Project Challenge 2013 
Presentation by Antony Della Porta 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Case Study on Using 
AgilePM 
in a 
PRINCE2 Project 
This presentation will be taking a look at a project where 
“Agile Project Management” and PRINCE2 methods of 
project delivery were successfully employed together. The 
project was to delivery a new bandwidth usage protocol, 
Quality of Service (QoS), configuration onto a Bank’s National 
Network, to enable Application bandwidth prioritization for 
the new Java-based applications project for the Retail Bank 
Division Teller System 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
The purpose of this 
Presentation 
Agile Project Management and PRINCE2® In Projects
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Presenter 
Antony 
C. 
Della 
Porta 
• Antony has over 25 years experience of working in project 
delivery, rescue and consultancy roles 
• Major verticals such as Finance, Travel, Media and 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
Pharmaceuticals. 
• Established trainer in delivering courses in Project 
Management methodologies, and courses relevant to the 
delivery and realisation of business strategy. 
• Started using PRINCE2®, in earnest, over 14 years ago, 
along with Agile Project management 
• Fairly unique in having successfully managed and 
implemented a number of PRINCE2® -AgilePM projects 
prior to quite recently becoming a trainer. 
• APMG accredited and member of Institute of Consultants
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Introduction to Relationship between 
PRINCE2 and AgilePM methodologies 
• The following slide will show a graphic view of 
the correlation of processes in PRINCE2 and 
the Phases employed by Atern Agile Project 
Management 
• AgilePM established with PRINCE2 
• Correlation of the Processes/Stages to 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
Phases/Increments 
• Relationship of plans and lifecycles 
Agile Project Management and 
PRINCE2® In Projects
Process Overview of PRINCE2 and AgilePM 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
Key: AgilePM; PRINCE2®
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
The Project - 
St. George Bank Network Upgrade 
• Part of bank teller system replacement programme to employ Java based 
applications 
• Network to introduce QoS (Quality of Service) banding 
– Gold for high demand applications (40% b/w) 
– Silver for general demand applications (next 30%) 
– Bronze – backoffice applications (20% b/w) 
• QoS was a new concept indicating that the required solution to Prioritize traffic 
would have to evolve 
• Scope was two years old so requirements would have to be reviewed as well as 
equipment 
• Proof of Concept (PoC)facilities no longer available from the incoming Telco 
(Optus) so alternative had to be sourced 
• PoC was allocated one (1) month to complete defining, testing and piloting the 
Gold, Silver and Bronze (as Coulds). 
• Estimates for Effort would be broad as new functionality, and no known active 
solution for this type of network
• Initial Project Start Up employing PRINCE2® as the primary methodology 
• Stage 1- (P2) Initiating a Project used to setup and review Project in detail 
• Stage 2 - (P2) Redefine current scope, Tenders for Integrators, Pre Project phase for Stage 3 
• Stage 3 – (APM) Define and Develop requirements for technical solution, deploy 1st Pilot 
• Stage 4 – (APM-P2) Refine Technical solution (Pilot feedback), 1st Pilot - Engage Integrator 
• Stage 5 – (APM-P2) Refine Technical solution (Pilot feedback), 2nd Pilot - Plan National Roll-Out 
• Stage 6 – (P2) First group of Retail Banks for Live Upgrade 
• Stage 7 – (P2) Upgrade remaining 345 retail branches Nationwide 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
The Project Plan -
• Initial Project Start Up employing PRINCE2® as the primary methodology 
• Stage 1- (P2) Initiating a Project used to setup and review Project in detail 
• Stage 2 - (P2) Seek Integrators and Hardware requirements 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
SU and Stages 1-2 – PRINCE2 – High Level
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
SU and Stages 1-2 – PRINCE2 - Detail 
• Starting Up a Project: document and sign-off Project Brief and 
Approach - Use a hybrid of methodology using PRINCE2 and Agile 
• Initiating a Project: Usual IP activities and preparing Stage 2 , 
