Improving Effective Material Management by Identifying common
Factors in Building Construction Project
Yohannes Tedla1, Dixit Patel2
1Student,M. tech (construction project management), Parul University, Vadodara, Gujarat, India
2Professor, civil engineering, Parul University, Vadodara, Gujarat, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Management in materials has great problems for
many years to most firms in construction project. This paper
work is based on improving current material management
through identifying common factors for buildingconstruction.
Having the accurate materials and time is an essential aspect
for the accomplishment of construction project. Thisstudyhas
revealed that construction materials may constitute more
than 55% of overall cost for a distinctive construction project.
One of the main difficulties in delaying construction projectsis
improper materials and equipment management.Inthisstudy
factors affecting effective materialmanagementandInventory
management were listed in accordancewiththemostaffecting
factors based on literature review. In this paper Relative
important (RII) methods were used for data analysis.
Therefore the proper management of this single largest
element can improve the output and price efficiency of a
project and help ensure its timely completion.
Key Words: Construction Material, Inventory control,
Management, Project management, Relative important
index (RII) method
1. INTRODUCTION
Material management is a task that pointedly contributes to
the achievement of a project. Asprojectsdevelopinscaleand
difficulty, material management is required really to use
them. It remains the process that organizes planning,
purchasing, transporting, receiving and inspection, storing,
handling and monitoring of materials, reducingthewearand
tear and optimizing the productivity by minimizing cost of
materials. The objective of material controlling is to
safeguard that materials remain existing at their point of
usage when needed and accurate quantity and quality of
materials are appropriate selected, purchased,deliveredand
handled. Indeed material management will cause a huge
effect. On the whole project cost, time and quality. Material
management should be measured in constructionprojectsas
an energetic management to achieve superior productivity
and profit, which should be interpreted into cost discount
and successful completion with best quality. It is surely that
material management performs increase capability in
operations and reducesoverall costs. AccordingtoProfessor
Raju Narwade (2016) Cost remains an essentialconstraintof
every project. On the other hand when material availability
at site is delayed it will affect scheduling of activities.
Material must stay available trendy hand at right time for
effective completion of project.
1.1 Factors Associated With Material Management
There are many factors described in the area of material
management and each of these influencescan make to latent
problems. Zakeri et al (1996) recommendedthatfactorssuch
as: transport difficulties, waste, inappropriate handling on
site, lack of suitable work plan, misuse of the specifications,
inappropriate material transportation and extreme
paperwork totally adversely effectonmaterialmanagement.
Common factors mostly disturb material management are
enumerated as follow.
1.2 Problems arising lack of specialcareinmaterial
management.
 Receiving incorrect material type
 Increase materials quantity in storage
 Burglary, theft and vandalism
 Destroy material in shipping
 High cost in material transportation
 Unavailable required quantity
 Too early receiving of materials earlier usage
 Incorrect material take-off fromdrawinganddesign
 Material Shortage during construction
 Piling of inventory materials
 Poor material selection
 Project delay because of slow delivery materials
 Suddenly alternation price of materials
 Ineffective control of storage
1.3. Factors increase waste in constructionprojects
 Incomplete drawing design and specification
 Poor cutting of materials (glass, tiles, plywood)
 Inefficient utilization of temporary materials
(hoarding, formwork, scaffold)
 Poor security on site (theft and vandalism)
 Lack of care in transportation
 Inadequate skill in utilization of materials
 Insufficient places for material storing
 Wrong methods and regulations in materials usage
 Poor materials storage facility
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 147
 Lack of supervision and proper control during
storage
 Wrong material utilization
OBJECTIVES OF MATERIAL MANAGEMENT
 Efficient and effective materials planning
 Buying or Purchasing
 Obtaining or Procuring
 Receiving
 Inventory control
 Supply and delivery of materials
Components of material management:
 Material planning, forecasting and budgeting
 Scheduling, purchasing and procurement
 Receiving &inspection.
 Inventory control and storage
 Material management then delivery
Fig.1: Process of Material Management
Functions of material management
To accomplish the objectives of material management as
stated above to encounter the basic objectives and areas, the
functions performed in material management are classified
as primary and secondary functions.
