COMPARATIVE ANALYSIS OF FORMWORK IN MULTISTORY BUILDING Sandip.P.Pawar1, P.M.Atterde2 1P.G. Student Deptt of civil Engineering SSGBCOET Bhusawal Maharashtra 2Guide, Deptt of civil Engineering SSGBCOET Bhusawal Maharashtra Abstract One of the most important factors in determing the success of a construction project in terms of speed, quality cost and safety of work is the formwork used in the project as it accounts about 40% of the total project cost of the structure. When considering a construction project both the client and contractor want to finish the job early as the client wants to use the building for the intended purpose as soon as possible. The contractor wants to finish the construction as soon as possible to gain a higher profit. The most efficient way to speed up the work in high-rise building construction is by achieving a very short floor cycle. The floor cycle of a building mainly depend on the formwork type as it is the main time factor of a building project. The aim of this paper is to present about the existing formwork types in Maharashtra and to show each one will affect the project duration, project cost and the quality of the work. For that a research has been carried out and the results will present in this paper. Keywords: Formwork,Duration,cost,quality 
---------------------------------------------------------------------***--------------------------------------------------------------------- 1.INTRODUCTION Formwork is defined as temporary structure whos purpose is to provide support and containment for fresh concrete until it can support itself. It moulds the concrete to the desired shape and size and controls its position and alignment. The development of formworks is parallel with the growth of concrete construction throughout the 20th century. The advancement of technology, increase of population and the space limitation lead the way to construct high-rise buildings. But the task was not very easy at the beginning but now the man made the task easy by inventing new machinery and new techniques. The most important factor in terms of cost, quality and speed in a high-rise building construction project is the type of the formwork used in the project. The first formwork type to be used is the conventional type formwork where the timber planks were supported on timber columns. With the advancement of technology it developed gradually and people used ply wood sheets instead of timber planks and steel pipes with jacks were used to support the ply wood. Then people invented small units of formworks and connect the repeating units in the construction. The larger units were invented like formworks for slab panels, formworks for columns, beams…etc. when the same elements are repeating. Then finally the whole system of formwork is made and initially the material used to it was steel and it was very heavy. Then the aim was to reduce the weight of the system and the materials for formwork have extended to aluminium, plastic, fiber glass…etc. 
contractors are in a belief that the system formwork is suitable only for super tall buildings as the initial cost of the system formwork is a bit high. Though the initial cost of the system formwork is a bit high it reduces the project duration and hence the total project cost. When considering the overall construction of a high-rise building the system formwork is much more economical that to all the other primary formwork types as it reduces the project duration, gives a smooth concrete surface and the repetitive use of the system. This is suitable for even for a two or three storey housing scheme of several houses. 2. TYPES OF FORMWORKS Conventional Formwork: This is the oldest type of formwork used in the construction industry. This type uses timber, bamboo, masonry and carpentry in the construction. This type is very much suitable for small houses with two to three storeys and still they are in use for such constructions. But this is not suitable for the big projects or high-rise buildings. Low initial cost, low experience factor, low weight are some of the advantages of this type and poor finish, high labor requirement, skilled labor. requirement and consume lot of time are some of the disadvantages. 
Modern Conventional Formwork: This type is very much closer to the conventional formwork and in simple words this is one step advanced than the conventional type. The same technique has used in the both types and the only difference is the materials use for the formworks. In modern conventional formwork more advanced materials are used and they can reuse for several times. The differences of both types are that steel props and various types of jacks (U jacks, T jacks) are used as supports in the formwork instead of timber supports and ply wood sheets are used instead of timber planks on slab decks, beams and columns. Low initial cost, low skilled labor requirement, can even use in small places and when there are lot of deviations in the structure are some of the advantages while poor finish of the
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 
_______________________________________________________________________________________ 
Volume: 03 Special Issue: 09 | NCETCE-2014 | June-2014, Available @ http://www.ijret.org 23 
