COST ESTIMATE
DEVELOPMENT
SEQUENCE
ImplementA System
Adjust For Better Performance
Your biggest challenges as a cost
estimator:
Your biggest challenges as a cost
estimator:
■ Accurate and complete project information
Your biggest challenges as a cost
estimator:
■ Accurate and complete project information
■ Access to cost data
Your biggest challenges as a cost
estimator:
■ Accurate and complete project information
■ Access to cost data
■ Produce a cost estimate that meets the expectations of the review team
Your biggest challenges as a cost
estimator:
■ Accurate and complete project information
■ Access to cost data
■ Produce a cost estimate that meets the expectations of the review team
■ Meet the deadline for cost estimate completion
Your biggest challenges as a cost
estimator:
■ Accurate and complete project information
■ Access to cost data
■ Produce a cost estimate that meets the expectations of the review team
■ Meet the deadline for cost estimate completion
■ Validate the cost estimate
You can overcome those challenges by…
You can overcome those challenges by…
■ Planning your cost estimating development activities
You can overcome those challenges by…
■ Planning your cost estimating development activities
■ Measure your performance
You can overcome those challenges by…
■ Planning your cost estimating development activities
■ Measure your performance
■ Ask for feedback from the review team
You can overcome those challenges by…
■ Planning your cost estimating development activities
■ Measure your performance
■ Ask for feedback from the review team
■ Adjust your plan for the next cost estimate
You can overcome those challenges by…
■ Planning your cost estimating development activities
■ Measure your performance
■ Ask for feedback from the review team
■ Adjust your plan for the next cost estimate
■ Rinse and repeat!
So, here is my step-by-step strategy:
Step 1
Step 1
1. Review all available documents
Step 1
1. Review all available documents
– Ask for clarifications
Step 1
1. Review all available documents
– Ask for clarifications
– Take notes on all missing/incomplete information
Step 1
1. Review all available documents
– Ask for clarifications
– Take notes on all missing/incomplete information
– Set-up a request for clarification registry
Step 1
1. Review all available documents
– Ask for clarifications
– Take notes on all missing/incomplete information
– Set-up a request for clarification registry
– Set-up a risk/opportunity registry and add all relevant information
Step 1
1. Review all available documents
– Ask for clarifications
– Take notes on all missing/incomplete information
– Set-up a request for clarification registry
– Set-up a risk/opportunity registry and add all relevant information
– Make a habit to review documents for all specifications which might have an impact
on cost
Step 1
1. Review all available documents
– Ask for clarifications
– Take notes on all missing/incomplete information
– Set-up a request for clarification registry
– Set-up a risk/opportunity registry and add all relevant information
– Make a habit to review documents for all specifications which might have an impact
on cost
– Build-up the project in your mind theatre and take the time to see the big picture
Step 2
Step 2
2. Define the purpose of the cost estimate:
Step 2
2. Define the purpose of the cost estimate:
– Is it a cost estimate for a tender submission?
Step 2
2. Define the purpose of the cost estimate:
– Is it a cost estimate for a tender submission?
– Or, is it a budget cost estimate for a client/owner/engineering firm? If so, what is the
expected accuracy?
Step 3
Step 3
3. Set-up the cost estimate development kick-off meeting
Step 3
3. Set-up the cost estimate development kick-off meeting
– Invite all cost estimate review team members
Step 3
3. Set-up the cost estimate development kick-off meeting
– Invite all cost estimate review team members
– Feel free to invite construction professionals within the company who might have a
valuable input
Step 3
3. Set-up the cost estimate development kick-off meeting
– Invite all cost estimate review team members
– Feel free to invite construction professionals within the company who might have a
valuable input
– Discuss:
Step 3
3. Set-up the cost estimate development kick-off meeting
– Invite all cost estimate review team members
– Feel free to invite construction professionals within the company who might have a
valuable input
– Discuss:
■ Constructability methods
Step 3
3. Set-up the cost estimate development kick-off meeting
– Invite all cost estimate review team members
– Feel free to invite construction professionals within the company who might have a
valuable input
– Discuss:
■ Constructability methods
■ Price sourcing strategy
Step 3
3. Set-up the cost estimate development kick-off meeting
– Invite all cost estimate review team members
– Feel free to invite construction professionals within the company who might have a
valuable input
– Discuss:
■ Constructability methods
■ Price sourcing strategy
– What scope will be subcontracted?
