IMPACT OF DELAYNESS ON CONSTRUCTION PROJECTS
Swadesh Singh Bhadoria,1 Sohit Agrawal,2 Swetank Sharma,2, Dr.Mukesh Kumar Pandey,3
B.Tech+M.tech(INT) P.G student, Construction technology & Management, I.T.M University Madhya Pradesh, India.
Asst.Professor DEPT.OF CIVIL ENGINEERING, I.T.M university Madhyapradesh, India.
Professor DEPT.OF CIVIL ENGINEERING, I.T.M university Madhyapradesh ,India
-------------------------------------------------------------***------------------------------------------------------------------
Abstract:
This paper deals with the attributes of delay
which extremely effect on the residential and
multi-stories construction projects in Gwalior
City in India. Time delays and cost overruns
have become a challenge for civil engineering
section of India. . This research theme deals
with the analysis of properties of delay &
ranking of attributes by RII (relative
importance index). Which are extremely
effected on construction projects of buildings in
India. This study included analysis of delay
factors, ranking of factors of delays and also
compared among three groups (i.e, Owner,
Contractor & consultant). Total 38 causes are
identified under 8 major groups. An Interview
questionnaire was taken for survey the critical
causes of delays in building area. Total 35
respondents included in this research, i.e., 9
owners, 12 contractors and 14consultants.This
paper suggest the simplest way to find out the
ranking of attributes of delay by RII (Relative
importance technique). After determining
results of all attributes of delays is that
ten factors out of all total are highly effected in
the execution of large building construction.
They are shortage of labour, delay in
delivery of resources on the site, Rework due
to errors on the site, delay current payment by
owner, poor site management at the site
and direction by contractor etc.
Key Words- Analysis of delay’s Factors, Survey,
Relative important index (RII), Effects of delay.
1.INTRODUCTION
The delay in the construction work department
can also be said as the project does not deliver
on the date of completion of the project and
also the expansion in the estimated cost project
as compare to the actual cost of a project, it
means the project is delayed due to delays in
time and values overruns. Toward the owner of
the project delay suggests that price overruns
attributable to lack of production
and rentable area. Toward the contractor
delay implies that higher
overhead price attributable to enlargement in
time of project, high material price, machinery
and labour price increment.. The procedure of
execution of a construction project is subjected
to various and unwanted factors which result
from many sources. These sources contained
availability of resources on site, environment,
condition, the performance of various parties,
Role of other parties and contractual
relationship. Delay means more activities are
pending which mentioned within the contract
duration of the project.
For various parties definition of delayness in
construction project is different such as For
owner delay means low income in more time,
For consultant delay means more work
remaining in less time period etc. so because of
delay project cost, material cost, government
charges and overall cost are increase. All these
factors are related to causes of delay so we
can realize the attributes of delays in
construction to extend the performance of
project. For any construction projects
requirement of work is very high so, owner
needs planning at which time and price of
project is satisfy. This can be listed out by
proper -scheduling and by identification of
causes of delays. So, it is necessary to explain
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1327
the most critical causes of delay which have
great effect on the construction project in order
to minimize and try to avoid the delays in the
construction of multi-stories and residential
building project in India.
1.1 Effect of delays
 Time overrun
 Cost overrun
 Dispute
 Arbitration
 Total abandonment
 Litigation
2. Objectives of study:
The main objectives of this present study are as
follows:
To study and analyse the attributes of delay in
building construction projects from the point of
view of owner, contractor and consultant.
To rank the causes of delay by Relative
importance index technique (RII).
Try to minimize the causes of Delay.
3. LITERATURE REVIEW
Ashraf Samara and Ghanim A. Bekr (2016)
identified the 55 important factors of delay in
Jordan which had hardly effected by Time
overruns and expansion of cost. They were
carried out a survey to identiy the critical
factors of delay which has stopped the
performance of Jordan construction in which
146 respondents are involved. Top ten factors
causing delays for public sector projects in
Jordan are: (1) inadequate management and
supervision by the contractor, (2) client's
changes of the design, (3) inadequate planning
and control by the contractor, (4) using lowest
bid that lead to low performance, (5) changes
in the extent of the project , (6) errors in design
and contract documents , (7) progress
payments are not made in time by the client,
(8) Rework due to mistakes during
construction, (9) Changes in the original design
and (10)Low level productivity.
Mohammad Saiful, Bambang Trigunarsyah
and Sadi Assaf (2015) evaluating the 79
different significant factors of delays in the
construction of multi-stories building and
residential building in construction industry of
Bangladesh. They were conducted a survey to
identifying the causes of delay in large large
building construction projects in which 70
respondents participated i.e, (owner,
consultant, contractor) by using importance
index method. About their results, they
concluded the lack of experience construction
manager ,lowest bidder selection, improper
planning & scheduling ,lack of proper working
management are the most critical causes of
delay which are highly contributed to occur
delay in construction project..
