A Review Paper on Effective Material Management to Minimize
Problem in Building Construction Project
Noor Rahman Stanik zai1, Shalika Mehta2
1M.Tech Scholar, Chandigarh University, Punjab, India
2Academic Coordinator, Chandigarh University, Punjab, India
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - Most of the construction company concern about
the material management it’s planning, controlling delivery,
inventory control management from their design phase to
construction phase. Material has a direct impact on the cost,
quality and time of the project so having materialsattheright
place, right time, right quality and right quantity is essential
for effective execution of building project. The reduction of
wastage during transport of materials, handling of materials,
storage of materials, should be used top management
inventory control technique.
Key Words: Construction Material, Project Management.
Construction site management
1. INTRODUCTION
Management of material for a construction project is very
important as material are the major resource for the
company. The total cost of material for a project is 50% or
more of the total cost. So here we can define material
management the process of providing materials at the right
time for the right place, from the right source, right quality
and right quantity to minimize the cost of project and finish
the project on time. To manage well thematerial areconcern
with Planning, inspection, issue procedure, inventory
control, purchasing, material supply, transportation,
material handling, maintenance and information system are
the main requirements. The material managementshouldbe
consider from the purchasing phase throughout the
construction period. Generally construction materials are
heavy, bulky, critical, expensive, and its stock in a large
amount to construction site there for there is a need for
effective material management to minimize problems for
handling materials. It’s theroleofthematerialsmanagement
is strongly economical for all organization in every time the
organization must ensure all the material islowestfinal cost,
assurance of supply, lowest administrative cost, buying
material with economical cost, operating costwithoptimum
quality and profits can be increased.
2. Components of Material Management
• Purchasing
• Transport & Handling
• Inspection
• Storage
Figure 1. Components of material management
3. Problems of Material Management.
Material management have over a long period many
problems most for the construction organizations. As the
size of project increases the scale of activities concerning
with material management there are numbers of problems
related to material management, the problems may be
associated with planning, storage requirement, lack of
communication, delivery problems, handling problems,lack
of security, etc. some of these problems are describe.
Planning: problems related to planning include
scheduling of time, ordering, measuring it emphasized
that planning is very important for the increase of
productivity, and timely completion of the project.Ifthe
construction materials planning process is not
implemented properlytheproductivityofprojectwill be
hang down.
Delivery problems. Problems in construction material
have negative impact on time completion of
construction project. Many situation are exist in which
material cant arrive on time
Lack of security. Security in the construction industry
is becoming increasingly important. It means that how
we manage risk arising from unauthorized access to,
sharing of Data, systems & information the end result of
poor security could affect project financial margins.
Understanding the lack of security profile and
conducting effective management will help safe and
productive construction environment.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 572
Storage requirement. Intheconstructionindustry,itis
essential that the storage of equipment and materials is
considered for the total of the project. A large numberof
materials required more storage depends on the
magnitude of the project also it is very important to
keep lots of material and equipment which are used on
the construction project. All the material must have
proper space, safety, as well as dry.
Storage requirement. Intheconstructionindustry,itis
essential that the storage of equipment and materials is
considered for the total of the project. A large numberof
materials required more storage depends on the
magnitude of the project also it is very important to
keep lots of material and equipment which are used on
the construction project. All the material must have
proper space, safety, as well as dry.
4. Literature review:
(Madhavi, Mathew et al. 2013)havefocusedontheproblems
which is comes to place in construction industries. In this
investigation authors have found that improper material
management construction conducted that construction
project cost is depend on material, machine, manpower,
subcontractor, overhead cost and general condition may
affect project cost if the material is not managed well it will
create cost variance. Project costcanbecontrolledaccording
to schedule of project.[1]
(Hadi, Vencheh, 2010) the paper showthe extendversionof
Ng-Mode for multiple criteria of inventory control ABC
analysis they provide an example which is compared the
ABC model with Ng model.[2]
(Soni, Harsh et al. 2016) most of the organization are using
now a days the inventory control techniques after using the
always better control analysis it will reduced 20% cost of
materials in total cost. The major factors for the material
management is poor management of time, cost and poor
inventory control which delay the project.[3]
(Mohopadkar, patil 2017) inventory control in the
construction industry is one of the most important factors
there for the organization have to know about proper
material management techniques for the success of the
project with the given time. Paper is on the importance and
technique of inventory management it shows that the
materials entire expenditure of constructionprojectisabout
to 60% to 70% so its possible to reduce the overall cost of
the project.[4]
(Rajgor, Pitroda 2017) materials are in construction phase
one of the important phase especially in residential and
industrial construction material are the main factor for the
completion of the project it describe the importance of
material management in construction industry and those
function for the successful completion of a project.
Importance of material management (1) lack of
communication (2) reduce lead cost (3) utilization of
resources (4) supply of material (5) product control[5]