concrete surface, high labor requirement and the higher floor cycle are the disadvantages This type is much more advanced than the modern conventional type. In this type there are pre-fabricated formwork items such as pre-fabricated formworks for slab panels and supports and ply wood should be used additionally for slab deck, beams and columns for the surface. There are other forms of semi system formwork such as table forms, flying forms…etc. DOCA is the most famous brand for this type of formwork and some people know about this type only as “DOCA formwork”. System Formwork: System formwork has prefabricated modular components with casting panels. The system formwork is fabricated as it suits the required shape. The biggest advantage of this type is the speedy and quality construction. But the high initial cost is the main disadvantage and hence it is not economical to use in low – rise buildings. But this is the most economical form of formwork type to be used in high-rise building construction when it is having few typical storeys. 3. RESEARCH STUDY The expectation of this study is to find the most economical formwork type to be used in a high-rise building project. When considering a construction project there are many cost components contributing to the total cost of the project. Preliminary cost is a key cost component when comparing the total cost of a project, and the duration of the project is the governing factor for the preliminary running cost. Total Project Cost = Materials and labour + Preliminary cost + Machinery & equipment t+ Waste material handling + Safety + Finishes + … Preliminary Cost = Salaries + work establishment charge + Security … When a building construction project is considered the material requirement is unique as it depends on the design. But the labor requirement and the duration of the project are directly affected by the technologies and the construction methods used in the project. The speed of the project is directly affected by the formwork type used in the project. This is the most critical in high-rise building construction. When using latest technologies, the labor requirement and the time duration can beminimized in the project, mainly for the super structure. In high-rise building projects time controlling factor is the formwork as it directly affect the floor cycle and hence it will reduce the time taken to construct the main structure and because of that the total duration of the project will go down drastically. In this research cost comparisons of total project cost has done for several projects when all the two types of formwork types are used in the same project. 
4. THE RESULTS 
4.1 The Results Obtained 
Data is collected from M/s Sai Construction Ahmednagar .Name of Construction work on Residetial Building of KARAN RHEA Wing A,Wing B,&Wing C at Wadegaon Sheri, Pune projects and calculations are done for the total project cost of the selected projects when using different types of formworks in the construction. In the calculations all the parameters are kept same and only the formwork type is changed. At the same time all the factors affect due to the formwork type is considered. The results can be shown in a table as follows. Table .1 
Project 
No.of Floor 
Area of each floor (sqm) 
Total cost of Project 
Wing A 
10 
418 
11,24,42,000 
Wing B 
15 
510 
13,71,90,000 
Wing C 
20 
600 
16,14,40,000 
Table .2 
Analysis of the Aluminium formwork for Typical Floor 
Wing A aA1 11 
Wing B 2 
Wing C 3 
Form work cost in Laks 
9.82 
11.98 
14.1 
Waist disposal cost in Laks 
0 
0 
0 
Machinary cost in Laks 
0.9 
1.12 
1.98 
For Aluminium form work Table 3 
. Analysis of the conventional formwork for Typical Floor 
Wing A aA1 11 
Wing B 2 
Wing C 3 
Form work cost in Laks 
6.27 
7.65 
9.0 
Waist disposal cost in Laks 
0.31 
0.38 
0.45 
0 
5 
10 
15 
Tower 1 
Tower 2 
Tower 3 
Form work cost in Laks 
Waist disposal cost in Laks
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 
_______________________________________________________________________________________ 
Volume: 03 Special Issue: 09 | NCETCE-2014 | June-2014, Available @ http://www.ijret.org 24 
Machinary cost in Laks 
0.5 
0.85 
1.25 
For Conventional Form work 
5. CONCLUSIONS From the results obtained we can come to a conclusion that when the system formwork is used in the construction project, the total project cost and the duration of the project is lesser than the other formwork types. The main important thing is that the aluminium panel system formwork is the most expensive formwork type from those three types. At the same time the highest total project cost is obtained when modern conventional type of formwork is used in the building construction project which is the least expensive formwork type. So it is clearly seen that that not the cost of formwork directly affected to the total project cost but the type of formwork. The floor cycle will be 6-10 days when the system formwork is in use and hence the total project duration will be reduced. At the same time a smooth concrete surface can be obtained as the system can be assembled without any discontinuities in the surface and hence less finishing work will be there and hence the cost for finishes will be reduced. There will be less waste disposal and less machinery usage. Not only the direct benefits, there are many indirect benefits of using aluminium panel system formwork in the high-rise building construction projects. For example the system can be sold after using, it can be used in other slabs doing slight variations (there is no need to buy materials again). REFERENCES 
[1] Hurd, M.K. 1989. Formwork for Concrete, 6th ed. American Concrete Institute, Detroit, MI. 
[2] Nolan, É. Innovation in concrete frame construction 1995–2015. IHS BRE Press, Garston. BR 483. 44pp 
[3] Moore, C.E. 1977. Concrete Form Construction. Van Nostrand Reinhold, New York. 
[4] Ratay, R.T. 1984. Handbook of Temporary Structures in Construction. McGraw-Hill, New York 
[5] Peurifoy, P.E. 1976. Formwork for Concrete Structures. McGraw-Hill, New York. Plasticizer” International Scholarly Research Network ISRN Civil Engineering Volume 2012, Article ID 469272, 5 pages doi:10.5402/2012/469272 2005. 
[6] Ketan Shah, " Modular formwork for faster, economical and quality construction", Indian Concrete Journal, July 2005, Volume 79,Pg.6-23. 
[7] “Formwork & Scaffolding”, CE & CR, September 1992, Vol. 05, No. 9, Pg. 46-57. 
[8] Ashok Mandal, "Scaffolding & Formwork- Maintenance & Safety",CE & CR, August 2006, Vol. 19, No. 8, Pg. 46-50. 
[9] "Emerging Trends In Formwork And Scaffolding", CE & CR, Sep 92,Pg.46-49. 
[10] "ConstructionEquipment",CE&CR,Mayl992,Pg.50- 52. 
[11] IS14687(Falsework For Concrete Structures- Guidelines) 
BIOGRAPHIES 
Sandip P.Pawar Completed B.E. in civil Engineering 2009 and M.E appear in Construction Technology & Management in North Maharashtra University Jalgaon (MS). 
P.M.Atterde (Department of civil engineering SSGBCOET Bhusawal) 
0 
2 
4 
6 
8 
10 
Tower 1 
Tower 2 
Tower 3 
Form work cost in Laks 
Waist disposal cost in Laks