Step 3
3. Set-up the cost estimate development kick-off meeting
– Invite all cost estimate review team members
– Feel free to invite construction professionals within the company who might have a
valuable input
– Discuss:
■ Constructability methods
■ Price sourcing strategy
– What scope will be subcontracted?
– What scope will be self-performed?
Step 3
3. Set-up the cost estimate development kick-off meeting
– Invite all cost estimate review team members
– Feel free to invite construction professionals within the company who might have a
valuable input
– Discuss:
■ Constructability methods
■ Price sourcing strategy
– What scope will be subcontracted?
– What scope will be self-performed?
– How many quotations will be required to validate a price?
Step 4
Step 4
4. Develop the cost estimate schedule:
Step 4
4. Develop the cost estimate schedule:
– List all activities needed to be performed to complete the cost estimate
Step 4
4. Develop the cost estimate schedule:
– List all activities needed to be performed to complete the cost estimate
– Estimate the time required for each activity
Step 4
4. Develop the cost estimate schedule:
– List all activities needed to be performed to complete the cost estimate
– Estimate the time required for each activity
– Build the schedule logic and determine the milestones
Step 4
4. Develop the cost estimate schedule:
– List all activities needed to be performed to complete the cost estimate
– Estimate the time required for each activity
– Build the schedule logic and determine the milestones
– Determine the resource required for cost estimate completion
Step 4
4. Develop the cost estimate schedule:
– List all activities needed to be performed to complete the cost estimate
– Estimate the time required for each activity
– Build the schedule logic and determine the milestones
– Determine the resource required for cost estimate completion
– Communicate with management regarding the resource requirements
Step 4
4. Develop the cost estimate schedule:
– List all activities needed to be performed to complete the cost estimate
– Estimate the time required for each activity
– Build the schedule logic and determine the milestones
– Determine the resource required for cost estimate completion
– Communicate with management regarding the resource requirements
– Build-in time for unexpected activities: last minute take-off for subcontractor price
review and validation, changes to the project documents, etc.
Step 4
4. Develop the cost estimate schedule:
– List all activities needed to be performed to complete the cost estimate
– Estimate the time required for each activity
– Build the schedule logic and determine the milestones
– Determine the resource required for cost estimate completion
– Communicate with management regarding the resource requirements
– Build-in time for unexpected activities: last minute take-off for subcontractor price
review and validation, changes to the project documents, etc.
– Build-in time for cost estimate reviews
Step 5
Step 5
5. DevelopWork Breakdown Structure to meet the following requirements:
Step 5
5. DevelopWork Breakdown Structure to meet the following requirements:
– Tender closing and submission
Step 5
5. DevelopWork Breakdown Structure to meet the following requirements:
– Tender closing and submission
– Cost estimate review
Step 5
5. DevelopWork Breakdown Structure to meet the following requirements:
– Tender closing and submission
– Cost estimate review
– Price sourcing strategy
Step 5
5. DevelopWork Breakdown Structure to meet the following requirements:
– Tender closing and submission
– Cost estimate review
– Price sourcing strategy
– Construction methodology
Step 5
5. DevelopWork Breakdown Structure to meet the following requirements:
– Tender closing and submission
– Cost estimate review
– Price sourcing strategy
– Construction methodology
– Estimate validation and benchmarking
Step 5
5. DevelopWork Breakdown Structure to meet the following requirements:
– Tender closing and submission
– Cost estimate review
– Price sourcing strategy
– Construction methodology
– Estimate validation and benchmarking
– Internal database update
Step 6
Step 6
6. Develop the cost estimate:
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
– Develop indirect costs based on preliminary construction schedule
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
– Develop indirect costs based on preliminary construction schedule
– Optimize resources
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
– Develop indirect costs based on preliminary construction schedule
– Optimize resources
– Update costs as they become available from subcontractors/suppliers
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
– Develop indirect costs based on preliminary construction schedule
– Optimize resources
– Update costs as they become available from subcontractors/suppliers
– Incorporate all additional information if applicable (changes to the project
documents, clarifications, etc.)
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
– Develop indirect costs based on preliminary construction schedule
– Optimize resources
– Update costs as they become available from subcontractors/suppliers
– Incorporate all additional information if applicable (changes to the project
documents, clarifications, etc.)
