BLD 60104 CONSTRUCTION TECHNOLOGY
1
Site and Temporary Works
Leong Li Jing 0323628
Gillian Chong 0323941
Chia Sze Sian 0323574
Chan Qi Han 0324315
Yap Zheng Xiang 0322411
Michelle Tung Man Kaye 0324175
Accessibility to Site
 Accessible routes from all entrances and exit
for construction and public use
 New sites or existing sites
 Conditions:
- Slope
- Bends
- Sharp corners
- Gradient
- Width
Services
 Actions:
 Planning the works
 Locating and identifying buried services
 Safe excavation
 Examples:
 Electricity cables
 Water pipes
 Gas pipes
 Telecommunication cables
Facilities
School
Fire station
Playground
Bus station Hospital
Police station
Water Table
High Water Level Low Water Level
Water pressure in the soil is high and likely to be
corresponding weaker
Water pressure is low and cause the soil to
Affect the stability of slopping ground Lose most of the moisture will cause building to
crack
Surrounded by areas of higher ground,
underground water tend to flow to the site
*save more costs and laborer work
Causes flooding
*necessary to pump excavations and provide
drainage to remove the water
*which will need additional costs
Sub-Soil
Types of Soil Advantage Disadvantage
Hardrock Great Foundation Characteristics High Excavation Costs
Gravel Strong and Easily Drained Bearing capacity halved
when water table is high
Clay Good Bearing Capacity Does not Drain Well
Sand Cheap excavation Loose
Site clearance
■ Removal of bushes and trees
■ Removal of soil to reduce level
■ Demolition of existing building
■ Plants that can be use for demolition
a) Back-hoe
b) Lorries
c) bulldozer
Site setting out
■ Establish a baseline
a) Mark the position of line
b) Measure on-site by using steel tape
■ Setting out main line
a) Mark each corner of the building by using stout peg
b) Make sure the angles and lengths are right
■ Setting up profile board
a) Foundation trench positions and walls
Temporary works
1. Accommodation For Workers
■ This facility will be strategic to the progress of
the project because it allows workers to live
close to their work sites. This will help them
stay within reach of their ultimate goal,
notably by avoiding unnecessary trips
2. Security
■ Fencing
- defines the limit of the site
- deterrent to trespasser
Temporary works
Types of Scaffolding
1) Putlog Scaffolding:
■ Standards are joined together with horizontal
members.
■ Spacing is the same on a putlog scaffold as on a
general purpose scaffold.
■ The building supports the scaffolding.
2) Independent Scaffolding:
• 2 rows of standards at about 1m apart are tied
by cross-members-transform because it does not
rely on the building.
• Diagonal braces are fitted between standards to
give stability.
3) Mobile Access Tower:
■ Workers have easier access to buildings for
constructing purposes
■ Able to move manually on ground and workers are
free standing when on the platform
■ Safe and adaptable style of scaffold that is nicely
suited to perform around the typical house like
bungalows.
Timbering
There are 3 main components of timbering:
a) Poling boards
■ When the soil is soft, such as soft clay or sand,
it will be necessary to use more closely spaced
poling boards to prevent the sides of the trench
between the struts from falling in.
b) Walings
■ Running the length of trench and support poling boards
c) Struts
■ It used to put across the width of the trench, supporting open poling boards, close poling boards
and walings or poling boards and sheeting
THANK YOU

More Related Content

PDF
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
PDF
BUILDING CONSTRUCTION 1
PPTX
Telecommunication Tower
PDF
Construction of telecommunication towers
PDF
PROJECT 1 (BUILDING CONSTRUCTION 1)
PPTX
Construction Project Management.
PDF
Bcon revised
PDF
Building construction ii report (1)
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
BUILDING CONSTRUCTION 1
Telecommunication Tower
Construction of telecommunication towers
PROJECT 1 (BUILDING CONSTRUCTION 1)
Construction Project Management.
Bcon revised
Building construction ii report (1)

What's hot (19)

