High Voltage Gas Insulated Switchgear
(GIS) Field Testing according to IEEE C37.122
The final assembly of the gas insulated substation is then
completed in the field, where all the various components
that comprise a GIS meet for the first time. Even if the gas
insulated Substation could be completely assembled in one
factory, it would still need to be disassembled for shipment,
shipped, and then reassembled at the job site.
The purpose of the field tests is to verify that all the GIS
components perform satisfactorily, both electrically and
mechanically, after assembly at the job site. The tests
provide a method of demonstrating that the GIS apparatus
has been assembled and wired correctly and will perform
satisfactorily.
1- Mechanical tests: Gas Leakage and Gas Quality (Moisture,
Purity, and Density):
All gas compartments shall be filled with sulfur hexafluoride gas (SF6) or a required gas
mixture to the manufacturer’s required rated filling pressure and tested to detect any gas
leaks. An initial test is performed to detect any and all gas leaks and ensure compliance
with the specified maximum gas leak rate. These gas leak tests need to include all
enclosure flanges, welds of enclosures, and all gas monitoring devices, gas valves, and
interconnecting gas piping that have been assembled at the job site.
The moisture content of the gas shall be measured prior to energization. In order to get a
reliable measurement, the moisture content shall be measured some time after filling as
recommended by the manufacturer. The moisture content shall not exceed the limit
prescribed by the manufacturer or as agreed to between the manufacturer and user,
whichever value is lower.
The purity of the gas, as a percentage of SF6, shall be verified prior to energization. The
gas purity shall meet the requirements prescribed by the manufacturer.
The density of the gas shall be measured and verified to be in accordance with the
manufacturer’s nominal rated filling requirements.
2-Electrical Tests: Contact Resistance:
Contact resistance measurements of the main current carrying circuits need to be
performed on each bus connecting joint, circuit breaker, disconnect switch, grounding
switch, bushing, and power cable connection to demonstrate and verify that the
resistance values are within specified requirements. Contact resistance measurements
also need to be made on the GIS enclosure bonding connections, in cases where an
isolated (single) phase bus is being used.
The resistivity measurements shall not exceed the maximum values permissible limits
according to IEEE Stud C37.100.1.
Omicron
timing and
contact
resistance
equipment
test on ABB
GIS
3-Electrical Tests: low frequency AC voltage withstand test:
The gaseous and solid insulation (dielectrics) of the GIS shall be subjected to a low
frequency (30 Hz to 200 Hz) conditioning voltage application at voltage levels and
durations specified by the manufacturer. The conditioning voltage application shall be
followed by a one minute low frequency (30 Hz to 200 Hz).
This one-minute low frequency voltage withstand test is performed at 80% of the rated
low frequency withstand voltage performed in the manufacturer’s factory. The purpose of
these high voltage tests is to verify that the components of the gas insulated substation
have survived shipment, have been assembled correctly, that no extraneous material
has been left inside the enclosures, and that the GIS can withstand the test voltage.
AC frequency
tuned resonant
test sets for on-
site testing of GIS
4-Electrical Tests: AC Voltage Withstand Requirements and
Conditions:
Voltage withstand tests need to be made between each energized phase and the
grounded enclosure. For enclosures containing all three phases, each phase
needs to be tested, one at a time, with the enclosure and the other two phases
grounded. Before voltage withstand tests are initiated, all power transformers,
surge arresters, protective gaps, power cables, overhead transmission lines, and
voltage transformers need to be disconnected. Voltage transformers may be
tested up to the saturation voltage of the transformer at the frequency of the test.
5-Electrical tests: low frequency ac voltage withstand
requirements and conditions:
Voltage withstand tests shall be made between each energized phase and the
grounded enclosure. For enclosures containing all three phases, each phase shall
be tested, one at a time, with the enclosure and the other two phases grounded.
The insulation between each two phase conductors are not required to be
subjected to any other field voltage withstand tests.
Before voltage withstand tests are initiated, all power transformers, surge
arresters, protective gaps, power cables, and overhead transmission
