JOB LAYOUT
1
NAME
DALAL JAY RAKESHBHAI
BALAR RAJ PRAVINBHAI
KANZARIYA NIKHIL JIVRAJBHAI
GANDHI RAJ MINESHBHAI
GANGANI SAGAR ASHOKBHAI
What is Job Layout?
• A job layout is prepared to promise that work proceeds smoothly
without any obstruction. The various construction resources such as
material, men, machinery etc. should be arranged in such way to
achieve optimal utilization of space. The larger and more complex
the project, greater will be the need for planned job layout and
detailing at site. And job layout can be defined as a site drawing of
the proposed construction showing the location of entry, exit,
temporary services, material stores and stocks, plant or equipment
and site offices.
2
o A job layout is a scaled drawing of the propose construction site showing
all relevant features
• Entry point
• Exit point
• Storage are of materials-bricks-cement-sand-aggregate
• Temporary services-washing and toilet
• Contractor site office
• Area of keeping equipment such as mixer
• Bar bending area
• Labor housing
3
History
• Static models can not consider the changes in facility location that occur on
construction sites onto the progress of time. These models assume that all
facilities exist on the site for the entire duration of the project. Static models can
be conformable for projects where space is plenteous, having large construction
sites with short durations and for project where there are not many changes in
the layout of the construction site over the course of time. However, where
number of facilities to come and leave the project site over the course of
construction in more complicated projects, static model are not practical with
longer durations. Static models do not allow reusing the space occupied by
facility which is no longer required on the site.
4
• Dynamic models consider the changes that occur on construction
sites over the course of progress in project. The space usage on
the site changes over the course of construction. The time and
duration for which the facilities are required on the site depends
on the activities they are attached with. The role of facilities on
the construction site is to provide base for construction activities.
A model shares locations to facilities where they can have better
assistance for the activities. The dynamic model described that,
both the required facilities and the space required to help them
on the site, are subject to change.
5
Purpose of preparing job layout
• To save time in delivering construction material at the side of construction
• To safeguard construction material from damage and deterioration
• To keep the lead of cartage minimum, so that cartage expenses may be minimum
• To adopt the best mode of working
• To complete the work with the minimum use of equipment and machinery
• To lake maximum output from labor and machinery
6
• To provide safety to workers and passer-by etc.
• To avoid damage due to construction activities to the
nearby properties
• To common use materials as fine and coarse aggregate
should be stored to near to each other
• To store construction materials as near the place of the
utilization as possible
7
Advantage of a good job layout
• Smooth and economical working of the project.
• Reduces the completion time of the project.
• Provide more safety in the working of the project.
• Material wastage and deterioration are reduced.
• Material transection become easy speedy and economical.
• Increases the output from labor and machinery.
8
Factor affection job layout
• Nature of the project
• Construction method
• Availability of resources
• Material facility
• Constructer’s, site engineer’s offices
• Provision for temporary roads
• Other facility’s
9
Principal preparation of job layout
• Administrative block
• Warehouse
• Entry and exits
• Location of workshop
• Service
• Temporary roads
• Staff accommodation
10
Identification of facility
• The Following are the temporary facilities are identified to be
constructed on site
• 1) Site Office 2) Booking office 3) Subcontractor’s office 4) First
Aid and Medical Room 5) Guard Room 6) Toilet on Site 7)
Engineer and Staff quarters 8) Labor quarters 9) Equipment
Maintenance room 10) Parking for machines 11) Bar bending shop
12) Fabricated rebar storage yard 13) Carpentry shop 14) Cement
warehouse 15) Batching plant and aggregates storage 16) Testing
Lab 17) Material storage lab 18) Water tank 19) Scaffolding storage
20) Canteen
11
Relationship chart
12
13
Facility movement
• The decision of fixing the facility location is depend on the entry
location, exit and how will be the flow of facility occurs on site. In
this construction project, we have fixed the entry location and exit.
The entry should be fixed at the west side of plot where there is
approaching a road of width 20m. The purpose behind the fixation of
entry on west side is to attract the customer by showing them the
extent of construction project. The extension of construction project
cannot be visualized from any other side. The exit is kept on north
side of the plot, where there is approaching road of width 30m. After
fixing the entry location, we are going to think on facility movement
on site
14
• Now, grouping or bundle of the same or nearly same function of
facility can be done to get the initial relationship diagram. The
grouping of facility is done in oval shape. The grouping of facility is
shown below.
• Group 1
• 1) Site office
• 2) Booking office
• 3) Subcontractor office
• 4) First aid and medical room
• 5) Toilet on site
• 6) Labor quarter
• 7) Guard room
15
• Group 2
• 1) Toilet on site
• 2) Carpentry shop
• 3) Water tank
• 4) Scaffolding storage.
• Group 3
• 1) Cement warehouse
• 2) Batching plant and aggregate storage
• Group 4
• 1) Toilet on site
• 2) Staff and engineer quarter
16
• Group 5
• 1) Bar bending shop
• 2) Fabricated rebar storage yard
• Group 6
• 1) Testing lab
• 2) Material storage lab
• Group 7
• 1) Equipment maintenance room
• 2) Parking for machines
17
• Group 8
• 1) Canteen
• 2) Toilet on site.
• Others
• 1) Internal Road
• 2) Electric Poles
18
Space requirements
• Once work relationships were worked out to the optimized level,
the group involved in the construction project including project
manager, senior Engineer, site Engineer etc. wants to establish the
space relationships for each facility. Once again, this process was
accomplished over a series of weekly, one hour meetings. Each
person listed their personal space needs and these were presented
orally and discussed by all. The process of working through this
activities area discussion added much understanding to how the
business operates now and should operate in the future.
19
20
Activity relationship diagram
• After completion of grouping of facility task, each group is now
moving according to others group or move according to the relation
that group with other group. The relation among the group can be
shown in figure by single, two, three and four line between the
groups. The meanings of those four lines between groups indicate
that it is absolutely necessary that these groups should be close
together. Three lines show an especially important closeness
relationship. Two lines illustrate that it is important that they
may or may not be close. One line illustrate that there is no need to
be close that groups. Figure obtain is called as activity
relationship diagram.
21
22
23

