SlideShare a Scribd company logo
Improving Substation ReliabilityImproving Substation ReliabilityImproving Substation ReliabilityImproving Substation Reliability
and Availabilityand Availability
2009 PCIC2009 PCIC –– 40402009 PCIC2009 PCIC –– 4040
Authors:Authors:Authors:Authors:
Robert M. SpiewakRobert M. Spiewak Jerry PittmanJerry Pittman Daniel WilsonDaniel Wilson
Dashiell, LLC. Valero Energy Corporation Valero Port Arthur RefiningDashiell, LLC. Valero Energy Corporation Valero Port Arthur Refining
Dominik PieniazekDominik Pieniazek Floyd WeisseFloyd Weisse
VI E i i LLCVI E i i LLC D hi ll LLCD hi ll LLCVI Engineering, LLC.VI Engineering, LLC. Dashiell, LLC.Dashiell, LLC.
2009 Petroleum and Chemical Industry Committee Technical Conference2009 Petroleum and Chemical Industry Committee Technical Conference
Anaheim, CaliforniaAnaheim, California
September 14September 14--16, 200916, 2009
Today’s PresentationToday’s Presentation
Improving Substation Reliability and AvailabilityImproving Substation Reliability and Availability
Background
Substation Documentation
Automation, Data Retrieval, Historian andAutomation, Data Retrieval, Historian and
Alarm Annunciation
Monitoring and OperationMonitoring and Operation
Critical Auxiliaries
Reliability, Numbers and Statistics
Recommendations
Conclusions
Background
BackgroundBackground
Project OverviewProject Overview
Large expansion at an existing refineryLarge expansion at an existing refinery
–– Electrical Reliability ImprovementElectrical Reliability Improvement
–– Additional onAdditional on--site generationsite generationgg
Multiple parties involved:Multiple parties involved:
–– Two Owner/OperatorsTwo Owner/OperatorsTwo Owner/OperatorsTwo Owner/Operators
–– Three engineering companiesThree engineering companies
Two construction companiesTwo construction companies–– Two construction companiesTwo construction companies
–– One third party testing companyOne third party testing company
One UtilityOne Utility–– One UtilityOne Utility
BackgroundBackground
Refinery Electrical SystemRefinery Electrical System
BackgroundBackground
Electrical Events After Expansion
Nov-
06
South Sub Ground on 13.8KV overhead line. Two new transformers installed with 400A
resistor in existing 1000 A ground system. Both transformers ground relays
set to trip on Pick Up.
Sep- Refinery Balanced load to generation. Trip 80MW generator, refinery imports throughSep
07
Refinery
Blackout,
Post
Hurricane
Humberto
Balanced load to generation. Trip 80MW generator, refinery imports through
230kV lines L1 & L2. Utility 230kV lines L554 & L591 in service. L554 faults on
blown debris, no reclosing. Seconds later L591 faults on lightning strike, no
reclosing. Refinery attempted to serve its load plus local community.
Generation trips on overload and blacks out.
N PP2 Li it d ti t PP2 I t d B il h t it hi fNov-
07
PP2 Limited generation at PP2, Import mode. Boiler house operators switching for
maintenance to replace pole in tie line 205 A/B. Over current relay picked up
and tripped remaining tie line 402A/B. Training issues as refinery eliminates
tie lines and TGs.
Mar- PP6 & PP7 GTG 1 out for maintenance. Loss of a transformer along with GTG1, causes
08
g ,
overload on second transformer. DC batteries and chargers for equipment are
in PP5. Lost a single battery charger, batteries discharged, Microprocessor
relays lost power, When power restored, microprocessor relay initiated
breaker failure tripping first transformer, second transformer tripped on
overloadoverload.
BackgroundBackground
Electrical Events After Expansion (con’t)
Jul-08 PP7 Installed temporary battery charger at PS5. Tripped overnight, repowering DC
system relays previously causing trips had been disabled, a line differential
microprocessor relay initiated an unexplained trip on repowering causing an
outage.outage.
Jul-08 230kV
private L1
Test "blue Button" trips line under a scheduled utility/refinery communication
test. Logic at both ends in microprocessor relays did not match causing trip.
Mar-
08
SG Sub TR1 & TR2 Microprocessor relay. Set to trip on pick up instead of TOC;
M SG S b TR2 t i d i ti d t h i t i t t tMar-
08
SG Sub TR2 tripped on energization due to harmonic restraint not set
Apr-08 SG Sub Sync lights stay on all the time due to unproven wiring
Jun-
08
69kV Ties Overcurrent set points in microprocessor relays set incorrectly
Substation Documentation
Substation DocumentationSubstation Documentation
Requirements
Last items considered on new projectsLast items considered on new projects
Must specify your requirements beforeMust specify your requirements before
awarding project, “Toolawarding project, “Tool--Kit”Kit”
WhyWhy
–– Downsized staffDownsized staff
–– Document control issues with advancing electronicDocument control issues with advancing electronic
formatsformats
St & t i l d i ti f dSt & t i l d i ti f d–– Storage & retrieval during times of needStorage & retrieval during times of need
–– Tracking recall or advisory bulletinsTracking recall or advisory bulletins
–– FAT & SATFAT & SAT–– FAT & SATFAT & SAT
Substation DocumentationSubstation Documentation
Special Provisions
Microprocessor relays have replacedMicroprocessor relays have replaced
h d i d l l i ith t l i dih d i d l l i ith t l i dihardwired relay logic without logic diagramshardwired relay logic without logic diagrams
–– Complex relay schemes difficult to testComplex relay schemes difficult to test
D t t ( l tti )D t t ( l tti )–– Data storage (relay settings)Data storage (relay settings)
Electrical Operating ProceduresElectrical Operating Procedures
FAT/SAT Test records is benchmark dataFAT/SAT Test records is benchmark data
BOM and O&M manualsBOM and O&M manuals
Automation, Data Retrieval,
St Hi t iStorage, Historian,
andand
Alarm AnnunciationAlarm Annunciation
Automation, Data Retrieval, …Alarm Annunciation
What…?
