TRANSFORMING EXISTING 220 kV D/C LINE INTO
400 kV S/C LINE (TWIN CONDUCTORS)
CASE STUDY TOWARDS THE ENQUIRY FLOATED BY
RELIANCE INFRASTRUCTURE
SUPREME & CO. PVT. LTD.
P-200, BENARAS ROAD, HOWRAH -711108, WEST BENGAL, INDIA
Phone : +91-033-26516701 TO 05
Fax : +91-033-26516706
Email : sales@supreme.in & info@supreme.in
Website : www.supreme.in
1
WHY UPRATING / UPGRADING
IS REQUIRED ?
Existing and planned infrastructures have made it
extremely difficult to build new transmission line to
meet the electricity demand-supply gap.
It becomes highly pertinent to uprate or upgrade the
already existing line rather than constructing new
transmission line.2
PROCEDURE
System study
Analysis
Design and validation
Implementation
3
SYSTEM STUDY
 Study on existing power transmission system for
selecting the optimum solution.
 Conceptual study for optimal solution regarding
the upgrading of the existing 220 kV double
circuit transmission line corridor.
4
ANALYSIS OF SYSTEM
Identify an optimum alternative to upgrade the
transmission line corridor.
Evaluate the performance of the power
transmission system.
Investigating the capability of existing towers and
foundations to withstand new mechanical
loadings.
Undertake financial analysis for most promising
alternative.
Estimate cost of various alternatives.5
 Possible configurations are indicated towards the preliminary
study conducted over the data available for existing towers [1].
POSSIBLE CONFIGURATIONS
6
Technical
advantages
No new land
acquisition cost
Cost of erection is
minimized
Minimize
environmental
restriction
Reduces cost of
maintenance
Visually aesthetics
Foot print remains
the same*
* If the foundation has to be strengthened, there may be a mere increase in fo7
INCREASING POWER RATING
Power in a circuit is increased by:
 Uprating (increase in current flow).
 Upgrading (increase in voltage level).
 Both upgrading and uprating.
 Surge impedance loading.
8
UPRATING
 Line modification that yields increase in current flow
limits is known as uprating [2].
 Conductors are normally operated below the thermal
rating of the line.
 Current flow is increased to operate the conductor
closer to its thermal limit.
 Reconductoring the line with HTLS conductor is one
of the solutions.
9
HIGH PERFORMANCE
CONDUCTOR
 Carbon fibre core
 High operating temperature
 Ampacity twice as that of ACSR.
 Low sag.
 Higher Aluminium content.
 Resistance comparatively low.
10
HIGH PERFORMANCE
CONDUCTOR FITTINGS
Supreme has developed and
conducted electrical tests on
conductor fittings, specifically
designed for HTLS conductors.
Since HTLS conductors
operate at higher
temperature, they require
special type of clamps and
fittings.
11
LINE UPGRADING
Modifications that allow operation at higher voltage
level.
Results in higher increase in power flow, compared to
uprating.
Percentage voltage drop decreases.
Need to replace substation equipments.
Maintaining the electrical clearance increase as per
the voltage rating by reconfiguring insulator and12
FACTORS TO BE CONSIDERED FOR
LINE UPGRADING
Electrical Clearance.
RoW acquisition (may be required in exceptional
cases).
Civil and structural modifications (may be required).
Mitigation of Corona and Radio Interference Voltage
(RIV).
13
CLEARANCES FOR 400 kV
AC Nominal Voltage 400 kV
Minimum clearance above ground
8.84 m
Minimum live metal clearance
2.6 m
Minimum phase to phase clearance
3.9 m
Angle of shield (maximum)
200
Minimum mid span clearance
9 m
14
METHODS ADOPTED FOR
UPGRADING
Insulated Crossarms
Inter Phase Spacers
Intermediate Structures
Change of Conductor and Earthwire
15
PRINCIPLE OF AN
INSULATOR
 Freedom of movement provided
to the conductor determines the
clearance required for the line
[3].
 Clearance should be provided
for both inward and outward
swing of the conductor.
 For a suspension insulator,
freedom of movement is very
high and hence more clearance
will be required.
16
INSULATED CROSSARM
 Insulated crossarms are polymer
insulators that directly fixed to the