More Related Content

PDF
Analysis of Formwork in Multistory Building
PDF
EVALUATION OF PRECAST TECHNOLOGY ON PROJECT PROFITABILITY
PDF
Bachelor in quantity surveying 2
PPT
Modular construction
PDF
Role of bim in modular construction converted
PDF
modular construction
PPT
Modular construction for_low_cost_housing_in_india
PDF
Capitalizing on modular construction as the next frontier for innovation
Analysis of Formwork in Multistory Building
EVALUATION OF PRECAST TECHNOLOGY ON PROJECT PROFITABILITY
Bachelor in quantity surveying 2
Modular construction
Role of bim in modular construction converted
modular construction
Modular construction for_low_cost_housing_in_india
Capitalizing on modular construction as the next frontier for innovation

What's hot (17)

PPTX
Off site fabrication
PDF
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
PDF
ace cover pg 2829
PDF
Modular building institute improving construction efficiency & productivity...
PPTX
Modular Construction Solution For Rapid Cost-effective Development Of Housing
PDF
IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...
PDF
Modular Construction and Prefabrication: The Masterclass
PDF
Earth quake response of different shapes of mivan wall tall buildings
PDF
The Time Is Now For Modular Construction
PPTX
076 Modular Construction
PDF
The Articulation of the High-Rise Residential Building Envelope: A Review fro...
PDF
SEM 6 : BTECH 2 PROJECT 2
PPTX
3D Monolithic Modular- Defence seminar on new construction technologies and m...
PPT
Prefabricated structure
DOCX
01ADNAN Mtech
PPTX
Modular housing/building
PPTX
Overview of Modular Construction
Off site fabrication
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
ace cover pg 2829
Modular building institute improving construction efficiency & productivity...
Modular Construction Solution For Rapid Cost-effective Development Of Housing
IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...
Modular Construction and Prefabrication: The Masterclass
Earth quake response of different shapes of mivan wall tall buildings
The Time Is Now For Modular Construction
076 Modular Construction
The Articulation of the High-Rise Residential Building Envelope: A Review fro...
SEM 6 : BTECH 2 PROJECT 2
3D Monolithic Modular- Defence seminar on new construction technologies and m...
Prefabricated structure
01ADNAN Mtech
Modular housing/building
Overview of Modular Construction
Ad

Viewers also liked (20)

