High Voltage Gas Insulated Substation (GIS)
Routine Tests According to IEEE C37.122
Article 4:(30.09.2018):
Routine tests, often referred to as production tests, are performed to
ensure that each GIS operates as it has been designed and type-tested
for. The routine tests are performed for each GIS after assembly and
marks a major quality gate before the GIS leaves the factory. The test
parameters are based on the type test results, which means that, within
certain tolerances, the routine tests need to reflect the type test data.
The following sections describe briefly Routine Tests included in IEEE
C37.122 standard:
1- Dielectric Tests: The dielectric tests are done after the mechanical
routine testing and demonstrate the dielectric performance of the GIS,
ensuring the correct assembly, correctly manufactured parts from a
dielectric point of view, and the absence of particles and other
A-Power frequency dielectric test: .For routine tests, the dielectric test is
a power frequency withstand voltage test. Impulse testing, such as
lighting and switching impulse, is not typically part of the routine
testing. At minimum functional SF6 pressure, the following conditions
are tested: phase-to-ground, phase to-phase (in the case of three phases
in one enclosure design), and across open switching devices.
Successfully withstanding the one minute withstand level without a
disruptive discharge is the main criteria to mark that the test passed
successfully.
B-The measurement of partial discharges: shall be performed to detect
possible material and manufacturing defects. The measurement of
partial discharges shall be performed with dielectric tests after
mechanical routine tests. The test shall be carried out on all components
of the gas-insulated switchgear.
2-Measurement of the Resistance of the Main Circuits: Typically, the
voltage drop or resistance of main circuits are measured using a DC current of 100
A for this test. The test data should be within a 20% tolerance band compared with
the type test data.
3-Tightness Tests: Using devices such as SF6 piping, adaptation of SF6 leakage
detectors, all areas of enclosures assemblies, SF6 gauges, and SF6 density
monitoring will be checked for leaks.
4-Pressure Tests of Enclosures:
After complete machining of enclosures, pressure tests are made at 1.3
times the design pressure for welded aluminum and welded steel
enclosures and at 2 times the design pressure for cast
enclosures. Automated test stations facilitate the inclusion of a tightness
test using helium after the pressure test of the enclosure. The standard
test pressure shall be:
-1.3 times design pressure for welded aluminum and welded steel
enclosures.
- 2 times design pressure for cast aluminum and composite aluminum
enclosures.
The test pressure shall be maintained for at least 1 min. No rupture or
permanent deformation should occur during this test.
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C37.122
5-Mechanical Operation Tests :Mechanical operation tests include all
devices of the GIS that will be mechanically operated, such as a circuit
breaker, disconnect switches, ground switches, and high-speed ground
switches. The tests include a certain number of operation cycles at different
control voltage levels and the correct function of the related auxiliary
equipment; for example, auxiliary switches to indicate the position of the
circuit breaker and switches.
6-Tests on Auxiliary and Control Circuits: These tests confirm that, during
manufacturing, all wiring has been done correctly according the related
circuit diagrams. Auxiliary and control circuits shall conform to the
schematics, wiring diagrams, and technical data provided by the
manufacturer. Technical data may include the number, class, type, capacity of
available contacts, and electrical power of shunt releases (other than
auxiliary and control contacts, electrical power of shunt releases, etc.). This
A-Functional tests: A functional test of all low-voltage circuits shall be made
to verify the proper functioning of auxiliary and control circuits in conjunction
with the other parts of the switchgear. The test procedures depend on the
nature and the complexity of the low-voltage circuits of the device.
B-Verification of protection against electrical shock: Protection against
direct contact with the main circuit and safe accessibility to the auxiliary and
control equipment parts liable to be touched during normal operation shall
be checked by visual inspection.
C-Dielectric tests on auxiliary and control circuits: Only power-frequency
withstand voltage tests shall be performed. All control wiring associated with
current and linear coupler transformer secondary's and potential device
secondary's shall receive a power-frequency withstand test of 2500 V for one
minute. All other control wiring shall receive a power-frequency withstand
test of 1500 V for 1 min or 1800 V for 1 sec.
7-Pressure Tests on Partitions: Partitions are gas tight insulators that
separate one gas compartment from the other. They allow full pressure
on one side and vacuum on the other. Each partition has to be tested to
twice that of the design pressure. It has to be ensured that the weakest
mechanical direction of the device is being considered for the test. This
test verifies that the partition has been manufactured correctly to
withstand the pressure the partition is designed for. Partitions will also
be tested to the dielectric withstand capability and a sensitive partial
discharge measurement. Pressure tests shall be made on enclosures
after complete machining. Each partition shall be subjected to a
pressure test at twice the design pressure for 1 min in the weakest
direction. For the pressure test the partition shall be secured in exactly
the same manner as in service. The partition shall not show any sign of
over stress or leakage.
References:
*IEEE Standard for High Voltage Gas-Insulated Substations Rated
Above 52 kV :IEEE Std C37.122.
*Gas Insulated Substations Book by Edited by Hermann Koch.
*IEEE C37.122-1 (2013) Guide for Gas Insulated Substations
Rated Above 52 kV.
*High-voltage Tests and Measurements during the Life Cycle of
GIS article from SIEMENS company Authors: U. Schichler E.
Kynast
*High Voltage Testing of Gas (SF6) Insulated Substation article by
John De Britto C