tower [4].
 This eliminates the use of metallic
crossarm.
 With the freedom of movement
restricted, the conductors swing
will be reduced significantly.
 This reduces the required live -
metal clearance level and thus
making the line compact.
17
INTER PHASE SPACERS
 Inter Phase Spacers are used to
maintain phase to phase
clearance even under high wind
condition.
 This reduces short circuit
problems encountered in many
high voltage lines.
 Composite insulators which has
high strength to weight ratio are
mainly used as inter phase
spacer.18
INTERMEDIATE STRUCTURE
If an intermediate structure is
needed after final analysis, we
could opt the use of monopoles.
Monopoles will require lesser foot
print when compared with a lattice
tower.
Foot print can be restricted as per
the availability of space
19
DISCONNECTION OF EXISTING LINK
DURING UPGRADING
Line shutdown is required for
making the erection works.
Temporary towers, supported by
guy wires without civil foundations,
can be installed in parallel with
existing line.
Line will be disconnected only at
the time of by-passing.
Power outage will only be in the20
Conductor type ACSR
Code name Moose
Diameter 31.77 mm
Area 597 sq mm
Weight 2.004 kg/m
UTS 16438 kgf
CONDUCTOR DETAILS
21
CORONA INCEPTION VALUE
The voltage gradient necessary to produce corona at the
conductor surface is given by,
𝐸0 = 30 ∗ 𝑚 1 +
0.301
𝑟
where
r : radius of the conductor and
m : surface irregularity factor
For example, consider Moose conductor with radius 1.5885
cm and surface irregularity factor, m= 0.80
We get, E0 = 30.76 kV/cm.
Beyond or near this value, the conductor has corona effect.
22
CALCULATION FOR CONDUCTOR
SURFACE GRADIENT:
The conductor surface gradient is calculated from the following
equation [5]:
E = (V/√3)*(b/(r*ln ((a/Re)*2h/ √(4h2+a2))))
where
E : conductor surface voltage gradient (kV/cm)
V : line voltage (kV)
b : factor for multiple conductors
r : radius of conductor (cm)
R : outside radius of bundle (cm)
Re : equivalent radius of bundle conductor (cm)
S : distance between component conductor centers (cm)
a : phase spacing (cm)
h : height of conductor above ground (cm)
n : number of component conductors in bundle
23
FOR SINGLE CONDUCTOR FOR TWIN CONDUCTOR
Number of Conductors in Bundle: 1 Number of Conductors in Bundle: 2
Rated Voltage: 400 kV Rated Voltage: 400 kV
Phase Spacing: 390 cm Phase Spacing: 390 cm
Height of Conductor above Ground: 884 cm Height of Conductor above Ground: 884 cm
Voltage Gradient E = 26.5316 kV/cm Voltage Gradient E = 20.4383 kV/cm
Distance between Component Conductors:
Conductors: 45 cm
R =22.5000 cm
Re = 8.0246 cm
β = 0.5318
RESULTS OF CORONA CALCULATION
24
SAG-TENSION CALCULATION
SPAN: 335 m; WIND ZONE: 3; TERRAIN CATEGORY: 1
LOADING CONDITION SAG (m) TENSION (kgf)
Initial Condition 7.664 2983.640
48° C Full Wind 5.805 3939.268
48° C 28% Wind 8.192 2791.232
48° C No Wind 8.613 2654.896
85° C Full Wind 6.585 3472.508
85° C 28% Wind 9.517 2402.742
85° C No Wind 10.039 2277.604
25
RESULTS FROM TECHNICAL AND
FINANCIAL EVALUATION
Costs are substantially reduced when compared with
the costs of a new 400 kV OHL.
No land or right of way acquisition is necessary for
project implementation compared with the new line
solution.
Minimum environmental impact.
26
REFERENCES
1. D. Marginean, E. Mateescu, H.S. Wechsler, G.
Florea, C. Matea, “Transforming Existing 220 kV
Double Circuit Line into 400 kV Single Circuit Line
in Romania”, IEEE- 2011.
2. Manual on Transmission Line, CBIP, 2014.
3. EPRI Transmission Line Reference Book—115-345
kV Compact Line Design, “The Blue Book”, 2008.
4. K. Papailiou, F. Schmuck, “Silicone Composite
Insulators: Materials, Design, Applications”,
Springer, 2012.
5. Cigre Green Book on Overhead Lines, 2014.
27
THANK YOU
SUPREME & CO. PVT. LTD.
P-200, BENARAS ROAD, HOWRAH -711108, WEST BENGAL, INDIA
Phone : +91-033-26516701 TO 05
Fax : +91-033-26516706
Email : sales@supreme.in & info@supreme.in
Website : www.supreme.in
28