Utilizing Installed IEDs
“Data Mining”, trending, equipment status
estimation
System Minimum Configurations
Integration Best PracticesIntegration Best Practices
Use data to “Increase productivity and
d t”reduce cost”
Automation, Data Retrieval, …Alarm Annunciation
Typical IEDs existing within substations
Protective relays and meters
O li t h d ltOn-line tap changers and voltage
regulators
Reclosers and digital fault recordersReclosers and digital fault recorders
Bushing monitoring devices
Circuit breaker monitoring devicesCircuit breaker monitoring devices
Dissolved gas in oil monitors
Partial discharge monitorsPartial discharge monitors
CCTV cameras
Phone event messengersPhone event messengers
Substation access system
Automation, Data Retrieval, …Alarm Annunciation
Example of monitoring class III transformer
Automation, Data Retrieval, …Alarm Annunciation
Mining of Data…
Data mining is the process of extracting
patterns from data.
As more data are available and gathered,g
data mining is becoming an increasingly
important tool to transform these data intop
information.
– It is commonly used in a wide range of profilingy g p g
practices, such as marketing, surveillance, fraud
detection and scientific discovery,
– Time for industrial application.
Automation, Data Retrieval, …Alarm Annunciation
“Data mining”…
Can effectively help determine:
– required maintenance intervals,
– replace interval-maintenance with risk-based
maintenance approach,
– detect equipment deterioration at early stages,
– or estimate other system properties.
Automation, Data Retrieval, …Alarm Annunciation
“Data mining”…
When such data is properly identified, the
facility has adequate time to
– acquire replacement parts,
– schedule required maintenance,
– importantly avoid catastrophic failure.
Automation, Data Retrieval, …Alarm Annunciation
Configuration and best practices
Some of the best practices:
– Ensure system can integrate devices from
various manufacturers
– Ensure system supports multiple technologies /
protocols
– Utilize multifunction IEDs
– Choose best IED for assigned function
– Make system as flexible as possible
Automation, Data Retrieval, …Alarm Annunciation
Configuration and best practices
Integrated system shall provide:
– Increased system functionality
– Increased system reliability/availability
(limit/eliminate outage time)
– Increased system safety
– Decrease a cost for automation
– Decrease a cost for protection
– Adequate tools at the fingertips of the engineer
Monitoring and Operation
Monitoring and Operation
Remote monitoring
For not-networked / not-connected
apparatus obtaining data about the present
state of the apparatus, IED, transformer or
IED that monitors this transformer is:
expensive,
time consuming,
could be risky.
F “i t lli t” (IED t k d) d tFor “intelligent” (IEDs are networked), data
is stored in a database and repository and
t i il blremote access is available.
Monitoring and Operation
First most manifested benefit
In not-networked system, to obtain
configuration files, SER, or DFR from IEDs,
the engineer needed to travel to the site and
obtain files from the devices
In networked system, the engineer cany g
access historical data from a historian, verify
what is stored in the IED presently and howp y
historical data compares with present data
Monitoring and Operation
Examples of usage
IEDs, CTs, VTs problems detection,
System recovery, switching unexpected
loads and disturbances,
Analysis of changes required to the system
for changing operating conditions,
F l h i i f d h i– For example: changing consistency of gas and how it
will influence starting and loading of the compressor
etc.,
Automatic change of protection parameters,
– For example: different seasons, mode of operations
tetc.,
Isolation from utility for special conditions.
Monitoring and Operation
Remote operation
Remote control of:
– circuit breakers,
– switches,
– lockout relays (LOR) and
– other apparatus that at present requires anpp p q
operator to control it locally,
– CCTV cameras,
– Access doors and gates.
Monitoring and Operation
FOREMOST safety benefit
Performing switching operation remotely
eliminates arc-flash hazard exposure to the
operator / electrician by removing him from
the danger zone.
– Note: safety procedures shall be established
first before remote operation is allowed.
Critical Auxiliaries
Critical Auxiliaries
Almost always forgotten…
Substation aspects considered as auxiliary in
nature:
– Control Power Supply
– Time Synchronization
– Enabling SER and DFR recorders
Critical Auxiliaries
Control and auxiliary power supply
Control Power Supply should be:
– Maintained
– Monitored
– Redundant
Critical Auxiliaries
Control and auxiliary power supply
DC CONTROL POWER SUPPLY BLOCK DIAGRAM, NON-
REDUNDANT WITH MONITORING
AC
SOURCE
BATTERY
CB
TEST
SOURCE
DS1 DS2
MCBFCB
DISTRIBUTIONDISTRIBUTION
PANEL
Critical Auxiliaries
Control and auxiliary power supply
DC CONTROL POWER SUPPLY BLOCK DIAGRAM, AC
CHARGING REDUNDANT, DC BUS NON-REDUNDANT
WITH MONITORINGWITH MONITORING
Critical Auxiliaries
Control and auxiliary power supply
DC CONTROL POWER SUPPLY BLOCK DIAGRAM,
2 x 100% REDUNDANT WITH MONITORING
Critical Auxiliaries
SER and DFR
SER and DFR default settings enable only
basic functionality at best case
– Not utilized to collect operation and fault
information
– The table in paper / Attachment C lists analog
channels and digital element recommended for
monitoring and data-collection applications
Critical Auxiliaries
Time synchronization
Cannot depend on internal clock
…circuit timing “drifts” with usage time, temperature,
environmental instability and other factors
Th ti t dd i ifi t i f tiThe time stamp adds significant information
Not synchronized information creates havoc
Time Synchronization could become a law
Some utilities require Time SynchronizationSome utilities require Time Synchronization
measurements at the Inter-Tie point
Reliability, Numbers, Statistics
and
Hidd F ilHidden Failures
Reliability, Numbers,…Hidden Failures
What is reliability?
