Otta Seal
(Design &Construction Procedures)
Sujit Dhital
Quality Management and Monitoring Specialist
SNRTP (PMU West )
SURFACING OPTION
Non Structural
Sand Seal
Otta Seal
DBSD
Structural
Asphalt Concrete
FACTORS AFFECTING CHOICES
Traffic Volume
Riding Quality Required
Operational Factor
Safety
Environmental Considerations
Construction and Maintenance
 Properties of Available Aggregate
Construction Cost
Required Service Life
OTTA SEAL
An Otta seal is a thin bituminous seal
comprising Natural or crushed
aggregate of all sizes and either a cut-
back or soft penetration grade bitumen
with or without sand cover seal
MECHANISM
Graded aggregate is placed on a relatively
thick film of comparatively soft binder
which on rolling and trafficking, works its
way upwards through the aggregate
interstices. The graded aggregate relies both
on mechanical interlocking and bitumen
binding for its strength
GENERAL
Similar to Conventional Chip Seal
(DBSD)
Binder Spray – Aggregate
Spreading – Rolling
Prime Normally Not Required
Like All Other Surface Treatments, An
Otta Seal Will Not Contribute Directly
To The Structural Strength Of The
Pavement
Pavement Must Be Properly Designed
To Withstand The Traffic Loading
Throughout Its Designed Life
OTTA SEAL CHOICES
LIMITATIONS
Lack of information regarding the Otta
Seal, properties, design, construction
and performance
 Reluctance to adopt new technology
Extra contractual Obligation
Otta seal Guiding Document
RECOMMENDED TYPE OF OTTA SEAL
IN RELATION TO TRAFFIC
PREFERRED AGGREGATE GRADING
DESIGN OF OTTA SEAL
GRADING GUIDELINES
Sieve
Sizes
(mm)
Open Grading Medium Grading Dense Grading
(% passing) (% passing) (% passing)
16.0 100 100 100
13.2 52 - 82 68 - 94 84 - 100
9.5 36 - 58 44 - 73 70 - 98
6.7 20 - 40 29 - 54 54 - 80
4.75 10 - 30 19 - 42 44 - 70
2.0 0 - 8 3 - 18 20 - 48
1.18 0 - 5 1 - 14 15 - 38
.425 0 - 2 0 - 6 7 - 25
.075 0 - 1 0 - 2 3 - 10
DESIGN OF OTTA SEAL
STRENGTH REQUIREMENT
Los Angeles
Abrasion value
IS: 2386 40 percent (Max)
Aggregate
Impact value
IS: 2386 30 percent (Max)
FI
IS: 2386 35 percent (Max)
Stripping Value
5 percent (Max)
DESIGN OF OTTA SEAL
Type of
Seal
Aggregate Spread Rates (m3/m2)
Open
Grading
Medium
Grading
Dense
Grading
Otta Seals 0.013-0.016 0.013-0.016 0.016-0.020
Sand Seals 0.010-0.012
Aggregate Application Rates
DESIGN OF OTTA SEAL
Binder Spray Rates Depends on:
Traffic (AADT)
Aggregate Grading
(Open/Medium/Dense)
Absorbency of Aggregate Particles
Priming of Base Course
DESIGN OF OTTA SEAL
Choice of Binder
 MC 3000, in warm weather
 MC 800, in cold weather when night temperature <10°
C.
 Blending of 80/ 100(VG10) with kerosene done at site
to produce required consistency
WEATHER LIMITATIONS
The minimum surface temperatures for
spraying of the different types and grades of
binder shall be :
 80/100 penetration grade bitumen: 50
o
C
 MC-3000 cutback bitumen: 22
o
C
 MC-800 cutback bitumen: 15
o
C
 MC-30 cutback bitumen: 10
o
C
 Emulsions: 5
o
C
DESIGN OF OTTA SEAL
Choice of Binder
AADT at
Construction
Type of Bitumen for Different Aggregate grading
Open Medium Dense
>1000 NA 150/200 pen MC 3000
MC 800 in cold
100 – 1000 150/200 pen 150/200 pen in