More Related Content

PPT
Power systems (2)
PDF
Power system slide notes
PDF
Rural electrification
PDF
PPTX
Distribution system 2
PPSX
Akt tl design01
PPTX
Ehv line design
PPTX
Mechanical Design of Transmission Line (In context of Nepal)
Power systems (2)
Power system slide notes
Rural electrification
Distribution system 2
Akt tl design01
Ehv line design
Mechanical Design of Transmission Line (In context of Nepal)

What's hot (18)

PPT
Substation overview
PDF
Principles of Cable Sizing
PPT
Lec transmission line
DOCX
Electrical testing
PDF
Construction EHV Transmission Line
PDF
Mitsubishi - substation insulation coordination studies-sparacino
PDF
Le.h insulation coordination - Digsilent
PPT
Electrical Systems Safety
PDF
The sheath voltage_limiter
PPT
Problems in overhead transmission line
PPTX
Chapter 3 transmission line performance
PPTX
High voltage transmission
PDF
DOCX
EHV AC
PDF
Substation grounding grid design using Alternative Transients Program-ATP and...
PPTX
Transmission Line
PPTX
Bundle conductors in transmission line
Substation overview
Principles of Cable Sizing
Lec transmission line
Electrical testing
Construction EHV Transmission Line
Mitsubishi - substation insulation coordination studies-sparacino
Le.h insulation coordination - Digsilent
Electrical Systems Safety
The sheath voltage_limiter
Problems in overhead transmission line
Chapter 3 transmission line performance
High voltage transmission
EHV AC
Substation grounding grid design using Alternative Transients Program-ATP and...
Transmission Line
Bundle conductors in transmission line
Ad

Viewers also liked (20)

PPT
Cerc slideshow
PPT
ABT a complete report and a case study
PDF
Sf6 gas properties
PPTX
Training report on 400 kV GSS
PDF
Power grid corporation of india ltd
PPTX
Performance of 400 kv line insulators under pollution.
PDF
Micro-Grid Power: Working Intelligently and Working Together
PPSX
ABT-UI & Deviation Settlement Mechanism (DSM)
PPTX
Smart Microgrids: Overview and Outlook
PPTX
SF6 circuit breaker
PPTX
Visit to 400 kV substation, Hadala
PPS
SF6 CIRCUIT BREAKER
PPTX
1.substation layouts
PPT
Solar water pumping_solution
PPTX
SF6 Circuit breaker by Khalid, NIT Warangal 2014 Batch
PPT
Generator protection by bhushan kumbhalkar
PPT
Microgrid
PPTX
Powergrid Corporation India Limited industrial training
PPTX
Microgrid Presentation
PPT
protection of transmission lines[distance relay protection scheme]
Cerc slideshow
ABT a complete report and a case study
Sf6 gas properties
Training report on 400 kV GSS
Power grid corporation of india ltd
Performance of 400 kv line insulators under pollution.
Micro-Grid Power: Working Intelligently and Working Together
ABT-UI & Deviation Settlement Mechanism (DSM)
Smart Microgrids: Overview and Outlook
SF6 circuit breaker
Visit to 400 kV substation, Hadala
SF6 CIRCUIT BREAKER
1.substation layouts
Solar water pumping_solution
SF6 Circuit breaker by Khalid, NIT Warangal 2014 Batch
Generator protection by bhushan kumbhalkar
Microgrid
Powergrid Corporation India Limited industrial training
Microgrid Presentation
protection of transmission lines[distance relay protection scheme]
Ad

Similar to Line upgrade (20)