Definition of reliabilityDefinition of reliability
–– IEEE Std 100 “EE Standard Dictionary…”IEEE Std 100 “EE Standard Dictionary…”
The ability to perform a required functionThe ability to perform a required function under statedunder stated
ditiditi f t t d i d f tif t t d i d f ticonditionsconditions for a stated period of time…for a stated period of time…
–– IEEE “Gold Book” addsIEEE “Gold Book” adds
Th tit ti li bilit l ti it li bilitThe quantitative reliability evaluation… permit reliability
indexes … to be computed from knowledge of thefrom knowledge of the
reliability … of the constituent components of thereliability … of the constituent components of the
systemsystem
–– IEEE C37.100IEEE C37.100
Reliability: a measure of the degree of certainty that the
relay, or relay system, will perform correctlywill perform correctly
Reliability, Numbers,…Hidden Failures
What is reliability?
What are we looking for when we evaluateWhat are we looking for when we evaluate
equipment / system reliability performance?equipment / system reliability performance?
–– How system should perform,How system should perform,
–– Highest reliability vs. CAPEX cost,Highest reliability vs. CAPEX cost,
–– Equipment replacement,Equipment replacement,
–– Are we considering all parameters?Are we considering all parameters?
–– Wide gap between design and operationWide gap between design and operationg p g pg p g p
calculationscalculations
Reliability, Numbers,…Hidden Failures
How calculated?
Reliability modeling principles and data we
are using do not consider:
– Varying parameters environmental parameters
– Random, unpredictable “chaotic” disturbances
– Large set samples
– Other major reliability influences
Parameters used in reliability analysis areParameters used in reliability analysis are
based on very small sampling set of data
Reliability, Numbers,…Hidden Failures
Hidden Failure
“Hidden failures”“Hidden failures”
–– IN PROTECTION SYSTEM / UTILITYIN PROTECTION SYSTEM / UTILITYIN PROTECTION SYSTEM / UTILITYIN PROTECTION SYSTEM / UTILITY
APPROACHAPPROACH
“a permanent defect that will cause a relay system to“a permanent defect that will cause a relay system top y yp y y
incorrectly and inappropriately removeincorrectly and inappropriately remove a circuit elementa circuit element
as a direct consequence of another switching event”as a direct consequence of another switching event”
IN PROCESS INDUSTY SYSTEMIN PROCESS INDUSTY SYSTEM–– IN PROCESS INDUSTY SYSTEMIN PROCESS INDUSTY SYSTEM
“a permanent defect that will cause an EI&C system to“a permanent defect that will cause an EI&C system to
incorrectly and inappropriately remove a circuit elementincorrectly and inappropriately remove a circuit elementincorrectly and inappropriately remove a circuit elementincorrectly and inappropriately remove a circuit element
as a direct consequence of another usually abnormalas a direct consequence of another usually abnormal
event in EI&C system and/or plant process”event in EI&C system and/or plant process”
Reliability, Numbers,…Hidden Failures
Causes of Hidden Failure Examples
Cause examples:Cause examples:
– Circuit fault
– Shortage of reactive power
Random operation of DC power system– Random operation of DC power system
– Inadequate testing / commissioning
– Operation of E&IC system in “seldom used state”Operation of E&IC system in seldom used state
Reliability, Numbers,…Hidden Failures
Hidden Failure “Host” Examples
Hidden failure “host”Hidden failure “host” examples:
– Control schemes from previous projects
– Not performing FAT or SAT to minimize cost
Removing monitoring equipment– Removing monitoring equipment
– Selecting vendor/contractor based on capital
cost
– Applying firmware without testing
– Not updating firmware
Reliability, Numbers and Statistics
How applies to reliability?
RELIABILITY INDICES COMPARISON
WITH AND WITHOUT HIDDEN FAILURES CONTINGENCES
RELIABILITY
INDEX
NAME
HIDDEN
FAILURES
NOT
HIDDEN FAILURES
INCLUDED
CASE 1 CASE 2NAME
INCLUDED CASE 1 CASE 2
FAILURE PROB
1.1130E-03
1.1880E-03 1.6850E-03
INCREASE 107% 151%
FAILURE FREQ [ /YR]
0.4425
0.4586 0.6034
INCREASE 104% 136%
FAILURE DURATION
[HRS/YEAR] 22.03
22.68 24.68
INCREASE 103% 112%
Note: Hidden failure probabilities: Case 1 - 10e-3, Case 2 - 10e-2
Reliability, Numbers and Statistics
Reliability
Data in “Gold Book” is a “generic”
Small sample set
Sample set collected in minimal certainSample set collected in minimal certain
conditions
Calculated indicesCalculated indices do not represent realityCalculated indicesCalculated indices do not represent reality…
Paper is focusing on improving VAILABILITY
f th EI&C t t “ li bilit i di ”of the EI&C system, not “reliability indices”
Summary
Summary
Formulate practices, standards, and data
documentation applicable to your
organization
Include in RFQ requirements special needs
that are not included in industry guides,y g
specification, practices…
Evaluate how the project should beEvaluate how the project should be
executed
Assure contractual “cooperation” with utilityAssure contractual cooperation with utility
for “post mortem” analysis
Summary
Include provisions in POs allowing for third
party to provide testing services without
altering contractual responsibilities and
obligations
Incorporate procedures for updating andp p p g
storing advisory bulletins and recall
information for all apparatus and IEDspp
Apply automation for communication with
IEDs and file managementIEDs and file management
Summary
Implement procedures and software for
analysis of the collected data
Apply reliable engineering principles for ACpp y g g p p
and/or DC control power sources design
Test periodically power system alarms andTest periodically power system alarms and
monitoring
Start collecting power system data applyStart collecting power system data apply
time synchronization
Conclusions
Conclusions
Reliability and availability of the EI&C system
in process plants:
– Difficult to estimate
– Not considers “project” factors
– Sensitive to input parameters and environmental
conditions
– Based on very small sample set of data
Conclusions
The reliability and availability of EI&C system
can be improved by focusing on time-tested:
– Good engineering practices,
– Appropriate and correct documentation,
– Apparatus/equipment testing, commissioning
and monitoring,
– Applications of available technologies to
performed monitoring tasks with minimum
human supervision,
– Perform tasks routinely to eliminate “hidden
failures” in the system.