(Indrasan, Rajput et al. 2018) in this paper for an inventory
control management the existingsituationwasanalyzedand
twofold improvement is proposed by using ABC and EOQ
analysis for better inventory management to decrease the
organization inventory level and cost overruns by avoiding
overstocks and use the technical way.[6]
(Jadhav, Magadum, et, al. 2018) it was a case study for the
Indian residential construction project to find out the most
significant factors causing delays the collection data was
through questionnaire survey the participants was
consultants, contractors, and owners thefactorwasbyusing
RII method and recommended to avoid delays in
construction projects.[7]
(Mishra, et al. 2018) themethodologyforthisinvestigationis
Innovation Action Research (IAR) for two important
question 1. How to find and convey material information for
scheduling of project? 2. How to prepare material with
nearest term scheduling? The paper have proposea solution
for the material from their design phase to construction
phase in construction project.[8]
(Aku okarocha, 2013) the author has analysis those factors
which effect the material management in building
construction project. Primary and secondary data was
collected the statistical analysis was used thought the use of
multiple regression show it’s veryimportantforthe effective
material management in building construction project. To
manage well material give as cost control, on time execution
of project, failure of project[9]
(Kulkarni-et al-(2017) the researcher has found the factors
which effecting material management in building
construction project furthermore has carried the voids
created by the improper material in a construction
project.[10]
(Karoriya, Pandey 2018) every construction project
management is maintaining to manage and minimize
wastage of construction materials for the successful
completion of constructionprojectswithina giventime,cost,
with design quality and handling of materials, requires
systematic planning and controlling the researcher have
used inventory control technique for the cost overruns in
construction projects.[11]
(kumar, lilhare et, al. 2016) all organizationshavetobalance
the critical stock outs and minimize the inventory costs the
investigator have used ABC analysis inventory control
technique and find to help managers during management of
inventory items it help to understand of problems occurs in
inventory and safety stock.[12]
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 573
5. Conclusion & Recommendations:
Studying effective material management in a construction
project to minimize problems with applying inventory
control technique maintain material managementprocesses
from the design stage to construction stage and efficiency of
project completion on time, qualityandunderbudget.Thisis
because the poor construction material management can
effects the overall performance of project in the terms of
time, cost & quality. One of the issue that may happen with
every construction project that is the wastage of material
management if it not manage well and minimizing wastage
of construction materials at construction project.
For the successful execution of a project it is important that
top management must pay more attention forall activitiesof
a construction project.
On time of completion of project it’s important that
top management should pay moreattentiontoward
material management in construction project.
Use of software such us MS project, Primavera etc.
to avoid errors in material management.
Inventory control technique ABC analysisshouldbe
used to find out the total annual usage value in
percentage.
All organization should maintain the balance
between critical stock outs and minimizing
inventory costs.
Construction material management plays a keyrole
in making the project successful.
A successful project s that to finish on a specific
time, cost and quality.
Its need of material management system to save
time and cost.
ACKNOWLEDGEMENT
I am student of M.E CTM Construction Technology
Management of Chandigarh University. A review paper on
Effective Material Management to Minimize Problems in
Building Construction Project Is Based by my Own Work
Carried out Review of My StudyandundertheSupervisionof
Shalika Mehta Assistant Professor at Chandigarh University.
REFERENCES
[1] koti, “Ijret_110213075,” IJRET Int. J. Res. Eng.
Technol., pp. 2319–1163, 2013.
[2] A. Hadi-Vencheh, “An improvement to multiple
criteria ABC inventory classification,” Eur. J. Oper.
Res., vol. 201, no. 3, pp. 962–965, 2010, doi:
10.1016/j.ejor.2009.04.013.
[3] H. Soni, J. Pitroda, and J. J. Bhavshar, “Analyzing
Inventory Material Management Control Technique
on Residential Construction,” Int. Conf. “Engineering
Issues, Oppor. Challenges Dev., no. May, pp. 41–53,
2016.
[4] J. Sanjeev Mohopadkar, “International Journal on
Recent and Innovation Trends in Computing and
Communication Application of Inventory
Management in Construction Industry,” Int.J.Recent
Innov. TrendsComput.Commun.,pp.229–231,2017.
[5] M. B. Rajgor and J. Pitroda, “A Review on Material
Management : Valuable Approach in Construction
Industry,” vol. 3, no. 1, pp. 1–4, 2017.
[6] R. Chidamabaram and S. Suresh, “Importance of
Material ManagementinConstructionIndustry,”Adv.
Proj. real estate Manag., vol. 1, pp. 1–19, 2017.
[7] D. S. Jadhav, “Delay Analysis inConstructionProject,”
Int. J. Res. Appl. Sci. Eng. Technol., vol. 6, no. 3, pp.
2244–2247, 2018, doi: 10.22214/ijraset.2018.3355.
[8] P. Mishra, P. Mishra, and R. Purohit, “Material
delivery problems in construction projects: A
possible solution,” Mater. Today Proc., vol. 5, no. 2,
pp. 6497–6501, 2018, doi:
10.1016/j.matpr.2018.01.135.
[9] K. Othman, “International Journal of Management
Sciences and Business Research, 2013 ISSN (2226-
8235) Vol-2, Issue 12,” Int. J. Manag. Sci. Bus. Res.,
vol. 2, no. 12, pp. 138–142, 2013.
[10] V. Kulkarni, R. Sharma, M. Hote, and M. E. Civil,
“Factors affecting material management on
construction site,” Int. Res. J. Eng. Technol., vol. 4, no.
1, pp. 474–478, 2017.
[11] D. Karoriya and M. Pandey, “Efficient Techniques of
Construction Material Management in Construction
Projects,” pp. 3–6, 2018.
[12] A. Sahu, “ABC Analysis for Inventory Management-
Case Study of Sponge Iron Plant,” vol. 4, no. Iii, pp.
32–36, 2016.
BIOGRAPHIES
My name is Noor Rahman Stanikzai
student of M-Tech Research Scholarin
Civil Engineering From Chandigarh
University Punjab, India. Having Two
Years’ Experience in Construction
Industry.
Name. Shalika Mehta
Designation. Academic Coordinator at
Chandigarh University Mohali Punjab
India.

