Lean PMO
                         Oxymoron or Possible?
                                    Mike Edwards
                                           SDEC 2012




                              Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Which resembles your
                              projects?




                              Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Agenda
                    •    Introduction to Lean

                    •    Step through the assessment model & take the
                         assessment

                    •    Interact and share our experiences

                    •    What do the results tell us?

                    •    Next steps!


                                       Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Introductions!




                           Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
This is Lean!


                         Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Optimizing   Eliminating
                                                                the whole       Waste




      This is Lean!                             High Product
                                                  Integrity               Value       Always
                                                                                     Learning



                                                            Team & People  Always
                                                               Focus      Delivering




                         Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Why another model?!?
                    •    Iterative approaches produce better outcomes
                         •   Build-Measure-Learn (Eric Ries - Lean Startup)
                         •   Plan-Do-Check-Act (Deming)
                         •   Observe-Orient-Decide-Act (John Boyd)

                    •    Higher value from quick iterations (aka Fail Fast!)

                    •    Need something light weight

                    •    Less costly approach to suit the times

                    •    Experience shows we can learn a lot in one day

                                            Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Assessment Model




                             Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Assessment Model
           They’re People                                                      People’s
           not Resources!                                                     Satisfaction




          Business risk,
        schedule and cost                                                       Quality
            pressure
                             Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Assessment Model
           They’re People                                                      People’s
           not Resources!                                                     Satisfaction




          Business risk,
        schedule and cost                                                       Quality
            pressure
                             Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Assessment Model
           They’re People                          People                              People’s
           not Resources!                                                             Satisfaction




                         Process                                                    Product


          Business risk,
        schedule and cost                                                               Quality
            pressure
                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Assessment Model
           They’re People                          People                              People’s
           not Resources!                                                             Satisfaction




                         Process                                                    Product


          Business risk,
        schedule and cost                                                               Quality
            pressure
                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
People




                         Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
People


              All people impacted by or who
                interact with your project


                         Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
People
                  Master           Leadership                                Servant


   Disempowered                   Ownership                                 Empowered


               Exclusive      Collaboration                                  Inclusive



                           Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Take the survey!
                        Answer the People section of the survey
                 Plot the three items on the chart and connect the dots

                         Discuss the outcome with your neighbour



                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Process

                          Focus on how you use a process



                         Don’t focus on what process is used


                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Process
                  Once              Improving                               Ongoing


          Established                  Process                              Evolving


                   Rigid          Application                               Scaled



                           Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Take the survey!
                        Answer the Process section of the survey
                 Plot the three items on the chart and connect the dots

                         Discuss the outcome with your neighbour



                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Product




                         Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Product

                           IT organizations only exists to
                         deliver valuable products & tools to
                          enable our customers to succeed



                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Product
                 Control   Response to change                                Respond


                 Project   Achievement Focus                                 Customer


                 Defined    Product Definition                                 Learned



                            Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Take the survey!
                        Answer the Product section of the survey
                 Plot the three items on the chart and connect the dots

                         Discuss the outcome with your neighbour



                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
What do the
                         results tell us?



                             Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Assessment Model
           They’re People                          People                              People’s
           not Resources!                                                             Satisfaction




                         Process                                                    Product


          Business risk,
        schedule and cost                                                               Quality
            pressure
                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Assessment Model
           They’re People                          People                              People’s
           not Resources!                                                             Satisfaction




                         Process                                                    Product


          Business risk,
        schedule and cost                                                               Quality
            pressure
                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Assessment Model
           They’re People                          People                              People’s
           not Resources!                                                             Satisfaction




                         Process                                                    Product


          Business risk,
        schedule and cost                                                               Quality
            pressure
                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
Where to
                 from here?

                         Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
What now?
                    •    The assessment is only the start
                    •    Listen to the people
                    •    Everyone must commit to an
                         improvement program
                    •    Measure outcomes
                    •    For best results - get help!