Conclusions
Data collected during monitoring of the EI&C
system and equipment could
– “Foresee” approaching equipment failure, trigger
an alarm i.e. safe time and money!
– Aid at verifying, adjusting, calibrating power
system models for power studies
Use data to your advantage!!!Use data to your advantage!!!
Do not forget about Test Switches…
TEST SWITCH IS YOUR FRIEND !!!TEST SWITCH IS YOUR FRIEND !!!
Questions?
Thank you

More Related Content

PPTX
High Voltage Electrical Compliance and Safety Operating Procedures
DOCX
Clearences
PPTX
Maintenance schedule of Substation.
PDF
Portable Appliance Testing
PPTX
220 KV Substation Operation & Maintenance
PDF
Case Study - How we solved an Earth-fault (mal)Tripping that was causing comp...
PPTX
Power Transformer Protection
PPTX
Testing of circuit breakers
High Voltage Electrical Compliance and Safety Operating Procedures
Clearences
Maintenance schedule of Substation.
Portable Appliance Testing
220 KV Substation Operation & Maintenance
Case Study - How we solved an Earth-fault (mal)Tripping that was causing comp...
Power Transformer Protection
Testing of circuit breakers

What's hot (20)

PDF
Power system protection topic 1
PDF
Power system security
PDF
Transformer & OLTC
DOCX
Switchgear Equipment in a Substation
PPT
Practical Electrical Substation Safety for Engineers and Technicians
PDF
Short Circuit, Protective Device Coordination
PPTX
Storage tank inspection presentation
PPT
Power System Protection course - Part I
PDF
ETAP - Coordination and protecion
PDF
DIESEL GENERATOR DETAILS
PPT
POWER SYSTEM PROTECTION
PPT
Practical HV and LV Switching Operations and Safety Rules
PPTX
MTA GENERATOR PROTECTION .PPT.pptx
DOCX
Electrical substations: 132 KV
PDF
Ipsa mv relay co-ordiantion shaik adam
PDF
RELAY CO-ORDINATION WITH FAULT CALCULATION
PDF
Motor Protection
PPTX
Switchgear presentation
PDF
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
PDF
Case Study Importance of relay selection in grid connected industries
Power system protection topic 1
Power system security
Transformer & OLTC
Switchgear Equipment in a Substation
Practical Electrical Substation Safety for Engineers and Technicians
Short Circuit, Protective Device Coordination
Storage tank inspection presentation
Power System Protection course - Part I
ETAP - Coordination and protecion
DIESEL GENERATOR DETAILS
POWER SYSTEM PROTECTION
Practical HV and LV Switching Operations and Safety Rules
MTA GENERATOR PROTECTION .PPT.pptx
Electrical substations: 132 KV
Ipsa mv relay co-ordiantion shaik adam
RELAY CO-ORDINATION WITH FAULT CALCULATION
Motor Protection
Switchgear presentation
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Case Study Importance of relay selection in grid connected industries
Ad

Viewers also liked (20)

PDF
IEEE Motor Presentation
PPTX
2012 ieee pes lunch ethics 020112
PDF
Electrical Condition monitoring part 1
PDF
Electrical condition monitoring part 2
PDF
IEEE substation design
PPTX
ESI Electro Service India - Float Cum Battery Charger
DOCX
Substation equipments & its functions
POT
Chapter ( 1 ) (4)
PDF
Design, Modelling& Simulation of Double Sided Linear Segmented Switched Reluc...
PDF
Descrição da sociedade capitalista p 2
DOCX
indian railway training report
PDF
Impact of Soft Errors in Silicon on Reliability and Availability of Servers
PPTX
Hadoop Summit 2012 | HDFS High Availability
PPTX
EMMA IEEE
PPT
Electrical substation general_equipments
PPT
PDF
High Availability Infrastructure for Cloud Computing
PPTX
PPT
IEEE Code Of Conduct/Ethics
PPTX
Dual Converter using Thyristors
IEEE Motor Presentation
2012 ieee pes lunch ethics 020112
Electrical Condition monitoring part 1
Electrical condition monitoring part 2
IEEE substation design
ESI Electro Service India - Float Cum Battery Charger
Substation equipments & its functions
Chapter ( 1 ) (4)
Design, Modelling& Simulation of Double Sided Linear Segmented Switched Reluc...