PPTX
SWITCHYARD ELECTRICAL SUBSTATION PRESENTATION.pptx
PDF
Wireless Power Transfer Project
PDF
WIRELESS POWER TRANSMISSION Project
PDF
System Studies on interaction of HTS cables with power grids
PDF
800-kV-TL-Design.pdfvvvvvvvvvv vvvvvbvbbbbbbbbb
PPT
Transmission Line presentation______.ppt
PPTX
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
PDF
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
PPTX
ELECTRICAL POWER TRANSMISSION-3.pptx
PPTX
Busduct___Busbar.pptx
PDF
HTLS conductor requirements PGCIL ppt.pdf
PPT
transmission line
PDF
Darkawi_et_al_CEIDP_2012_VF_IEEE
PPTX
High Voltage Direct Current(Hvdc) transmission
PDF
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
PPTX
Concept of energy transmission & distribution
PDF
Nexans high-voltage.pdf
PPT
Eee 465 ppt 1
PPTX
Thermal power plant working
PDF
Effect of the Cable Capacitance of Long Control Cables on the Actuation of Co...
SWITCHYARD ELECTRICAL SUBSTATION PRESENTATION.pptx
Wireless Power Transfer Project
WIRELESS POWER TRANSMISSION Project
System Studies on interaction of HTS cables with power grids
800-kV-TL-Design.pdfvvvvvvvvvv vvvvvbvbbbbbbbbb
Transmission Line presentation______.ppt
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
ELECTRICAL POWER TRANSMISSION-3.pptx
Busduct___Busbar.pptx
HTLS conductor requirements PGCIL ppt.pdf
transmission line
Darkawi_et_al_CEIDP_2012_VF_IEEE
High Voltage Direct Current(Hvdc) transmission
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
Concept of energy transmission & distribution
Nexans high-voltage.pdf
Eee 465 ppt 1
Thermal power plant working
Effect of the Cable Capacitance of Long Control Cables on the Actuation of Co...

More from Harish Agarwal (17)

PPTX
Aerial fibre optics
PPTX
Line upgrade
PPTX
Monopole
PPTX
Koshika cause & impact kolkata meetings 16.01.18
PPTX
Covered conductor
PPTX
Line upgrade
PPTX
Fittings for lv abc
PPTX
Covered conductor
PPTX
Harish aggarwal
PPTX
Case study sterlite deadend grip
PPTX
PPTX
Innovative solution for line uprating
PPTX
Pole type structures
PPTX
Innovative solution for line uprating
PDF
Effect of GST in solar industry
PPT
Development and testing of ipc
PPT
INTER PHASE SPACERS
Aerial fibre optics
Line upgrade
Monopole
Koshika cause & impact kolkata meetings 16.01.18
Covered conductor
Line upgrade
Fittings for lv abc
Covered conductor
Harish aggarwal
Case study sterlite deadend grip
Innovative solution for line uprating
Pole type structures
Innovative solution for line uprating
Effect of GST in solar industry
Development and testing of ipc
INTER PHASE SPACERS

Recently uploaded (20)

PPTX
IITM - FINAL Option - 01 - 12.08.25.pptx
PPTX
Chapter 2 strategic Presentation (6).pptx
PDF
Value-based IP Management at Siemens: A Cross-Divisional Analysis
PPTX
Portfolio Example- Market & Consumer Insights – Strategic Entry for BYD UK.pptx
PDF
Vinod Bhatt - Most Inspiring Supply Chain Leader in India 2025.pdf
PDF
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
PDF
Sustainable Digital Finance in Asia_FINAL_22.pdf
PPTX
BUSINESS CYCLE_INFLATION AND UNEMPLOYMENT.pptx
PPTX
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
DOCX
Handbook of entrepreneurship- Chapter 7- Types of business organisations
PPTX
operations management : demand supply ch
DOCX
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
PDF
Communication Tactics in Legal Contexts: Historical Case Studies (www.kiu.ac...
PDF
HQ #118 / 'Building Resilience While Climbing the Event Mountain
PDF
Stacey L Stevens - Canada's Most Influential Women Lawyers Revolutionizing Th...
PDF
Middle East's Most Impactful Business Leaders to Follow in 2025
DOCX
Hand book of Entrepreneurship 4 Chapters.docx
PDF
Business Communication for MBA Students.
PPTX
Project Management_ SMART Projects Class.pptx
IITM - FINAL Option - 01 - 12.08.25.pptx
Chapter 2 strategic Presentation (6).pptx
Value-based IP Management at Siemens: A Cross-Divisional Analysis
Portfolio Example- Market & Consumer Insights – Strategic Entry for BYD UK.pptx
Vinod Bhatt - Most Inspiring Supply Chain Leader in India 2025.pdf
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
Sustainable Digital Finance in Asia_FINAL_22.pdf
BUSINESS CYCLE_INFLATION AND UNEMPLOYMENT.pptx
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
Handbook of entrepreneurship- Chapter 7- Types of business organisations
operations management : demand supply ch
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
Communication Tactics in Legal Contexts: Historical Case Studies (www.kiu.ac...
HQ #118 / 'Building Resilience While Climbing the Event Mountain
Stacey L Stevens - Canada's Most Influential Women Lawyers Revolutionizing Th...
Middle East's Most Impactful Business Leaders to Follow in 2025
Hand book of Entrepreneurship 4 Chapters.docx
Business Communication for MBA Students.
Project Management_ SMART Projects Class.pptx