More Related Content

PDF
Assesing the various problems facing in arranging appropirate labour and qual...
PDF
IRJET-Improving Effective Material Management by Identifying Common Factors i...
PDF
IRJET- Efficient Techniques of Construction Material Management in Constr...
PDF
IRJET- An Assessment of Role of Material Management in Construction Projects
PDF
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
PDF
Material Management Practices of “Foundation Silver Spring” Residential Build...
PDF
Management for Construction Materials and Control of Construction Waste in Co...
PDF
A Computerized System for Managing Con-struction Materials for Gaza Strip Bui...
Assesing the various problems facing in arranging appropirate labour and qual...
IRJET-Improving Effective Material Management by Identifying Common Factors i...
IRJET- Efficient Techniques of Construction Material Management in Constr...
IRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
Material Management Practices of “Foundation Silver Spring” Residential Build...
Management for Construction Materials and Control of Construction Waste in Co...
A Computerized System for Managing Con-struction Materials for Gaza Strip Bui...

What's hot (20)

PDF
An assessment of material management on building construction sites
PDF
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
PDF
IRJET- Assessment of Role of Material Management in Construction Projects
PDF
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
PDF
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
PDF
The Impact of Materials Management on Profitability of Manufacturing Companie...
PDF
IRJET- Study on Economic Sustainability of Industrial Buildings
PDF
IRJET- Efficient Techniques of Construction Material Management in Constr...
PDF
IRJET- Daily Updates on Construction Sites Progress
PDF
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
PDF
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
PDF
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
PPTX
Lean construction
PDF
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
PDF
IRJET-A Review of Impact on Labour Management in Construction Industry
PDF
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
PDF
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
PDF
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
PDF
IRJET - Optimum Utilization of Construction Resources: A Review
PDF
IRJET- Review on Study of Quality Practices in Construction
An assessment of material management on building construction sites
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
The Impact of Materials Management on Profitability of Manufacturing Companie...
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET- Efficient Techniques of Construction Material Management in Constr...
IRJET- Daily Updates on Construction Sites Progress
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
Lean construction
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET - Optimum Utilization of Construction Resources: A Review
IRJET- Review on Study of Quality Practices in Construction
Ad

Similar to IRJET - A Review Paper on Effective Material Management to Minimize Problem in Building Construction Project (20)