cold
MC 3000
MC 800 in cold
<100 150/200 pen MC 3000 MC 800
DESIGN OF OTTA SEAL
Binder Spray Rates (in litres/m2)
Type of Otta Seal Grading
Open Medium Dense
Double 1st Layer 1.6 1.7 1.8
2nd Layer 1.5 1.6 2.0
Single with
a Sand
Cover Seal
Fine Sand 0.7 0.7 0.6
Coarse sand 0.9 0.8 0.7
1st Layer 1.6 1.7 2.0
Single 1.7 1.8 2.0
Maintenance Reseal 1.5 1.6 1.8
DESIGN OF OTTA SEAL
Blending Guidelines
Required
Product
Cutter (kerosene) in percent of total
80/100 base Bitumen
150/200 Base
Bitumen
150/200
3-5% (flux oil is used
instead of Cutter)
-
MC 3000 8-10% 5-8%
MC 800 18-20% 15-18%
*
Design and construction procedure of otta seal
PRIME
Normally Not Required
Required only when calcareous base
Required because of High
Amount of Bitumen
Absorption
CONSTRUCTION PROCESS
Sub-grade preparation
Preparation of Sub Base
Preparation of CRM
Binder application
Aggregate spreading
Rolling
Sand sealing after about 8
weeks
OTTA SEAL CONSTRUCTION
EQUIPMENT USED:
 Bitumen boiler 1 No.
 Bitumen distributor 1 No.
 Pneumatic rollers 2 Nos.
 Steel roller 1 No.
 Chips spreader 1 No.
 Air compressor 1 No.
 speed of the distributor can be calculated from
equation
Speed of distributor = S/(R*W)
Where S is the rate of delivery (mass) from
the spray bar in kg/s
R is the design spray rate (mass) in kg/m
W is the sprayed width in metres
The required speed will then be in m/s.
DISTRIBUTOR CALIBRATION
PREPARATION OF BASE COURSE
Good Bond Between Base Course and
Surfacing Necessary
Brooming Dust and Foreign Matter
Light Watering to Suppress Dust and to
Facilitate Penetration of Binder
SEALING OPERATION
Spraying of Binder
Spreading of Aggregate
Initial Rolling
(On the Day of Construction)
Rolling Afterwards(Back Rolling )
ROLLING
Extensive Rolling with PTR is
Essential to Achieve a Good Result
One Pass with a Steel Roller will
Improve the Embedment of the
Larger Aggregate
TREATMENT
 Commercial Traffic Allowed After Initial
Rolling With PTR
 A Speed Limit (?) Should be Enforced for
2-3 Weeks
 Road may be reopen to traffic after
minimum of three passes with restricted
speed.
 On the Day of Construction :15 Passes
with PTR + 1 Pass with Steel Roller
 For Each of Next 2 Days :15 Passes with
PTR
 During First 2- 3 Weeks: Brooming Back
Aggregate
 2-3 Weeks After Construction :Sweep Off
Excess Aggregate and speed restriction
lifted.
ROLLING REQUIREMENTS
POST CONSTRUCTION
 Minimum of 8 - 12 Weeks Between First and
Second Layers
 Bleeding in Localised Areas and Wheel Path
is Normal in Otta Seals
 Any Available Fine Aggregate Can be Used for
Blinding Off
 In Case of Extensive Bleeding, Coarse
Aggregate May be Used
ADDITIONAL CONSIDERATIONS
Curing of 1st Seal for 8 – 12
Weeks
Enough Cover Aggregate to be
Applied for Sand Cover Seal and
Broomed Back Regularly until fully
Embedded. Normally 4 Weeks.
Design and construction procedure of otta seal
Design and construction procedure of otta seal
Design and construction procedure of otta seal
Design and construction procedure of otta seal
Design and construction procedure of otta seal
COMPLETED SECTION
 Single Otta
Seal +
Sand Seal
COMPLETED SECTION
 Single Otta
Seal without
Sand Seal
THANK YOU