I. Primary Functions
Tomeet the objectivesofthe studyin construction materials,
the primary functions are noted as follows.
 Materials Supplies Planning
 Acquiring or Purchasing
 Storage Planning and Control
 Find out and Maintaining the MovementandSource
of Materials
II. Secondary Functions
 Regulation and Simplification
 purchase and Acquisition Decisions
 Coding and Grouping of Materials
 Estimating and Planning
PROJECT MANAGEMENT
Different trainingmeetingsshould be settled on site to notify
the workers concerning the newest techniques.
Manufacturing machinery has to be well-run regularly to
avoid any break down. Labors and contractors ought to be
guided for correct training to accomplish a specific task.
According to Berliner B. “project controlling is mostly based
on effective budgetary management and performance
measures.
PLANNING
Themost frequently used basis forplanningthingsoutforthe
project is the BOQ prepared by the client. Most companies
have two mainlevelsinplanning-micro andmacrolevel.The
planning would be reviewed regularly as possible whether
the work is continued as per planned or not
INVENTORY CONTROL
Sundersan M. defines inventory as the sum of the worth of
raw materials, petroleum and lubricants, replacement parts,
maintenance usable at any specific point of time. Kasim.et.al
(2012) analyzed an improving on site material tracking for
store management in construction. It is essential to manage
all materials and records throughout construction activities.
Failure in site inventory management will consequence in
cost overrun, and interruptions in project closing time
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 148
2. Problems identified in material management
Table -1: Phase 1- Materials Identification
Problem Description
Undefined scope
No right explanation of
whatever is wanted
Lack of communication Lack of communication
between parties involved
Incomplete drawings Plans are not finished and
details are missing
Lack of certification to What is required by the
requirements purchaser is not what is
prepared
Nonstandard
specifications Use of descriptions that are
not commonly used
Incomplete / ineffective Issues not determined during
meetings meetings
Phase 2- Vendor Selection criteria
Problem Description
Uncontrollable bid list
Have too numerous
suppliers
and too little evidence
Incomplete proposals
Suppliers do not contain
all
documents required
Phase 3: identification of Procurement Problem
Problem Description
Matching price to Price discount to match
competitor’s price competitor’s price
Late deliveries/delay of
material on construction
site
Resources are not transported
as
per schedule
Poor communication Lack of communication
between parties
Unrealistic delivery dates Delivery dates difficult to
meet
Phase 4: Construction Phase
Problems Description
Delivery wrong materials There are variances in
material
ordered and delivered
Incorrect sizes delivered
Incorrect quantities
delivered
Keeping track of
material
Don’t know where materials
are at specific time
Rehandling of material
Storage of material
Loss of material
Damage
No supplier QA No quality declaration from
supplier
Poor communication
Receiving, handling and
storage of unused
materials
LITERATURE REVIEW
There are various factors which facilitate poor material
controlling in construction engineering. Zakeri et al. (1996)
find out those factorswhich cause transportation problems,
wastage, inappropriate handling on site, wrong use of the
specifications, and absence of appropriate work plan,
unsuitable material transport and too much paperwork all
badly effect on material management. [2]
Improper materials management can consequence in
increased costs throughout construction project. Efficient
and effective management of materials can result in
considerable savings in project costs. Materials may
deteriorate in store or get stolen if special attention is not
taken. Delays and additional costs may be sustained if
materials required for particular works are not available.
(Hemishkumar Patel, Dr. Jayeshkumar Pitroda). [3]
According to Pande and Sabihuddin (2017) Material
management method is a critical element oftheconstruction
business. A properly executed materials management plan
can accomplish the timely movement of materials to the
jobsite, and consequently to simplify improved work
appearance planning, improved labour productivity, better
schedule. [4]
According to Dr. Kevin .A explained that factors disturbing
material management for the selected case study of building
sites and practice of right material in the right place at the
right time is necessary for effective implementation of a
building project. The research concluded that Material
management indications to effective cost control,toincrease
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 149
the quality and time execution of their projects and reduces
failure of a project. [5]
Productive and well-organized material management
trainings are important in construction industry. The study
indicates that construction materials constitute about 70%
of the entire cost for a typical construction project. Proper
management ethics and practices are required for this
component which will improvise the efficiency and cost
effectiveness of the project and thus helping on time
completion of the project. (Khyomesh V. et. 2011) [6]
Poor documentation of material, in appropriate and
insufficient storage cause damages in labor output and
overall delays that can incidentally increase total task cost.
