METHOD STATEMENT 
Table of contents 
of 
LEAN CONCRETE 
for 
BUILDING WORKS
1. General. 
2. Sequence of works. 
3. Backfill or excavate to the design level 
4. Formwork design. 
5. Placing of concrete. 
6. Compaction of concrete. 
7. Curing 
8. Dewatering 
9. Electricity 
10.Equipment & Manpower 
Appendix 
A. Plan of three main building 
B. Formwork design & Typical of filling materials 
1. General 
This method statement describe how we construct lean concrete for Building Works
Pleased refer to Appendix A for the plan of three main buildings. 
This method statement covers for the lean concrete of all Building Works. The filling 
material under lean concrete may be varied in difference location. 
Concrete class shall be approved ready-mix concrete B7.5 (Grade 15NM/m2) 
Excavation or Backfilling 
to Design Level 
2. Sequence of works. 
Leveling & Compaction 
Setting Formworks 
Placing lean concrete 
Curing for Concrete 
3. Backfill or Excavate to the design level 
Excavation works will be carried out by manpower or by backhoe depend on soil 
condition. 
Backfilling works will carry out layer by layer. Thickness of each layer is not more than 
300mm.
a) Filling under piles cap of the building have piling foundation 
Material using for backfilling works will be existing soil on site area or other approved 
material if the existing soil is not enough. 
b) Filling under directed foundation 
The ground will be excavated up to soil treatment level, and then backfill up to design 
level following approved design & material. Design of sub layer and proposed material 
shall be submit separately. 
Please refer to Appendix B for typical of filling material. 
4. Formworks Design 
After finish leveling and compaction works, formwork will be set out. 
Please refer to Appendix B for formworks design. 
Timber or steel will be used for formwork. 
5. Placing of Concrete 
Approved ready-mix concrete will transported from batching plant to the site by mixer 
truck. 
From mixer truck concrete will be delivered to casting location by bucket & wheel barrow 
then pour out by showel or directly to the position. 
6. Compaction of Concrete. 
Concrete after pouring to position shall compacted by immersion vibrator. 
7. Curing. 
Curing of concrete will be carried out by spraying water periodically to the surface of the 
newly placed concrete. 
8. Dewatering 
Two nos of water pump (one for spare) shall be arranged on site with enough hose 
9. Electricity 
Electricity will supplied by stand by generator on site.
10. Equipment & Manpower 
a)Equipment 
Equipment Unit Quantity 
Mixer truck Nos 02 
Tamping Ramer No 01 
Vibrator Nos 02 
Wheel barrow Nos 05 
Water Pump 2 HP No 01 
Water Pump 1HP No 01 
Generator 15KVA No 01 
Generator 10KVA Nos 02 
Bucket Nos 10 
Showel Nos 05 
Trowel Nos 05 
b)Equipment 
Description Unit Quantity 
Supervisor No 01 
Surveyor Nos 02 
Foreman No 01 
Electrician No 01 
Worker Nos 08
APPENDIX A
FOUNDATION PLAN OF THREE MAIN BUILDING
APPENDIX B 
FORMWORK DESIGN & TYPICAL OF FILLING 
MATERIAL

More Related Content

DOCX
495265750-Hydro-Test-Procedure.docx
PPTX
Chapter 4 (a) stone masonry
PPTX
Repair techniques : Grouting (RR&S)
PDF
10 Things your Audience Hates About your Presentation
DOCX
Method statement tank base concrete pouring
PPTX
Production of concrete
PDF
Ms for-mechanical-piping-system-installation-work
PPTX
Lecture slides4; Construction Project Planning
495265750-Hydro-Test-Procedure.docx
Chapter 4 (a) stone masonry
Repair techniques : Grouting (RR&S)
10 Things your Audience Hates About your Presentation
Method statement tank base concrete pouring
Production of concrete
Ms for-mechanical-piping-system-installation-work
Lecture slides4; Construction Project Planning

What's hot (20)

DOC
Method statement for structural concrete repair rev.0
PDF
Ms for concrete repairing
DOC
Column & beam
DOCX
02 - Method Statement for Concrete pouring.docx
DOCX
Method statement honycomb repairing
PDF
Method statement for civil works
DOC
Piling work method statement cm- ms- bw - 002
DOC
Building work method statement cm - ms- bw - 001
PPT
Cofferdam
DOC
Concrete method rev02
PDF
Construction Methods & Sequence
PPTX
Construction process''column,beam,slab''
DOC
Method statement for repair of concrete surface
PDF
ERECTION METHOD STATEMENT
DOC
Excavation method rectified 13-11-2010
DOC
Itp civil
PPT
Boq piling works
DOCX
Method statement for structure excavation
PPTX
Construction of substructure
PDF
SMM7 Bill of Quantities
Method statement for structural concrete repair rev.0
Ms for concrete repairing
Column & beam
02 - Method Statement for Concrete pouring.docx
Method statement honycomb repairing
Method statement for civil works
Piling work method statement cm- ms- bw - 002
Building work method statement cm - ms- bw - 001
Cofferdam
Concrete method rev02
Construction Methods & Sequence
Construction process''column,beam,slab''
Method statement for repair of concrete surface
ERECTION METHOD STATEMENT
Excavation method rectified 13-11-2010
Itp civil
Boq piling works
Method statement for structure excavation
Construction of substructure
SMM7 Bill of Quantities
Ad