More Related Content

PPTX
Highway Drainage System
PPTX
Types of failure in rigid pavements
PPT
Rigid Pavements Design Part - I
PPTX
Flexible pavement presentation
PPTX
economic channel section
PPTX
BALANCED CANTILEVER BRIDGE
PDF
6. Pavement Engineering.pdf
PPTX
Determining equivalent single wheel load.(ESWL)
Highway Drainage System
Types of failure in rigid pavements
Rigid Pavements Design Part - I
Flexible pavement presentation
economic channel section
BALANCED CANTILEVER BRIDGE
6. Pavement Engineering.pdf
Determining equivalent single wheel load.(ESWL)

What's hot (20)

PPTX
Earth pressure
PPTX
Khosla theory
PPTX
Reservoir Planning
PPTX
Losses IN Canals
PDF
Highway Development & Planning
PPT
Flexible and-rigid-pavements
PPTX
Railway Engineering: Turnouts
PPTX
Intersection,types
PPT
Rigid pavement
PPTX
Geometrical design of highways
PPTX
Bearings in bridges
PPTX
PERMANANT WAY
PPTX
Scope of soil engineering
PPTX
Cbr test
PPTX
PPTX
GEOMETRIC DESIGN OF HIGHWAY
PPTX
Design consideration Of Earth Dams
PPT
ogee design
PDF
Failure of weir and barrage
PPTX
Dynamic Pile Formulae
Earth pressure
Khosla theory
Reservoir Planning
Losses IN Canals
Highway Development & Planning
Flexible and-rigid-pavements
Railway Engineering: Turnouts
Intersection,types
Rigid pavement
Geometrical design of highways
Bearings in bridges
PERMANANT WAY
Scope of soil engineering
Cbr test
GEOMETRIC DESIGN OF HIGHWAY
Design consideration Of Earth Dams
ogee design
Failure of weir and barrage
Dynamic Pile Formulae
Ad

Similar to Design and construction procedure of otta seal (20)

PDF
20190906103937279.pdf
PDF
Sap parts technology brochure
PPT
Pre Submission Seminar on latests trends
PDF
The International Journal of Engineering and Science (The IJES)
PPT
CMT-L9-Shotcrete.ppt in construction industry
PDF
Tobee TG Gravel Pump..pdf
PDF
IRJET - Study on Foundry Sand as a Partial Replacement for the Fine Aggregate
PPTX
Material Testing - Aggregates Impact Value.pptx
PDF
Concrete compaction [compatibility mode]
DOCX
Method statement for expansion joint
PPT
TBBtires
PDF
Effect of Dolomitic Marble Dust Powder and Calcitic Marble Dust Powder on C...
PDF
Esite Norton Vortex Rapid Blend
DOCX
ORIENTATION REPORT SYED MOHSAN RAZA (1)
PPT
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa.ppt
PDF
dMT SPC® dry surface coatings for the ultimate wear protection on industrial ...
PDF
Kellingray
PDF
Mechanized Surface Dressing in India and countries within tropical and sub tr...
PPTX
Guniting ppt.pptx
PPT
Qulaity Control of Bridges and Grade Separators.ppt
20190906103937279.pdf
Sap parts technology brochure
Pre Submission Seminar on latests trends
The International Journal of Engineering and Science (The IJES)
CMT-L9-Shotcrete.ppt in construction industry
Tobee TG Gravel Pump..pdf
IRJET - Study on Foundry Sand as a Partial Replacement for the Fine Aggregate
Material Testing - Aggregates Impact Value.pptx
Concrete compaction [compatibility mode]
Method statement for expansion joint
TBBtires
Effect of Dolomitic Marble Dust Powder and Calcitic Marble Dust Powder on C...
Esite Norton Vortex Rapid Blend
ORIENTATION REPORT SYED MOHSAN RAZA (1)
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa.ppt
dMT SPC® dry surface coatings for the ultimate wear protection on industrial ...
Kellingray
Mechanized Surface Dressing in India and countries within tropical and sub tr...
Guniting ppt.pptx
Qulaity Control of Bridges and Grade Separators.ppt
Ad

Recently uploaded (20)