Descrição da sociedade capitalista p 2
indian railway training report
Impact of Soft Errors in Silicon on Reliability and Availability of Servers
Hadoop Summit 2012 | HDFS High Availability
EMMA IEEE
Electrical substation general_equipments
High Availability Infrastructure for Cloud Computing
IEEE Code Of Conduct/Ethics
Dual Converter using Thyristors
Ad

Similar to Improving substation reliability & availability (20)

PDF
ETAP - Arc flash analysis done Right
PDF
arc-flash-analysis-done-right.pdf
PDF
ETAP - Arc flash analysis etap
PDF
IJSRED-V2I2P7
PDF
Electrical-Safety-Productoverview_PROSP_en
PDF
GaN Devices for Power Electronics: Patent Investigation
PDF
Network Protection Automation Guide Peter Rush
PDF
Network Protection Automation Guide Peter Rush
PDF
IRJET- Design and Realization of Labview based Monitoring and Control of ...
PDF
You're not in kansas anymore - the strange physical world of industrial ether...
PPT
Inter Solar2009 Observations
PPTX
radar tank gauging and dcs
PDF
Techimp Products and Services Portfolio
PPTX
digital tank gauging system and DCS
PDF
STMicroelectronics Proximity & Flood Illuminator in the Apple iPhone X - reve...
PDF
CLASS 2018 - Palestra de Julio Oliveira (Gerente de Tecnologia, Power Grids G...
PDF
Application_of_numerical_distance_relay.pdf
PDF
IRJET- Fire Fighting Robotic Vehicle
PPTX
IEEE Conference - Industrial Ethernet
PPT
The Wattminder Vision2009
ETAP - Arc flash analysis done Right
arc-flash-analysis-done-right.pdf
ETAP - Arc flash analysis etap
IJSRED-V2I2P7
Electrical-Safety-Productoverview_PROSP_en
GaN Devices for Power Electronics: Patent Investigation
Network Protection Automation Guide Peter Rush
Network Protection Automation Guide Peter Rush
IRJET- Design and Realization of Labview based Monitoring and Control of ...
You're not in kansas anymore - the strange physical world of industrial ether...
Inter Solar2009 Observations
radar tank gauging and dcs
Techimp Products and Services Portfolio
digital tank gauging system and DCS
STMicroelectronics Proximity & Flood Illuminator in the Apple iPhone X - reve...
CLASS 2018 - Palestra de Julio Oliveira (Gerente de Tecnologia, Power Grids G...
Application_of_numerical_distance_relay.pdf
IRJET- Fire Fighting Robotic Vehicle
IEEE Conference - Industrial Ethernet
The Wattminder Vision2009

More from Vincent Wedelich, PE MBA (20)

PDF
Part 3 motor application considerations understanding power concepts rev 5 vi...
PDF
Electrical master plan for chemical engineers and managers
PPT
Executive compensation main ppt
PDF
Affordable automobile for low income families
PPT
Amerada hess final presentation
PPT
American barrick vww
PPT
Balanced scorecard presentation rev 0
PPT
THE PROFIT CHAIN
PPT
MANAGEMENT ACCOUNTING STUDY PPT
PPT
MANAGEMENT ACCOUNTING STUDY PPT
PPT
FUTURES TRADING
PPT
Frontier corporation
PPT
Good to great ppt (vww)
PPT
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
PPT
Financial Derivatives and Options
PPT
Tracking firm presentation (vincent wedelich) mmm
PPT
Iceland krona vincent wedelich
PPT
Tracking firm presentation (vincent wedelich) mmm 3M
Part 3 motor application considerations understanding power concepts rev 5 vi...
Electrical master plan for chemical engineers and managers
Executive compensation main ppt
Affordable automobile for low income families
Amerada hess final presentation
American barrick vww
Balanced scorecard presentation rev 0
THE PROFIT CHAIN
MANAGEMENT ACCOUNTING STUDY PPT
MANAGEMENT ACCOUNTING STUDY PPT
FUTURES TRADING
Frontier corporation
Good to great ppt (vww)
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
Financial Derivatives and Options
Tracking firm presentation (vincent wedelich) mmm
Iceland krona vincent wedelich
Tracking firm presentation (vincent wedelich) mmm 3M

Recently uploaded (20)

PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
Fundamentals of Mechanical Engineering.pptx
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
Geodesy 1.pptx...............................................
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PDF
Well-logging-methods_new................
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
DOCX
573137875-Attendance-Management-System-original
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Automation-in-Manufacturing-Chapter-Introduction.pdf
Internet of Things (IOT) - A guide to understanding
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Categorization of Factors Affecting Classification Algorithms Selection
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
III.4.1.2_The_Space_Environment.p pdffdf
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Fundamentals of Mechanical Engineering.pptx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Geodesy 1.pptx...............................................
Embodied AI: Ushering in the Next Era of Intelligent Systems
Well-logging-methods_new................