lines shall be disconnected. Voltage transformers shall be tested up to
the saturation voltage of the transformer at the frequency of the test.
Isolating sections of the GIS apparatus may give an additional benefit of
field testing the open gap of some disconnecting switches, although
such a field test is not a requirement. In addition, it may be necessary to
isolate sections of the GIS to facilitate location of a disruptive discharge
or to limit the energy potentially discharged during a disruptive
discharge.
A measurement of partial discharges may be performed to detect
possible intrusion of conductive particles or damage to high-voltage
insulating components occurring during factory testing, transportation,
or installation. The gas-insulated switchgear shall be essentially free of
partial discharge. The procedure for partial measurement and
interpretations shall be provided by manufacturer and agreed between user
6-Electrical Tests: DC Voltage Withstand Tests:
DC voltage withstand testing is not recommended on a completed GIS.
However, it may be necessary to perform a DC voltage withstand test on
power cables connected to a GIS. these test voltages would, by necessity,
be applied from the end of the cable opposite to that of the GIS, therefore
subjecting a small portion of the GIS to the DC voltage. It is recommended
that the portion of the GIS subjected to this DC voltage be kept as small as
possible. The manufacturer should be consulted before performing these
tests.
7-Electrical tests: tests on auxiliary circuits:
Dielectric, continuity, and resistivity tests shall be performed on all interconnecting
control wiring installed in the field.
8-Mechanical and Electrical Functional and Operational Tests:
The following need to be verified after assembly of the GIS at the job site:
a. The torque value of all bolts and connections assembled in the field need to be
verified to be in accordance with the specified requirements.
b. The conformity of the control wiring needs to be verified to be in accordance with the
schematic and wiring diagrams.
c. The proper function of each electrical, pneumatic, hydraulic, mechanical, key, or
combination of interlock methods needs to be verified for correct operation in both the
permissive and blocking condition.
d. The proper function of the controls, gas, pneumatic, and hydraulic monitoring and
alarming systems, protective and regulating equipment, operation counters, including
heaters and lights, needs to be verified.
e. Each mechanical and electrical position indicator for each circuit breaker, disconnect
switch, and grounding switch needs to be verified that it correctly indicates the device’s
position, both open and closed.
f. The conformity of the gas zones, gas zone identification, gas valves, gas valve
positions, and interconnecting piping needs to be verified to be in accordance with the
physical drawings.
g. The operating parameters, such as contact alignment, contact travel, velocity, opening
time, and closing time of each circuit breaker, disconnect switch, and grounding switch
need to be verified in accordance with the specified requirements.
h. The correct operation of compressors, pumps, auxiliary contacts, and anti-pump
schemes needs to be verified to be in conformance with the specified requirements.
i. The circuit breakers need to be trip-tested at minimum and maximum control voltages
to verify correct operation.
g. The secondary wiring needs to be verified to have correct wire lugs, correct crimping,
tightened terminal block screws, correct wire and cable markers, and correct wiring in
accordance with the manufacturer’s drawings.
Connecting the GIS to the Electrical System:
Once the gas insulated substation has been completely installed, wired, and all field testing has been
completed satisfactorily, the new apparatus is ready to be connected to the existing electrical system. This
effort involves another series of testing to verify protective relay operation, ability of the circuit breakers to
trip on command from remote locations, and proper phase relationships with various transmission lines. This
second series of tests is expected to be similar, if not exactly the same, as the tests performed on an AIS
References:
* IEC 6227-1 (2011) High-Voltage switchgear and Control gear
– Part 1: Common Specifications.
* IEEE C37.122 (2010) IEEE Standard for Gas-Insulated
Substations.
* IEEE C37.122-1 (2013) Guide for Gas Insulated Substations
Rated Above 52 kV.
* Gas Insulated Substations Book Edited by Hermann Koch.
* https://www.omicronenergy.com
* High-voltage Tests and Measurements during the Life Cycle
of GIS Article Authors: U.Schichler,E. Kynast
* On site tests of GIS S.M. Neuhold FKH Fachkommission für
Hochspannungsfragen Zürich, Schweiz.