(Ashwini R. Patil, et.al 2013) [7]
Materials management methods require a renovation to
improve the totally in management of materials for more
efficiency and effectiveness on the construction site. This is
since poor handling of construction materials disturbs the
overall performance of construction projects.(A.A.Gulghane
2015) [8]
According to Ms. Priyadarshani .et.al (2017) most of
constricting companies are reflected the main problems in
using computer in material management are lack of user-
friendly computer program and no understanding for
importance of computer program. [9]
According to Harsh Soni, Dr. Jayeshkumar Pitroda, and
Prof.J.J.Bhavshar (2016) selective inventory control method
to maintain adequate stock of raw material during the time
of short supply, to protect inventory against decline and
control asset in recordsand to keep it at an optimumlevelby
using an inventory control techniques. [10]
According to Abhilin G B, (2017) applying enough stock of
raw materials in period of short supply, to protect inventory
against deterioration and control investment in inventories
and to keep it in an optimum level by using an inventory
control techniques. [11]
RESEARCH METHODOLOGY
The research methods which used for data analysis
regarding factors disturbing material management were
called Relative Important Index (RII). Relative Importance
Index were used to determine the relative importance of
many factors affecting construction materialmanagementin
construction firms and used for ranking delays in many
construction industries. The five-point scale (Likert scale)
ranged from one (very little degree affect) to five (very high
degree affect) is adopted and transformed to relative
importance indices for each factor as follows:
Where, W = is the weighting given to each factor by the
respondents (ranging from 1 to 5),
A =is the highest weight (i.e. 5 in this case), and
N= is the total number of respondents.
3. CONCLUSIONS
This research has studied the current material
management in local building construction projects. This
paperdefinesmaterialmanagementasmeasuresforeffective
material management, factors commonly affecting material
managementin building construction projects andproblems
related with material management. Generally, we will
recommend that to improve effective material management
in building construction sites.
 There should be anintegratedmaterialmanagement
group co-ordination among the site and the
organization.
 Proper control, monitoring and tracking of the
system is required.
 Attentiveness and liability should be generated
inside the organization
 There is a necessityof an efficientMIS integratingall
aspects of material management.
 Firms employing suitable material management
mandate to increase their overall efficiency
Content comes here Conclusion content comes here .
Conclusion content comes here
REFERENCES
[1] Professor, RajuNarwade andSayali Shet”,“An Empirical
Case Study Of Material Management In Construction Of
Industrial Building By Using Various Techniques
“International Journal of Civil Engineering and
Technology (IJCIET) Volume 7, Issue 5, September-
October 2016, pp. 393–400.
[2] Nann Lwin Phu, and Aye Mya Cho, “Factors Affecting
Material Management in BuildingConstructionProjects”,
Internal Journal of scientificEngineeringandTechnology
Research, Vol.03,Issue.10, May-2014, Pages:2133-2137.
[3] Hemishkumar Patel, Dr. Jayeshkumar Pitroda, Prof. J. J.
Bhavsar, “Analysis of Factor Affecting Material
Management and Inventory Management: Survey of
ConstructionFirmsin Gujarat Region of India”Volume1,
Issue 10 May2015
[4] Professor, Aditya A. Pande and S .Sabihuddin”, “Study of
Material Management Techniques on Construction
Project “, Volume 2, Issue 9, May 2015
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 150
[5] DR. Kevin Aku Okorocha, Ph.D., RSV, “Factors Affecting
Effective Materials Management In Building
Construction Projects- A Case Study OfSelectedBuilding
Sites, In Imo State, Nigeria”, International Journal of
Management Sciencesand BusinessResearch Volume2,
Issue 4- ISSN (2226-8235)
[6] Khyomesh V. Patel,” Construction Materials
Management On Project Sites” National Conference on
Recent Trends in Engineering & Technology, 13-14 May
2011
[7] Ashwini R. Patil, Smita V. Pataskar’’, Analyzing Material
Management Techniques on Construction Project,
International Journal of Engineering and Innovative
Technology (IJEIT) Volume 3, Issue 4, October 2013
[8] A. A. Gulghane and Prof P. V. Khandve, Management for
Construction Materials and Control of Construction
Waste in Construction Industry: A Review, Int. Journalof
Engineering Research and Applications Vol. 5, Issue 4, (
Part -1) April 2015, pp.59-64.
