
Developing a project Plan for the market
PPT
ch08 (1).pptttttttttttttttþtttttttttttttt
PPTX
Project networks
PDF
Activity on nodes presentation for software project management
PPTX
Unit2 network optimization
PPT
08. Project Time Management Upload
PPTX
Project evaluation and review techniques and cpm basics
PPT
Network Analysis : Pert & C P Management
PPT
3- Project Time Management.ppt
Project Management The Manegerial Process
6. Developing Project Plan.pptx
Chap 6 Developing A Project Plan
PM Session 5
CHAPTER 6.pptx
Larson2024_Ch06_PowerPoint_Accessible.pptx
Chapter SixDeveloping a Project Plan6-1Copyright © 2018
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
08_lecture_scheduling.pdf based on project management
Developing a project Plan for the market
ch08 (1).pptttttttttttttttþtttttttttttttt
Project networks
Activity on nodes presentation for software project management
Unit2 network optimization
08. Project Time Management Upload
Project evaluation and review techniques and cpm basics
Network Analysis : Pert & C P Management
3- Project Time Management.ppt
Ad

Recently uploaded (20)

PPTX
Amazon (Business Studies) management studies
PDF
IFRS Notes in your pocket for study all the time
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PDF
Training And Development of Employee .pdf
PPTX
5 Stages of group development guide.pptx
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
PDF
Dr. Enrique Segura Ense Group - A Self-Made Entrepreneur And Executive
PPTX
Probability Distribution, binomial distribution, poisson distribution
PPT
Chapter four Project-Preparation material
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
Types of control:Qualitative vs Quantitative
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
Nidhal Samdaie CV - International Business Consultant
DOCX
Business Management - unit 1 and 2
PDF
Deliverable file - Regulatory guideline analysis.pdf
PDF
Business model innovation report 2022.pdf
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
Amazon (Business Studies) management studies
IFRS Notes in your pocket for study all the time
Reconciliation AND MEMORANDUM RECONCILATION
Training And Development of Employee .pdf
5 Stages of group development guide.pptx
Ôn tập tiếng anh trong kinh doanh nâng cao
Dr. Enrique Segura Ense Group - A Self-Made Entrepreneur And Executive
Probability Distribution, binomial distribution, poisson distribution
Chapter four Project-Preparation material
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
340036916-American-Literature-Literary-Period-Overview.ppt
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
Belch_12e_PPT_Ch18_Accessible_university.pptx
Types of control:Qualitative vs Quantitative
HR Introduction Slide (1).pptx on hr intro
Nidhal Samdaie CV - International Business Consultant
Business Management - unit 1 and 2
Deliverable file - Regulatory guideline analysis.pdf
Business model innovation report 2022.pdf
Power and position in leadershipDOC-20250808-WA0011..pdf

Chapter 6 - Developing a Project Plan.pdf

  • 1. 6–1 Chapter 6 - Developing a Project Plan
  • 2. 6–2 Developing the Project Plan • The Project Network –A flow chart that graphically depicts the sequence, interdependencies, and start and finish times of the project job plan of activities that is the critical path through the network. • Provides the basis for scheduling labor and equipment. • Enhances communication among project participants. • Provides an estimate of the project’s duration. • Provides a basis for budgeting cash flow. • Identifies activities that are critical. • Highlights activities that are “critical” and can not be delayed. • Help managers get and stay on plan.
  • 3. 6–3 Constructing a Project Network • Terminology –Activity: an element of the project that requires time. –Merge Activity: an activity that has two or more preceding activities on which it depends. –Parallel (Concurrent) Activities: Activities that can occur independently and, if desired, not at the same time. A C D B
  • 4. 6–4 Constructing a Project Network (cont’d) • Terminology –Path: a sequence of connected, dependent activities. –Critical path: the longest path through the activity network that allows for the completion of all project- related activities; the shortest expected time in which the entire project can be completed. Delays on the critical path will delay completion of the entire project. A B D (Assumes that minimum of A + B > minimum of C in length of times to complete activities.) C
  • 5. 6–5 Constructing a Project Network (cont’d) • Terminology –Event: a point in time when an activity is started or completed. It does not consume time. –Burst Activity: an activity that has more than one activity immediately following it (more than one dependency arrow flowing from it). • Two Approaches –Activity-on-Node (AON) • Uses a node to depict an activity. –Activity-on-Arrow (AOA) • Uses an arrow to depict an activity. B D A C
  • 6. 6–6 Basic Rules to Follow in Developing Project Networks 1. Networks typically flow from left to right. 2. An activity cannot begin until all preceding connected activities are complete. 3. Arrows indicate precedence and flow and can cross over each other. 4. Each activity must have a unique identify number that is greater than any of its predecessor activities. 5. Looping is not allowed. 6. Conditional statements are not allowed. 7. Use common start and stop nodes.
  • 12. 6–12 Network Computation Process • Forward Pass—Earliest Times –How soon can the activity start? (early start—ES) –How soon can the activity finish? (early finish—EF) –How soon can the project finish? (expected time—ET) • Backward Pass—Latest Times –How late can the activity start? (late start—LS) –How late can the activity finish? (late finish—LF) –Which activities represent the critical path? –How long can activity be delayed? (slack or float—SL)
  • 16. 6–16 Forward Pass Computation • Add activity times along each path in the network (ES + Duration = EF). • Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless… • The next succeeding activity is a merge activity, in which case the largest EF of all preceding activities is selected.
  • 18. 6–18 Backward Pass Computation • Subtract activity times along each path in the network (LF - Duration = LS). • Carry the late start (LS) to the next activity where it becomes its late finish (LF) unless • The next succeeding activity is a burst activity, in which case the smallest LF of all preceding activities is selected.
  • 19. 6–19 Determining Free Slack (or Float) • Free Slack (or Float) –Is the amount of time an activity can be delayed after the start of a longer parallel activity or activities. –Is how long an activity can exceed its early finish date without affecting early start dates of any successor(s). –Allows flexibility in scheduling scarce resources. • Sensitivity –The likelihood the original critical path(s) will change once the project is initiated. –The critical path is the network path(s) that has (have) the least slack in common.
  • 23. 6–23 Extended Network Techniques to Come Close to Reality • Laddering –Activities are broken into segments so the following activity can begin sooner and not delay the work.
  • 24. 6–24 Example of Laddering Using Finish-to-Start Relationship FIGURE 6.13