More Related Content

PDF
Siemens MV GIS Switchgear
PPTX
Relay coordination
PPTX
GIS (Gas-Insulated Substation) by Bharat & Shanni
PDF
400kV GIS Substation
PPTX
importance of reactive power in power system
PPSX
Switch yard & Protection
PPTX
Protection and control of Microgrid
PPTX
Gas insulated substation
Siemens MV GIS Switchgear
Relay coordination
GIS (Gas-Insulated Substation) by Bharat & Shanni
400kV GIS Substation
importance of reactive power in power system
Switch yard & Protection
Protection and control of Microgrid
Gas insulated substation

What's hot (20)

PDF
132 33kv substation documentation
PPTX
Flexible ac transmission system
PPTX
Auto reclosers
PPTX
presentation on substation layout and BUS bar arrangement.
PPTX
Types of conductors in high termission lines
PPT
Problems in overhead transmission line
PPTX
220 KV Substation Operation & Maintenance
PPTX
Sub stations-air insulated substations
PPTX
Interconnection issue in microgrid
PDF
Introduction to reactive power control in electrical power
PPTX
Gcsc gto thyristor controlled series capacitor
PPTX
Industrial Training at Howrah 220 kV Substation.
PPTX
Smart grid ppt
PPTX
Generator Protection
PPTX
Fault Level Calculation
PPTX
Flexible AC Transmission Sytstem
PPTX
Industrial summer training on 220 kv substation ppt
PPT
Fault level calculations
PDF
Gas insulated substation.
PPTX
Ppt on protection of power transformers
132 33kv substation documentation
Flexible ac transmission system
Auto reclosers
presentation on substation layout and BUS bar arrangement.
Types of conductors in high termission lines
Problems in overhead transmission line
220 KV Substation Operation & Maintenance
Sub stations-air insulated substations
Interconnection issue in microgrid
Introduction to reactive power control in electrical power
Gcsc gto thyristor controlled series capacitor
Industrial Training at Howrah 220 kV Substation.
Smart grid ppt
Generator Protection
Fault Level Calculation
Flexible AC Transmission Sytstem
Industrial summer training on 220 kv substation ppt
Fault level calculations
Gas insulated substation.
Ppt on protection of power transformers
Ad

Similar to High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C37.122 (20)

PPTX
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
PDF
substation 101
PPTX
Govind S N.pptx
PPTX
Seminar on Gas Insulated Substation
PDF
GIS PRESENTATION.pdf
PPTX
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
PPTX
Gas insulated substation
PPTX
Gases insulation powerstation
PPTX
PPTX
Gas insulated substation
PPTX
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
PPTX
Gas insulated substation 2
PDF
End of-life factors in high voltage gas insulated switchgear with sf6 or with...
PPTX
Gas insulated substation 1
PPT
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
PPTX
GSS (GIS) OLD POWER HOUSE JODHPUR
PPTX
Deepak kumar
PDF
Gis91
PPTX
Compact DC switch gear
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
substation 101
Govind S N.pptx
Seminar on Gas Insulated Substation
GIS PRESENTATION.pdf
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
Gas insulated substation
Gases insulation powerstation
Gas insulated substation
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Gas insulated substation 2
End of-life factors in high voltage gas insulated switchgear with sf6 or with...
Gas insulated substation 1
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
GSS (GIS) OLD POWER HOUSE JODHPUR
Deepak kumar
Gis91
Compact DC switch gear
Ad

More from Ali Sepehri (9)

PDF
My CV with photo
PPTX
Technical information for high voltage disconnector & earthing switch in enqu...
PPTX
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
PPTX
Out of phase current switching in High Voltage Circuit Breakers
PPTX
Transient Recovery Voltage(TRV) in Interruption of Small Inductive Currents b...
PPTX
AC Circuit Breakers Routine Tests according to IEC 62271-100
PPTX
Voltage Escalation in Shunt Reactor Switching in Circuit Breakers
PDF
Hybrid HVDC Circuit Breaker Definitions
PDF
Vacuum Circuit Breakers Testing Methods
My CV with photo
Technical information for high voltage disconnector & earthing switch in enqu...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
Out of phase current switching in High Voltage Circuit Breakers
Transient Recovery Voltage(TRV) in Interruption of Small Inductive Currents b...
AC Circuit Breakers Routine Tests according to IEC 62271-100
Voltage Escalation in Shunt Reactor Switching in Circuit Breakers
Hybrid HVDC Circuit Breaker Definitions
Vacuum Circuit Breakers Testing Methods

Recently uploaded (20)