– Price and incorporate risk registry items as applicable
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
– Develop indirect costs based on preliminary construction schedule
– Optimize resources
– Update costs as they become available from subcontractors/suppliers
– Incorporate all additional information if applicable (changes to the project
documents, clarifications, etc.)
– Price and incorporate risk registry items as applicable
– Review cost estimate draft with the review team
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
– Develop indirect costs based on preliminary construction schedule
– Optimize resources
– Update costs as they become available from subcontractors/suppliers
– Incorporate all additional information if applicable (changes to the project
documents, clarifications, etc.)
– Price and incorporate risk registry items as applicable
– Review cost estimate draft with the review team
– Update the cost estimate as per review notes
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
– Develop indirect costs based on preliminary construction schedule
– Optimize resources
– Update costs as they become available from subcontractors/suppliers
– Incorporate all additional information if applicable (changes to the project
documents, clarifications, etc.)
– Price and incorporate risk registry items as applicable
– Review cost estimate draft with the review team
– Update the cost estimate as per review notes
– Update costs as more information becomes available from subcontractors/suppliers
Step 6
6. Develop the cost estimate:
– Quantity take-offs based onWBS and price sourcing strategy
– Develop direct costs
– Develop indirect costs based on preliminary construction schedule
– Optimize resources
– Update costs as they become available from subcontractors/suppliers
– Incorporate all additional information if applicable (changes to the project
documents, clarifications, etc.)
– Price and incorporate risk registry items as applicable
– Review cost estimate draft with the review team
– Update the cost estimate as per review notes
– Update costs as more information becomes available from subcontractors/suppliers
– Final cost estimate and tender submission review.
Your turn now!What is your best
strategy?
Please leave your comments and share what works best for you. How do you manage to
finish your cost estimates on time and have them pass the final review?
Do you want to see what others are saying about the challenges they face as cost
estimators?Take the survey, it is anonymous:
https://goo.gl/forms/udLFq83q5Su7j5uY2
Thank you for clicking through the full slide deck!
Want to read more about cost estimating?You can find me blogging at
www.LearnCostEstimating.com
Or, send me an email at Doina.Dobre@EmeraldGroup.ca

More Related Content

PPTX
Composite Crews in Construction Cost Estimating
PDF
PPT on Construction Costing
PPT
Estimation and costing
PPTX
ESTIMATING AND COSTING
PPTX
Purpose of estimation
PDF
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
PPTX
Workshop costing elements
PPTX
Ppv ppt
Composite Crews in Construction Cost Estimating
PPT on Construction Costing
Estimation and costing
ESTIMATING AND COSTING
Purpose of estimation
Preparing cost estimate for manufactured products.ppt by-aragaw gebremedhin
Workshop costing elements
Ppv ppt

What's hot (20)

PPTX
Estimation and Costing
PPTX
Approximate estimate
PDF
Costing_Actual spendings & pricing
PPT
Project cost stimating
PDF
Cost estimation
PPT
Estimation (power point)
PDF
Estimating part 1
PPTX
Estimating and Costing
PPT
Construction Estimating
PDF
Key Components of Cost Estimation in construction
PDF
Chapter2 -cost_estimation_umy_sep2011
PDF
5. cost estimation
PPTX
Job costing and batch costing
PPTX
Contract costing
PPTX
Cost and management accounting
PPTX
Contract account
PPTX
Job,batch and contract costing
PPTX
Over head expensions IN process planning & cost estimation by G.DINESHPIRAN
PPTX
Contract costing
PPT
Cost estimating & Costing
Estimation and Costing
Approximate estimate
Costing_Actual spendings & pricing
Project cost stimating
Cost estimation
Estimation (power point)
Estimating part 1
Estimating and Costing
Construction Estimating
Key Components of Cost Estimation in construction
Chapter2 -cost_estimation_umy_sep2011
5. cost estimation
Job costing and batch costing
Contract costing
Cost and management accounting
Contract account
Job,batch and contract costing
Over head expensions IN process planning & cost estimation by G.DINESHPIRAN
Contract costing
Cost estimating & Costing
Ad

Viewers also liked (20)

PDF
Construction Cost Estimating Training
PPTX
Construction Cost Estimating
PPTX
Construction Cost Estimating - Quality Cost Estimating
PPTX
Learn Detailed Cost Estimating for Concrete Structures in 26 days!