PPTX
Innovative timber buildings – including cross laminated timber and laminated ...
PPT
Timber frame construction presentation`gr
PDF
Run time dynamic partial reconfiguration using
PDF
Online review mining for forecasting sales
PDF
An understanding of graphical perception
PDF
Comparative analysis of c99 and topictiling text
PDF
Performance evaluation of path loss parameters for broadcasting applications
PDF
Study on shear strength characteristics of coir mat reinforced sand
PDF
Compressive strength variability of brown coal fly ash geopolymer concrete
PDF
A survey on ontology based web personalization
PDF
Searching and tracking of neighboring base stations
PDF
Critical comparison of ground motion attenuation formulae for recent earthqua...
PDF
Comparison of physical and rheological properties of
PDF
.Net compiler using cloud computing
PDF
Swarm robotics for intelligent warehousing an
PDF
Effect of concentration on structural and optical
PDF
The use of polynomial shape function in the buckling
PDF
Seismic evaluation of rc framed buildings with
PDF
Scheduling for interference mitigation using enhanced intercell interference ...
PDF
Open channel flow velocity profiles for different
Innovative timber buildings – including cross laminated timber and laminated ...
Timber frame construction presentation`gr
Run time dynamic partial reconfiguration using
Online review mining for forecasting sales
An understanding of graphical perception
Comparative analysis of c99 and topictiling text
Performance evaluation of path loss parameters for broadcasting applications
Study on shear strength characteristics of coir mat reinforced sand
Compressive strength variability of brown coal fly ash geopolymer concrete
A survey on ontology based web personalization
Searching and tracking of neighboring base stations
Critical comparison of ground motion attenuation formulae for recent earthqua...
Comparison of physical and rheological properties of
.Net compiler using cloud computing
Swarm robotics for intelligent warehousing an
Effect of concentration on structural and optical
The use of polynomial shape function in the buckling
Seismic evaluation of rc framed buildings with
Scheduling for interference mitigation using enhanced intercell interference ...
Open channel flow velocity profiles for different
Ad

Similar to Comparative analysis of formwork in multistory buildin gv (20)

PDF
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
PDF
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
PDF
SELECTION OF FORMWORKS FOR BUILDING CONSTRUCTION
PDF
Effects of longer span floor system in the constancy of the multistoried stru...
PDF
Aluminium Formwork Vs Conventional Formwork
PDF
July2013 MASTERBUILDERS- FORMWORK
PDF
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
PDF
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
PDF
Development OF Low Cost Durable Precast Compound Wall
PPTX
A PRESENTATION ON PREFABRICATED STRUCTURES
PDF
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
PDF
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
PDF
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
PDF
Time, Cost , Productivity and Quality Analysis of Precast Buildings
PDF
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
PDF
The Study of Measurement of Over-Engineering in Construction Project
PDF
IRJET- Cost Estimation of a Building using Cost Effective Building Materials
PDF
ANALYSIS OF G+2 MONO-COLUMN BUILDING FOR DIFFERENT PLAN CONFIGURATIONS WITH T...
PDF
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
PPTX
MIVAN FRAMEWORK
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
SELECTION OF FORMWORKS FOR BUILDING CONSTRUCTION
Effects of longer span floor system in the constancy of the multistoried stru...
Aluminium Formwork Vs Conventional Formwork
July2013 MASTERBUILDERS- FORMWORK
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Development OF Low Cost Durable Precast Compound Wall
A PRESENTATION ON PREFABRICATED STRUCTURES
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
The Study of Measurement of Over-Engineering in Construction Project
IRJET- Cost Estimation of a Building using Cost Effective Building Materials
ANALYSIS OF G+2 MONO-COLUMN BUILDING FOR DIFFERENT PLAN CONFIGURATIONS WITH T...
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
MIVAN FRAMEWORK

More from eSAT Publishing House (20)