PDF
Factors Affecting Material Management on Construction Site
PDF
Review of Inventory Management System to Ensure the Optimization of Resources
PDF
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRY
PDF
Application of ABC Analysis for Material Management of a Residential Building
PPTX
site planing and abc analysis of residential building of material management
PDF
IRJET-Influence of Material Management on Construction Project
PDF
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
PDF
B1304021217
PDF
Material management in construction – a case study
PDF
Material management in construction – a case study
PDF
Material management in construction – a case study
PPTX
Construction Material Management
PPTX
constraction material constraction material management .pptx4.pptx
PDF
Constructionmaterialmanagement 140920032237-phpapp01
PPT
Lecture notes Cons 3Mat Magt edited 2016 ed (2).ppt
PPTX
Material management in construction jeemi
PDF
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
DOCX
Inventory management
DOCX
Inventory management
PDF
Optimization in Supply Logistics Cost of Construction Projects of a Company
Factors Affecting Material Management on Construction Site
Review of Inventory Management System to Ensure the Optimization of Resources
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRY
Application of ABC Analysis for Material Management of a Residential Building
site planing and abc analysis of residential building of material management
IRJET-Influence of Material Management on Construction Project
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
B1304021217
Material management in construction – a case study
Material management in construction – a case study
Material management in construction – a case study
Construction Material Management
constraction material constraction material management .pptx4.pptx
Constructionmaterialmanagement 140920032237-phpapp01
Lecture notes Cons 3Mat Magt edited 2016 ed (2).ppt
Material management in construction jeemi
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
Inventory management
Inventory management
Optimization in Supply Logistics Cost of Construction Projects of a Company
Ad

More from IRJET Journal (20)

PDF
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
PDF
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
PDF
Kiona – A Smart Society Automation Project
PDF
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
PDF
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
PDF
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
PDF
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
PDF
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
PDF
BRAIN TUMOUR DETECTION AND CLASSIFICATION
PDF
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
PDF
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
PDF
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
PDF
Breast Cancer Detection using Computer Vision
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
Kiona – A Smart Society Automation Project
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
BRAIN TUMOUR DETECTION AND CLASSIFICATION
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
Breast Cancer Detection using Computer Vision
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...

Recently uploaded (20)

PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
Geodesy 1.pptx...............................................
PPTX
Current and future trends in Computer Vision.pptx
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
Well-logging-methods_new................
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
Construction Project Organization Group 2.pptx
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
Sustainable Sites - Green Building Construction
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
Artificial Intelligence
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PDF
737-MAX_SRG.pdf student reference guides
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Geodesy 1.pptx...............................................
Current and future trends in Computer Vision.pptx
III.4.1.2_The_Space_Environment.p pdffdf
Foundation to blockchain - A guide to Blockchain Tech
Well-logging-methods_new................
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Construction Project Organization Group 2.pptx
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Sustainable Sites - Green Building Construction
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Mechanical Engineering MATERIALS Selection
Internet of Things (IOT) - A guide to understanding
Artificial Intelligence
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
737-MAX_SRG.pdf student reference guides
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
CYBER-CRIMES AND SECURITY A guide to understanding