4. RESEARCH METHODOLOGY
 LITERATURE COLLECTION
 REVISION OF LITERATURE
 IDENTIFICATION OF DELAY’S
CAUSES& EFFECTS
 QUESTIONNAIRE PREPRATION
 QUESTIONNAIRE SURVEY
 ANALYSIS OF CAUSES BY (RII)
TECHNIQUE
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1328
4. DATA ANALYSIS APPROCH
(i). Relative Importance Index technique:
By exploitation the Relative Importance Index
technique to the ranking of causes of delay is
easy with compare to alternative. The same
method is taken in this present study within
three groups which are owners, consultants or
contractors. The grading of five-point scale 1
for (very low importance) to 5 for very high
importance) is considered and converted into
relative importance indices (RII) for each factor
as follows:
∑W
RII = (0< RII <1)
A* N
Where:
W – is the response weight given to each
attribute by the personnel and range vary from
1 to 5, (where “1” is “very low importance” and
“5” is “very high importance”);
A – is the highest weight (i.e. 5 in this case) and;
N – is the overall number of stakeholders.
Table -1: significant Causes of delay by RII Method
Figure -1: significant Causes of delay by RII Method
Table 5.2 : Ranking of group of causes of delay
by All three Parties
0.8510.846
0.811
0.7940.7890.7770.7710.7660.7540.743
0.68
0.7
0.72
0.74
0.76
0.78
0.8
0.82
0.84
0.86
Reworkdueto…
Originalcontract…
Shortageoflabor
Inadequate…
Difficultiesin…
Delayinprogress…
Shortageof…
1 2 3 4 5 6 7 8 9 10
RII
RII
No. Critical Cause of delay RII
1 Rework due to errors during
construction 0.851
2 Inadequate planning and scheduling
of project by contractor 0.846
3 Original contract duration is too
short 0.811
4 Delay in material delivery 0.794
5 Shortage of labour 0.789
6 Poor site management and
supervision by the contractor 0.777
7 Inadequate contractor’s work
experience 0.771
8 Difficulties in financing project by
contractor 0.766
9 Delay in progress payment by owner 0.754
10 Shortage of equipment 0.743
S.NO. No.of
Groups
OWNE
R RII
R
A
N
K
Contra
ctor
RII
R
A
N
K
Consul
tant
RII
R
A
N
K
1. contracto
r
0.78 1 0.59 8 0.77 1
2. consultan
t
0.64 5 0.71 4 0.51 8
3. project 0.66 4 0.79 1 0.72 2
4. owner 0.50 7 0.76 2 0.56 7
5. labour 0.68 3 0.72 3 0.68 3
6. Design 0.55 6 0.60 7 0.65 5
7. material 0.71 2 0.61 6 0.62 6
8. equipme
nt
0.48 8 0.65 5 0.66 4
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1329
Figure-2 : Ranking of group of causes of delay
by All three Partie
6. Conclusion
The first step in reducing the delays in
infrastructure construction project is to
understand the root causes of the delay. This
results provide a listing of root causes and
issues that are directly responsible for most
infrastructure construction project delays.
Additionally, it is found that fundamental
principles must be adopted before significant
improvements can be made. The data were
collected from the following construction
Infrastructure companies.
According to results, some factors have found
that which are highly effected on the
construction projects Rework due to mistakes,
Inadequate planning & scheduling of project by
contractor, Original contract duration is too
short, Delay in material delivery on site,
Shortage of labour , Poor site management &
supervision by contractor, Inadequate
contractor’s experience, Difficulties in financing
by contractor, Shortage of equipment, Delay in
progress payment by owner .
7.Recommendation
The following points can be recommended by
all parties in order to minimize and control
delays in construction projects:
7.1. Contractor’s Should Consider The
Following Factors
Shortage and low productivity of labor: enough
number of labors should be assigned and
motivated to improve productivity.
Financial and cash flow problems: contractor
should manage his financial resources and plan
cash flow by utilizing progress payment.
7.2. Consultant’s Should Look To The
Following Factors
Reviewing and approving design documents
any delay caused by the consultant engineer in
checking, reviewing and approving the design
submittals prior to construction phase, could
delay the progress of the work;
Inflexibility: Consultants should be flexible in
evaluating contractor works. Compromising
between the cost and high quality should be
considered.
7.3. Owner’s Should Give Special Attention
To The Following Factors
Pay progress payment to the contractor on
time because it impairs the contractor’s ability
to finance the work.
Reduce the frequent changing in orders during
construction to neglect delays.
8.REFRENCES
1. Hemanta Doloi, Anil Sawhney, K.C.Iyer, Sameer
Rentala (2012).Analysing factors affecting daelays in
Indian construction projects International journal of
project management 30,479-489
2. Mamta Rajgor, Chauhan Paresh, Patel Dhruv, Panchal
Chirag. RII&IMPI: Effective techniques for finding
delay in construction projects. International
Research Journal of
Engineering&TechnologyVolume:03.Issue:01|JAN-
2016.
3.YawFrimpong,JacobOluwoye,LynnCrawford.Causes of
delay and cost overruns in construction of ground
water projects in developing countries in Ghana
International journal of project
management21(2013),321-326.
4.Siddesh K Pai,Mr.J.Raj Bharath. Analysis of critical
causes of Delay in Indian Infrastructure Projects.
0.78
0.64 0.66
0.5
0.68
0.55
0.71
0.48
0.59
0.71
0.790.76
0.72
0.60.61
0.65
0.77
0.51
0.72
0.56
0.680.650.62
0.66
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1 3 5 7 9 11 13 15 17
OWNER RII
Contractor RII
Consultant RII
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1330
International journal of Innovative Research &
Development VOL2:Issue:March-2013.
5.Mega Desai, Rajiv Bhatt. Critical causes of Delay in
Residential Construction Projects: Case Study of
Central Gujarat Region in India. .International
Research Journal of Engineering Trends and
Technology Volume:4.Issue:4|April-2013
6.Murat Gunduj, Yasemin Nielsen, Mustafa Ozdemir.
Quantification of Delay Factors Using the RII Method
for Construction Projects in Turkey. Journal of
Management in Engineering(2013),29(2):133-139.