PDF
Likely impacts of hudhud on the environment of visakhapatnam
PDF
Impact of flood disaster in a drought prone area – case study of alampur vill...
PDF
Hudhud cyclone – a severe disaster in visakhapatnam
PDF
Groundwater investigation using geophysical methods a case study of pydibhim...
PDF
Flood related disasters concerned to urban flooding in bangalore, india
PDF
Enhancing post disaster recovery by optimal infrastructure capacity building
PDF
Effect of lintel and lintel band on the global performance of reinforced conc...
PDF
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
PDF
Wind damage to buildings, infrastrucuture and landscape elements along the be...
PDF
Shear strength of rc deep beam panels – a review
PDF
Role of voluntary teams of professional engineers in dissater management – ex...
PDF
Risk analysis and environmental hazard management
PDF
Review study on performance of seismically tested repaired shear walls
PDF
Monitoring and assessment of air quality with reference to dust particles (pm...
PDF
Low cost wireless sensor networks and smartphone applications for disaster ma...
PDF
Coastal zones – seismic vulnerability an analysis from east coast of india
PDF
Can fracture mechanics predict damage due disaster of structures
PDF
Assessment of seismic susceptibility of rc buildings
PDF
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
PDF
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Likely impacts of hudhud on the environment of visakhapatnam
Impact of flood disaster in a drought prone area – case study of alampur vill...
Hudhud cyclone – a severe disaster in visakhapatnam
Groundwater investigation using geophysical methods a case study of pydibhim...
Flood related disasters concerned to urban flooding in bangalore, india
Enhancing post disaster recovery by optimal infrastructure capacity building
Effect of lintel and lintel band on the global performance of reinforced conc...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Shear strength of rc deep beam panels – a review
Role of voluntary teams of professional engineers in dissater management – ex...
Risk analysis and environmental hazard management
Review study on performance of seismically tested repaired shear walls
Monitoring and assessment of air quality with reference to dust particles (pm...
Low cost wireless sensor networks and smartphone applications for disaster ma...
Coastal zones – seismic vulnerability an analysis from east coast of india
Can fracture mechanics predict damage due disaster of structures
Assessment of seismic susceptibility of rc buildings
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...

Recently uploaded (20)

PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
Safety Seminar civil to be ensured for safe working.
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
UNIT 4 Total Quality Management .pptx
DOCX
573137875-Attendance-Management-System-original
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PPT
introduction to datamining and warehousing
PPTX
additive manufacturing of ss316l using mig welding
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PPTX
Internet of Things (IOT) - A guide to understanding
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Construction Project Organization Group 2.pptx
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PDF
737-MAX_SRG.pdf student reference guides
PPTX
Current and future trends in Computer Vision.pptx
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Fundamentals of safety and accident prevention -final (1).pptx
Safety Seminar civil to be ensured for safe working.
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
UNIT 4 Total Quality Management .pptx
573137875-Attendance-Management-System-original
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
introduction to datamining and warehousing
additive manufacturing of ss316l using mig welding
Embodied AI: Ushering in the Next Era of Intelligent Systems
R24 SURVEYING LAB MANUAL for civil enggi
Internet of Things (IOT) - A guide to understanding
Mechanical Engineering MATERIALS Selection
Construction Project Organization Group 2.pptx
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Categorization of Factors Affecting Classification Algorithms Selection
737-MAX_SRG.pdf student reference guides
Current and future trends in Computer Vision.pptx
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...