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
573137875-Attendance-Management-System-original

Improving substation reliability & availability

  • 1. Improving Substation ReliabilityImproving Substation ReliabilityImproving Substation ReliabilityImproving Substation Reliability and Availabilityand Availability 2009 PCIC2009 PCIC –– 40402009 PCIC2009 PCIC –– 4040 Authors:Authors:Authors:Authors: Robert M. SpiewakRobert M. Spiewak Jerry PittmanJerry Pittman Daniel WilsonDaniel Wilson Dashiell, LLC. Valero Energy Corporation Valero Port Arthur RefiningDashiell, LLC. Valero Energy Corporation Valero Port Arthur Refining Dominik PieniazekDominik Pieniazek Floyd WeisseFloyd Weisse VI E i i LLCVI E i i LLC D hi ll LLCD hi ll LLCVI Engineering, LLC.VI Engineering, LLC. Dashiell, LLC.Dashiell, LLC. 2009 Petroleum and Chemical Industry Committee Technical Conference2009 Petroleum and Chemical Industry Committee Technical Conference Anaheim, CaliforniaAnaheim, California September 14September 14--16, 200916, 2009
  • 2. Today’s PresentationToday’s Presentation Improving Substation Reliability and AvailabilityImproving Substation Reliability and Availability Background Substation Documentation Automation, Data Retrieval, Historian andAutomation, Data Retrieval, Historian and Alarm Annunciation Monitoring and OperationMonitoring and Operation Critical Auxiliaries Reliability, Numbers and Statistics Recommendations Conclusions
  • 4. BackgroundBackground Project OverviewProject Overview Large expansion at an existing refineryLarge expansion at an existing refinery –– Electrical Reliability ImprovementElectrical Reliability Improvement –– Additional onAdditional on--site generationsite generationgg Multiple parties involved:Multiple parties involved: –– Two Owner/OperatorsTwo Owner/OperatorsTwo Owner/OperatorsTwo Owner/Operators –– Three engineering companiesThree engineering companies Two construction companiesTwo construction companies–– Two construction companiesTwo construction companies –– One third party testing companyOne third party testing company One UtilityOne Utility–– One UtilityOne Utility
  • 6. BackgroundBackground Electrical Events After Expansion Nov- 06 South Sub Ground on 13.8KV overhead line. Two new transformers installed with 400A resistor in existing 1000 A ground system. Both transformers ground relays set to trip on Pick Up. Sep- Refinery Balanced load to generation. Trip 80MW generator, refinery imports throughSep 07 Refinery Blackout, Post Hurricane Humberto Balanced load to generation. Trip 80MW generator, refinery imports through 230kV lines L1 & L2. Utility 230kV lines L554 & L591 in service. L554 faults on blown debris, no reclosing. Seconds later L591 faults on lightning strike, no reclosing. Refinery attempted to serve its load plus local community. Generation trips on overload and blacks out. N PP2 Li it d ti t PP2 I t d B il h t it hi fNov- 07 PP2 Limited generation at PP2, Import mode. Boiler house operators switching for maintenance to replace pole in tie line 205 A/B. Over current relay picked up and tripped remaining tie line 402A/B. Training issues as refinery eliminates tie lines and TGs. Mar- PP6 & PP7 GTG 1 out for maintenance. Loss of a transformer along with GTG1, causes 08 g , overload on second transformer. DC batteries and chargers for equipment are in PP5. Lost a single battery charger, batteries discharged, Microprocessor relays lost power, When power restored, microprocessor relay initiated breaker failure tripping first transformer, second transformer tripped on overloadoverload.
  • 7. BackgroundBackground Electrical Events After Expansion (con’t) Jul-08 PP7 Installed temporary battery charger at PS5. Tripped overnight, repowering DC system relays previously causing trips had been disabled, a line differential microprocessor relay initiated an unexplained trip on repowering causing an outage.outage. Jul-08 230kV private L1 Test "blue Button" trips line under a scheduled utility/refinery communication test. Logic at both ends in microprocessor relays did not match causing trip. Mar- 08 SG Sub TR1 & TR2 Microprocessor relay. Set to trip on pick up instead of TOC; M SG S b TR2 t i d i ti d t h i t i t t tMar- 08 SG Sub TR2 tripped on energization due to harmonic restraint not set Apr-08 SG Sub Sync lights stay on all the time due to unproven wiring Jun- 08 69kV Ties Overcurrent set points in microprocessor relays set incorrectly
  • 9. Substation DocumentationSubstation Documentation Requirements Last items considered on new projectsLast items considered on new projects Must specify your requirements beforeMust specify your requirements before awarding project, “Toolawarding project, “Tool--Kit”Kit” WhyWhy –– Downsized staffDownsized staff –– Document control issues with advancing electronicDocument control issues with advancing electronic formatsformats St & t i l d i ti f dSt & t i l d i ti f d–– Storage & retrieval during times of needStorage & retrieval during times of need –– Tracking recall or advisory bulletinsTracking recall or advisory bulletins –– FAT & SATFAT & SAT–– FAT & SATFAT & SAT
  • 10. Substation DocumentationSubstation Documentation Special Provisions Microprocessor relays have replacedMicroprocessor relays have replaced h d i d l l i ith t l i dih d i d l l i ith t l i dihardwired relay logic without logic diagramshardwired relay logic without logic diagrams –– Complex relay schemes difficult to testComplex relay schemes difficult to test D t t ( l tti )D t t ( l tti )–– Data storage (relay settings)Data storage (relay settings) Electrical Operating ProceduresElectrical Operating Procedures FAT/SAT Test records is benchmark dataFAT/SAT Test records is benchmark data BOM and O&M manualsBOM and O&M manuals
  • 11. Automation, Data Retrieval, St Hi t iStorage, Historian, andand Alarm AnnunciationAlarm Annunciation
  • 12. Automation, Data Retrieval, …Alarm Annunciation What…? Utilizing Installed IEDs “Data Mining”, trending, equipment status estimation System Minimum Configurations Integration Best PracticesIntegration Best Practices Use data to “Increase productivity and d t”reduce cost”
  • 13. Automation, Data Retrieval, …Alarm Annunciation Typical IEDs existing within substations Protective relays and meters O li t h d ltOn-line tap changers and voltage regulators Reclosers and digital fault recordersReclosers and digital fault recorders Bushing monitoring devices Circuit breaker monitoring devicesCircuit breaker monitoring devices Dissolved gas in oil monitors Partial discharge monitorsPartial discharge monitors CCTV cameras Phone event messengersPhone event messengers Substation access system
  • 14. Automation, Data Retrieval, …Alarm Annunciation Example of monitoring class III transformer
  • 15. Automation, Data Retrieval, …Alarm Annunciation Mining of Data… Data mining is the process of extracting patterns from data. As more data are available and gathered,g data mining is becoming an increasingly important tool to transform these data intop information. – It is commonly used in a wide range of profilingy g p g practices, such as marketing, surveillance, fraud detection and scientific discovery, – Time for industrial application.