                                   Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12
http://leanpmsolutions.ca/the-lean-pmo-is-possible/




                                       Copyright Lean PM Solutions Inc - October 2012


Sunday, 28 October, 12

More Related Content

PPTX
Rational Agility
PPT
Great Webinars (ASTD PS)
PPT
PMI SCC Social Medial & Project Management
PPT
Edd...
PPT
ASTD 2012 ICE: Great Webinars
PPT
Great Webinars
PPT
Great Webinars - ASTD Rocky Mt.
PPTX
NHRDN Virtual Learning Session on Dynamic Decision Making
Rational Agility
Great Webinars (ASTD PS)
PMI SCC Social Medial & Project Management
Edd...
ASTD 2012 ICE: Great Webinars
Great Webinars
Great Webinars - ASTD Rocky Mt.
NHRDN Virtual Learning Session on Dynamic Decision Making

What's hot (20)

PDF
Introduction to decision management
PPT
Great Webinars (Pfeiffer)
PPT
Great Webinars for Pearson
PDF
Designing for Patient-Centred Innovation
PDF
Brend Brevé - Philips Industry Consulting
PPT
Great Webinars Bellevue College
PPTX
Addressing Today's Challenges in Application Development
PDF
Agile presentation ONA12
PPT
Influence Skills National Oilwell Varco October 2012
PPT
Camp It, June 2012, How To Design Your Bi Architecture To Capitalize on New T...
PPTX
Consulting toolkit structuring the problem
PDF
Leading Innovation: Insights From the Real World
PDF
Introduction To Lean Six Sigma
PDF
Dan perron lim
PDF
Managing Change_ISHAE Winter Conference
PPTX
Building Flexible, Easy to Change, and Rock-Solid Applications with BRFplus D...
PDF
Enterprise 2.0 by Dr Yves Caseau
PDF
Andy van der Gugten, Agile Tauranga 2018 Presentation
PDF
Creating Successful Change Using Continuous Improvement Methods
PPT
Great Webinars - SEVA ASTD Chapter
Introduction to decision management
Great Webinars (Pfeiffer)
Great Webinars for Pearson
Designing for Patient-Centred Innovation
Brend Brevé - Philips Industry Consulting
Great Webinars Bellevue College
Addressing Today's Challenges in Application Development
Agile presentation ONA12
Influence Skills National Oilwell Varco October 2012
Camp It, June 2012, How To Design Your Bi Architecture To Capitalize on New T...
Consulting toolkit structuring the problem
Leading Innovation: Insights From the Real World
Introduction To Lean Six Sigma
Dan perron lim
Managing Change_ISHAE Winter Conference
Building Flexible, Easy to Change, and Rock-Solid Applications with BRFplus D...
Enterprise 2.0 by Dr Yves Caseau
Andy van der Gugten, Agile Tauranga 2018 Presentation
Creating Successful Change Using Continuous Improvement Methods
Great Webinars - SEVA ASTD Chapter
Ad

Viewers also liked (17)

PPTX
How will the PMO at the Future be like?
PDF
Macrosolutions Training: PMO – Project Management Office
PPT
PMO 3.0 - Next Gen Lean Model - Doug Floyd
PPTX
PMO 2.0 - The Strategic Focused PMO
PDF
3 Critical Steps to Project Management Office (PMO) Development
PDF
PMO 3.0 - Program Management Office
PDF
A Leaner PMO in The Federal Government
PPTX
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
PDF
PPT
Leadership and project management concepts
PDF
PMO - Added value instead of administration
DOCX
Organizing a Project Management Office
PPTX
The Agile PMO: From Process Police to Adaptive Leadership
PPTX
Traditional vs Lean Portfolio Management, Agile PMO & Organisations
PPS
100 Day Plan for Directing a PMO
PDF
Gartner pmo best in class
PDF
The First 90 days
How will the PMO at the Future be like?
Macrosolutions Training: PMO – Project Management Office
PMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 2.0 - The Strategic Focused PMO
3 Critical Steps to Project Management Office (PMO) Development
PMO 3.0 - Program Management Office
A Leaner PMO in The Federal Government
PROJECT MANAGEMENT OFFICE (PMO) SETTING UP AND MANAGEMENT
Leadership and project management concepts
PMO - Added value instead of administration
Organizing a Project Management Office
The Agile PMO: From Process Police to Adaptive Leadership
Traditional vs Lean Portfolio Management, Agile PMO & Organisations
100 Day Plan for Directing a PMO
Gartner pmo best in class
The First 90 days
Ad