IRJET - A Review Paper on Effective Material Management to Minimize Problem in Building Construction Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 571 A Review Paper on Effective Material Management to Minimize Problem in Building Construction Project Noor Rahman Stanik zai1, Shalika Mehta2 1M.Tech Scholar, Chandigarh University, Punjab, India 2Academic Coordinator, Chandigarh University, Punjab, India ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - Most of the construction company concern about the material management it’s planning, controlling delivery, inventory control management from their design phase to construction phase. Material has a direct impact on the cost, quality and time of the project so having materialsattheright place, right time, right quality and right quantity is essential for effective execution of building project. The reduction of wastage during transport of materials, handling of materials, storage of materials, should be used top management inventory control technique. Key Words: Construction Material, Project Management. Construction site management 1. INTRODUCTION Management of material for a construction project is very important as material are the major resource for the company. The total cost of material for a project is 50% or more of the total cost. So here we can define material management the process of providing materials at the right time for the right place, from the right source, right quality and right quantity to minimize the cost of project and finish the project on time. To manage well thematerial areconcern with Planning, inspection, issue procedure, inventory control, purchasing, material supply, transportation, material handling, maintenance and information system are the main requirements. The material managementshouldbe consider from the purchasing phase throughout the construction period. Generally construction materials are heavy, bulky, critical, expensive, and its stock in a large amount to construction site there for there is a need for effective material management to minimize problems for handling materials. It’s theroleofthematerialsmanagement is strongly economical for all organization in every time the organization must ensure all the material islowestfinal cost, assurance of supply, lowest administrative cost, buying material with economical cost, operating costwithoptimum quality and profits can be increased. 2. Components of Material Management • Purchasing • Transport & Handling • Inspection • Storage Figure 1. Components of material management 3. Problems of Material Management. Material management have over a long period many problems most for the construction organizations. As the size of project increases the scale of activities concerning with material management there are numbers of problems related to material management, the problems may be associated with planning, storage requirement, lack of communication, delivery problems, handling problems,lack of security, etc. some of these problems are describe. Planning: problems related to planning include scheduling of time, ordering, measuring it emphasized that planning is very important for the increase of productivity, and timely completion of the project.Ifthe construction materials planning process is not implemented properlytheproductivityofprojectwill be hang down. Delivery problems. Problems in construction material have negative impact on time completion of construction project. Many situation are exist in which material cant arrive on time Lack of security. Security in the construction industry is becoming increasingly important. It means that how we manage risk arising from unauthorized access to, sharing of Data, systems & information the end result of poor security could affect project financial margins. Understanding the lack of security profile and conducting effective management will help safe and productive construction environment.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 572 Storage requirement. Intheconstructionindustry,itis essential that the storage of equipment and materials is considered for the total of the project. A large numberof materials required more storage depends on the magnitude of the project also it is very important to keep lots of material and equipment which are used on the construction project. All the material must have proper space, safety, as well as dry. Storage requirement. Intheconstructionindustry,itis essential that the storage of equipment and materials is considered for the total of the project. A large numberof materials required more storage depends on the magnitude of the project also it is very important to keep lots of material and equipment which are used on the construction project. All the material must have proper space, safety, as well as dry. 4. Literature review: (Madhavi, Mathew et al. 2013)havefocusedontheproblems which is comes to place in construction industries. In this investigation authors have found that improper material management construction conducted that construction project cost is depend on material, machine, manpower, subcontractor, overhead cost and general condition may affect project cost if the material is not managed well it will create cost variance. Project costcanbecontrolledaccording to schedule of project.[1] (Hadi, Vencheh, 2010) the paper showthe extendversionof Ng-Mode for multiple criteria of inventory control ABC analysis they provide an example which is compared the ABC model with Ng model.[2] (Soni, Harsh et al. 2016) most of the organization are using now a days the inventory control techniques after using the always better control analysis it will reduced 20% cost of materials in total cost. The major factors for the material management is poor management of time, cost and poor inventory control which delay the project.[3] (Mohopadkar, patil 2017) inventory control in the construction industry is one of the most important factors there for the organization have to know about proper material management techniques for the success of the project with the given time. Paper is on the importance and technique of inventory management it shows that the materials entire expenditure of constructionprojectisabout to 60% to 70% so its possible to reduce the overall cost of the project.