More Related Content

PDF
400kV GIS Substation Erection Sequence
PDF
Short Circuit, Protective Device Coordination
PDF
400kV GIS Substation
PPT
Power System Protection course - Part I
PDF
IEEE substation design
PPTX
Switchgear - complete guide
PDF
Testing of Transformers.
PDF
400kV GIS Substation Erection Sequence
Short Circuit, Protective Device Coordination
400kV GIS Substation
Power System Protection course - Part I
IEEE substation design
Switchgear - complete guide
Testing of Transformers.

What's hot (20)

PPT
Fault level calculations
PDF
Transmission and distribution system design
PDF
RELAY CO-ORDINATION WITH FAULT CALCULATION
PDF
Lv switchgear & lv cable sizing
PPTX
Power System Operation and Control
PDF
Principles of Cable Sizing
PPTX
Gas insulated substation
PPTX
Reactive power compensation
PPTX
PDF
RELAY ETTING CALCULATION REV-A (DG-298).pdf
PDF
Transformer overcurrent
PDF
Generator protection calculations settings
PDF
Bus Bar protection
PPTX
Testing of transformer
PPSX
Underground cables
PPTX
Faults on Power System
PPT
Operation and maintenance of transformer
PPTX
GIS (Gas-Insulated Substation) by Bharat & Shanni
PPTX
Relays
PPTX
Fault level calculations
Transmission and distribution system design
RELAY CO-ORDINATION WITH FAULT CALCULATION
Lv switchgear & lv cable sizing
Power System Operation and Control
Principles of Cable Sizing
Gas insulated substation
Reactive power compensation
RELAY ETTING CALCULATION REV-A (DG-298).pdf
Transformer overcurrent
Generator protection calculations settings
Bus Bar protection
Testing of transformer
Underground cables
Faults on Power System
Operation and maintenance of transformer
GIS (Gas-Insulated Substation) by Bharat & Shanni
Relays
Ad

Similar to High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C37.122 (20)