More Related Content

PDF
Management For Construction Project:-Various Aspects Of Delay
PDF
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
PDF
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
PDF
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
PDF
IRJET- Quality Assurance & Project Scheduling for Residential Building
PDF
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
PDF
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
PDF
Factor Affecting Construction Cost and Time in road project
Management For Construction Project:-Various Aspects Of Delay
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Quality Assurance & Project Scheduling for Residential Building
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Factor Affecting Construction Cost and Time in road project

What's hot (19)

PDF
Effect of construction delays on project time overrun
PDF
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
PDF
IRJET- Delay in Construction its Causes and Mitigation: A Review
PDF
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
PDF
IRJET- Review on Study of Quality Practices in Construction
PDF
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
PDF
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
PPTX
causes and implication of delay in construction
PDF
A Review of Cost overruns in Construction Project Management
PDF
Analysis of Cost Over Run in Construction Projects
PDF
Project delay and_cost_overrun-libre
PPTX
Time overruns
PDF
A systematic study on site overhead costs in construction industry
PDF
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
PDF
Developing an effective workflow module for productivity analysis using stati...
PDF
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
PDF
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
PDF
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
PDF
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Effect of construction delays on project time overrun
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET- Review on Study of Quality Practices in Construction
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
causes and implication of delay in construction
A Review of Cost overruns in Construction Project Management
Analysis of Cost Over Run in Construction Projects
Project delay and_cost_overrun-libre
Time overruns
A systematic study on site overhead costs in construction industry
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
Developing an effective workflow module for productivity analysis using stati...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Ad