PDF
Aisc w
PPTX
Commissioning of Industrial Projects - Cost Estimating Considerations
PDF
Construction Estimate worksheet
PPTX
Preliminary estimate
PPTX
Estimation and quantity surveying
PDF
Estimating and-costing book
PDF
The professional interview questions
PPTX
Types of estimates
PDF
COMPARATIVE STUDY OF THE EFFECT OF TREATED COIR FIBER AND NATURAL RUBBER MODI...
PPT
Economics1 216181522-111024050500-phpapp01
PDF
12 theory of cost and estimation
DOC
Building estimator performance appraisal
PPTX
Waste Plastic Recycling For Bitumen
PDF
Cost Theory and Estimation
PPT
Business Economics 07 Theory of Cost
PDF
Capital cost estimating – owner’s costs in an EPC project delivery method
Construction Cost Estimating Training
Construction Cost Estimating
Construction Cost Estimating - Quality Cost Estimating
Learn Detailed Cost Estimating for Concrete Structures in 26 days!
Aisc w
Commissioning of Industrial Projects - Cost Estimating Considerations
Construction Estimate worksheet
Preliminary estimate
Estimation and quantity surveying
Estimating and-costing book
The professional interview questions
Types of estimates
COMPARATIVE STUDY OF THE EFFECT OF TREATED COIR FIBER AND NATURAL RUBBER MODI...
Economics1 216181522-111024050500-phpapp01
12 theory of cost and estimation
Building estimator performance appraisal
Waste Plastic Recycling For Bitumen
Cost Theory and Estimation
Business Economics 07 Theory of Cost
Capital cost estimating – owner’s costs in an EPC project delivery method
Ad

Similar to Cost Estimate Development Sequence (20)

PPSX
Show of pac presentation process and template
PPTX
Session 9 4th edition PMP
PPTX
Editable Elements
PPTX
Value Stream Mapping
PPTX
PPT
E success client-software-development
DOCX
(DRAFT)Assessment 2 Appendix B – Learning and de.docx
PPTX
feasibility study and idea alanysis-- semi 1
PPT
Project life cycle_management by Subbu
PPT
PGP New Product Generation Project 2003
PPTX
Inside Gainsight’s New Post-Sales Structure: Reorganizing the Team to Drive C...
PDF
How We Reorganized Our Entire Post-Sales Organization
PDF
Project Management
PDF
Process Improvement Framework
PPTX
PMP-Cost Management area
PPTX
Risk Management & Value Engineering.pptx
PPTX
capability-visioning-peeling-the-onion-templates.pptx
PPT
7 cost managmenet
PPT
importance of estimation power point presentation
PPT
Quality Function Deployment (QFD) Seminar Presentation
Show of pac presentation process and template
Session 9 4th edition PMP
Editable Elements
Value Stream Mapping
E success client-software-development
(DRAFT)Assessment 2 Appendix B – Learning and de.docx
feasibility study and idea alanysis-- semi 1
Project life cycle_management by Subbu
PGP New Product Generation Project 2003
Inside Gainsight’s New Post-Sales Structure: Reorganizing the Team to Drive C...
How We Reorganized Our Entire Post-Sales Organization
Project Management
Process Improvement Framework
PMP-Cost Management area
Risk Management & Value Engineering.pptx
capability-visioning-peeling-the-onion-templates.pptx
7 cost managmenet
importance of estimation power point presentation
Quality Function Deployment (QFD) Seminar Presentation

Recently uploaded (20)

DOCX
mcsp232projectguidelinesjan2023 (1).docx
PDF
MCQ Practice CBT OL Official Language 1.pptx.pdf
PPT
notes_Lecture2 23l3j2 dfjl dfdlkj d 2.ppt
DOC
field study for teachers graduating samplr
PPTX
cse couse aefrfrqewrbqwrgbqgvq2w3vqbvq23rbgw3rnw345
PPT
BCH3201 (Enzymes and biocatalysis)-JEB (1).ppt
PPTX
Prokaryotes v Eukaryotes PowerPoint.pptx
PPTX
Surgical thesis protocol formation ppt.pptx
PDF
Understanding the Rhetorical Situation Presentation in Blue Orange Muted Il_2...