PPTX
Final slides
PPTX
Bcon final
PDF
Bcon draft
PPTX
CT3 1c aluminium formwork+
PPTX
Final BUILDING CONSTRUCTION 1
PDF
Planning and locating service cores.
PDF
Be con
PPTX
Service core
PPTX
Building Construction
PPTX
Construction of metro station
PDF
Building Construction 1: Project 1
PDF
BUILDING CONSTRUCTION
PDF
Building construction 1 experiencing construction (zone innovation park klang)
PPTX
Part 3 Guy Tower Structure
PPTX
Aluminium window
PDF
Ct2 presentation
PDF
B CON REPORT
PPTX
Part 2 Self Supporting tower structures
PDF
Report on HIGH RISE
Final slides
Bcon final
Bcon draft
CT3 1c aluminium formwork+
Final BUILDING CONSTRUCTION 1
Planning and locating service cores.
Be con
Service core
Building Construction
Construction of metro station
Building Construction 1: Project 1
BUILDING CONSTRUCTION
Building construction 1 experiencing construction (zone innovation park klang)
Part 3 Guy Tower Structure
Aluminium window
Ct2 presentation
B CON REPORT
Part 2 Self Supporting tower structures
Report on HIGH RISE
Ad

Similar to Ct tutorial 2 (20)

PDF
Chapter 2
PDF
Lecture_all.pdf
PPTX
Q1 presentation
DOCX
Construction site
PPTX
UMAID IQBAL SEMINAR.pptx
PPTX
Construction Technology I Presentation Slides
PDF
Building Construction 1: project 1
PDF
Report 150720083151-lva1-app6892
PPTX
Demolition of building and blasting equipment
PPTX
The construction method for surface drainage (housing)
PPTX
training1 (1).pptx
PPTX
national building code
PPTX
Devanshu PT final year presentation.pptx
PPTX
Mod. 1.pptx
DOCX
Site visit report
PDF
HIGH-RISE BUILDING- FORM WORK essential for efficiently shaping and supportin...
PPTX
Ducted distribution of services
DOCX
Site report
PPTX
TOS REPORTM. .SITE VISIT OF SAFRON MALL.
PPTX
Prefabricated Column
Chapter 2
Lecture_all.pdf
Q1 presentation
Construction site
UMAID IQBAL SEMINAR.pptx
Construction Technology I Presentation Slides
Building Construction 1: project 1
Report 150720083151-lva1-app6892
Demolition of building and blasting equipment
The construction method for surface drainage (housing)
training1 (1).pptx
national building code
Devanshu PT final year presentation.pptx
Mod. 1.pptx
Site visit report
HIGH-RISE BUILDING- FORM WORK essential for efficiently shaping and supportin...
Ducted distribution of services
Site report
TOS REPORTM. .SITE VISIT OF SAFRON MALL.
Prefabricated Column
Ad

More from Tung97Michelle (20)

PPTX
Ct tutorial-1
PDF
DOCX
No.1 course outline march 2015
PDF
E portfolio assignment september 2015
PPTX
Pyramid and frustum adds (area) (1)
DOCX
Math statistics (1)
PDF
Maths project brief jan 2015 project - statistics
DOC
Math module outline jan 2015 (1)
DOCX
FNBE basic accounting
DOC
Acc30205 basic accounting assignment rev september 2015
DOC
Bk course outline september 2015 semester
DOC
Eng 2 course outline
DOCX
Course outline-social-psy
DOCX
Economics assignment
DOC
Ecn30205 economics assignment sept 2015 intake
DOC
Econs course outline september 2015 semester
DOC
Fnbe january 2015 assignment 2
DOC
Compare and comtrast essay
DOCX
Compare & contrast essay
DOCX
Eng assignment 1
Ct tutorial-1
No.1 course outline march 2015
E portfolio assignment september 2015
Pyramid and frustum adds (area) (1)
Math statistics (1)
Maths project brief jan 2015 project - statistics
Math module outline jan 2015 (1)
FNBE basic accounting
Acc30205 basic accounting assignment rev september 2015
Bk course outline september 2015 semester
Eng 2 course outline
Course outline-social-psy
Economics assignment
Ecn30205 economics assignment sept 2015 intake
Econs course outline september 2015 semester
Fnbe january 2015 assignment 2
Compare and comtrast essay
Compare & contrast essay
Eng assignment 1

Recently uploaded (20)