Viewers also liked (20)

PDF
A review towards various hash algorithms and their comparative analysis
PDF
An analysis of effect of variable compression ratio in C.I. engine using turb...
PDF
Color to sound converter for blind people
PDF
Free vibration analysis on cantilever beam-A review
PDF
IOT Based Water Level Monitoring System For Lake
PDF
A Distributed Time Triggered Control for a Feedback Control System
PDF
Study of Multipurpose Road Cleaning Machine
PDF
Strength and geotechnical characterization of copper slag as partial replacem...
PDF
Sag/Swell Compensation by using BES DVR in Industrial Drives Applications
PDF
Privacy Recommendations and Ranking of User Images on Content Sharing Sites
PDF
Localization of wireless sensor network
PDF
Portable voice communication system on raspberry pi
PDF
Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...
PDF
Automatic pneumatic bumper
PDF
Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...
PDF
A Paper on Study & Design of Multipurpose Riveting Machine
PDF
An Investigation of DAF Protocol in Wireless Communication
PDF
A Review Paper on Pneumatic Operated Collapsable Steering System
PDF
Forward and Inverse Kinematic Analysis of Robotic Manipulators
PDF
A Geo-PFM Model for Point Of Interest Recommendation
A review towards various hash algorithms and their comparative analysis
An analysis of effect of variable compression ratio in C.I. engine using turb...
Color to sound converter for blind people
Free vibration analysis on cantilever beam-A review
IOT Based Water Level Monitoring System For Lake
A Distributed Time Triggered Control for a Feedback Control System
Study of Multipurpose Road Cleaning Machine
Strength and geotechnical characterization of copper slag as partial replacem...
Sag/Swell Compensation by using BES DVR in Industrial Drives Applications
Privacy Recommendations and Ranking of User Images on Content Sharing Sites
Localization of wireless sensor network
Portable voice communication system on raspberry pi
Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...
Automatic pneumatic bumper
Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...
A Paper on Study & Design of Multipurpose Riveting Machine
An Investigation of DAF Protocol in Wireless Communication
A Review Paper on Pneumatic Operated Collapsable Steering System
Forward and Inverse Kinematic Analysis of Robotic Manipulators
A Geo-PFM Model for Point Of Interest Recommendation
Ad

Similar to Impact of delayness on construction projects (20)

PDF
RII & IMPI: Effective Techniques for Finding Delay in Construction Project
PDF
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
PDF
Investigating the Factors Affecting Delays in Infrastructure Projects
PDF
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
PDF
IRJET- Review on Study of Factors Affecting Quality of Construction Project
PDF
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
PDF
I012646171
PDF
I012646171
PDF
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
PDF
journalsresaim,+IJRESM_V3_I7_70.pdf
PDF
IRJET- Analysis of Change Order in Road Construction Projects
PDF
Delay Analysis in Construction of Redevelopment Residential Project
PDF
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
PDF
Element of Cost overrun and Delay in Construction: A Review
PDF
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
PDF
IRJET- To Study the Causes and Effects of Delays in Construction Project
PDF
A study on the analysis and evaluation of delays in private construction Proj...
PDF
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
PDF
Ijciet 08 04_220
PDF
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
RII & IMPI: Effective Techniques for Finding Delay in Construction Project
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
Investigating the Factors Affecting Delays in Infrastructure Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
I012646171
I012646171
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
journalsresaim,+IJRESM_V3_I7_70.pdf
IRJET- Analysis of Change Order in Road Construction Projects
Delay Analysis in Construction of Redevelopment Residential Project
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
Element of Cost overrun and Delay in Construction: A Review
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- To Study the Causes and Effects of Delays in Construction Project
A study on the analysis and evaluation of delays in private construction Proj...
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
Ijciet 08 04_220
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...