PDF
LSR CASEBOOK 2024-25.pdf. very nice casbook
PPTX
microtomy kkk. presenting to cryst in gl
PPT
NO000387 (1).pptsbsnsnsnsnsnsnsmsnnsnsnsjsnnsnsnsnnsnnansnwjwnshshshs
PDF
Blue-Modern-Elegant-Presentation (1).pdf
PDF
servsafecomprehensive-ppt-full-140617222538-phpapp01.pdf
PDF
313302 DBMS UNIT 1 PPT for diploma Computer Eng Unit 2
PDF
CV of Architect Professor A F M Mohiuddin Akhand.pdf
PPTX
PE3-WEEK-3sdsadsadasdadadwadwdsdddddd.pptx
PPTX
Definition and Relation of Food Science( Lecture1).pptx
PPTX
Job-opportunities lecture about it skills
PPTX
Slideham presentation for the students a
mcsp232projectguidelinesjan2023 (1).docx
MCQ Practice CBT OL Official Language 1.pptx.pdf
notes_Lecture2 23l3j2 dfjl dfdlkj d 2.ppt
field study for teachers graduating samplr
cse couse aefrfrqewrbqwrgbqgvq2w3vqbvq23rbgw3rnw345
BCH3201 (Enzymes and biocatalysis)-JEB (1).ppt
Prokaryotes v Eukaryotes PowerPoint.pptx
Surgical thesis protocol formation ppt.pptx
Understanding the Rhetorical Situation Presentation in Blue Orange Muted Il_2...
LSR CASEBOOK 2024-25.pdf. very nice casbook
microtomy kkk. presenting to cryst in gl
NO000387 (1).pptsbsnsnsnsnsnsnsmsnnsnsnsjsnnsnsnsnnsnnansnwjwnshshshs
Blue-Modern-Elegant-Presentation (1).pdf
servsafecomprehensive-ppt-full-140617222538-phpapp01.pdf
313302 DBMS UNIT 1 PPT for diploma Computer Eng Unit 2
CV of Architect Professor A F M Mohiuddin Akhand.pdf
PE3-WEEK-3sdsadsadasdadadwadwdsdddddd.pptx
Definition and Relation of Food Science( Lecture1).pptx
Job-opportunities lecture about it skills
Slideham presentation for the students a

Cost Estimate Development Sequence

  • 2. Your biggest challenges as a cost estimator:
  • 3. Your biggest challenges as a cost estimator: ■ Accurate and complete project information
  • 4. Your biggest challenges as a cost estimator: ■ Accurate and complete project information ■ Access to cost data
  • 5. Your biggest challenges as a cost estimator: ■ Accurate and complete project information ■ Access to cost data ■ Produce a cost estimate that meets the expectations of the review team
  • 6. Your biggest challenges as a cost estimator: ■ Accurate and complete project information ■ Access to cost data ■ Produce a cost estimate that meets the expectations of the review team ■ Meet the deadline for cost estimate completion
  • 7. Your biggest challenges as a cost estimator: ■ Accurate and complete project information ■ Access to cost data ■ Produce a cost estimate that meets the expectations of the review team ■ Meet the deadline for cost estimate completion ■ Validate the cost estimate
  • 8. You can overcome those challenges by…
  • 9. You can overcome those challenges by… ■ Planning your cost estimating development activities
  • 10. You can overcome those challenges by… ■ Planning your cost estimating development activities ■ Measure your performance
  • 11. You can overcome those challenges by… ■ Planning your cost estimating development activities ■ Measure your performance ■ Ask for feedback from the review team
  • 12. You can overcome those challenges by… ■ Planning your cost estimating development activities ■ Measure your performance ■ Ask for feedback from the review team ■ Adjust your plan for the next cost estimate
  • 13. You can overcome those challenges by… ■ Planning your cost estimating development activities ■ Measure your performance ■ Ask for feedback from the review team ■ Adjust your plan for the next cost estimate ■ Rinse and repeat!