[9] Ms. Priyadarshani N. Mane , Dr. A. K. Gupta & Prof. D. B.
Desai, A Review Paper on Onsite Material Management
for Construction Projects , Imperial Journal of
Interdisciplinary Research (IJIR) Vol-3, Issue-2, 2017.
[10] Harsh Soni, Dr. Jayeshkumar Pitroda, Prof. J.J.Bhavshar”,
“Analyzing Inventory Material Management Control
Technique On Residential Construction Project”, Vol-2
Issue-3 2016 IJARIIE-ISSN (O)-2395-4396
[11] AbhilinGB, and Vishak MS”,“Effective MaterialLogistics
in Construction Industries” International Journal of
Science and Research (IJSR) Volume 6 Issue 3, March
2017

More Related Content

PDF
IRJET - A Review Paper on Effective Material Management to Minimize Probl...
PDF
An assessment of material management on building construction sites
PDF
IRJET- An Assessment of Role of Material Management in Construction Projects
PDF
Application of ABC Analysis for Material Management of a Residential Building
PDF
Assesing the various problems facing in arranging appropirate labour and qual...
PDF
The Impact of Materials Management on Profitability of Manufacturing Companie...
PDF
IRJET- Efficient Techniques of Construction Material Management in Constr...
PDF
Material management in construction – a case study
IRJET - A Review Paper on Effective Material Management to Minimize Probl...
An assessment of material management on building construction sites
IRJET- An Assessment of Role of Material Management in Construction Projects
Application of ABC Analysis for Material Management of a Residential Building
Assesing the various problems facing in arranging appropirate labour and qual...
The Impact of Materials Management on Profitability of Manufacturing Companie...
IRJET- Efficient Techniques of Construction Material Management in Constr...
Material management in construction – a case study

What's hot (20)

PDF
IRJET- Efficient Techniques of Construction Material Management in Constr...
PDF
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
PPTX
Construction quality management plan (Construction Productivity Analysis)
PPT
027 Fast-Tracked Projects-Materials
PDF
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
PDF
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
PDF
The Study of Measurement of Over-Engineering in Construction Project
PDF
Production planning and Control, Sale's forecasting
DOC
PPTX
construction quality management
PDF
Scope and functons of materals management
PDF
Construction quality management_Construction Management (2180611) (Semester-8...
PPTX
Design and production tools
PPT
Cost of quality in home building
PDF
(Student assignment) riordan manufacturing process improvement final
PDF
Vskills production planning and control professional sample material
PDF
IRJET- Review on Study of Quality Practices in Construction
DOCX
Rahul Jibhe CV
PDF
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- Efficient Techniques of Construction Material Management in Constr...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Construction quality management plan (Construction Productivity Analysis)
027 Fast-Tracked Projects-Materials
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
The Study of Measurement of Over-Engineering in Construction Project
Production planning and Control, Sale's forecasting
construction quality management
Scope and functons of materals management
Construction quality management_Construction Management (2180611) (Semester-8...
Design and production tools
Cost of quality in home building
(Student assignment) riordan manufacturing process improvement final
Vskills production planning and control professional sample material
IRJET- Review on Study of Quality Practices in Construction
Rahul Jibhe CV
IRJET- Assessment of Role of Material Management in Construction Projects
Ad

Similar to IRJET-Improving Effective Material Management by Identifying Common Factors in Building Construction Project (20)

PDF
Factors Affecting Material Management on Construction Site
PDF
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
PDF
IRJET-Influence of Material Management on Construction Project
PDF
Infrastrcture project management
PPTX
constraction material constraction material management .pptx4.pptx
PDF
A Computerized System for Managing Con-struction Materials for Gaza Strip Bui...