  • 16. Automation, Data Retrieval, …Alarm Annunciation “Data mining”… Can effectively help determine: – required maintenance intervals, – replace interval-maintenance with risk-based maintenance approach, – detect equipment deterioration at early stages, – or estimate other system properties.
  • 17. Automation, Data Retrieval, …Alarm Annunciation “Data mining”… When such data is properly identified, the facility has adequate time to – acquire replacement parts, – schedule required maintenance, – importantly avoid catastrophic failure.
  • 18. Automation, Data Retrieval, …Alarm Annunciation Configuration and best practices Some of the best practices: – Ensure system can integrate devices from various manufacturers – Ensure system supports multiple technologies / protocols – Utilize multifunction IEDs – Choose best IED for assigned function – Make system as flexible as possible
  • 19. Automation, Data Retrieval, …Alarm Annunciation Configuration and best practices Integrated system shall provide: – Increased system functionality – Increased system reliability/availability (limit/eliminate outage time) – Increased system safety – Decrease a cost for automation – Decrease a cost for protection – Adequate tools at the fingertips of the engineer
  • 21. Monitoring and Operation Remote monitoring For not-networked / not-connected apparatus obtaining data about the present state of the apparatus, IED, transformer or IED that monitors this transformer is: expensive, time consuming, could be risky. F “i t lli t” (IED t k d) d tFor “intelligent” (IEDs are networked), data is stored in a database and repository and t i il blremote access is available.
  • 22. Monitoring and Operation First most manifested benefit In not-networked system, to obtain configuration files, SER, or DFR from IEDs, the engineer needed to travel to the site and obtain files from the devices In networked system, the engineer cany g access historical data from a historian, verify what is stored in the IED presently and howp y historical data compares with present data
  • 23. Monitoring and Operation Examples of usage IEDs, CTs, VTs problems detection, System recovery, switching unexpected loads and disturbances, Analysis of changes required to the system for changing operating conditions, F l h i i f d h i– For example: changing consistency of gas and how it will influence starting and loading of the compressor etc., Automatic change of protection parameters, – For example: different seasons, mode of operations tetc., Isolation from utility for special conditions.
  • 24. Monitoring and Operation Remote operation Remote control of: – circuit breakers, – switches, – lockout relays (LOR) and – other apparatus that at present requires anpp p q operator to control it locally, – CCTV cameras, – Access doors and gates.
  • 25. Monitoring and Operation FOREMOST safety benefit Performing switching operation remotely eliminates arc-flash hazard exposure to the operator / electrician by removing him from the danger zone. – Note: safety procedures shall be established first before remote operation is allowed.
  • 27. Critical Auxiliaries Almost always forgotten… Substation aspects considered as auxiliary in nature: – Control Power Supply – Time Synchronization – Enabling SER and DFR recorders
  • 28. Critical Auxiliaries Control and auxiliary power supply Control Power Supply should be: – Maintained – Monitored – Redundant
  • 29. Critical Auxiliaries Control and auxiliary power supply DC CONTROL POWER SUPPLY BLOCK DIAGRAM, NON- REDUNDANT WITH MONITORING AC SOURCE BATTERY CB TEST SOURCE DS1 DS2 MCBFCB DISTRIBUTIONDISTRIBUTION PANEL
  • 30. Critical Auxiliaries Control and auxiliary power supply DC CONTROL POWER SUPPLY BLOCK DIAGRAM, AC CHARGING REDUNDANT, DC BUS NON-REDUNDANT WITH MONITORINGWITH MONITORING
  • 31. Critical Auxiliaries Control and auxiliary power supply DC CONTROL POWER SUPPLY BLOCK DIAGRAM, 2 x 100% REDUNDANT WITH MONITORING
  • 32. Critical Auxiliaries SER and DFR SER and DFR default settings enable only basic functionality at best case – Not utilized to collect operation and fault information – The table in paper / Attachment C lists analog channels and digital element recommended for monitoring and data-collection applications
  • 33. Critical Auxiliaries Time synchronization Cannot depend on internal clock …circuit timing “drifts” with usage time, temperature, environmental instability and other factors Th ti t dd i ifi t i f tiThe time stamp adds significant information Not synchronized information creates havoc Time Synchronization could become a law Some utilities require Time SynchronizationSome utilities require Time Synchronization measurements at the Inter-Tie point
  • 35. Reliability, Numbers,…Hidden Failures What is reliability? Definition of reliabilityDefinition of reliability –– IEEE Std 100 “EE Standard Dictionary…”IEEE Std 100 “EE Standard Dictionary…” The ability to perform a required functionThe ability to perform a required function under statedunder stated ditiditi f t t d i d f tif t t d i d f ticonditionsconditions for a stated period of time…for a stated period of time… –– IEEE “Gold Book” addsIEEE “Gold Book” adds Th tit ti li bilit l ti it li bilitThe quantitative reliability evaluation… permit reliability indexes … to be computed from knowledge of thefrom knowledge of the reliability … of the constituent components of thereliability … of the constituent components of the systemsystem –– IEEE C37.100IEEE C37.100 Reliability: a measure of the degree of certainty that the relay, or relay system, will perform correctlywill perform correctly
