DEMOBILIZATION PLAN
1. INTRODUCTION
This document spells out the activities to be done by Wilkins engineering as part of
demobilization from Kasoa BSP project. This has become necessary due the state of the project
drawing to the end of its cycle. Wilkins engineering as a sub-contractor was mandated to carry
out the installation of electrical works on the project. This demobilization plan is intended to
provide direction to all assigned resources on the project, as well as the responsibilities, to be
followed when demobilizing from this project.
2. PROJECT TEAM
At present, we have a total number of seventeen (17) manpower. This number comprises of a
project manager, installation manager, Health and safety officer, Quality Assurance/Control
officer, two (2) logistics officers. two (2) foremen, five (5) technicians, two (2) electricians and
two (2) helpers. The team is mandated to aid in the testing and commissioning of the SVC and
any other relevant works that may pop up in readiness of the final commissioning. As part of our
planning towards demobilization, this team shall be stationed at the project site to carry out all
the remaining works positioning the construction site for final takeover by the client in
consultation with SIEMENS Energy as the contractor.
3. RESPONSIBILITIES
The installation manager together with the logistic officers shall in the process of demobilization
retard allresources (tools, equipment) to their original locations before the project. Thesepeople
shall orchestrate the activities needed to complete the exercise, satisfactorily to the client and
other stakeholder on the project.
4. DEMOBILIZATION PROCESS
The demobilization exercise shall be conducted in phases due to the type of resources involved.
The commencing phase will involve correlating all the resources at the project site in terms of its
weight, size, height and so on. All demobilization activities/actions will be accomplished in the
most cost effective and safest manner. These resources shall be moved upon authorization
granted by a representative of the client in conjunction with the logistic officer of Wilkins
engineering. Our concern during this demobilization is to ensure the safety of all resources.
5. RELEASE PROCEDURE
Once all the authorizing person(s) have consented to the process of demobilization, the
resources will be moved from the project site to the final locations. It is important to note that
no resource shall be moved whose relevance is still in use.

More Related Content

PPT
Save Papers
PPTX
Go green, Go paperless!
PPT
Maintenance strategies
PPTX
PDF
Drawings & Documents Required for Solar Projects
PDF
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
PPTX
Cable Tray Installation 211215
PDF
Construction Company Profile To Attract Clients Powerpoint Presentation Slides
Save Papers
Go green, Go paperless!
Maintenance strategies
Drawings & Documents Required for Solar Projects
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
Cable Tray Installation 211215
Construction Company Profile To Attract Clients Powerpoint Presentation Slides

What's hot (20)

PDF
Risk assessment for testing & commissioning of cranes
PDF
DOCX
11 piling operations with rebar cage installation risk assessment templates
DOCX
21 confined space working risk assessment templates
PPTX
Construction safety
DOCX
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
PDF
risk assessment - pile cap.pdf
PPTX
Visitors SHE Induction Presentation 2016
PDF
Risk Assessment Example.pdf
PPTX
Work At Height
DOC
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
DOCX
8 lifting operations with mobile crane risk assessment templates
DOCX
16 scaffolding (temporary works) risk assessment templates
DOCX
MOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docx
DOCX
Health and safety plan generic
PDF
Working at height slides
PPTX
Presentation working at height
PPTX
working at height
DOCX
13 initial project site office set up risk assessment templates
PDF
Risk Assessment (Master).pdf
Risk assessment for testing & commissioning of cranes
11 piling operations with rebar cage installation risk assessment templates
21 confined space working risk assessment templates
Construction safety
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
risk assessment - pile cap.pdf
Visitors SHE Induction Presentation 2016
Risk Assessment Example.pdf
Work At Height
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
8 lifting operations with mobile crane risk assessment templates
16 scaffolding (temporary works) risk assessment templates
MOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docx
Health and safety plan generic
Working at height slides
Presentation working at height
working at height
13 initial project site office set up risk assessment templates
Risk Assessment (Master).pdf
Ad

Similar to DEMOBILIZATION PLAN.docx (20)