PDF
Material management in construction – a case study
PDF
Material management in construction – a case study
PPT
Lecture notes Cons 3Mat Magt edited 2016 ed (2).ppt
PDF
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRY
PDF
IRJET- Cost Control Methods used in Construction Projects
PDF
journalsresaim,+IJRESM_V3_I7_70.pdf
PDF
IRJET- Analysis of Material Requirement Planning for Construction Project : C...
PDF
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
PDF
Management For Construction Project:-Various Aspects Of Delay
PDF
Constructionmaterialmanagement 140920032237-phpapp01
PPTX
Construction Material Management
PPT
027 fast-tracked projects-materials
PPT
042 integrating lean construction
Factors Affecting Material Management on Construction Site
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
IRJET-Influence of Material Management on Construction Project
Infrastrcture project management
constraction material constraction material management .pptx4.pptx
A Computerized System for Managing Con-struction Materials for Gaza Strip Bui...
Material management in construction – a case study
Material management in construction – a case study
Lecture notes Cons 3Mat Magt edited 2016 ed (2).ppt
A REVIEW ON FACTORS AFFECTING MATERIAL MANAGEMENT ON CONSTRUCTION INDUSTRY
IRJET- Cost Control Methods used in Construction Projects
journalsresaim,+IJRESM_V3_I7_70.pdf
IRJET- Analysis of Material Requirement Planning for Construction Project : C...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
Management For Construction Project:-Various Aspects Of Delay
Constructionmaterialmanagement 140920032237-phpapp01
Construction Material Management
027 fast-tracked projects-materials
042 integrating lean construction
Ad

More from IRJET Journal (20)

PDF
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
PDF
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
PDF
Kiona – A Smart Society Automation Project
PDF
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
PDF
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
PDF
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
PDF
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
PDF
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
PDF
BRAIN TUMOUR DETECTION AND CLASSIFICATION
PDF
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
PDF
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
PDF
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
PDF
Breast Cancer Detection using Computer Vision
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
Kiona – A Smart Society Automation Project
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
BRAIN TUMOUR DETECTION AND CLASSIFICATION
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
Breast Cancer Detection using Computer Vision
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...

Recently uploaded (20)

PPTX
Artificial Intelligence
PPTX
Construction Project Organization Group 2.pptx
PPTX
UNIT 4 Total Quality Management .pptx
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
PPT on Performance Review to get promotions
PPTX
OOP with Java - Java Introduction (Basics)
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
bas. eng. economics group 4 presentation 1.pptx
DOCX
573137875-Attendance-Management-System-original
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
Current and future trends in Computer Vision.pptx
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Artificial Intelligence
Construction Project Organization Group 2.pptx
UNIT 4 Total Quality Management .pptx
R24 SURVEYING LAB MANUAL for civil enggi
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Fundamentals of safety and accident prevention -final (1).pptx
Foundation to blockchain - A guide to Blockchain Tech
III.4.1.2_The_Space_Environment.p pdffdf
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPT on Performance Review to get promotions
OOP with Java - Java Introduction (Basics)
Embodied AI: Ushering in the Next Era of Intelligent Systems
bas. eng. economics group 4 presentation 1.pptx
573137875-Attendance-Management-System-original
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Current and future trends in Computer Vision.pptx
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...