PPTX
Lesson notes of climatology university.
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PDF
Weekly quiz Compilation Jan -July 25.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PDF
RMMM.pdf make it easy to upload and study
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PDF
LNK 2025 (2).pdf MWEHEHEHEHEHEHEHEHEHEHE
PPTX
master seminar digital applications in india
PDF
Trump Administration's workforce development strategy
PDF
What if we spent less time fighting change, and more time building what’s rig...
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
Classroom Observation Tools for Teachers
PPTX
Cell Types and Its function , kingdom of life
PDF
Yogi Goddess Pres Conference Studio Updates
PPTX
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
PDF
Microbial disease of the cardiovascular and lymphatic systems
Lesson notes of climatology university.
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
Weekly quiz Compilation Jan -July 25.pdf
Final Presentation General Medicine 03-08-2024.pptx
Anesthesia in Laparoscopic Surgery in India
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
RMMM.pdf make it easy to upload and study
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
LNK 2025 (2).pdf MWEHEHEHEHEHEHEHEHEHEHE
master seminar digital applications in india
Trump Administration's workforce development strategy
What if we spent less time fighting change, and more time building what’s rig...
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
Supply Chain Operations Speaking Notes -ICLT Program
Classroom Observation Tools for Teachers
Cell Types and Its function , kingdom of life
Yogi Goddess Pres Conference Studio Updates
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
Microbial disease of the cardiovascular and lymphatic systems

Ct tutorial 2

  • 1. BLD 60104 CONSTRUCTION TECHNOLOGY 1 Site and Temporary Works Leong Li Jing 0323628 Gillian Chong 0323941 Chia Sze Sian 0323574 Chan Qi Han 0324315 Yap Zheng Xiang 0322411 Michelle Tung Man Kaye 0324175
  • 2. Accessibility to Site  Accessible routes from all entrances and exit for construction and public use  New sites or existing sites  Conditions: - Slope - Bends - Sharp corners - Gradient - Width
  • 3. Services  Actions:  Planning the works  Locating and identifying buried services  Safe excavation  Examples:  Electricity cables  Water pipes  Gas pipes  Telecommunication cables
  • 5. Water Table High Water Level Low Water Level Water pressure in the soil is high and likely to be corresponding weaker Water pressure is low and cause the soil to Affect the stability of slopping ground Lose most of the moisture will cause building to crack Surrounded by areas of higher ground, underground water tend to flow to the site *save more costs and laborer work Causes flooding *necessary to pump excavations and provide drainage to remove the water *which will need additional costs
  • 6. Sub-Soil Types of Soil Advantage Disadvantage Hardrock Great Foundation Characteristics High Excavation Costs Gravel Strong and Easily Drained Bearing capacity halved when water table is high Clay Good Bearing Capacity Does not Drain Well Sand Cheap excavation Loose
  • 7. Site clearance ■ Removal of bushes and trees ■ Removal of soil to reduce level ■ Demolition of existing building ■ Plants that can be use for demolition a) Back-hoe b) Lorries c) bulldozer
  • 8. Site setting out ■ Establish a baseline a) Mark the position of line b) Measure on-site by using steel tape ■ Setting out main line a) Mark each corner of the building by using stout peg b) Make sure the angles and lengths are right ■ Setting up profile board a) Foundation trench positions and walls
  • 9. Temporary works 1. Accommodation For Workers ■ This facility will be strategic to the progress of the project because it allows workers to live close to their work sites. This will help them stay within reach of their ultimate goal, notably by avoiding unnecessary trips
  • 10. 2. Security ■ Fencing - defines the limit of the site - deterrent to trespasser Temporary works
  • 11. Types of Scaffolding 1) Putlog Scaffolding: ■ Standards are joined together with horizontal members. ■ Spacing is the same on a putlog scaffold as on a general purpose scaffold. ■ The building supports the scaffolding. 2) Independent Scaffolding: • 2 rows of standards at about 1m apart are tied by cross-members-transform because it does not rely on the building. • Diagonal braces are fitted between standards to give stability.
  • 12. 3) Mobile Access Tower: ■ Workers have easier access to buildings for constructing purposes ■ Able to move manually on ground and workers are free standing when on the platform ■ Safe and adaptable style of scaffold that is nicely suited to perform around the typical house like bungalows.
  • 13. Timbering There are 3 main components of timbering: a) Poling boards ■ When the soil is soft, such as soft clay or sand, it will be necessary to use more closely spaced poling boards to prevent the sides of the trench between the struts from falling in. b) Walings ■ Running the length of trench and support poling boards c) Struts ■ It used to put across the width of the trench, supporting open poling boards, close poling boards and walings or poling boards and sheeting