PPTX
Principal presentation for NAAC (1).pptx
PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PPTX
Feature types and data preprocessing steps
PDF
Unit1 - AIML Chapter 1 concept and ethics
PPTX
Information Storage and Retrieval Techniques Unit III
PDF
UEFA_Carbon_Footprint_Calculator_Methology_2.0.pdf
PPTX
Measurement Uncertainty and Measurement System analysis
PDF
August 2025 - Top 10 Read Articles in Network Security & Its Applications
PDF
LOW POWER CLASS AB SI POWER AMPLIFIER FOR WIRELESS MEDICAL SENSOR NETWORK
PPTX
ai_satellite_crop_management_20250815030350.pptx
PPTX
CONTRACTS IN CONSTRUCTION PROJECTS: TYPES
PPTX
Petroleum Refining & Petrochemicals.pptx
DOC
T Pandian CV Madurai pandi kokkaf illaya
PDF
Java Basics-Introduction and program control
PDF
First part_B-Image Processing - 1 of 2).pdf
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PPTX
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
PDF
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
PPTX
Software Engineering and software moduleing
PDF
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf
Principal presentation for NAAC (1).pptx
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
Feature types and data preprocessing steps
Unit1 - AIML Chapter 1 concept and ethics
Information Storage and Retrieval Techniques Unit III
UEFA_Carbon_Footprint_Calculator_Methology_2.0.pdf
Measurement Uncertainty and Measurement System analysis
August 2025 - Top 10 Read Articles in Network Security & Its Applications
LOW POWER CLASS AB SI POWER AMPLIFIER FOR WIRELESS MEDICAL SENSOR NETWORK
ai_satellite_crop_management_20250815030350.pptx
CONTRACTS IN CONSTRUCTION PROJECTS: TYPES
Petroleum Refining & Petrochemicals.pptx
T Pandian CV Madurai pandi kokkaf illaya
Java Basics-Introduction and program control
First part_B-Image Processing - 1 of 2).pdf
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
Software Engineering and software moduleing
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf

High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C37.122

  • 1. High Voltage Gas Insulated Switchgear (GIS) Field Testing according to IEEE C37.122
  • 2. The final assembly of the gas insulated substation is then completed in the field, where all the various components that comprise a GIS meet for the first time. Even if the gas insulated Substation could be completely assembled in one factory, it would still need to be disassembled for shipment, shipped, and then reassembled at the job site. The purpose of the field tests is to verify that all the GIS components perform satisfactorily, both electrically and mechanically, after assembly at the job site. The tests provide a method of demonstrating that the GIS apparatus has been assembled and wired correctly and will perform satisfactorily.
  • 3. 1- Mechanical tests: Gas Leakage and Gas Quality (Moisture, Purity, and Density): All gas compartments shall be filled with sulfur hexafluoride gas (SF6) or a required gas mixture to the manufacturer’s required rated filling pressure and tested to detect any gas leaks. An initial test is performed to detect any and all gas leaks and ensure compliance with the specified maximum gas leak rate. These gas leak tests need to include all enclosure flanges, welds of enclosures, and all gas monitoring devices, gas valves, and interconnecting gas piping that have been assembled at the job site. The moisture content of the gas shall be measured prior to energization. In order to get a reliable measurement, the moisture content shall be measured some time after filling as recommended by the manufacturer. The moisture content shall not exceed the limit prescribed by the manufacturer or as agreed to between the manufacturer and user, whichever value is lower. The purity of the gas, as a percentage of SF6, shall be verified prior to energization. The gas purity shall meet the requirements prescribed by the manufacturer. The density of the gas shall be measured and verified to be in accordance with the manufacturer’s nominal rated filling requirements.
  • 4. 2-Electrical Tests: Contact Resistance: Contact resistance measurements of the main current carrying circuits need to be performed on each bus connecting joint, circuit breaker, disconnect switch, grounding switch, bushing, and power cable connection to demonstrate and verify that the resistance values are within specified requirements. Contact resistance measurements also need to be made on the GIS enclosure bonding connections, in cases where an isolated (single) phase bus is being used. The resistivity measurements shall not exceed the maximum values permissible limits according to IEEE Stud C37.100.1. Omicron timing and contact resistance equipment test on ABB GIS
  • 5. 3-Electrical Tests: low frequency AC voltage withstand test: The gaseous and solid insulation (dielectrics) of the GIS shall be subjected to a low frequency (30 Hz to 200 Hz) conditioning voltage application at voltage levels and durations specified by the manufacturer. The conditioning voltage application shall be followed by a one minute low frequency (30 Hz to 200 Hz). This one-minute low frequency voltage withstand test is performed at 80% of the rated low frequency withstand voltage performed in the manufacturer’s factory. The purpose of these high voltage tests is to verify that the components of the gas insulated substation have survived shipment, have been assembled correctly, that no extraneous material has been left inside the enclosures, and that the GIS can withstand the test voltage. AC frequency tuned resonant test sets for on- site testing of GIS
  • 6. 4-Electrical Tests: AC Voltage Withstand Requirements and Conditions: Voltage withstand tests need to be made between each energized phase and the grounded enclosure. For enclosures containing all three phases, each phase needs to be tested, one at a time, with the enclosure and the other two phases grounded. Before voltage withstand tests are initiated, all power transformers, surge arresters, protective gaps, power cables, overhead transmission lines, and voltage transformers need to be disconnected. Voltage transformers may be tested up to the saturation voltage of the transformer at the frequency of the test. 5-Electrical tests: low frequency ac voltage withstand requirements and conditions: Voltage withstand tests shall be made between each energized phase and the grounded enclosure. For enclosures containing all three phases, each phase shall be tested, one at a time, with the enclosure and the other two phases grounded. The insulation between each two phase conductors are not required to be subjected to any other field voltage withstand tests.
  • 7. Before voltage withstand tests are initiated, all power transformers, surge arresters, protective gaps, power cables, and overhead transmission lines shall be disconnected. Voltage transformers shall be tested up to the saturation voltage of the transformer at the frequency of the test. Isolating sections of the GIS apparatus may give an additional benefit of field testing the open gap of some disconnecting switches, although such a field test is not a requirement. In addition, it may be necessary to isolate sections of the GIS to facilitate location of a disruptive discharge or to limit the energy potentially discharged during a disruptive discharge. A measurement of partial discharges may be performed to detect possible intrusion of conductive particles or damage to high-voltage insulating components occurring during factory testing, transportation, or installation. The gas-insulated switchgear shall be essentially free of partial discharge. The procedure for partial measurement and interpretations shall be provided by manufacturer and agreed between user
  • 8. 6-Electrical Tests: DC Voltage Withstand Tests: DC voltage withstand testing is not recommended on a completed GIS. However, it may be necessary to perform a DC voltage withstand test on power cables connected to a GIS. these test voltages would, by necessity, be applied from the end of the cable opposite to that of the GIS, therefore subjecting a small portion of the GIS to the DC voltage. It is recommended that the portion of the GIS subjected to this DC voltage be kept as small as possible. The manufacturer should be consulted before performing these tests.
  • 9. 7-Electrical tests: tests on auxiliary circuits: Dielectric, continuity, and resistivity tests shall be performed on all interconnecting control wiring installed in the field. 8-Mechanical and Electrical Functional and Operational Tests: The following need to be verified after assembly of the GIS at the job site: a. The torque value of all bolts and connections assembled in the field need to be verified to be in accordance with the specified requirements. b. The conformity of the control wiring needs to be verified to be in accordance with the schematic and wiring diagrams. c. The proper function of each electrical, pneumatic, hydraulic, mechanical, key, or combination of interlock methods needs to be verified for correct operation in both the permissive and blocking condition. d. The proper function of the controls, gas, pneumatic, and hydraulic monitoring and alarming systems, protective and regulating equipment, operation counters, including heaters and lights, needs to be verified. e. Each mechanical and electrical position indicator for each circuit breaker, disconnect switch, and grounding switch needs to be verified that it correctly indicates the device’s position, both open and closed.
  • 10. f. The conformity of the gas zones, gas zone identification, gas valves, gas valve positions, and interconnecting piping needs to be verified to be in accordance with the physical drawings. g. The operating parameters, such as contact alignment, contact travel, velocity, opening time, and closing time of each circuit breaker, disconnect switch, and grounding switch need to be verified in accordance with the specified requirements. h. The correct operation of compressors, pumps, auxiliary contacts, and anti-pump schemes needs to be verified to be in conformance with the specified requirements. i. The circuit breakers need to be trip-tested at minimum and maximum control voltages to verify correct operation. g. The secondary wiring needs to be verified to have correct wire lugs, correct crimping, tightened terminal block screws, correct wire and cable markers, and correct wiring in accordance with the manufacturer’s drawings. Connecting the GIS to the Electrical System: Once the gas insulated substation has been completely installed, wired, and all field testing has been completed satisfactorily, the new apparatus is ready to be connected to the existing electrical system. This effort involves another series of testing to verify protective relay operation, ability of the circuit breakers to trip on command from remote locations, and proper phase relationships with various transmission lines. This second series of tests is expected to be similar, if not exactly the same, as the tests performed on an AIS
  • 11. References: * IEC 6227-1 (2011) High-Voltage switchgear and Control gear – Part 1: Common Specifications. * IEEE C37.122 (2010) IEEE Standard for Gas-Insulated Substations. * IEEE C37.122-1 (2013) Guide for Gas Insulated Substations Rated Above 52 kV. * Gas Insulated Substations Book Edited by Hermann Koch. * https://www.omicronenergy.com * High-voltage Tests and Measurements during the Life Cycle of GIS Article Authors: U.Schichler,E. Kynast * On site tests of GIS S.M. Neuhold FKH Fachkommission für Hochspannungsfragen Zürich, Schweiz.