IRJET-Improving Effective Material Management by Identifying Common Factors in Building Construction Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 146 Improving Effective Material Management by Identifying common Factors in Building Construction Project Yohannes Tedla1, Dixit Patel2 1Student,M. tech (construction project management), Parul University, Vadodara, Gujarat, India 2Professor, civil engineering, Parul University, Vadodara, Gujarat, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Management in materials has great problems for many years to most firms in construction project. This paper work is based on improving current material management through identifying common factors for buildingconstruction. Having the accurate materials and time is an essential aspect for the accomplishment of construction project. Thisstudyhas revealed that construction materials may constitute more than 55% of overall cost for a distinctive construction project. One of the main difficulties in delaying construction projectsis improper materials and equipment management.Inthisstudy factors affecting effective materialmanagementandInventory management were listed in accordancewiththemostaffecting factors based on literature review. In this paper Relative important (RII) methods were used for data analysis. Therefore the proper management of this single largest element can improve the output and price efficiency of a project and help ensure its timely completion. Key Words: Construction Material, Inventory control, Management, Project management, Relative important index (RII) method 1. INTRODUCTION Material management is a task that pointedly contributes to the achievement of a project. Asprojectsdevelopinscaleand difficulty, material management is required really to use them. It remains the process that organizes planning, purchasing, transporting, receiving and inspection, storing, handling and monitoring of materials, reducingthewearand tear and optimizing the productivity by minimizing cost of materials. The objective of material controlling is to safeguard that materials remain existing at their point of usage when needed and accurate quantity and quality of materials are appropriate selected, purchased,deliveredand handled. Indeed material management will cause a huge effect. On the whole project cost, time and quality. Material management should be measured in constructionprojectsas an energetic management to achieve superior productivity and profit, which should be interpreted into cost discount and successful completion with best quality. It is surely that material management performs increase capability in operations and reducesoverall costs. AccordingtoProfessor Raju Narwade (2016) Cost remains an essentialconstraintof every project. On the other hand when material availability at site is delayed it will affect scheduling of activities. Material must stay available trendy hand at right time for effective completion of project. 1.1 Factors Associated With Material Management There are many factors described in the area of material management and each of these influencescan make to latent problems. Zakeri et al (1996) recommendedthatfactorssuch as: transport difficulties, waste, inappropriate handling on site, lack of suitable work plan, misuse of the specifications, inappropriate material transportation and extreme paperwork totally adversely effectonmaterialmanagement. Common factors mostly disturb material management are enumerated as follow. 1.2 Problems arising lack of specialcareinmaterial management.  Receiving incorrect material type  Increase materials quantity in storage  Burglary, theft and vandalism  Destroy material in shipping  High cost in material transportation  Unavailable required quantity  Too early receiving of materials earlier usage  Incorrect material take-off fromdrawinganddesign  Material Shortage during construction  Piling of inventory materials  Poor material selection  Project delay because of slow delivery materials  Suddenly alternation price of materials  Ineffective control of storage 1.3. Factors increase waste in constructionprojects  Incomplete drawing design and specification  Poor cutting of materials (glass, tiles, plywood)  Inefficient utilization of temporary materials (hoarding, formwork, scaffold)  Poor security on site (theft and vandalism)  Lack of care in transportation  Inadequate skill in utilization of materials  Insufficient places for material storing  Wrong methods and regulations in materials usage  Poor materials storage facility
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 147  Lack of supervision and proper control during storage  Wrong material utilization OBJECTIVES OF MATERIAL MANAGEMENT  Efficient and effective materials planning  Buying or Purchasing  Obtaining or Procuring  Receiving  Inventory control  Supply and delivery of materials Components of material management:  Material planning, forecasting and budgeting  Scheduling, purchasing and procurement  Receiving &inspection.  Inventory control and storage  Material management then delivery Fig.1: Process of Material Management Functions of material management To accomplish the objectives of material management as stated above to encounter the basic objectives and areas, the functions performed in material management are classified as primary and secondary functions. I. Primary Functions Tomeet the objectivesofthe studyin construction materials, the primary functions are noted as follows.  