Line upgrade

  • 1. TRANSFORMING EXISTING 220 kV D/C LINE INTO 400 kV S/C LINE (TWIN CONDUCTORS) CASE STUDY TOWARDS THE ENQUIRY FLOATED BY RELIANCE INFRASTRUCTURE SUPREME & CO. PVT. LTD. P-200, BENARAS ROAD, HOWRAH -711108, WEST BENGAL, INDIA Phone : +91-033-26516701 TO 05 Fax : +91-033-26516706 Email : sales@supreme.in & info@supreme.in Website : www.supreme.in 1
  • 2. WHY UPRATING / UPGRADING IS REQUIRED ? Existing and planned infrastructures have made it extremely difficult to build new transmission line to meet the electricity demand-supply gap. It becomes highly pertinent to uprate or upgrade the already existing line rather than constructing new transmission line.2
  • 4. SYSTEM STUDY  Study on existing power transmission system for selecting the optimum solution.  Conceptual study for optimal solution regarding the upgrading of the existing 220 kV double circuit transmission line corridor. 4
  • 5. ANALYSIS OF SYSTEM Identify an optimum alternative to upgrade the transmission line corridor. Evaluate the performance of the power transmission system. Investigating the capability of existing towers and foundations to withstand new mechanical loadings. Undertake financial analysis for most promising alternative. Estimate cost of various alternatives.5
  • 6.  Possible configurations are indicated towards the preliminary study conducted over the data available for existing towers [1]. POSSIBLE CONFIGURATIONS 6
  • 7. Technical advantages No new land acquisition cost Cost of erection is minimized Minimize environmental restriction Reduces cost of maintenance Visually aesthetics Foot print remains the same* * If the foundation has to be strengthened, there may be a mere increase in fo7
  • 8. INCREASING POWER RATING Power in a circuit is increased by:  Uprating (increase in current flow).  Upgrading (increase in voltage level).  Both upgrading and uprating.  Surge impedance loading. 8
  • 9. UPRATING  Line modification that yields increase in current flow limits is known as uprating [2].  Conductors are normally operated below the thermal rating of the line.  Current flow is increased to operate the conductor closer to its thermal limit.  Reconductoring the line with HTLS conductor is one of the solutions. 9
  • 10. HIGH PERFORMANCE CONDUCTOR  Carbon fibre core  High operating temperature  Ampacity twice as that of ACSR.  Low sag.  Higher Aluminium content.  Resistance comparatively low. 10
  • 11. HIGH PERFORMANCE CONDUCTOR FITTINGS Supreme has developed and conducted electrical tests on conductor fittings, specifically designed for HTLS conductors. Since HTLS conductors operate at higher temperature, they require special type of clamps and fittings. 11
  • 12. LINE UPGRADING Modifications that allow operation at higher voltage level. Results in higher increase in power flow, compared to uprating. Percentage voltage drop decreases. Need to replace substation equipments. Maintaining the electrical clearance increase as per the voltage rating by reconfiguring insulator and12
  • 13. FACTORS TO BE CONSIDERED FOR LINE UPGRADING Electrical Clearance. RoW acquisition (may be required in exceptional cases). Civil and structural modifications (may be required). Mitigation of Corona and Radio Interference Voltage (RIV). 13
  • 14. CLEARANCES FOR 400 kV AC Nominal Voltage 400 kV Minimum clearance above ground 8.84 m Minimum live metal clearance 2.6 m Minimum phase to phase clearance 3.9 m Angle of shield (maximum) 200 Minimum mid span clearance 9 m 14
  • 15. METHODS ADOPTED FOR UPGRADING Insulated Crossarms Inter Phase Spacers Intermediate Structures Change of Conductor and Earthwire 15
  • 16. PRINCIPLE OF AN INSULATOR  Freedom of movement provided to the conductor determines the clearance required for the line [3].  Clearance should be provided for both inward and outward swing of the conductor.  For a suspension insulator, freedom of movement is very high and hence more clearance will be required. 16