  • 14. So, here is my step-by-step strategy: Step 1
  • 15. Step 1 1. Review all available documents
  • 16. Step 1 1. Review all available documents – Ask for clarifications
  • 17. Step 1 1. Review all available documents – Ask for clarifications – Take notes on all missing/incomplete information
  • 18. Step 1 1. Review all available documents – Ask for clarifications – Take notes on all missing/incomplete information – Set-up a request for clarification registry
  • 19. Step 1 1. Review all available documents – Ask for clarifications – Take notes on all missing/incomplete information – Set-up a request for clarification registry – Set-up a risk/opportunity registry and add all relevant information
  • 20. Step 1 1. Review all available documents – Ask for clarifications – Take notes on all missing/incomplete information – Set-up a request for clarification registry – Set-up a risk/opportunity registry and add all relevant information – Make a habit to review documents for all specifications which might have an impact on cost
  • 21. Step 1 1. Review all available documents – Ask for clarifications – Take notes on all missing/incomplete information – Set-up a request for clarification registry – Set-up a risk/opportunity registry and add all relevant information – Make a habit to review documents for all specifications which might have an impact on cost – Build-up the project in your mind theatre and take the time to see the big picture
  • 23. Step 2 2. Define the purpose of the cost estimate:
  • 24. Step 2 2. Define the purpose of the cost estimate: – Is it a cost estimate for a tender submission?
  • 25. Step 2 2. Define the purpose of the cost estimate: – Is it a cost estimate for a tender submission? – Or, is it a budget cost estimate for a client/owner/engineering firm? If so, what is the expected accuracy?
  • 27. Step 3 3. Set-up the cost estimate development kick-off meeting
  • 28. Step 3 3. Set-up the cost estimate development kick-off meeting – Invite all cost estimate review team members
  • 29. Step 3 3. Set-up the cost estimate development kick-off meeting – Invite all cost estimate review team members – Feel free to invite construction professionals within the company who might have a valuable input
  • 30. Step 3 3. Set-up the cost estimate development kick-off meeting – Invite all cost estimate review team members – Feel free to invite construction professionals within the company who might have a valuable input – Discuss:
  • 31. Step 3 3. Set-up the cost estimate development kick-off meeting – Invite all cost estimate review team members – Feel free to invite construction professionals within the company who might have a valuable input – Discuss: ■ Constructability methods
  • 32. Step 3 3. Set-up the cost estimate development kick-off meeting – Invite all cost estimate review team members – Feel free to invite construction professionals within the company who might have a valuable input – Discuss: ■ Constructability methods ■ Price sourcing strategy
  • 33. Step 3 3. Set-up the cost estimate development kick-off meeting – Invite all cost estimate review team members – Feel free to invite construction professionals within the company who might have a valuable input – Discuss: ■ Constructability methods ■ Price sourcing strategy – What scope will be subcontracted?
  • 34. Step 3 3. Set-up the cost estimate development kick-off meeting – Invite all cost estimate review team members – Feel free to invite construction professionals within the company who might have a valuable input – Discuss: ■ Constructability methods ■ Price sourcing strategy – What scope will be subcontracted? – What scope will be self-performed?
  • 35. Step 3 3. Set-up the cost estimate development kick-off meeting – Invite all cost estimate review team members – Feel free to invite construction professionals within the company who might have a valuable input – Discuss: ■ Constructability methods ■ Price sourcing strategy – What scope will be subcontracted? – What scope will be self-performed? – How many quotations will be required to validate a price?
  • 37. Step 4 4. Develop the cost estimate schedule:
  • 38. Step 4 4. Develop the cost estimate schedule: – List all activities needed to be performed to complete the cost estimate
  • 39. Step 4 4. Develop the cost estimate schedule: – List all activities needed to be performed to complete the cost estimate – Estimate the time required for each activity
  • 40. Step 4 4. Develop the cost estimate schedule: – List all activities needed to be performed to complete the cost estimate – Estimate the time required for each activity – Build the schedule logic and determine the milestones
  • 41. Step 4 4. Develop the cost estimate schedule: – List all activities needed to be performed to complete the cost estimate – Estimate the time required for each activity – Build the schedule logic and determine the milestones – Determine the resource required for cost estimate completion
  • 42. Step 4 4. Develop the cost estimate schedule: – List all activities needed to be performed to complete the cost estimate – Estimate the time required for each activity – Build the schedule logic and determine the milestones – Determine the resource required for cost estimate completion – Communicate with management regarding the resource requirements
  • 43. Step 4 4. Develop the cost estimate schedule: – List all activities needed to be performed to complete the cost estimate – Estimate the time required for each activity – Build the schedule logic and determine the milestones – Determine the resource required for cost estimate completion – Communicate with management regarding the resource requirements – Build-in time for unexpected activities: last minute take-off for subcontractor price review and validation, changes to the project documents, etc.