planning the project to engage both delivery approaches: Agile 
for the PoC and PRINCE2 for the main rollout and overall 
Organisation and governance mapping for Roles and 
Responsibilities 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
• Stage 2 
o Review current scope (2 years old at this point) 
o Define resource requirements (original Proof of Concept facilities no longer valid) 
o Define Approach for PoC delivery (AgilePM) for Stage 3 
o Plan Stage 3 - AgilePM Feasibility/Foundations and then move into first Development Phase 
(Exploration and Engineering Timeboxes)
Stage 3 – AgilePM managed Increment (P2 stage) HighLevel 
• Stage 3 – (APM) Define and Develop requirements for technical solution, 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
deploy 1st and 2nd Pilots to check initial design
Stage 3 – AgilePM Development Phase 
• Use Feasibility/Foundations to define and prioritize the requirements to be delivered 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
over how many increments. 
• Approach was to build the “Gold” application configuration requirements during the 
1st increment and deploy into the 1st Pilot 
• Feedback on the 1st Pilot (HeadOffice branch) was fed back to 2nd Timebox for further 
refinement 
• 2nd Pilot used for checking Telco configurations and hence full “Gold” function
• Agile: Refine Technical solution (Pilot feedback), 2nd Pilot 
• PRINCE2: Engage Integrator, Preparations for Hardware builds and 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
configuration 
Stage 4 – Joint AgilePM and PRINCE2
Stage 4 - PRINCE2 managed stage – AgilePM Develop solution 
Agile: 
• Refine Technical solution for Gold using Pilot feedback (1st Pilot) 
• Commence development of configurations for Silver and Bronze 
• Deploy Silver and Bronze solutions and commence 2nd Pilot 
PRINCE2 
• Engage Integrator 
• Start planning the roll-out stages 6 and 7 with Integrator 
• Define and order hardware requirements 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
Stage 5 - PRINCE2 managed stage – AgilePM - Develop solution 
• AgilePM - Refine Technical solution (Pilot feedback), 2nd Pilot 
• PRINCE2 - Plan National Roll-Out in detail 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
Stage 5 - PRINCE2 managed stage – AgilePM Develop solution 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
AgilePM 
• Timeboxes under this Development Increment used to 
• Refine Silver and Bronze applications 
• Develop other requirements (including any dropped from earlier Timeboxes) 
• Complete Pilot stage and sign-off developed solution now ready for 
Deployment and hand back to PRINCE2 
PRINCE2 
• Finalize plans for 1st Stage roll-out in Stage 6 
• Ensure resources in place and hardware (replacement network) preconfigured
Stages 6 and 7 - PRINCE2 managed stages: Main Project Roll-Out 
• Stage 6 – (P2) First group of Retail Banks for Live Upgrade 
• Stage 7 – (P2) Upgrade remaining 345 retail branches Nationwide 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
Stages 6 and 7 - PRINCE2 managed stages: Main Project Roll-Out 
• Stage 6 - Upgrade the first 20 Branches spread nationally: 5 a night 4 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Stage 
6 
Controlling 
a Stage 
Controlling 
a Stage 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
nights 
• Stage 7 – On successful completion of Stage 6 and sign-off, follow rest of 
the Roll-out plan and upgrade the remaining 345 Nation-wide branches 
• Post Project – Agile to monitor the success of the Bandwidth Prioritization 
Post Project 
MP 
Work 
Package 
1 
Stage 
Boun 
dary 
MP 
Work 
Package 
1 
Closin 
g 
Project 
Stage 
7
Summary of Presentation 
• PRINCE2 and Atern AgilePM can be used to deliver projects of 
varying delivery requirements and needs 
• Most projects are probably in reality managed this way 
• There are some direct correlations between the processes/ 
phases of both methodologies 
• Not necessary to marry these up directly, more important to 
know and understand how each can be best employed for 
each project 
• This project was in 2003 to show the two approaches being 
used together back then! 
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net 
Contact Details for Presenter 
Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office 
The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. 
Antony della Porta 
Telephone: +44 7533 240 675 
Email: acdp@d-p-c.net