More from IRJET Journal (20)

PDF
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
PDF
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
PDF
Kiona – A Smart Society Automation Project
PDF
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
PDF
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
PDF
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
PDF
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
PDF
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
PDF
BRAIN TUMOUR DETECTION AND CLASSIFICATION
PDF
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
PDF
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
PDF
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
PDF
Breast Cancer Detection using Computer Vision
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
Kiona – A Smart Society Automation Project
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
BRAIN TUMOUR DETECTION AND CLASSIFICATION
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
Breast Cancer Detection using Computer Vision
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...

Recently uploaded (20)

PPTX
Current and future trends in Computer Vision.pptx
PPT
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
PDF
737-MAX_SRG.pdf student reference guides
PDF
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PDF
Analyzing Impact of Pakistan Economic Corridor on Import and Export in Pakist...
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PPT
introduction to datamining and warehousing
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
PPT
Occupational Health and Safety Management System
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PDF
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
PPTX
Information Storage and Retrieval Techniques Unit III
PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
PPT
Total quality management ppt for engineering students
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
UNIT - 3 Total quality Management .pptx
Current and future trends in Computer Vision.pptx
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
737-MAX_SRG.pdf student reference guides
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
III.4.1.2_The_Space_Environment.p pdffdf
Analyzing Impact of Pakistan Economic Corridor on Import and Export in Pakist...
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
introduction to datamining and warehousing
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
Occupational Health and Safety Management System
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
Information Storage and Retrieval Techniques Unit III
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
Total quality management ppt for engineering students
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
Automation-in-Manufacturing-Chapter-Introduction.pdf
UNIT - 3 Total quality Management .pptx