Materials Supplies Planning  Acquiring or Purchasing  Storage Planning and Control  Find out and Maintaining the MovementandSource of Materials II. Secondary Functions  Regulation and Simplification  purchase and Acquisition Decisions  Coding and Grouping of Materials  Estimating and Planning PROJECT MANAGEMENT Different trainingmeetingsshould be settled on site to notify the workers concerning the newest techniques. Manufacturing machinery has to be well-run regularly to avoid any break down. Labors and contractors ought to be guided for correct training to accomplish a specific task. According to Berliner B. “project controlling is mostly based on effective budgetary management and performance measures. PLANNING Themost frequently used basis forplanningthingsoutforthe project is the BOQ prepared by the client. Most companies have two mainlevelsinplanning-micro andmacrolevel.The planning would be reviewed regularly as possible whether the work is continued as per planned or not INVENTORY CONTROL Sundersan M. defines inventory as the sum of the worth of raw materials, petroleum and lubricants, replacement parts, maintenance usable at any specific point of time. Kasim.et.al (2012) analyzed an improving on site material tracking for store management in construction. It is essential to manage all materials and records throughout construction activities. Failure in site inventory management will consequence in cost overrun, and interruptions in project closing time
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 148 2. Problems identified in material management Table -1: Phase 1- Materials Identification Problem Description Undefined scope No right explanation of whatever is wanted Lack of communication Lack of communication between parties involved Incomplete drawings Plans are not finished and details are missing Lack of certification to What is required by the requirements purchaser is not what is prepared Nonstandard specifications Use of descriptions that are not commonly used Incomplete / ineffective Issues not determined during meetings meetings Phase 2- Vendor Selection criteria Problem Description Uncontrollable bid list Have too numerous suppliers and too little evidence Incomplete proposals Suppliers do not contain all documents required Phase 3: identification of Procurement Problem Problem Description Matching price to Price discount to match competitor’s price competitor’s price Late deliveries/delay of material on construction site Resources are not transported as per schedule Poor communication Lack of communication between parties Unrealistic delivery dates Delivery dates difficult to meet Phase 4: Construction Phase Problems Description Delivery wrong materials There are variances in material ordered and delivered Incorrect sizes delivered Incorrect quantities delivered Keeping track of material Don’t know where materials are at specific time Rehandling of material Storage of material Loss of material Damage No supplier QA No quality declaration from supplier Poor communication Receiving, handling and storage of unused materials LITERATURE REVIEW There are various factors which facilitate poor material controlling in construction engineering. Zakeri et al. (1996) find out those factorswhich cause transportation problems, wastage, inappropriate handling on site, wrong use of the specifications, and absence of appropriate work plan, unsuitable material transport and too much paperwork all badly effect on material management. [2] Improper materials management can consequence in increased costs throughout construction project. Efficient and effective management of materials can result in considerable savings in project costs. Materials may deteriorate in store or get stolen if special attention is not taken. Delays and additional costs may be sustained if materials required for particular works are not available. (Hemishkumar Patel, Dr. Jayeshkumar Pitroda). [3] According to Pande and Sabihuddin (2017) Material management method is a critical element oftheconstruction business. A properly executed materials management plan can accomplish the timely movement of materials to the jobsite, and consequently to simplify improved work appearance planning, improved labour productivity, better schedule. [4] According to Dr. Kevin .A explained that factors disturbing material management for the selected case study of building sites and practice of right material in the right place at the right time is necessary for effective implementation of a building project. The research concluded that Material management indications to effective cost control,toincrease