More Related Content

PDF
A real life case study of using Agile and PRINCE2 together - AgilePM
PDF
Nordic project zone talk on Agile and PRINCE2
PDF
Discover how agile can enhance your organization’s project delivery
PDF
PRINCE2 and SCRUM (AGILE)
PPTX
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...
PPTX
PMBOK and Scrum: Best of both worlds
PDF
PRINCE2 Agile Guidance Preview
A real life case study of using Agile and PRINCE2 together - AgilePM
Nordic project zone talk on Agile and PRINCE2
Discover how agile can enhance your organization’s project delivery
PRINCE2 and SCRUM (AGILE)
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...
PMBOK and Scrum: Best of both worlds
PRINCE2 Agile Guidance Preview

What's hot (20)

PPT
Prince2
PDF
Prince2 Vs PMBOK
PDF
Novare Consulting PRINCE2 Agile Roadshow
PDF
PRINCE2 Foundation Workshops -- Organization
PPTX
PRINCE2 2017 - laster update of the most popular project management method
PDF
An introduction to prince2
PDF
Prince2 & PMBOK Comparison Demystified
PPT
PMBOK® Vs PRINCE2®
PDF
A simple PRINCE2 glossary
PDF
Prince2 quick guide
PPTX
Between Scrum and Kanban - define test process for Agile methodologies
PPTX
Agile, PMI and PMBOK
PPTX
Webinar on PRINCE2 + Agile - by Ashish Dhoke (projectingIT)
PPT
Prince2 2005 Vs Prince2 2009
PPTX
Prince2 for Value Driven Project Management
PPTX
PRINCE2 Executive Briefing
PDF
PRINCE2 and Agile Project Management - ProjectingIT APMG ATO
PDF
Learn the PRINCE2 Principles ebook
Prince2
Prince2 Vs PMBOK
Novare Consulting PRINCE2 Agile Roadshow
PRINCE2 Foundation Workshops -- Organization
PRINCE2 2017 - laster update of the most popular project management method
An introduction to prince2
Prince2 & PMBOK Comparison Demystified
PMBOK® Vs PRINCE2®
A simple PRINCE2 glossary
Prince2 quick guide
Between Scrum and Kanban - define test process for Agile methodologies
Agile, PMI and PMBOK
Webinar on PRINCE2 + Agile - by Ashish Dhoke (projectingIT)
Prince2 2005 Vs Prince2 2009
Prince2 for Value Driven Project Management
PRINCE2 Executive Briefing
PRINCE2 and Agile Project Management - ProjectingIT APMG ATO
Learn the PRINCE2 Principles ebook
Ad

Similar to How "AgilePM" and PRINCE2 were used in the same project (20)

PDF
Prince2 2009 & its benefits potifob stefan ondek
PDF
PRINCE2 Agile™ Guidance Preview (published by Axelos)
PPT
Prince2 2009 & its benefits
PDF
PRINCE2 and Agile
PPTX
Prince 2 F+P Course Preview
PPT
Prince 2 - Project Management principles
PDF
International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...
PPT
Intl. pm standards prince2, pmi & co. - potifob 2011
PDF
Prince2 resources e-book 1
PPTX
Prince2
PPTX
PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013
PDF
Project Management 2015
PPT
Agile Presentation Final
PPT
Prince2 2009 Launch Presentation
PPT
Project management slide - Introduction
PDF
The prince2 business case
PDF
Prince2 resources e book 2
PDF
Prince 2 + XLPM - Semcon - Bert Hedeman
PDF
Directing Successful Projects With Prince2 The Essential Guide For Project Bo...
PDF
DagvdPM_PRINCE2AgileIntro
Prince2 2009 & its benefits potifob stefan ondek
PRINCE2 Agile™ Guidance Preview (published by Axelos)
Prince2 2009 & its benefits
PRINCE2 and Agile
Prince 2 F+P Course Preview
Prince 2 - Project Management principles
International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...
Intl. pm standards prince2, pmi & co. - potifob 2011
Prince2 resources e-book 1
Prince2
PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013
Project Management 2015
Agile Presentation Final
Prince2 2009 Launch Presentation
Project management slide - Introduction
The prince2 business case
Prince2 resources e book 2
Prince 2 + XLPM - Semcon - Bert Hedeman
Directing Successful Projects With Prince2 The Essential Guide For Project Bo...
DagvdPM_PRINCE2AgileIntro
Ad

Recently uploaded (20)