Impact of delayness on construction projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1326 IMPACT OF DELAYNESS ON CONSTRUCTION PROJECTS Swadesh Singh Bhadoria,1 Sohit Agrawal,2 Swetank Sharma,2, Dr.Mukesh Kumar Pandey,3 B.Tech+M.tech(INT) P.G student, Construction technology & Management, I.T.M University Madhya Pradesh, India. Asst.Professor DEPT.OF CIVIL ENGINEERING, I.T.M university Madhyapradesh, India. Professor DEPT.OF CIVIL ENGINEERING, I.T.M university Madhyapradesh ,India -------------------------------------------------------------***------------------------------------------------------------------ Abstract: This paper deals with the attributes of delay which extremely effect on the residential and multi-stories construction projects in Gwalior City in India. Time delays and cost overruns have become a challenge for civil engineering section of India. . This research theme deals with the analysis of properties of delay & ranking of attributes by RII (relative importance index). Which are extremely effected on construction projects of buildings in India. This study included analysis of delay factors, ranking of factors of delays and also compared among three groups (i.e, Owner, Contractor & consultant). Total 38 causes are identified under 8 major groups. An Interview questionnaire was taken for survey the critical causes of delays in building area. Total 35 respondents included in this research, i.e., 9 owners, 12 contractors and 14consultants.This paper suggest the simplest way to find out the ranking of attributes of delay by RII (Relative importance technique). After determining results of all attributes of delays is that ten factors out of all total are highly effected in the execution of large building construction. They are shortage of labour, delay in delivery of resources on the site, Rework due to errors on the site, delay current payment by owner, poor site management at the site and direction by contractor etc. Key Words- Analysis of delay’s Factors, Survey, Relative important index (RII), Effects of delay. 1.INTRODUCTION The delay in the construction work department can also be said as the project does not deliver on the date of completion of the project and also the expansion in the estimated cost project as compare to the actual cost of a project, it means the project is delayed due to delays in time and values overruns. Toward the owner of the project delay suggests that price overruns attributable to lack of production and rentable area. Toward the contractor delay implies that higher overhead price attributable to enlargement in time of project, high material price, machinery and labour price increment.. The procedure of execution of a construction project is subjected to various and unwanted factors which result from many sources. These sources contained availability of resources on site, environment, condition, the performance of various parties, Role of other parties and contractual relationship. Delay means more activities are pending which mentioned within the contract duration of the project. For various parties definition of delayness in construction project is different such as For owner delay means low income in more time, For consultant delay means more work remaining in less time period etc. so because of delay project cost, material cost, government charges and overall cost are increase. All these factors are related to causes of delay so we can realize the attributes of delays in construction to extend the performance of project. For any construction projects requirement of work is very high so, owner needs planning at which time and price of project is satisfy. This can be listed out by proper -scheduling and by identification of causes of delays. So, it is necessary to explain
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1327 the most critical causes of delay which have great effect on the construction project in order to minimize and try to avoid the delays in the construction of multi-stories and residential building project in India. 1.1 Effect of delays  Time overrun  Cost overrun  Dispute  Arbitration  Total abandonment  Litigation 2. Objectives of study: The main objectives of this present study are as follows: To study and analyse the attributes of delay in building construction projects from the point of view of owner, contractor and consultant. To rank the causes of delay by Relative importance index technique (RII). Try to minimize the causes of Delay. 3. LITERATURE REVIEW Ashraf Samara and Ghanim A. Bekr (2016) identified the 55 important factors of delay in Jordan which had hardly effected by Time overruns and expansion of cost. They were carried out a survey to identiy the critical factors of delay which has stopped the performance of Jordan construction in which 146 respondents are involved. Top ten factors causing delays for public sector projects in Jordan are: (1) inadequate management and supervision by the contractor, (2) client's changes of the design, (3) inadequate planning and control by the contractor, (4) using lowest bid that lead to low performance, (5) changes in the extent of the project , (6) errors in design and contract documents , (7) progress payments are not made in time by the client, (8) Rework due to mistakes during construction, (9) Changes in the original design and (10)Low level productivity. Mohammad Saiful, Bambang Trigunarsyah and Sadi Assaf (2015) evaluating the 79 different significant factors of delays in the construction of multi-stories building and residential building in construction industry of Bangladesh. They were conducted a survey to identifying the causes of delay in large large building construction projects in which 70 respondents participated i.e, (owner, consultant, contractor) by using importance index method. About their results, they concluded the lack of experience construction manager ,lowest bidder selection, improper planning & scheduling ,lack of proper working management are the most critical causes of delay which are highly contributed to occur delay in construction project.. 4. RESEARCH METHODOLOGY  LITERATURE COLLECTION  REVISION OF LITERATURE  IDENTIFICATION OF DELAY’S CAUSES& EFFECTS  QUESTIONNAIRE PREPRATION  QUESTIONNAIRE SURVEY  ANALYSIS OF CAUSES BY (RII) TECHNIQUE