Similar to Lean PMO - Oxymoron or Possible - SDEC'12 (20)

PDF
Lean pmo oxymoron or possible - potsdam
PDF
Being agile while standing in a waterfall pm connect
PDF
Being agile while standing in a waterfall pm connect
PDF
Lean project management oxymoron or possible - ottawa - apr 2013
PDF
Human Process Engineering
PDF
I don't do Agile, I AM Agile!
PDF
Lean PMO in everyday agile
PDF
Licg Profile 2010 Rev5
PDF
Offering Booklet Draft - Generic
PDF
Smiling Lean Office Introduction (Eng Version)
PDF
20150114_Jan 14 Board Work Session Pre-Read -why process improvement_Final
PPTX
Lean project management
PPTX
Lean Software 101
PDF
Lean Project Management
PDF
Cc Concepts Presentation Of Services
PPTX
Program Management Office Lean Software Development and Six Sigma
PPTX
LEAN Practices
PDF
Lean thinking and the agile culture
PPTX
Shift Left and Lean techniques for Agile Software Development
Lean pmo oxymoron or possible - potsdam
Being agile while standing in a waterfall pm connect
Being agile while standing in a waterfall pm connect
Lean project management oxymoron or possible - ottawa - apr 2013
Human Process Engineering
I don't do Agile, I AM Agile!
Lean PMO in everyday agile
Licg Profile 2010 Rev5
Offering Booklet Draft - Generic
Smiling Lean Office Introduction (Eng Version)
20150114_Jan 14 Board Work Session Pre-Read -why process improvement_Final
Lean project management
Lean Software 101
Lean Project Management
Cc Concepts Presentation Of Services
Program Management Office Lean Software Development and Six Sigma
LEAN Practices
Lean thinking and the agile culture
Shift Left and Lean techniques for Agile Software Development

More from Mike Edwards (13)

PDF
So you want change lets talk fear - agile tdusa
PDF
Bullshit stop telling me it's impossible
PDF
Bullsh*t stop telling me it's impossible
PDF
Leading for Change
PDF
Leading for change
PDF
Value from meh to wow
PDF
Shifting value into high gear
PDF
Shifting value into high gear
PDF
Responsibility at the core of great things
PDF
Being agile while standing in a waterfall
PDF
Being agile while standing in a waterfall
PDF
Being agile while standing in a waterfall
PDF
Lean project mgmt oxymoron or possible - toronto xp - may 2013
So you want change lets talk fear - agile tdusa
Bullshit stop telling me it's impossible
Bullsh*t stop telling me it's impossible
Leading for Change
Leading for change
Value from meh to wow
Shifting value into high gear
Shifting value into high gear
Responsibility at the core of great things
Being agile while standing in a waterfall
Being agile while standing in a waterfall
Being agile while standing in a waterfall
Lean project mgmt oxymoron or possible - toronto xp - may 2013

Recently uploaded (20)