PPTX
4 5 6 7 Intro to Ramayan MANAGEMENT LESSONS and Qualities.pptx
PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PPTX
Improved_Leadership_in_Total_Quality_Lesson.pptx
PPTX
Self-Awareness and Values Development presentation
PDF
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
PPTX
Course Overview of the Course Titled.pptx
PDF
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
PPTX
Human Resources management _HR structure
PDF
TED Talk on how to make TED Talk slides.pdf
PDF
Certified Information Systems Security Professional (CISSP) Specialization Ce...
PDF
1_Corporate Goverance presentation topic
PPT
Project Management - Scope Management.ppt
PDF
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PDF
The Cyber SwarmShield by Stéphane Nappo
PPTX
Human Resource Management | Introduction,Meaning and Definition
PPTX
2. CYCLE OF FUNCTIONING RIFLE -PP Presentation..pptx
PPTX
Course Overview of the Course Titled.pptx
PDF
CISSP Domain 6: Security Assessment and Testing
PPTX
Principles & Theories of Mgt-Master in PM.pptx
4 5 6 7 Intro to Ramayan MANAGEMENT LESSONS and Qualities.pptx
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
Improved_Leadership_in_Total_Quality_Lesson.pptx
Self-Awareness and Values Development presentation
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
Course Overview of the Course Titled.pptx
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
Human Resources management _HR structure
TED Talk on how to make TED Talk slides.pdf
Certified Information Systems Security Professional (CISSP) Specialization Ce...
1_Corporate Goverance presentation topic
Project Management - Scope Management.ppt
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
_ISO_Presentation_ISO 9001 and 45001.pptx
The Cyber SwarmShield by Stéphane Nappo
Human Resource Management | Introduction,Meaning and Definition
2. CYCLE OF FUNCTIONING RIFLE -PP Presentation..pptx
Course Overview of the Course Titled.pptx
CISSP Domain 6: Security Assessment and Testing
Principles & Theories of Mgt-Master in PM.pptx