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1328 4. DATA ANALYSIS APPROCH (i). Relative Importance Index technique: By exploitation the Relative Importance Index technique to the ranking of causes of delay is easy with compare to alternative. The same method is taken in this present study within three groups which are owners, consultants or contractors. The grading of five-point scale 1 for (very low importance) to 5 for very high importance) is considered and converted into relative importance indices (RII) for each factor as follows: ∑W RII = (0< RII <1) A* N Where: W – is the response weight given to each attribute by the personnel and range vary from 1 to 5, (where “1” is “very low importance” and “5” is “very high importance”); A – is the highest weight (i.e. 5 in this case) and; N – is the overall number of stakeholders. Table -1: significant Causes of delay by RII Method Figure -1: significant Causes of delay by RII Method Table 5.2 : Ranking of group of causes of delay by All three Parties 0.8510.846 0.811 0.7940.7890.7770.7710.7660.7540.743 0.68 0.7 0.72 0.74 0.76 0.78 0.8 0.82 0.84 0.86 Reworkdueto… Originalcontract… Shortageoflabor Inadequate… Difficultiesin… Delayinprogress… Shortageof… 1 2 3 4 5 6 7 8 9 10 RII RII No. Critical Cause of delay RII 1 Rework due to errors during construction 0.851 2 Inadequate planning and scheduling of project by contractor 0.846 3 Original contract duration is too short 0.811 4 Delay in material delivery 0.794 5 Shortage of labour 0.789 6 Poor site management and supervision by the contractor 0.777 7 Inadequate contractor’s work experience 0.771 8 Difficulties in financing project by contractor 0.766 9 Delay in progress payment by owner 0.754 10 Shortage of equipment 0.743 S.NO. No.of Groups OWNE R RII R A N K Contra ctor RII R A N K Consul tant RII R A N K 1. contracto r 0.78 1 0.59 8 0.77 1 2. consultan t 0.64 5 0.71 4 0.51 8 3. project 0.66 4 0.79 1 0.72 2 4. owner 0.50 7 0.76 2 0.56 7 5. labour 0.68 3 0.72 3 0.68 3 6. Design 0.55 6 0.60 7 0.65 5 7. material 0.71 2 0.61 6 0.62 6 8. equipme nt 0.48 8 0.65 5 0.66 4
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1329 Figure-2 : Ranking of group of causes of delay by All three Partie 6. Conclusion The first step in reducing the delays in infrastructure construction project is to understand the root causes of the delay. This results provide a listing of root causes and issues that are directly responsible for most infrastructure construction project delays. Additionally, it is found that fundamental principles must be adopted before significant improvements can be made. The data were collected from the following construction Infrastructure companies. According to results, some factors have found that which are highly effected on the construction projects Rework due to mistakes, Inadequate planning & scheduling of project by contractor, Original contract duration is too short, Delay in material delivery on site, Shortage of labour , Poor site management & supervision by contractor, Inadequate contractor’s experience, Difficulties in financing by contractor, Shortage of equipment, Delay in progress payment by owner . 7.Recommendation The following points can be recommended by all parties in order to minimize and control delays in construction projects: 7.1. Contractor’s Should Consider The Following Factors Shortage and low productivity of labor: enough number of labors should be assigned and motivated to improve productivity. Financial and cash flow problems: contractor should manage his financial resources and plan cash flow by utilizing progress payment. 7.2. Consultant’s Should Look To The Following Factors Reviewing and approving design documents any delay caused by the consultant engineer in checking, reviewing and approving the design submittals prior to construction phase, could delay the progress of the work; Inflexibility: Consultants should be flexible in evaluating contractor works. Compromising between the cost and high quality should be considered. 7.3. Owner’s Should Give Special Attention To The Following Factors Pay progress payment to the contractor on time because it impairs the contractor’s ability to finance the work. Reduce the frequent changing in orders during construction to neglect delays. 8.REFRENCES 1. Hemanta Doloi, Anil Sawhney, K.C.Iyer, Sameer Rentala (2012).Analysing factors affecting daelays in Indian construction projects International journal of project management 30,479-489 2. Mamta Rajgor, Chauhan Paresh, Patel Dhruv, Panchal Chirag. RII&IMPI: Effective techniques for finding delay in construction projects. International Research Journal of Engineering&TechnologyVolume:03.Issue:01|JAN- 2016. 3.YawFrimpong,JacobOluwoye,LynnCrawford.Causes of delay and cost overruns in construction of ground water projects in developing countries in Ghana International journal of project management21(2013),321-326. 4.Siddesh K Pai,Mr.J.Raj Bharath. Analysis of critical causes of Delay in Indian Infrastructure Projects. 0.78 0.64 0.66 0.5 0.68 0.55 0.71 0.48 0.59 0.71 0.790.76 0.72 0.60.61 0.65 0.77 0.51 0.72 0.56 0.680.650.62 0.66 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 3 5 7 9 11 13 15 17 OWNER RII Contractor RII Consultant RII
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1330 International journal of Innovative Research & Development VOL2:Issue:March-2013. 5.Mega Desai, Rajiv Bhatt. Critical causes of Delay in Residential Construction Projects: Case Study of Central Gujarat Region in India. .International Research Journal of Engineering Trends and Technology Volume:4.Issue:4|April-2013 6.Murat Gunduj, Yasemin Nielsen, Mustafa Ozdemir. Quantification of Delay Factors Using the RII Method for Construction Projects in Turkey. Journal of Management in Engineering(2013),29(2):133-139.