  • 36. Reliability, Numbers,…Hidden Failures What is reliability? What are we looking for when we evaluateWhat are we looking for when we evaluate equipment / system reliability performance?equipment / system reliability performance? –– How system should perform,How system should perform, –– Highest reliability vs. CAPEX cost,Highest reliability vs. CAPEX cost, –– Equipment replacement,Equipment replacement, –– Are we considering all parameters?Are we considering all parameters? –– Wide gap between design and operationWide gap between design and operationg p g pg p g p calculationscalculations
  • 37. Reliability, Numbers,…Hidden Failures How calculated? Reliability modeling principles and data we are using do not consider: – Varying parameters environmental parameters – Random, unpredictable “chaotic” disturbances – Large set samples – Other major reliability influences Parameters used in reliability analysis areParameters used in reliability analysis are based on very small sampling set of data
  • 38. Reliability, Numbers,…Hidden Failures Hidden Failure “Hidden failures”“Hidden failures” –– IN PROTECTION SYSTEM / UTILITYIN PROTECTION SYSTEM / UTILITYIN PROTECTION SYSTEM / UTILITYIN PROTECTION SYSTEM / UTILITY APPROACHAPPROACH “a permanent defect that will cause a relay system to“a permanent defect that will cause a relay system top y yp y y incorrectly and inappropriately removeincorrectly and inappropriately remove a circuit elementa circuit element as a direct consequence of another switching event”as a direct consequence of another switching event” IN PROCESS INDUSTY SYSTEMIN PROCESS INDUSTY SYSTEM–– IN PROCESS INDUSTY SYSTEMIN PROCESS INDUSTY SYSTEM “a permanent defect that will cause an EI&C system to“a permanent defect that will cause an EI&C system to incorrectly and inappropriately remove a circuit elementincorrectly and inappropriately remove a circuit elementincorrectly and inappropriately remove a circuit elementincorrectly and inappropriately remove a circuit element as a direct consequence of another usually abnormalas a direct consequence of another usually abnormal event in EI&C system and/or plant process”event in EI&C system and/or plant process”
  • 39. Reliability, Numbers,…Hidden Failures Causes of Hidden Failure Examples Cause examples:Cause examples: – Circuit fault – Shortage of reactive power Random operation of DC power system– Random operation of DC power system – Inadequate testing / commissioning – Operation of E&IC system in “seldom used state”Operation of E&IC system in seldom used state
  • 40. Reliability, Numbers,…Hidden Failures Hidden Failure “Host” Examples Hidden failure “host”Hidden failure “host” examples: – Control schemes from previous projects – Not performing FAT or SAT to minimize cost Removing monitoring equipment– Removing monitoring equipment – Selecting vendor/contractor based on capital cost – Applying firmware without testing – Not updating firmware
  • 41. Reliability, Numbers and Statistics How applies to reliability? RELIABILITY INDICES COMPARISON WITH AND WITHOUT HIDDEN FAILURES CONTINGENCES RELIABILITY INDEX NAME HIDDEN FAILURES NOT HIDDEN FAILURES INCLUDED CASE 1 CASE 2NAME INCLUDED CASE 1 CASE 2 FAILURE PROB 1.1130E-03 1.1880E-03 1.6850E-03 INCREASE 107% 151% FAILURE FREQ [ /YR] 0.4425 0.4586 0.6034 INCREASE 104% 136% FAILURE DURATION [HRS/YEAR] 22.03 22.68 24.68 INCREASE 103% 112% Note: Hidden failure probabilities: Case 1 - 10e-3, Case 2 - 10e-2
  • 42. Reliability, Numbers and Statistics Reliability Data in “Gold Book” is a “generic” Small sample set Sample set collected in minimal certainSample set collected in minimal certain conditions Calculated indicesCalculated indices do not represent realityCalculated indicesCalculated indices do not represent reality… Paper is focusing on improving VAILABILITY f th EI&C t t “ li bilit i di ”of the EI&C system, not “reliability indices”
  • 44. Summary Formulate practices, standards, and data documentation applicable to your organization Include in RFQ requirements special needs that are not included in industry guides,y g specification, practices… Evaluate how the project should beEvaluate how the project should be executed Assure contractual “cooperation” with utilityAssure contractual cooperation with utility for “post mortem” analysis
  • 45. Summary Include provisions in POs allowing for third party to provide testing services without altering contractual responsibilities and obligations Incorporate procedures for updating andp p p g storing advisory bulletins and recall information for all apparatus and IEDspp Apply automation for communication with IEDs and file managementIEDs and file management
  • 46. Summary Implement procedures and software for analysis of the collected data Apply reliable engineering principles for ACpp y g g p p and/or DC control power sources design Test periodically power system alarms andTest periodically power system alarms and monitoring Start collecting power system data applyStart collecting power system data apply time synchronization
  • 48. Conclusions Reliability and availability of the EI&C system in process plants: – Difficult to estimate – Not considers “project” factors – Sensitive to input parameters and environmental conditions – Based on very small sample set of data
  • 49. Conclusions The reliability and availability of EI&C system can be improved by focusing on time-tested: – Good engineering practices, – Appropriate and correct documentation, – Apparatus/equipment testing, commissioning and monitoring, – Applications of available technologies to performed monitoring tasks with minimum human supervision, – Perform tasks routinely to eliminate “hidden failures” in the system.
  • 50. Conclusions Data collected during monitoring of the EI&C system and equipment could – “Foresee” approaching equipment failure, trigger an alarm i.e. safe time and money! – Aid at verifying, adjusting, calibrating power system models for power studies Use data to your advantage!!!Use data to your advantage!!!
  • 51. Do not forget about Test Switches… TEST SWITCH IS YOUR FRIEND !!!TEST SWITCH IS YOUR FRIEND !!!