PPTX
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
PDF
End of-life factors in high voltage gas insulated switchgear with sf6 or with...
PPTX
AC Circuit Breakers Routine Tests according to IEC 62271-100
PDF
substation 101
PPT
Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015
PPTX
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
PDF
GIS PRESENTATION.pdf
PDF
PDF
PDF
02 7922 9034-1-pb
PPTX
Gas insulated substation
PPTX
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
PPTX
Electrical testing javid iqbal sodagar
PDF
Dialectirc tests
PPTX
PPTX
Relay testing.............................
PPTX
13. Testing and Maintenance notesvvvvvvv
PPTX
Seminar on Gas Insulated Substation
PPT
PPT
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
End of-life factors in high voltage gas insulated switchgear with sf6 or with...
AC Circuit Breakers Routine Tests according to IEC 62271-100
substation 101
Gabriel Ojeah - HV CONFERENCE POWER POINT - PERTH 2015
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
GIS PRESENTATION.pdf
02 7922 9034-1-pb
Gas insulated substation
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
Electrical testing javid iqbal sodagar
Dialectirc tests
Relay testing.............................
13. Testing and Maintenance notesvvvvvvv
Seminar on Gas Insulated Substation
Ad

More from Ali Sepehri (7)

PDF
My CV with photo
PPTX
Technical information for high voltage disconnector & earthing switch in enqu...
PPTX
Out of phase current switching in High Voltage Circuit Breakers
PPTX
Transient Recovery Voltage(TRV) in Interruption of Small Inductive Currents b...
PPTX
Voltage Escalation in Shunt Reactor Switching in Circuit Breakers
PDF
Hybrid HVDC Circuit Breaker Definitions
PDF
Vacuum Circuit Breakers Testing Methods
My CV with photo
Technical information for high voltage disconnector & earthing switch in enqu...
Out of phase current switching in High Voltage Circuit Breakers
Transient Recovery Voltage(TRV) in Interruption of Small Inductive Currents b...
Voltage Escalation in Shunt Reactor Switching in Circuit Breakers
Hybrid HVDC Circuit Breaker Definitions
Vacuum Circuit Breakers Testing Methods

Recently uploaded (20)

PPTX
Construction Project Organization Group 2.pptx
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
DOCX
573137875-Attendance-Management-System-original
PPTX
additive manufacturing of ss316l using mig welding
PDF
PPT on Performance Review to get promotions
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
Artificial Intelligence
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
Geodesy 1.pptx...............................................
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
Digital Logic Computer Design lecture notes
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
Sustainable Sites - Green Building Construction
Construction Project Organization Group 2.pptx
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Internet of Things (IOT) - A guide to understanding
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
573137875-Attendance-Management-System-original
additive manufacturing of ss316l using mig welding
PPT on Performance Review to get promotions
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Artificial Intelligence
Automation-in-Manufacturing-Chapter-Introduction.pdf
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Safety Seminar civil to be ensured for safe working.
Geodesy 1.pptx...............................................
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Digital Logic Computer Design lecture notes
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Sustainable Sites - Green Building Construction

