Schedule Execution Metrics
2
Baseline Execution Index (BEI)
Baseline Execution Index (BEI) measures the number of tasks competed as a ratio to those tasks that should
have been completed to date (according to the original baseline). This index should be >=1.00. Average for
July is 0.96
1.04
0.96
0.96
0.99
0.95
0.96
0.95
0.97
0.95
0.89
1.02
0.85
0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
Project 7
Project 8
Project 9
Project 10
Project 11
Project 12
Baseline Execution Index (BEI)-
index
July avg: 0.96
2015 avg: 0.87
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
Baseline Execution Index (BEI)
Improvement/Erosion
BEI May BEI June BEI July Target
3
Critical Path Index (CPLI)
Critical Path Length is the number of days from time now to the early finish date of the task or milestone
representing program completion. The result is an index that measures the sufficiency of the total float available
relative to the remaining duration of the critical path. CPLI also measures the relative efficiency required to
complete the program's critical path on time. This index should be>= 1.00. Average for July is 0.97
1.00
1.07
0.70
1.00
1.00
0.98
1.17
0.81
0.89
1.01
1.02
1.00
0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
Project 7
Project 8
Project 9
Project 10
Project 11
Project 12
Critical Path Lenght Index (CPLI)-
index
July avg: 0.97
2015 avg: 0.99
0.50
0.60
0.70
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
Critical Path Lenght Index (CPLI)-index
Improvement/Erosion
CPLI May CPLI June CPLI July Target
4
Total Float Consumption Index (TFCI)
The focus of the TFCI is to provide a duration-based performance index calculating total float consumption as
an efficiency factor. The TFCI can be used to assess the achievability of the project's completion date in any
network schedule rather than just using the total float as a static indicator of projected completion. If the TFCI is
below 1.0, then the program may not complete on-time without mitigation. Average for July is 0.98
1.00
1.04
0.90
1.00
1.00
0.99
1.01
0.93
0.79
1.01
1.01
1.00
0.00 0.50 1.00 1.50
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
Project 7
Project 8
Project 9
Project 10
Project 11
Project 12
Total Float Consumption Index
(TFCI)-index
0.70
0.80
0.90
1.00
1.10
1.20
1.30
Total Float Consumption Index (TFCI)-index
Improvement/Erosion
TFCI May TFCI June TFCI July Target
July avg 0.98
2015 avg: 0.99
5
% of Activities on the Critical Path
This value represents the % of activities on the critical path, from the total number of activities on the schedule.
Ideally, this number should be less than 15%. Average for July is 8.43%
2%
5%
10%
1%
6%
11%
4%
16%
23%
8%
21%
11%
0% 5% 10% 15% 20% 25%
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
Project 7
Project 8
Project 9
Project 10
Project 11
Project 12
% of critical activities
July avg: 8.43%
2015 avg: 10.59%
0%
5%
10%
15%
20%
25%
30%
% of critical activities
Improvement/Erosion
% May % June % July Threshold
6
Trending Analysis – All Metrics
0.93
0.85
0.91
0.83 0.82
0.88
0.83 0.82
0.91
0.88
0.85 0.85
0.96
0.6
0.7
0.8
0.9
1
1.1
1.2
Baseline Execution Index (BEI)
Monthly Portfolio Average
Monthly avg Target
1.05 1.05 1.04 1.04
1
0.93
0.85
0.90
1.13
1.01 1.00
1.06
0.97
0.7
0.8
0.9
1
1.1
1.2
Critical Path Lenght Index (CPLI)
Monthly Portfolio Average
Monthly avg Threshold
1.05
1.02
1.06
1.04
0.99 0.98 0.98 0.98
1.02 1.01
0.99 1.00
0.98
0.8
0.9
1
1.1
1.2
Total Float Consumption Index
(TFCI) Monthly Portfolio Average
Monthly avg Threshold
6.0% 6.0%
10.0%
8.0%
10.0%
13.0%12.1%12.3%
9.2%
15.0%
9.0% 8.1%8.4%
0%
5%
10%
15%
20%
25%
30%
% of critical activities (%) Monthly
Portfolio Average
Monthly avg Threshold