How "AgilePM" and PRINCE2 were used in the same project

  • 1. m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Project Challenge 2013 Presentation by Antony Della Porta Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
  • 2. m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Case Study on Using AgilePM in a PRINCE2 Project This presentation will be taking a look at a project where “Agile Project Management” and PRINCE2 methods of project delivery were successfully employed together. The project was to delivery a new bandwidth usage protocol, Quality of Service (QoS), configuration onto a Bank’s National Network, to enable Application bandwidth prioritization for the new Java-based applications project for the Retail Bank Division Teller System Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. The purpose of this Presentation Agile Project Management and PRINCE2® In Projects
  • 3. m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Presenter Antony C. Della Porta • Antony has over 25 years experience of working in project delivery, rescue and consultancy roles • Major verticals such as Finance, Travel, Media and Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. Pharmaceuticals. • Established trainer in delivering courses in Project Management methodologies, and courses relevant to the delivery and realisation of business strategy. • Started using PRINCE2®, in earnest, over 14 years ago, along with Agile Project management • Fairly unique in having successfully managed and implemented a number of PRINCE2® -AgilePM projects prior to quite recently becoming a trainer. • APMG accredited and member of Institute of Consultants
  • 4. m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Introduction to Relationship between PRINCE2 and AgilePM methodologies • The following slide will show a graphic view of the correlation of processes in PRINCE2 and the Phases employed by Atern Agile Project Management • AgilePM established with PRINCE2 • Correlation of the Processes/Stages to Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. Phases/Increments • Relationship of plans and lifecycles Agile Project Management and PRINCE2® In Projects
  • 5. Process Overview of PRINCE2 and AgilePM m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. Key: AgilePM; PRINCE2®
  • 6. m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. The Project - St. George Bank Network Upgrade • Part of bank teller system replacement programme to employ Java based applications • Network to introduce QoS (Quality of Service) banding – Gold for high demand applications (40% b/w) – Silver for general demand applications (next 30%) – Bronze – backoffice applications (20% b/w) • QoS was a new concept indicating that the required solution to Prioritize traffic would have to evolve • Scope was two years old so requirements would have to be reviewed as well as equipment • Proof of Concept (PoC)facilities no longer available from the incoming Telco (Optus) so alternative had to be sourced • PoC was allocated one (1) month to complete defining, testing and piloting the Gold, Silver and Bronze (as Coulds). • Estimates for Effort would be broad as new functionality, and no known active solution for this type of network
  • 7. • Initial Project Start Up employing PRINCE2® as the primary methodology • Stage 1- (P2) Initiating a Project used to setup and review Project in detail • Stage 2 - (P2) Redefine current scope, Tenders for Integrators, Pre Project phase for Stage 3 • Stage 3 – (APM) Define and Develop requirements for technical solution, deploy 1st Pilot • Stage 4 – (APM-P2) Refine Technical solution (Pilot feedback), 1st Pilot - Engage Integrator • Stage 5 – (APM-P2) Refine Technical solution (Pilot feedback), 2nd Pilot - Plan National Roll-Out • Stage 6 – (P2) First group of Retail Banks for Live Upgrade • Stage 7 – (P2) Upgrade remaining 345 retail branches Nationwide m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. The Project Plan -
  • 8. • Initial Project Start Up employing PRINCE2® as the primary methodology • Stage 1- (P2) Initiating a Project used to setup and review Project in detail • Stage 2 - (P2) Seek Integrators and Hardware requirements m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. SU and Stages 1-2 – PRINCE2 – High Level
  • 9. m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net SU and Stages 1-2 – PRINCE2 - Detail • Starting Up a Project: document and sign-off Project Brief and Approach - Use a hybrid of methodology using PRINCE2 and Agile • Initiating a Project: Usual IP activities and preparing Stage 2 , planning the project to engage both delivery approaches: Agile for the PoC and PRINCE2 for the main rollout and overall Organisation and governance mapping for Roles and Responsibilities Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. • Stage 2 o Review current scope (2 years old at this point) o Define resource requirements (original Proof of Concept facilities no longer valid) o Define Approach for PoC delivery (AgilePM) for Stage 3 o Plan Stage 3 - AgilePM Feasibility/Foundations and then move into first Development Phase (Exploration and Engineering Timeboxes)
  • 10. Stage 3 – AgilePM managed Increment (P2 stage) HighLevel • Stage 3 – (APM) Define and Develop requirements for technical solution, m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. deploy 1st and 2nd Pilots to check initial design
  • 11. Stage 3 – AgilePM Development Phase • Use Feasibility/Foundations to define and prioritize the requirements to be delivered m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. over how many increments. • Approach was to build the “Gold” application configuration requirements during the 1st increment and deploy into the 1st Pilot • Feedback on the 1st Pilot (HeadOffice branch) was fed back to 2nd Timebox for further refinement • 2nd Pilot used for checking Telco configurations and hence full “Gold” function
  • 12. • Agile: Refine Technical solution (Pilot feedback), 2nd Pilot • PRINCE2: Engage Integrator, Preparations for Hardware builds and m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. configuration Stage 4 – Joint AgilePM and PRINCE2
  • 13. Stage 4 - PRINCE2 managed stage – AgilePM Develop solution Agile: • Refine Technical solution for Gold using Pilot feedback (1st Pilot) • Commence development of configurations for Silver and Bronze • Deploy Silver and Bronze solutions and commence 2nd Pilot PRINCE2 • Engage Integrator • Start planning the roll-out stages 6 and 7 with Integrator • Define and order hardware requirements m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
  • 14. Stage 5 - PRINCE2 managed stage – AgilePM - Develop solution • AgilePM - Refine Technical solution (Pilot feedback), 2nd Pilot • PRINCE2 - Plan National Roll-Out in detail m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
  • 15. Stage 5 - PRINCE2 managed stage – AgilePM Develop solution m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. AgilePM • Timeboxes under this Development Increment used to • Refine Silver and Bronze applications • Develop other requirements (including any dropped from earlier Timeboxes) • Complete Pilot stage and sign-off developed solution now ready for Deployment and hand back to PRINCE2 PRINCE2 • Finalize plans for 1st Stage roll-out in Stage 6 • Ensure resources in place and hardware (replacement network) preconfigured
  • 16. Stages 6 and 7 - PRINCE2 managed stages: Main Project Roll-Out • Stage 6 – (P2) First group of Retail Banks for Live Upgrade • Stage 7 – (P2) Upgrade remaining 345 retail branches Nationwide m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
  • 17. Stages 6 and 7 - PRINCE2 managed stages: Main Project Roll-Out • Stage 6 - Upgrade the first 20 Branches spread nationally: 5 a night 4 m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Stage 6 Controlling a Stage Controlling a Stage Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. nights • Stage 7 – On successful completion of Stage 6 and sign-off, follow rest of the Roll-out plan and upgrade the remaining 345 Nation-wide branches • Post Project – Agile to monitor the success of the Bandwidth Prioritization Post Project MP Work Package 1 Stage Boun dary MP Work Package 1 Closin g Project Stage 7
  • 18. Summary of Presentation • PRINCE2 and Atern AgilePM can be used to deliver projects of varying delivery requirements and needs • Most projects are probably in reality managed this way • There are some direct correlations between the processes/ phases of both methodologies • Not necessary to marry these up directly, more important to know and understand how each can be best employed for each project • This project was in 2003 to show the two approaches being used together back then! m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd.
  • 19. m: 44 7533 240 675; e: acdp@d-p-c.net; w: www.d-p-c.net Contact Details for Presenter Copyright © 2013 della porta consulting Ltd. All Rights Reserved. PRINCE2® ® is a Registered Trade Mark of the Cabinet Office The APMG Swirl Agile Project Management Device is a Trade Mark of APM Group Ltd. Antony della Porta Telephone: +44 7533 240 675 Email: acdp@d-p-c.net