The document discusses four schedule execution metrics for 12 projects in July:
1) The Baseline Execution Index (BEI) measures tasks completed versus planned, and the July average was 0.96.
2) The Critical Path Length Index (CPLI) measures float availability on the critical path, and the July average was 0.97.
3) The Total Float Consumption Index (TFCI) measures the achievability of on-time completion, and the July average was 0.98.
4) The percentage of activities on the critical path was on average 8.43% for July.