PPTX
Current and future trends in Computer Vision.pptx
PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PDF
22EC502-MICROCONTROLLER AND INTERFACING-8051 MICROCONTROLLER.pdf
PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PDF
August 2025 - Top 10 Read Articles in Network Security & Its Applications
PDF
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
PDF
737-MAX_SRG.pdf student reference guides
PPT
Total quality management ppt for engineering students
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
Soil Improvement Techniques Note - Rabbi
PPTX
Module 8- Technological and Communication Skills.pptx
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PPTX
Management Information system : MIS-e-Business Systems.pptx
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PPTX
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PPTX
introduction to high performance computing
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
Current and future trends in Computer Vision.pptx
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
22EC502-MICROCONTROLLER AND INTERFACING-8051 MICROCONTROLLER.pdf
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
August 2025 - Top 10 Read Articles in Network Security & Its Applications
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
737-MAX_SRG.pdf student reference guides
Total quality management ppt for engineering students
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
Soil Improvement Techniques Note - Rabbi
Module 8- Technological and Communication Skills.pptx
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Management Information system : MIS-e-Business Systems.pptx
Exploratory_Data_Analysis_Fundamentals.pdf
ASME PCC-02 TRAINING -DESKTOP-NLE5HNP.pptx
Categorization of Factors Affecting Classification Algorithms Selection
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
introduction to high performance computing
"Array and Linked List in Data Structures with Types, Operations, Implementat...