DOC
Rihan Height Project Execution Plan-Rev00
DOCX
DOCX
Regidor A. Manalo Sub-Agent (Corporate C.V)
PDF
Engr ilyas cv new
DOCX
Stevan Hicks Short
PPT
Seg 2 Fort Macon
PPTX
Subsea fibre optics Submarine cable laying.pptx
PDF
Relocations industrial installations
PDF
UON-Project-Handover-Guideline-v1.2-010920.pdf
PDF
Yogesh Kalaskar_Project Manager CV
DOC
Single Proprietorship JD
DOC
Dale Buzzelli Resume
DOC
METHOD STATEMENT
DOCX
DIWA ERWIN CV_2017
DOCX
Quality Control Program Proposal Final Draft
PPTX
Project Quality Management PPT.pptx
PDF
CVFTCabunoc
PDF
Beakal Likassa - Resume
DOCX
Henrys Resume 2016 Q3
PPT
Site Instruction Provision
Rihan Height Project Execution Plan-Rev00
Regidor A. Manalo Sub-Agent (Corporate C.V)
Engr ilyas cv new
Stevan Hicks Short
Seg 2 Fort Macon
Subsea fibre optics Submarine cable laying.pptx
Relocations industrial installations
UON-Project-Handover-Guideline-v1.2-010920.pdf
Yogesh Kalaskar_Project Manager CV
Single Proprietorship JD
Dale Buzzelli Resume
METHOD STATEMENT
DIWA ERWIN CV_2017
Quality Control Program Proposal Final Draft
Project Quality Management PPT.pptx
CVFTCabunoc
Beakal Likassa - Resume
Henrys Resume 2016 Q3
Site Instruction Provision
Ad

Recently uploaded (20)

PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PDF
Java Basics-Introduction and program control
PPTX
PRASUNET_20240614003_231416_0000[1].pptx
PPTX
ai_satellite_crop_management_20250815030350.pptx
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
PDF
Applications of Equal_Area_Criterion.pdf
PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PPTX
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
PPTX
Information Storage and Retrieval Techniques Unit III
PDF
distributed database system" (DDBS) is often used to refer to both the distri...
PDF
Unit I -OPERATING SYSTEMS_SRM_KATTANKULATHUR.pptx.pdf
PPTX
A Brief Introduction to IoT- Smart Objects: The "Things" in IoT
PPTX
mechattonicsand iotwith sensor and actuator
PPTX
Petroleum Refining & Petrochemicals.pptx
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PDF
Soil Improvement Techniques Note - Rabbi
PPTX
Software Engineering and software moduleing
PDF
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf
PPTX
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
PPTX
CONTRACTS IN CONSTRUCTION PROJECTS: TYPES
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Java Basics-Introduction and program control
PRASUNET_20240614003_231416_0000[1].pptx
ai_satellite_crop_management_20250815030350.pptx
"Array and Linked List in Data Structures with Types, Operations, Implementat...
Applications of Equal_Area_Criterion.pdf
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
Information Storage and Retrieval Techniques Unit III
distributed database system" (DDBS) is often used to refer to both the distri...
Unit I -OPERATING SYSTEMS_SRM_KATTANKULATHUR.pptx.pdf
A Brief Introduction to IoT- Smart Objects: The "Things" in IoT
mechattonicsand iotwith sensor and actuator
Petroleum Refining & Petrochemicals.pptx
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
Soil Improvement Techniques Note - Rabbi
Software Engineering and software moduleing
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
CONTRACTS IN CONSTRUCTION PROJECTS: TYPES

DEMOBILIZATION PLAN.docx

  • 1. DEMOBILIZATION PLAN 1. INTRODUCTION This document spells out the activities to be done by Wilkins engineering as part of demobilization from Kasoa BSP project. This has become necessary due the state of the project drawing to the end of its cycle. Wilkins engineering as a sub-contractor was mandated to carry out the installation of electrical works on the project. This demobilization plan is intended to provide direction to all assigned resources on the project, as well as the responsibilities, to be followed when demobilizing from this project. 2. PROJECT TEAM At present, we have a total number of seventeen (17) manpower. This number comprises of a project manager, installation manager, Health and safety officer, Quality Assurance/Control officer, two (2) logistics officers. two (2) foremen, five (5) technicians, two (2) electricians and two (2) helpers. The team is mandated to aid in the testing and commissioning of the SVC and any other relevant works that may pop up in readiness of the final commissioning. As part of our planning towards demobilization, this team shall be stationed at the project site to carry out all the remaining works positioning the construction site for final takeover by the client in consultation with SIEMENS Energy as the contractor.
  • 2. 3. RESPONSIBILITIES The installation manager together with the logistic officers shall in the process of demobilization retard allresources (tools, equipment) to their original locations before the project. Thesepeople shall orchestrate the activities needed to complete the exercise, satisfactorily to the client and other stakeholder on the project. 4. DEMOBILIZATION PROCESS The demobilization exercise shall be conducted in phases due to the type of resources involved. The commencing phase will involve correlating all the resources at the project site in terms of its weight, size, height and so on. All demobilization activities/actions will be accomplished in the most cost effective and safest manner. These resources shall be moved upon authorization granted by a representative of the client in conjunction with the logistic officer of Wilkins engineering. Our concern during this demobilization is to ensure the safety of all resources. 5. RELEASE PROCEDURE Once all the authorizing person(s) have consented to the process of demobilization, the resources will be moved from the project site to the final locations. It is important to note that no resource shall be moved whose relevance is still in use.