[4] (Rajgor, Pitroda 2017) materials are in construction phase one of the important phase especially in residential and industrial construction material are the main factor for the completion of the project it describe the importance of material management in construction industry and those function for the successful completion of a project. Importance of material management (1) lack of communication (2) reduce lead cost (3) utilization of resources (4) supply of material (5) product control[5] (Indrasan, Rajput et al. 2018) in this paper for an inventory control management the existingsituationwasanalyzedand twofold improvement is proposed by using ABC and EOQ analysis for better inventory management to decrease the organization inventory level and cost overruns by avoiding overstocks and use the technical way.[6] (Jadhav, Magadum, et, al. 2018) it was a case study for the Indian residential construction project to find out the most significant factors causing delays the collection data was through questionnaire survey the participants was consultants, contractors, and owners thefactorwasbyusing RII method and recommended to avoid delays in construction projects.[7] (Mishra, et al. 2018) themethodologyforthisinvestigationis Innovation Action Research (IAR) for two important question 1. How to find and convey material information for scheduling of project? 2. How to prepare material with nearest term scheduling? The paper have proposea solution for the material from their design phase to construction phase in construction project.[8] (Aku okarocha, 2013) the author has analysis those factors which effect the material management in building construction project. Primary and secondary data was collected the statistical analysis was used thought the use of multiple regression show it’s veryimportantforthe effective material management in building construction project. To manage well material give as cost control, on time execution of project, failure of project[9] (Kulkarni-et al-(2017) the researcher has found the factors which effecting material management in building construction project furthermore has carried the voids created by the improper material in a construction project.[10] (Karoriya, Pandey 2018) every construction project management is maintaining to manage and minimize wastage of construction materials for the successful completion of constructionprojectswithina giventime,cost, with design quality and handling of materials, requires systematic planning and controlling the researcher have used inventory control technique for the cost overruns in construction projects.[11] (kumar, lilhare et, al. 2016) all organizationshavetobalance the critical stock outs and minimize the inventory costs the investigator have used ABC analysis inventory control technique and find to help managers during management of inventory items it help to understand of problems occurs in inventory and safety stock.[12]
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 573 5. Conclusion & Recommendations: Studying effective material management in a construction project to minimize problems with applying inventory control technique maintain material managementprocesses from the design stage to construction stage and efficiency of project completion on time, qualityandunderbudget.Thisis because the poor construction material management can effects the overall performance of project in the terms of time, cost & quality. One of the issue that may happen with every construction project that is the wastage of material management if it not manage well and minimizing wastage of construction materials at construction project. For the successful execution of a project it is important that top management must pay more attention forall activitiesof a construction project. On time of completion of project it’s important that top management should pay moreattentiontoward material management in construction project. Use of software such us MS project, Primavera etc. to avoid errors in material management. Inventory control technique ABC analysisshouldbe used to find out the total annual usage value in percentage. All organization should maintain the balance between critical stock outs and minimizing inventory costs. Construction material management plays a keyrole in making the project successful. A successful project s that to finish on a specific time, cost and quality. Its need of material management system to save time and cost. ACKNOWLEDGEMENT I am student of M.E CTM Construction Technology Management of Chandigarh University. A review paper on Effective Material Management to Minimize Problems in Building Construction Project Is Based by my Own Work Carried out Review of My StudyandundertheSupervisionof Shalika Mehta Assistant Professor at Chandigarh University. REFERENCES [1] koti, “Ijret_110213075,” IJRET Int. J. Res. Eng. Technol., pp. 2319–1163, 2013. [2] A. Hadi-Vencheh, “An improvement to multiple criteria ABC inventory classification,” Eur. J. Oper. Res., vol. 201, no. 3, pp. 962–965, 2010, doi: 10.1016/j.ejor.2009.04.013. [3] H. Soni, J. Pitroda, and J. J. Bhavshar, “Analyzing Inventory Material Management Control Technique on Residential Construction,” Int. Conf. “Engineering Issues, Oppor. Challenges Dev., no. May, pp. 41–53, 2016. [4] J. Sanjeev Mohopadkar, “International Journal on Recent and Innovation Trends in Computing and Communication Application of Inventory Management in Construction Industry,” Int.J.Recent Innov. TrendsComput.Commun.,pp.229–231,2017. [5] M. B. Rajgor and J. Pitroda, “A Review on Material Management : Valuable Approach in Construction Industry,” vol. 3, no. 1, pp. 1–4, 2017. [6] R. Chidamabaram and S. Suresh, “Importance of Material ManagementinConstructionIndustry,”Adv. Proj. real estate Manag., vol. 1, pp. 1–19, 2017. [7] D. S. Jadhav, “Delay Analysis inConstructionProject,” Int. J. Res. Appl. Sci. Eng. Technol., vol. 6, no. 3, pp. 2244–2247, 2018, doi: 10.22214/ijraset.2018.3355. [8] P. Mishra, P. Mishra, and R. Purohit, “Material delivery problems in construction projects: A possible solution,” Mater. Today Proc., vol. 5, no. 2, pp. 6497–6501, 2018, doi: 10.1016/j.matpr.2018.01.135. [9] K. Othman, “International Journal of Management Sciences and Business Research, 2013 ISSN (2226- 8235) Vol-2, Issue 12,” Int. J. Manag. Sci. Bus. Res., vol. 2, no. 12, pp. 138–142, 2013. [10] V. Kulkarni, R. Sharma, M. Hote, and M. E. Civil, “Factors affecting material management on construction site,” Int. Res. J. Eng. Technol., vol. 4, no. 1, pp. 474–478, 2017. [11] D. Karoriya and M. Pandey, “Efficient Techniques of Construction Material Management in Construction Projects,” pp. 3–6, 2018. [12] A. Sahu, “ABC Analysis for Inventory Management- Case Study of Sponge Iron Plant,” vol. 4, no. Iii, pp. 32–36, 2016. BIOGRAPHIES My name is Noor Rahman Stanikzai student of M-Tech Research Scholarin Civil Engineering From Chandigarh University Punjab, India. Having Two Years’ Experience in Construction Industry. Name. Shalika Mehta Designation. Academic Coordinator at Chandigarh University Mohali Punjab India.