Design and construction procedure of otta seal

  • 1. Otta Seal (Design &Construction Procedures) Sujit Dhital Quality Management and Monitoring Specialist SNRTP (PMU West )
  • 2. SURFACING OPTION Non Structural Sand Seal Otta Seal DBSD Structural Asphalt Concrete
  • 3. FACTORS AFFECTING CHOICES Traffic Volume Riding Quality Required Operational Factor Safety Environmental Considerations Construction and Maintenance  Properties of Available Aggregate Construction Cost Required Service Life
  • 4. OTTA SEAL An Otta seal is a thin bituminous seal comprising Natural or crushed aggregate of all sizes and either a cut- back or soft penetration grade bitumen with or without sand cover seal
  • 5. MECHANISM Graded aggregate is placed on a relatively thick film of comparatively soft binder which on rolling and trafficking, works its way upwards through the aggregate interstices. The graded aggregate relies both on mechanical interlocking and bitumen binding for its strength
  • 6. GENERAL Similar to Conventional Chip Seal (DBSD) Binder Spray – Aggregate Spreading – Rolling Prime Normally Not Required Like All Other Surface Treatments, An Otta Seal Will Not Contribute Directly To The Structural Strength Of The Pavement Pavement Must Be Properly Designed To Withstand The Traffic Loading Throughout Its Designed Life
  • 8. LIMITATIONS Lack of information regarding the Otta Seal, properties, design, construction and performance  Reluctance to adopt new technology Extra contractual Obligation
  • 9. Otta seal Guiding Document
  • 10. RECOMMENDED TYPE OF OTTA SEAL IN RELATION TO TRAFFIC
  • 12. DESIGN OF OTTA SEAL GRADING GUIDELINES Sieve Sizes (mm) Open Grading Medium Grading Dense Grading (% passing) (% passing) (% passing) 16.0 100 100 100 13.2 52 - 82 68 - 94 84 - 100 9.5 36 - 58 44 - 73 70 - 98 6.7 20 - 40 29 - 54 54 - 80 4.75 10 - 30 19 - 42 44 - 70 2.0 0 - 8 3 - 18 20 - 48 1.18 0 - 5 1 - 14 15 - 38 .425 0 - 2 0 - 6 7 - 25 .075 0 - 1 0 - 2 3 - 10
  • 13. DESIGN OF OTTA SEAL STRENGTH REQUIREMENT Los Angeles Abrasion value IS: 2386 40 percent (Max) Aggregate Impact value IS: 2386 30 percent (Max) FI IS: 2386 35 percent (Max) Stripping Value 5 percent (Max)
  • 14. DESIGN OF OTTA SEAL Type of Seal Aggregate Spread Rates (m3/m2) Open Grading Medium Grading Dense Grading Otta Seals 0.013-0.016 0.013-0.016 0.016-0.020 Sand Seals 0.010-0.012 Aggregate Application Rates
  • 15. DESIGN OF OTTA SEAL Binder Spray Rates Depends on: Traffic (AADT) Aggregate Grading (Open/Medium/Dense) Absorbency of Aggregate Particles Priming of Base Course
  • 16. DESIGN OF OTTA SEAL Choice of Binder  MC 3000, in warm weather  MC 800, in cold weather when night temperature <10° C.  Blending of 80/ 100(VG10) with kerosene done at site to produce required consistency
  • 17. WEATHER LIMITATIONS The minimum surface temperatures for spraying of the different types and grades of binder shall be :  80/100 penetration grade bitumen: 50 o C  MC-3000 cutback bitumen: 22 o C  MC-800 cutback bitumen: 15 o C  MC-30 cutback bitumen: 10 o C  Emulsions: 5 o C
  • 18. DESIGN OF OTTA SEAL Choice of Binder AADT at Construction Type of Bitumen for Different Aggregate grading Open Medium Dense >1000 NA 150/200 pen MC 3000 MC 800 in cold 100 – 1000 150/200 pen 150/200 pen in cold MC 3000 MC 800 in cold <100 150/200 pen MC 3000 MC 800
  • 19. DESIGN OF OTTA SEAL Binder Spray Rates (in litres/m2) Type of Otta Seal Grading Open Medium Dense Double 1st Layer 1.6 1.7 1.8 2nd Layer 1.5 1.6 2.0 Single with a Sand Cover Seal Fine Sand 0.7 0.7 0.6 Coarse sand 0.9 0.8 0.7 1st Layer 1.6 1.7 2.0 Single 1.7 1.8 2.0 Maintenance Reseal 1.5 1.6 1.8
  • 20. DESIGN OF OTTA SEAL Blending Guidelines Required Product Cutter (kerosene) in percent of total 80/100 base Bitumen 150/200 Base Bitumen 150/200 3-5% (flux oil is used instead of Cutter) - MC 3000 8-10% 5-8% MC 800 18-20% 15-18% *
  • 22. PRIME Normally Not Required Required only when calcareous base Required because of High Amount of Bitumen Absorption
  • 23. CONSTRUCTION PROCESS Sub-grade preparation Preparation of Sub Base Preparation of CRM Binder application Aggregate spreading Rolling Sand sealing after about 8 weeks
  • 24. OTTA SEAL CONSTRUCTION EQUIPMENT USED:  Bitumen boiler 1 No.  Bitumen distributor 1 No.  Pneumatic rollers 2 Nos.  Steel roller 1 No.  Chips spreader 1 No.  Air compressor 1 No.
  • 25.  speed of the distributor can be calculated from equation Speed of distributor = S/(R*W) Where S is the rate of delivery (mass) from the spray bar in kg/s R is the design spray rate (mass) in kg/m W is the sprayed width in metres The required speed will then be in m/s. DISTRIBUTOR CALIBRATION
  • 26. PREPARATION OF BASE COURSE Good Bond Between Base Course and Surfacing Necessary Brooming Dust and Foreign Matter Light Watering to Suppress Dust and to Facilitate Penetration of Binder
  • 27. SEALING OPERATION Spraying of Binder Spreading of Aggregate Initial Rolling (On the Day of Construction) Rolling Afterwards(Back Rolling )
  • 28. ROLLING Extensive Rolling with PTR is Essential to Achieve a Good Result One Pass with a Steel Roller will Improve the Embedment of the Larger Aggregate
  • 29. TREATMENT  Commercial Traffic Allowed After Initial Rolling With PTR  A Speed Limit (?) Should be Enforced for 2-3 Weeks  Road may be reopen to traffic after minimum of three passes with restricted speed.
  • 30.  On the Day of Construction :15 Passes with PTR + 1 Pass with Steel Roller  For Each of Next 2 Days :15 Passes with PTR  During First 2- 3 Weeks: Brooming Back Aggregate  2-3 Weeks After Construction :Sweep Off Excess Aggregate and speed restriction lifted. ROLLING REQUIREMENTS
  • 31. POST CONSTRUCTION  Minimum of 8 - 12 Weeks Between First and Second Layers  Bleeding in Localised Areas and Wheel Path is Normal in Otta Seals  Any Available Fine Aggregate Can be Used for Blinding Off  In Case of Extensive Bleeding, Coarse Aggregate May be Used
  • 32. ADDITIONAL CONSIDERATIONS Curing of 1st Seal for 8 – 12 Weeks Enough Cover Aggregate to be Applied for Sand Cover Seal and Broomed Back Regularly until fully Embedded. Normally 4 Weeks.
  • 38. COMPLETED SECTION  Single Otta Seal + Sand Seal
  • 39. COMPLETED SECTION  Single Otta Seal without Sand Seal