  • 44. Step 4 4. Develop the cost estimate schedule: – List all activities needed to be performed to complete the cost estimate – Estimate the time required for each activity – Build the schedule logic and determine the milestones – Determine the resource required for cost estimate completion – Communicate with management regarding the resource requirements – Build-in time for unexpected activities: last minute take-off for subcontractor price review and validation, changes to the project documents, etc. – Build-in time for cost estimate reviews
  • 46. Step 5 5. DevelopWork Breakdown Structure to meet the following requirements:
  • 47. Step 5 5. DevelopWork Breakdown Structure to meet the following requirements: – Tender closing and submission
  • 48. Step 5 5. DevelopWork Breakdown Structure to meet the following requirements: – Tender closing and submission – Cost estimate review
  • 49. Step 5 5. DevelopWork Breakdown Structure to meet the following requirements: – Tender closing and submission – Cost estimate review – Price sourcing strategy
  • 50. Step 5 5. DevelopWork Breakdown Structure to meet the following requirements: – Tender closing and submission – Cost estimate review – Price sourcing strategy – Construction methodology
  • 51. Step 5 5. DevelopWork Breakdown Structure to meet the following requirements: – Tender closing and submission – Cost estimate review – Price sourcing strategy – Construction methodology – Estimate validation and benchmarking
  • 52. Step 5 5. DevelopWork Breakdown Structure to meet the following requirements: – Tender closing and submission – Cost estimate review – Price sourcing strategy – Construction methodology – Estimate validation and benchmarking – Internal database update
  • 54. Step 6 6. Develop the cost estimate:
  • 55. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy
  • 56. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs
  • 57. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs – Develop indirect costs based on preliminary construction schedule
  • 58. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs – Develop indirect costs based on preliminary construction schedule – Optimize resources
  • 59. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs – Develop indirect costs based on preliminary construction schedule – Optimize resources – Update costs as they become available from subcontractors/suppliers
  • 60. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs – Develop indirect costs based on preliminary construction schedule – Optimize resources – Update costs as they become available from subcontractors/suppliers – Incorporate all additional information if applicable (changes to the project documents, clarifications, etc.)
  • 61. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs – Develop indirect costs based on preliminary construction schedule – Optimize resources – Update costs as they become available from subcontractors/suppliers – Incorporate all additional information if applicable (changes to the project documents, clarifications, etc.) – Price and incorporate risk registry items as applicable
  • 62. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs – Develop indirect costs based on preliminary construction schedule – Optimize resources – Update costs as they become available from subcontractors/suppliers – Incorporate all additional information if applicable (changes to the project documents, clarifications, etc.) – Price and incorporate risk registry items as applicable – Review cost estimate draft with the review team
  • 63. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs – Develop indirect costs based on preliminary construction schedule – Optimize resources – Update costs as they become available from subcontractors/suppliers – Incorporate all additional information if applicable (changes to the project documents, clarifications, etc.) – Price and incorporate risk registry items as applicable – Review cost estimate draft with the review team – Update the cost estimate as per review notes
  • 64. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs – Develop indirect costs based on preliminary construction schedule – Optimize resources – Update costs as they become available from subcontractors/suppliers – Incorporate all additional information if applicable (changes to the project documents, clarifications, etc.) – Price and incorporate risk registry items as applicable – Review cost estimate draft with the review team – Update the cost estimate as per review notes – Update costs as more information becomes available from subcontractors/suppliers
  • 65. Step 6 6. Develop the cost estimate: – Quantity take-offs based onWBS and price sourcing strategy – Develop direct costs – Develop indirect costs based on preliminary construction schedule – Optimize resources – Update costs as they become available from subcontractors/suppliers – Incorporate all additional information if applicable (changes to the project documents, clarifications, etc.) – Price and incorporate risk registry items as applicable – Review cost estimate draft with the review team – Update the cost estimate as per review notes – Update costs as more information becomes available from subcontractors/suppliers – Final cost estimate and tender submission review.
  • 66. Your turn now!What is your best strategy? Please leave your comments and share what works best for you. How do you manage to finish your cost estimates on time and have them pass the final review? Do you want to see what others are saying about the challenges they face as cost estimators?Take the survey, it is anonymous: https://goo.gl/forms/udLFq83q5Su7j5uY2 Thank you for clicking through the full slide deck! Want to read more about cost estimating?You can find me blogging at www.LearnCostEstimating.com Or, send me an email at Doina.Dobre@EmeraldGroup.ca