  • 17. INSULATED CROSSARM  Insulated crossarms are polymer insulators that directly fixed to the tower [4].  This eliminates the use of metallic crossarm.  With the freedom of movement restricted, the conductors swing will be reduced significantly.  This reduces the required live - metal clearance level and thus making the line compact. 17
  • 18. INTER PHASE SPACERS  Inter Phase Spacers are used to maintain phase to phase clearance even under high wind condition.  This reduces short circuit problems encountered in many high voltage lines.  Composite insulators which has high strength to weight ratio are mainly used as inter phase spacer.18
  • 19. INTERMEDIATE STRUCTURE If an intermediate structure is needed after final analysis, we could opt the use of monopoles. Monopoles will require lesser foot print when compared with a lattice tower. Foot print can be restricted as per the availability of space 19
  • 20. DISCONNECTION OF EXISTING LINK DURING UPGRADING Line shutdown is required for making the erection works. Temporary towers, supported by guy wires without civil foundations, can be installed in parallel with existing line. Line will be disconnected only at the time of by-passing. Power outage will only be in the20
  • 21. Conductor type ACSR Code name Moose Diameter 31.77 mm Area 597 sq mm Weight 2.004 kg/m UTS 16438 kgf CONDUCTOR DETAILS 21
  • 22. CORONA INCEPTION VALUE The voltage gradient necessary to produce corona at the conductor surface is given by, 𝐸0 = 30 ∗ 𝑚 1 + 0.301 𝑟 where r : radius of the conductor and m : surface irregularity factor For example, consider Moose conductor with radius 1.5885 cm and surface irregularity factor, m= 0.80 We get, E0 = 30.76 kV/cm. Beyond or near this value, the conductor has corona effect. 22
  • 23. CALCULATION FOR CONDUCTOR SURFACE GRADIENT: The conductor surface gradient is calculated from the following equation [5]: E = (V/√3)*(b/(r*ln ((a/Re)*2h/ √(4h2+a2)))) where E : conductor surface voltage gradient (kV/cm) V : line voltage (kV) b : factor for multiple conductors r : radius of conductor (cm) R : outside radius of bundle (cm) Re : equivalent radius of bundle conductor (cm) S : distance between component conductor centers (cm) a : phase spacing (cm) h : height of conductor above ground (cm) n : number of component conductors in bundle 23
  • 24. FOR SINGLE CONDUCTOR FOR TWIN CONDUCTOR Number of Conductors in Bundle: 1 Number of Conductors in Bundle: 2 Rated Voltage: 400 kV Rated Voltage: 400 kV Phase Spacing: 390 cm Phase Spacing: 390 cm Height of Conductor above Ground: 884 cm Height of Conductor above Ground: 884 cm Voltage Gradient E = 26.5316 kV/cm Voltage Gradient E = 20.4383 kV/cm Distance between Component Conductors: Conductors: 45 cm R =22.5000 cm Re = 8.0246 cm β = 0.5318 RESULTS OF CORONA CALCULATION 24
  • 25. SAG-TENSION CALCULATION SPAN: 335 m; WIND ZONE: 3; TERRAIN CATEGORY: 1 LOADING CONDITION SAG (m) TENSION (kgf) Initial Condition 7.664 2983.640 48° C Full Wind 5.805 3939.268 48° C 28% Wind 8.192 2791.232 48° C No Wind 8.613 2654.896 85° C Full Wind 6.585 3472.508 85° C 28% Wind 9.517 2402.742 85° C No Wind 10.039 2277.604 25
  • 26. RESULTS FROM TECHNICAL AND FINANCIAL EVALUATION Costs are substantially reduced when compared with the costs of a new 400 kV OHL. No land or right of way acquisition is necessary for project implementation compared with the new line solution. Minimum environmental impact. 26
  • 27. REFERENCES 1. D. Marginean, E. Mateescu, H.S. Wechsler, G. Florea, C. Matea, “Transforming Existing 220 kV Double Circuit Line into 400 kV Single Circuit Line in Romania”, IEEE- 2011. 2. Manual on Transmission Line, CBIP, 2014. 3. EPRI Transmission Line Reference Book—115-345 kV Compact Line Design, “The Blue Book”, 2008. 4. K. Papailiou, F. Schmuck, “Silicone Composite Insulators: Materials, Design, Applications”, Springer, 2012. 5. Cigre Green Book on Overhead Lines, 2014. 27
  • 28. THANK YOU SUPREME & CO. PVT. LTD. P-200, BENARAS ROAD, HOWRAH -711108, WEST BENGAL, INDIA Phone : +91-033-26516701 TO 05 Fax : +91-033-26516706 Email : sales@supreme.in & info@supreme.in Website : www.supreme.in 28