Comparative analysis of formwork in multistory buildin gv

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Special Issue: 09 | NCETCE-2014 | June-2014, Available @ http://www.ijret.org 22 COMPARATIVE ANALYSIS OF FORMWORK IN MULTISTORY BUILDING Sandip.P.Pawar1, P.M.Atterde2 1P.G. Student Deptt of civil Engineering SSGBCOET Bhusawal Maharashtra 2Guide, Deptt of civil Engineering SSGBCOET Bhusawal Maharashtra Abstract One of the most important factors in determing the success of a construction project in terms of speed, quality cost and safety of work is the formwork used in the project as it accounts about 40% of the total project cost of the structure. When considering a construction project both the client and contractor want to finish the job early as the client wants to use the building for the intended purpose as soon as possible. The contractor wants to finish the construction as soon as possible to gain a higher profit. The most efficient way to speed up the work in high-rise building construction is by achieving a very short floor cycle. The floor cycle of a building mainly depend on the formwork type as it is the main time factor of a building project. The aim of this paper is to present about the existing formwork types in Maharashtra and to show each one will affect the project duration, project cost and the quality of the work. For that a research has been carried out and the results will present in this paper. Keywords: Formwork,Duration,cost,quality ---------------------------------------------------------------------***--------------------------------------------------------------------- 1.INTRODUCTION Formwork is defined as temporary structure whos purpose is to provide support and containment for fresh concrete until it can support itself. It moulds the concrete to the desired shape and size and controls its position and alignment. The development of formworks is parallel with the growth of concrete construction throughout the 20th century. The advancement of technology, increase of population and the space limitation lead the way to construct high-rise buildings. But the task was not very easy at the beginning but now the man made the task easy by inventing new machinery and new techniques. The most important factor in terms of cost, quality and speed in a high-rise building construction project is the type of the formwork used in the project. The first formwork type to be used is the conventional type formwork where the timber planks were supported on timber columns. With the advancement of technology it developed gradually and people used ply wood sheets instead of timber planks and steel pipes with jacks were used to support the ply wood. Then people invented small units of formworks and connect the repeating units in the construction. The larger units were invented like formworks for slab panels, formworks for columns, beams…etc. when the same elements are repeating. Then finally the whole system of formwork is made and initially the material used to it was steel and it was very heavy. Then the aim was to reduce the weight of the system and the materials for formwork have extended to aluminium, plastic, fiber glass…etc. contractors are in a belief that the system formwork is suitable only for super tall buildings as the initial cost of the system formwork is a bit high. Though the initial cost of the system formwork is a bit high it reduces the project duration and hence the total project cost. When considering the overall construction of a high-rise building the system formwork is much more economical that to all the other primary formwork types as it reduces the project duration, gives a smooth concrete surface and the repetitive use of the system. This is suitable for even for a two or three storey housing scheme of several houses. 2. TYPES OF FORMWORKS Conventional Formwork: This is the oldest type of formwork used in the construction industry. This type uses timber, bamboo, masonry and carpentry in the construction. This type is very much suitable for small houses with two to three storeys and still they are in use for such constructions. But this is not suitable for the big projects or high-rise buildings. Low initial cost, low experience factor, low weight are some of the advantages of this type and poor finish, high labor requirement, skilled labor. requirement and consume lot of time are some of the disadvantages. Modern Conventional Formwork: This type is very much closer to the conventional formwork and in simple words this is one step advanced than the conventional type. The same technique has used in the both types and the only difference is the materials use for the formworks. In modern conventional formwork more advanced materials are used and they can reuse for several times. The differences of both types are that steel props and various types of jacks (U jacks, T jacks) are used as supports in the formwork instead of timber supports and ply wood sheets are used instead of timber planks on slab decks, beams and columns. Low initial cost, low skilled labor requirement, can even use in small places and when there are lot of deviations in the structure are some of the advantages while poor finish of the