More Related Content

DOCX
Job layout per
PDF
Building Construction process
PDF
Construction Activities and Process
PPTX
Building Construction: Experiencing Construction
PPTX
Final BUILDING CONSTRUCTION 1
PPT
Stages in Construction
PDF
Construction activities and Process
PDF
Bungalow
Job layout per
Building Construction process
Construction Activities and Process
Building Construction: Experiencing Construction
Final BUILDING CONSTRUCTION 1
Stages in Construction
Construction activities and Process
Bungalow

What's hot (20)

PPTX
Shoring and underpinning
PPTX
PAVEMENT DESIGN & TYPES
PPTX
civil engineering-Contracts
PPTX
Crack repair techniques
PPTX
Pumped Concrete
PPTX
Sewer Appurtenances
PPTX
Polymer concrete and it's types
PPT
MAINTENANCE AND REPAIR STRATEGIES
PDF
Special Concretes
PPTX
Sulphur infiltrated concrete
PPTX
Chapter 1 repair stratergies
PPTX
Construction Planning
PPTX
Repair & Rehabilitation of Structures
PPT
Shotcrete
PPTX
prestressed concrete
PPTX
Construction of substructure
PPTX
Repair,Retrofitting and Rehabilitation
PPTX
Chapter 3 materials & techniques for repairs
PPTX
Mechanized construction
Shoring and underpinning
PAVEMENT DESIGN & TYPES
civil engineering-Contracts
Crack repair techniques
Pumped Concrete
Sewer Appurtenances
Polymer concrete and it's types
MAINTENANCE AND REPAIR STRATEGIES
Special Concretes
Sulphur infiltrated concrete
Chapter 1 repair stratergies
Construction Planning
Repair & Rehabilitation of Structures
Shotcrete
prestressed concrete
Construction of substructure
Repair,Retrofitting and Rehabilitation
Chapter 3 materials & techniques for repairs
Mechanized construction
Ad

Viewers also liked (20)

PPT
Selection Criteria of a Plant
PPSX
Microtunneling presentation 2014
PDF
Layout
PPT
High Tunnel Strawberries 2012
PPTX
3 4 chemplantdesign-general plant consideration
PDF
Site visit presentation: Kwun Tong line extension
PPTX
Digipak Layout Design Keanan Adams
PDF
Site Suitability For Construction(Dam)
PPT
Tunneling
PPTX
koteshwar hydro electric power plant 400 mw
PPT
Om lect 04_a(r0-aug08)_facility location & layout_mms_sies
PPT
Bangkok Mega Bridge Project Management 2007
PPT
114 site layout
PPS
KALA BAGH DAM Presentation by WAPDA . . .
PPTX
Plant location and layout
PPTX
1926 tunneling safety 2015
PPTX
Dam construction safety management (group 2, 7th reporter)
PPT
113 site layout design
PPTX
Plant location and layout
Selection Criteria of a Plant
Microtunneling presentation 2014
Layout
High Tunnel Strawberries 2012
3 4 chemplantdesign-general plant consideration
Site visit presentation: Kwun Tong line extension
Digipak Layout Design Keanan Adams
Site Suitability For Construction(Dam)
Tunneling
koteshwar hydro electric power plant 400 mw
Om lect 04_a(r0-aug08)_facility location & layout_mms_sies
Bangkok Mega Bridge Project Management 2007
114 site layout
KALA BAGH DAM Presentation by WAPDA . . .
Plant location and layout
1926 tunneling safety 2015
Dam construction safety management (group 2, 7th reporter)
113 site layout design
Plant location and layout
Ad