High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C37.122

  • 1. High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C37.122
  • 2. Article 4:(30.09.2018): Routine tests, often referred to as production tests, are performed to ensure that each GIS operates as it has been designed and type-tested for. The routine tests are performed for each GIS after assembly and marks a major quality gate before the GIS leaves the factory. The test parameters are based on the type test results, which means that, within certain tolerances, the routine tests need to reflect the type test data. The following sections describe briefly Routine Tests included in IEEE C37.122 standard: 1- Dielectric Tests: The dielectric tests are done after the mechanical routine testing and demonstrate the dielectric performance of the GIS, ensuring the correct assembly, correctly manufactured parts from a dielectric point of view, and the absence of particles and other
  • 3. A-Power frequency dielectric test: .For routine tests, the dielectric test is a power frequency withstand voltage test. Impulse testing, such as lighting and switching impulse, is not typically part of the routine testing. At minimum functional SF6 pressure, the following conditions are tested: phase-to-ground, phase to-phase (in the case of three phases in one enclosure design), and across open switching devices. Successfully withstanding the one minute withstand level without a disruptive discharge is the main criteria to mark that the test passed successfully. B-The measurement of partial discharges: shall be performed to detect possible material and manufacturing defects. The measurement of partial discharges shall be performed with dielectric tests after mechanical routine tests. The test shall be carried out on all components of the gas-insulated switchgear.
  • 4. 2-Measurement of the Resistance of the Main Circuits: Typically, the voltage drop or resistance of main circuits are measured using a DC current of 100 A for this test. The test data should be within a 20% tolerance band compared with the type test data. 3-Tightness Tests: Using devices such as SF6 piping, adaptation of SF6 leakage detectors, all areas of enclosures assemblies, SF6 gauges, and SF6 density monitoring will be checked for leaks.
  • 5. 4-Pressure Tests of Enclosures: After complete machining of enclosures, pressure tests are made at 1.3 times the design pressure for welded aluminum and welded steel enclosures and at 2 times the design pressure for cast enclosures. Automated test stations facilitate the inclusion of a tightness test using helium after the pressure test of the enclosure. The standard test pressure shall be: -1.3 times design pressure for welded aluminum and welded steel enclosures. - 2 times design pressure for cast aluminum and composite aluminum enclosures. The test pressure shall be maintained for at least 1 min. No rupture or permanent deformation should occur during this test.
  • 7. 5-Mechanical Operation Tests :Mechanical operation tests include all devices of the GIS that will be mechanically operated, such as a circuit breaker, disconnect switches, ground switches, and high-speed ground switches. The tests include a certain number of operation cycles at different control voltage levels and the correct function of the related auxiliary equipment; for example, auxiliary switches to indicate the position of the circuit breaker and switches. 6-Tests on Auxiliary and Control Circuits: These tests confirm that, during manufacturing, all wiring has been done correctly according the related circuit diagrams. Auxiliary and control circuits shall conform to the schematics, wiring diagrams, and technical data provided by the manufacturer. Technical data may include the number, class, type, capacity of available contacts, and electrical power of shunt releases (other than auxiliary and control contacts, electrical power of shunt releases, etc.). This
  • 8. A-Functional tests: A functional test of all low-voltage circuits shall be made to verify the proper functioning of auxiliary and control circuits in conjunction with the other parts of the switchgear. The test procedures depend on the nature and the complexity of the low-voltage circuits of the device. B-Verification of protection against electrical shock: Protection against direct contact with the main circuit and safe accessibility to the auxiliary and control equipment parts liable to be touched during normal operation shall be checked by visual inspection. C-Dielectric tests on auxiliary and control circuits: Only power-frequency withstand voltage tests shall be performed. All control wiring associated with current and linear coupler transformer secondary's and potential device secondary's shall receive a power-frequency withstand test of 2500 V for one minute. All other control wiring shall receive a power-frequency withstand test of 1500 V for 1 min or 1800 V for 1 sec.
  • 9. 7-Pressure Tests on Partitions: Partitions are gas tight insulators that separate one gas compartment from the other. They allow full pressure on one side and vacuum on the other. Each partition has to be tested to twice that of the design pressure. It has to be ensured that the weakest mechanical direction of the device is being considered for the test. This test verifies that the partition has been manufactured correctly to withstand the pressure the partition is designed for. Partitions will also be tested to the dielectric withstand capability and a sensitive partial discharge measurement. Pressure tests shall be made on enclosures after complete machining. Each partition shall be subjected to a pressure test at twice the design pressure for 1 min in the weakest direction. For the pressure test the partition shall be secured in exactly the same manner as in service. The partition shall not show any sign of over stress or leakage.
  • 10. References: *IEEE Standard for High Voltage Gas-Insulated Substations Rated Above 52 kV :IEEE Std C37.122. *Gas Insulated Substations Book by Edited by Hermann Koch. *IEEE C37.122-1 (2013) Guide for Gas Insulated Substations Rated Above 52 kV. *High-voltage Tests and Measurements during the Life Cycle of GIS article from SIEMENS company Authors: U. Schichler E. Kynast *High Voltage Testing of Gas (SF6) Insulated Substation article by John De Britto C