Similar to Method stm lean concrete (20)

DOC
Concreting of super structure
PDF
civil enginnering industrial training report
PDF
civil enginnering industrial training report
DOCX
Site visit report
PPT
07. BRIDGE CONSTRUCTION METHODS Precast bridge construction
PPTX
kuku.pptx
PDF
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
DOCX
Bored cast insitu
PPTX
Ppt of design of dams
PPT
BFC 31802 Chapter 4a - Copy.ppt
PPT
Construction basic SIP
PDF
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
PDF
Water proofing treatement
PDF
Irs concrete bridge code
PPT
concrete materials in constructions .ppt
PPTX
accelerated bridge construction(ABC)
PPTX
PPTX
Final PPT internship 4th year civil .pptx
PDF
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
PPTX
Overhead transmission lines_ Foundation.pptx
Concreting of super structure
civil enginnering industrial training report
civil enginnering industrial training report
Site visit report
07. BRIDGE CONSTRUCTION METHODS Precast bridge construction
kuku.pptx
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Bored cast insitu
Ppt of design of dams
BFC 31802 Chapter 4a - Copy.ppt
Construction basic SIP
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
Water proofing treatement
Irs concrete bridge code
concrete materials in constructions .ppt
accelerated bridge construction(ABC)
Final PPT internship 4th year civil .pptx
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
Overhead transmission lines_ Foundation.pptx
Ad

Method stm lean concrete

  • 1. METHOD STATEMENT Table of contents of LEAN CONCRETE for BUILDING WORKS
  • 2. 1. General. 2. Sequence of works. 3. Backfill or excavate to the design level 4. Formwork design. 5. Placing of concrete. 6. Compaction of concrete. 7. Curing 8. Dewatering 9. Electricity 10.Equipment & Manpower Appendix A. Plan of three main building B. Formwork design & Typical of filling materials 1. General This method statement describe how we construct lean concrete for Building Works
  • 3. Pleased refer to Appendix A for the plan of three main buildings. This method statement covers for the lean concrete of all Building Works. The filling material under lean concrete may be varied in difference location. Concrete class shall be approved ready-mix concrete B7.5 (Grade 15NM/m2) Excavation or Backfilling to Design Level 2. Sequence of works. Leveling & Compaction Setting Formworks Placing lean concrete Curing for Concrete 3. Backfill or Excavate to the design level Excavation works will be carried out by manpower or by backhoe depend on soil condition. Backfilling works will carry out layer by layer. Thickness of each layer is not more than 300mm.
  • 4. a) Filling under piles cap of the building have piling foundation Material using for backfilling works will be existing soil on site area or other approved material if the existing soil is not enough. b) Filling under directed foundation The ground will be excavated up to soil treatment level, and then backfill up to design level following approved design & material. Design of sub layer and proposed material shall be submit separately. Please refer to Appendix B for typical of filling material. 4. Formworks Design After finish leveling and compaction works, formwork will be set out. Please refer to Appendix B for formworks design. Timber or steel will be used for formwork. 5. Placing of Concrete Approved ready-mix concrete will transported from batching plant to the site by mixer truck. From mixer truck concrete will be delivered to casting location by bucket & wheel barrow then pour out by showel or directly to the position. 6. Compaction of Concrete. Concrete after pouring to position shall compacted by immersion vibrator. 7. Curing. Curing of concrete will be carried out by spraying water periodically to the surface of the newly placed concrete. 8. Dewatering Two nos of water pump (one for spare) shall be arranged on site with enough hose 9. Electricity Electricity will supplied by stand by generator on site.
  • 5. 10. Equipment & Manpower a)Equipment Equipment Unit Quantity Mixer truck Nos 02 Tamping Ramer No 01 Vibrator Nos 02 Wheel barrow Nos 05 Water Pump 2 HP No 01 Water Pump 1HP No 01 Generator 15KVA No 01 Generator 10KVA Nos 02 Bucket Nos 10 Showel Nos 05 Trowel Nos 05 b)Equipment Description Unit Quantity Supervisor No 01 Surveyor Nos 02 Foreman No 01 Electrician No 01 Worker Nos 08
  • 7. FOUNDATION PLAN OF THREE MAIN BUILDING
  • 8. APPENDIX B FORMWORK DESIGN & TYPICAL OF FILLING MATERIAL