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 149 the quality and time execution of their projects and reduces failure of a project. [5] Productive and well-organized material management trainings are important in construction industry. The study indicates that construction materials constitute about 70% of the entire cost for a typical construction project. Proper management ethics and practices are required for this component which will improvise the efficiency and cost effectiveness of the project and thus helping on time completion of the project. (Khyomesh V. et. 2011) [6] Poor documentation of material, in appropriate and insufficient storage cause damages in labor output and overall delays that can incidentally increase total task cost. (Ashwini R. Patil, et.al 2013) [7] Materials management methods require a renovation to improve the totally in management of materials for more efficiency and effectiveness on the construction site. This is since poor handling of construction materials disturbs the overall performance of construction projects.(A.A.Gulghane 2015) [8] According to Ms. Priyadarshani .et.al (2017) most of constricting companies are reflected the main problems in using computer in material management are lack of user- friendly computer program and no understanding for importance of computer program. [9] According to Harsh Soni, Dr. Jayeshkumar Pitroda, and Prof.J.J.Bhavshar (2016) selective inventory control method to maintain adequate stock of raw material during the time of short supply, to protect inventory against decline and control asset in recordsand to keep it at an optimumlevelby using an inventory control techniques. [10] According to Abhilin G B, (2017) applying enough stock of raw materials in period of short supply, to protect inventory against deterioration and control investment in inventories and to keep it in an optimum level by using an inventory control techniques. [11] RESEARCH METHODOLOGY The research methods which used for data analysis regarding factors disturbing material management were called Relative Important Index (RII). Relative Importance Index were used to determine the relative importance of many factors affecting construction materialmanagementin construction firms and used for ranking delays in many construction industries. The five-point scale (Likert scale) ranged from one (very little degree affect) to five (very high degree affect) is adopted and transformed to relative importance indices for each factor as follows: Where, W = is the weighting given to each factor by the respondents (ranging from 1 to 5), A =is the highest weight (i.e. 5 in this case), and N= is the total number of respondents. 3. CONCLUSIONS This research has studied the current material management in local building construction projects. This paperdefinesmaterialmanagementasmeasuresforeffective material management, factors commonly affecting material managementin building construction projects andproblems related with material management. Generally, we will recommend that to improve effective material management in building construction sites.  There should be anintegratedmaterialmanagement group co-ordination among the site and the organization.  Proper control, monitoring and tracking of the system is required.  Attentiveness and liability should be generated inside the organization  There is a necessityof an efficientMIS integratingall aspects of material management.  Firms employing suitable material management mandate to increase their overall efficiency Content comes here Conclusion content comes here . Conclusion content comes here REFERENCES [1] Professor, RajuNarwade andSayali Shet”,“An Empirical Case Study Of Material Management In Construction Of Industrial Building By Using Various Techniques “International Journal of Civil Engineering and Technology (IJCIET) Volume 7, Issue 5, September- October 2016, pp. 393–400. [2] Nann Lwin Phu, and Aye Mya Cho, “Factors Affecting Material Management in BuildingConstructionProjects”, Internal Journal of scientificEngineeringandTechnology Research, Vol.03,Issue.10, May-2014, Pages:2133-2137. [3] Hemishkumar Patel, Dr. Jayeshkumar Pitroda, Prof. J. J. Bhavsar, “Analysis of Factor Affecting Material Management and Inventory Management: Survey of ConstructionFirmsin Gujarat Region of India”Volume1, Issue 10 May2015 [4] Professor, Aditya A. Pande and S .Sabihuddin”, “Study of Material Management Techniques on Construction Project “, Volume 2, Issue 9, May 2015
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 150 [5] DR. Kevin Aku Okorocha, Ph.D., RSV, “Factors Affecting Effective Materials Management In Building Construction Projects- A Case Study OfSelectedBuilding Sites, In Imo State, Nigeria”, International Journal of Management Sciencesand BusinessResearch Volume2, Issue 4- ISSN (2226-8235) [6] Khyomesh V. Patel,” Construction Materials Management On Project Sites” National Conference on Recent Trends in Engineering & Technology, 13-14 May 2011 [7] Ashwini R. Patil, Smita V. Pataskar’’, Analyzing Material Management Techniques on Construction Project, International Journal of Engineering and Innovative Technology (IJEIT) Volume 3, Issue 4, October 2013 [8] A. A. Gulghane and Prof P. V. Khandve, Management for Construction Materials and Control of Construction Waste in Construction Industry: A Review, Int. Journalof Engineering Research and Applications Vol. 5, Issue 4, ( Part -1) April 2015, pp.59-64. [9] Ms. Priyadarshani N. Mane , Dr. A. K. Gupta & Prof. D. B. Desai, A Review Paper on Onsite Material Management for Construction Projects , Imperial Journal of Interdisciplinary Research (IJIR) Vol-3, Issue-2, 2017. [10] Harsh Soni, Dr. Jayeshkumar Pitroda, Prof. J.J.Bhavshar”, “Analyzing Inventory Material Management Control Technique On Residential Construction Project”, Vol-2 Issue-3 2016 IJARIIE-ISSN (O)-2395-4396 [11] AbhilinGB, and Vishak MS”,“Effective MaterialLogistics in Construction Industries” International Journal of Science and Research (IJSR) Volume 6 Issue 3, March 2017