Similar to Job layout of cinstruction site (20)

PPTX
Construction site planning group six ass
PPTX
Site Organization (Construction management)
PPTX
Plant layout and its types
PPT
Site Organization.ppt
PPT
Site Organization.ppt
PDF
Sample ppt facility location and layout
PDF
A Framework to optimize Construction Site Layout Planning
PDF
03.Location and Layout slides.pdf
PDF
Site layout cpm module4
DOCX
Chapter 16. Facility Layout DecisionAfter selecting a facility.docx
PPT
Bhel inventory management singh begun yeh
DOCX
Plant design description for a can opener factory
PPT
Road Project Schedule M S Project.ppt
PPTX
Facility+layout
PDF
Plant Layout Guide
PDF
Job Layout
PPTX
Facility layout
Construction site planning group six ass
Site Organization (Construction management)
Plant layout and its types
Site Organization.ppt
Site Organization.ppt
Sample ppt facility location and layout
A Framework to optimize Construction Site Layout Planning
03.Location and Layout slides.pdf
Site layout cpm module4
Chapter 16. Facility Layout DecisionAfter selecting a facility.docx
Bhel inventory management singh begun yeh
Plant design description for a can opener factory
Road Project Schedule M S Project.ppt
Facility+layout
Plant Layout Guide
Job Layout
Facility layout

Recently uploaded (20)

PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
PDF
Analyzing Impact of Pakistan Economic Corridor on Import and Export in Pakist...
PPT
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
PPTX
Current and future trends in Computer Vision.pptx
PDF
Soil Improvement Techniques Note - Rabbi
PPTX
Information Storage and Retrieval Techniques Unit III
PDF
Visual Aids for Exploratory Data Analysis.pdf
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
PPTX
Fundamentals of Mechanical Engineering.pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PDF
737-MAX_SRG.pdf student reference guides
PPT
Total quality management ppt for engineering students
PPT
introduction to datamining and warehousing
PPTX
communication and presentation skills 01
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS
R24 SURVEYING LAB MANUAL for civil enggi
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
Analyzing Impact of Pakistan Economic Corridor on Import and Export in Pakist...
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
Current and future trends in Computer Vision.pptx
Soil Improvement Techniques Note - Rabbi
Information Storage and Retrieval Techniques Unit III
Visual Aids for Exploratory Data Analysis.pdf
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
Fundamentals of Mechanical Engineering.pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
III.4.1.2_The_Space_Environment.p pdffdf
737-MAX_SRG.pdf student reference guides
Total quality management ppt for engineering students
introduction to datamining and warehousing
communication and presentation skills 01
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf

Job layout of cinstruction site

  • 1. JOB LAYOUT 1 NAME DALAL JAY RAKESHBHAI BALAR RAJ PRAVINBHAI KANZARIYA NIKHIL JIVRAJBHAI GANDHI RAJ MINESHBHAI GANGANI SAGAR ASHOKBHAI
  • 2. What is Job Layout? • A job layout is prepared to promise that work proceeds smoothly without any obstruction. The various construction resources such as material, men, machinery etc. should be arranged in such way to achieve optimal utilization of space. The larger and more complex the project, greater will be the need for planned job layout and detailing at site. And job layout can be defined as a site drawing of the proposed construction showing the location of entry, exit, temporary services, material stores and stocks, plant or equipment and site offices. 2
  • 3. o A job layout is a scaled drawing of the propose construction site showing all relevant features • Entry point • Exit point • Storage are of materials-bricks-cement-sand-aggregate • Temporary services-washing and toilet • Contractor site office • Area of keeping equipment such as mixer • Bar bending area • Labor housing 3
  • 4. History • Static models can not consider the changes in facility location that occur on construction sites onto the progress of time. These models assume that all facilities exist on the site for the entire duration of the project. Static models can be conformable for projects where space is plenteous, having large construction sites with short durations and for project where there are not many changes in the layout of the construction site over the course of time. However, where number of facilities to come and leave the project site over the course of construction in more complicated projects, static model are not practical with longer durations. Static models do not allow reusing the space occupied by facility which is no longer required on the site. 4
  • 5. • Dynamic models consider the changes that occur on construction sites over the course of progress in project. The space usage on the site changes over the course of construction. The time and duration for which the facilities are required on the site depends on the activities they are attached with. The role of facilities on the construction site is to provide base for construction activities. A model shares locations to facilities where they can have better assistance for the activities. The dynamic model described that, both the required facilities and the space required to help them on the site, are subject to change. 5
  • 6. Purpose of preparing job layout • To save time in delivering construction material at the side of construction • To safeguard construction material from damage and deterioration • To keep the lead of cartage minimum, so that cartage expenses may be minimum • To adopt the best mode of working • To complete the work with the minimum use of equipment and machinery • To lake maximum output from labor and machinery 6
  • 7. • To provide safety to workers and passer-by etc. • To avoid damage due to construction activities to the nearby properties • To common use materials as fine and coarse aggregate should be stored to near to each other • To store construction materials as near the place of the utilization as possible 7
  • 8. Advantage of a good job layout • Smooth and economical working of the project. • Reduces the completion time of the project. • Provide more safety in the working of the project. • Material wastage and deterioration are reduced. • Material transection become easy speedy and economical. • Increases the output from labor and machinery. 8
  • 9. Factor affection job layout • Nature of the project • Construction method • Availability of resources • Material facility • Constructer’s, site engineer’s offices • Provision for temporary roads • Other facility’s 9
  • 10. Principal preparation of job layout • Administrative block • Warehouse • Entry and exits • Location of workshop • Service • Temporary roads • Staff accommodation 10
  • 11. Identification of facility • The Following are the temporary facilities are identified to be constructed on site • 1) Site Office 2) Booking office 3) Subcontractor’s office 4) First Aid and Medical Room 5) Guard Room 6) Toilet on Site 7) Engineer and Staff quarters 8) Labor quarters 9) Equipment Maintenance room 10) Parking for machines 11) Bar bending shop 12) Fabricated rebar storage yard 13) Carpentry shop 14) Cement warehouse 15) Batching plant and aggregates storage 16) Testing Lab 17) Material storage lab 18) Water tank 19) Scaffolding storage 20) Canteen 11
  • 13. 13
  • 14. Facility movement • The decision of fixing the facility location is depend on the entry location, exit and how will be the flow of facility occurs on site. In this construction project, we have fixed the entry location and exit. The entry should be fixed at the west side of plot where there is approaching a road of width 20m. The purpose behind the fixation of entry on west side is to attract the customer by showing them the extent of construction project. The extension of construction project cannot be visualized from any other side. The exit is kept on north side of the plot, where there is approaching road of width 30m. After fixing the entry location, we are going to think on facility movement on site 14
  • 15. • Now, grouping or bundle of the same or nearly same function of facility can be done to get the initial relationship diagram. The grouping of facility is done in oval shape. The grouping of facility is shown below. • Group 1 • 1) Site office • 2) Booking office • 3) Subcontractor office • 4) First aid and medical room • 5) Toilet on site • 6) Labor quarter • 7) Guard room 15
  • 16. • Group 2 • 1) Toilet on site • 2) Carpentry shop • 3) Water tank • 4) Scaffolding storage. • Group 3 • 1) Cement warehouse • 2) Batching plant and aggregate storage • Group 4 • 1) Toilet on site • 2) Staff and engineer quarter 16
  • 17. • Group 5 • 1) Bar bending shop • 2) Fabricated rebar storage yard • Group 6 • 1) Testing lab • 2) Material storage lab • Group 7 • 1) Equipment maintenance room • 2) Parking for machines 17
  • 18. • Group 8 • 1) Canteen • 2) Toilet on site. • Others • 1) Internal Road • 2) Electric Poles 18
  • 19. Space requirements • Once work relationships were worked out to the optimized level, the group involved in the construction project including project manager, senior Engineer, site Engineer etc. wants to establish the space relationships for each facility. Once again, this process was accomplished over a series of weekly, one hour meetings. Each person listed their personal space needs and these were presented orally and discussed by all. The process of working through this activities area discussion added much understanding to how the business operates now and should operate in the future. 19
  • 20. 20
  • 21. Activity relationship diagram • After completion of grouping of facility task, each group is now moving according to others group or move according to the relation that group with other group. The relation among the group can be shown in figure by single, two, three and four line between the groups. The meanings of those four lines between groups indicate that it is absolutely necessary that these groups should be close together. Three lines show an especially important closeness relationship. Two lines illustrate that it is important that they may or may not be close. One line illustrate that there is no need to be close that groups. Figure obtain is called as activity relationship diagram. 21
  • 22. 22
  • 23. 23