PDF
Types of control:Qualitative vs Quantitative
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PDF
Roadmap Map-digital Banking feature MB,IB,AB
DOCX
Euro SEO Services 1st 3 General Updates.docx
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PDF
How to Get Funding for Your Trucking Business
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PPT
Chapter four Project-Preparation material
PDF
Laughter Yoga Basic Learning Workshop Manual
PPTX
5 Stages of group development guide.pptx
PPTX
Business Ethics - An introduction and its overview.pptx
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PPTX
Amazon (Business Studies) management studies
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
Chapter 5_Foreign Exchange Market in .pdf
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
Types of control:Qualitative vs Quantitative
340036916-American-Literature-Literary-Period-Overview.ppt
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
Roadmap Map-digital Banking feature MB,IB,AB
Euro SEO Services 1st 3 General Updates.docx
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
How to Get Funding for Your Trucking Business
Reconciliation AND MEMORANDUM RECONCILATION
COST SHEET- Tender and Quotation unit 2.pdf
Chapter four Project-Preparation material
Laughter Yoga Basic Learning Workshop Manual
5 Stages of group development guide.pptx
Business Ethics - An introduction and its overview.pptx
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
DOC-20250806-WA0002._20250806_112011_0000.pdf
Amazon (Business Studies) management studies
WRN_Investor_Presentation_August 2025.pdf
Chapter 5_Foreign Exchange Market in .pdf
unit 1 COST ACCOUNTING AND COST SHEET

Lean PMO - Oxymoron or Possible - SDEC'12

  • 1. Lean PMO Oxymoron or Possible? Mike Edwards SDEC 2012 Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 2. Which resembles your projects? Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 3. Agenda • Introduction to Lean • Step through the assessment model & take the assessment • Interact and share our experiences • What do the results tell us? • Next steps! Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 4. Introductions! Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 5. This is Lean! Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 6. Optimizing Eliminating the whole Waste This is Lean! High Product Integrity Value Always Learning Team & People Always Focus Delivering Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 7. Why another model?!? • Iterative approaches produce better outcomes • Build-Measure-Learn (Eric Ries - Lean Startup) • Plan-Do-Check-Act (Deming) • Observe-Orient-Decide-Act (John Boyd) • Higher value from quick iterations (aka Fail Fast!) • Need something light weight • Less costly approach to suit the times • Experience shows we can learn a lot in one day Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 8. Assessment Model Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 9. Assessment Model They’re People People’s not Resources! Satisfaction Business risk, schedule and cost Quality pressure Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 10. Assessment Model They’re People People’s not Resources! Satisfaction Business risk, schedule and cost Quality pressure Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 11. Assessment Model They’re People People People’s not Resources! Satisfaction Process Product Business risk, schedule and cost Quality pressure Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 12. Assessment Model They’re People People People’s not Resources! Satisfaction Process Product Business risk, schedule and cost Quality pressure Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 13. People Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 14. People All people impacted by or who interact with your project Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 15. People Master Leadership Servant Disempowered Ownership Empowered Exclusive Collaboration Inclusive Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 16. Take the survey! Answer the People section of the survey Plot the three items on the chart and connect the dots Discuss the outcome with your neighbour Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 17. Process Focus on how you use a process Don’t focus on what process is used Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 18. Process Once Improving Ongoing Established Process Evolving Rigid Application Scaled Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 19. Take the survey! Answer the Process section of the survey Plot the three items on the chart and connect the dots Discuss the outcome with your neighbour Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 20. Product Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 21. Product IT organizations only exists to deliver valuable products & tools to enable our customers to succeed Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 22. Product Control Response to change Respond Project Achievement Focus Customer Defined Product Definition Learned Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 23. Take the survey! Answer the Product section of the survey Plot the three items on the chart and connect the dots Discuss the outcome with your neighbour Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 24. What do the results tell us? Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 25. Assessment Model They’re People People People’s not Resources! Satisfaction Process Product Business risk, schedule and cost Quality pressure Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 26. Assessment Model They’re People People People’s not Resources! Satisfaction Process Product Business risk, schedule and cost Quality pressure Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 27. Assessment Model They’re People People People’s not Resources! Satisfaction Process Product Business risk, schedule and cost Quality pressure Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 28. Where to from here? Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 29. What now? • The assessment is only the start • Listen to the people • Everyone must commit to an improvement program • Measure outcomes • For best results - get help! Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12
  • 30. http://leanpmsolutions.ca/the-lean-pmo-is-possible/ Copyright Lean PM Solutions Inc - October 2012 Sunday, 28 October, 12