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Special Issue: 09 | NCETCE-2014 | June-2014, Available @ http://www.ijret.org 23 concrete surface, high labor requirement and the higher floor cycle are the disadvantages This type is much more advanced than the modern conventional type. In this type there are pre-fabricated formwork items such as pre-fabricated formworks for slab panels and supports and ply wood should be used additionally for slab deck, beams and columns for the surface. There are other forms of semi system formwork such as table forms, flying forms…etc. DOCA is the most famous brand for this type of formwork and some people know about this type only as “DOCA formwork”. System Formwork: System formwork has prefabricated modular components with casting panels. The system formwork is fabricated as it suits the required shape. The biggest advantage of this type is the speedy and quality construction. But the high initial cost is the main disadvantage and hence it is not economical to use in low – rise buildings. But this is the most economical form of formwork type to be used in high-rise building construction when it is having few typical storeys. 3. RESEARCH STUDY The expectation of this study is to find the most economical formwork type to be used in a high-rise building project. When considering a construction project there are many cost components contributing to the total cost of the project. Preliminary cost is a key cost component when comparing the total cost of a project, and the duration of the project is the governing factor for the preliminary running cost. Total Project Cost = Materials and labour + Preliminary cost + Machinery & equipment t+ Waste material handling + Safety + Finishes + … Preliminary Cost = Salaries + work establishment charge + Security … When a building construction project is considered the material requirement is unique as it depends on the design. But the labor requirement and the duration of the project are directly affected by the technologies and the construction methods used in the project. The speed of the project is directly affected by the formwork type used in the project. This is the most critical in high-rise building construction. When using latest technologies, the labor requirement and the time duration can beminimized in the project, mainly for the super structure. In high-rise building projects time controlling factor is the formwork as it directly affect the floor cycle and hence it will reduce the time taken to construct the main structure and because of that the total duration of the project will go down drastically. In this research cost comparisons of total project cost has done for several projects when all the two types of formwork types are used in the same project. 4. THE RESULTS 4.1 The Results Obtained Data is collected from M/s Sai Construction Ahmednagar .Name of Construction work on Residetial Building of KARAN RHEA Wing A,Wing B,&Wing C at Wadegaon Sheri, Pune projects and calculations are done for the total project cost of the selected projects when using different types of formworks in the construction. In the calculations all the parameters are kept same and only the formwork type is changed. At the same time all the factors affect due to the formwork type is considered. The results can be shown in a table as follows. Table .1 Project No.of Floor Area of each floor (sqm) Total cost of Project Wing A 10 418 11,24,42,000 Wing B 15 510 13,71,90,000 Wing C 20 600 16,14,40,000 Table .2 Analysis of the Aluminium formwork for Typical Floor Wing A aA1 11 Wing B 2 Wing C 3 Form work cost in Laks 9.82 11.98 14.1 Waist disposal cost in Laks 0 0 0 Machinary cost in Laks 0.9 1.12 1.98 For Aluminium form work Table 3 . Analysis of the conventional formwork for Typical Floor Wing A aA1 11 Wing B 2 Wing C 3 Form work cost in Laks 6.27 7.65 9.0 Waist disposal cost in Laks 0.31 0.38 0.45 0 5 10 15 Tower 1 Tower 2 Tower 3 Form work cost in Laks Waist disposal cost in Laks
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Special Issue: 09 | NCETCE-2014 | June-2014, Available @ http://www.ijret.org 24 Machinary cost in Laks 0.5 0.85 1.25 For Conventional Form work 5. CONCLUSIONS From the results obtained we can come to a conclusion that when the system formwork is used in the construction project, the total project cost and the duration of the project is lesser than the other formwork types. The main important thing is that the aluminium panel system formwork is the most expensive formwork type from those three types. At the same time the highest total project cost is obtained when modern conventional type of formwork is used in the building construction project which is the least expensive formwork type. So it is clearly seen that that not the cost of formwork directly affected to the total project cost but the type of formwork. The floor cycle will be 6-10 days when the system formwork is in use and hence the total project duration will be reduced. At the same time a smooth concrete surface can be obtained as the system can be assembled without any discontinuities in the surface and hence less finishing work will be there and hence the cost for finishes will be reduced. There will be less waste disposal and less machinery usage. Not only the direct benefits, there are many indirect benefits of using aluminium panel system formwork in the high-rise building construction projects. For example the system can be sold after using, it can be used in other slabs doing slight variations (there is no need to buy materials again). REFERENCES [1] Hurd, M.K. 1989. Formwork for Concrete, 6th ed. American Concrete Institute, Detroit, MI. [2] Nolan, É. Innovation in concrete frame construction 1995–2015. IHS BRE Press, Garston. BR 483. 44pp [3] Moore, C.E. 1977. Concrete Form Construction. Van Nostrand Reinhold, New York. [4] Ratay, R.T. 1984. Handbook of Temporary Structures in Construction. McGraw-Hill, New York [5] Peurifoy, P.E. 1976. Formwork for Concrete Structures. McGraw-Hill, New York. Plasticizer” International Scholarly Research Network ISRN Civil Engineering Volume 2012, Article ID 469272, 5 pages doi:10.5402/2012/469272 2005. [6] Ketan Shah, " Modular formwork for faster, economical and quality construction", Indian Concrete Journal, July 2005, Volume 79,Pg.6-23. [7] “Formwork & Scaffolding”, CE & CR, September 1992, Vol. 05, No. 9, Pg. 46-57. [8] Ashok Mandal, "Scaffolding & Formwork- Maintenance & Safety",CE & CR, August 2006, Vol. 19, No. 8, Pg. 46-50. [9] "Emerging Trends In Formwork And Scaffolding", CE & CR, Sep 92,Pg.46-49. [10] "ConstructionEquipment",CE&CR,Mayl992,Pg.50- 52. [11] IS14687(Falsework For Concrete Structures- Guidelines) BIOGRAPHIES Sandip P.Pawar Completed B.E. in civil Engineering 2009 and M.E appear in Construction Technology & Management in North Maharashtra University Jalgaon (MS). P.M.Atterde (Department of civil engineering SSGBCOET Bhusawal) 0 2 4 6 8 10 Tower 1 Tower 2 Tower 3 Form work cost in Laks Waist disposal cost in Laks