More Related Content

PPTX
Project monitoring lecture 1
PPTX
Cost management
PDF
PPTX
Sample balanced score card for project management
PPTX
project monitoring and control
PPTX
Project monitoring activity
PDF
Odoo experience 2015 earned value management
Project monitoring lecture 1
Cost management
Sample balanced score card for project management
project monitoring and control
Project monitoring activity
Odoo experience 2015 earned value management

What's hot (20)

PPTX
Update Project Progress (MS PROJECT)
PDF
IWP Timeline
PPTX
Kpi Lister Sto 061411
PDF
4. project cost management
PPTX
Monitoring development projects
DOCX
PPSX
PPTX
Project cost control
PPTX
Revenue ppt gm
PDF
ecosys-brochure-digital
PPTX
7.4 Earned Value Analysis
PPTX
PPTX
Cost & value management
PPTX
Project cost control techniques
PPTX
HM 418 2e hcpm08
PDF
Lecture 8 monitoring & controlling (1)
PDF
Methodologies of Project Progress Measurement
PPTX
Lesson in fs cpm,cpa
DOC
High Level Overview Of Using The Earned Value On A T24 Project
PPTX
Project cost & control
Update Project Progress (MS PROJECT)
IWP Timeline
Kpi Lister Sto 061411
4. project cost management
Monitoring development projects
Project cost control
Revenue ppt gm
ecosys-brochure-digital
7.4 Earned Value Analysis
Cost & value management
Project cost control techniques
HM 418 2e hcpm08
Lecture 8 monitoring & controlling (1)
Methodologies of Project Progress Measurement
Lesson in fs cpm,cpa
High Level Overview Of Using The Earned Value On A T24 Project
Project cost & control
Ad

Similar to Portfolio Schedule Execution Metrics (20)

PPTX
APIS Briefing
PDF
Schedule Execution Metrics Dashboard
PDF
Dashboard Schedule Healt
PDF
NG BB 27 Process Capability
PDF
NG BB 27 Process Capability
PPTX
Measuring for success: Goals, performances, and outcomes
PDF
PMI-ACP+Domain6.pdf5555555555555555555555555555555555555555555555555555555
PDF
Project Management Essentials
PPTX
Benchmarking Execution Performance and Earned Value
PDF
NG BB 18 Theory of Constraints
PPTX
Fusion Transport Intelligence in OTM
PDF
Test performance indicators
PPTX
CAPM study session 4
PDF
NG BB 02 Table of Contents
PPTX
ATS-15 Tools of the Trade: Prioritizing and Planning for Active Transportation
PDF
AgileGraphingCookbook
PPT
Quality Process KPIs Metrics
PDF
CEI-BEI Dashboard
PPT
Enterprise_wideindicators.pptEnterprise_wideindicators.ppt
PDF
Methods and tools_of_success_driven_project_management
APIS Briefing
Schedule Execution Metrics Dashboard
Dashboard Schedule Healt
NG BB 27 Process Capability
NG BB 27 Process Capability
Measuring for success: Goals, performances, and outcomes
PMI-ACP+Domain6.pdf5555555555555555555555555555555555555555555555555555555
Project Management Essentials
Benchmarking Execution Performance and Earned Value
NG BB 18 Theory of Constraints
Fusion Transport Intelligence in OTM
Test performance indicators
CAPM study session 4
NG BB 02 Table of Contents
ATS-15 Tools of the Trade: Prioritizing and Planning for Active Transportation
AgileGraphingCookbook
Quality Process KPIs Metrics
CEI-BEI Dashboard
Enterprise_wideindicators.pptEnterprise_wideindicators.ppt
Methods and tools_of_success_driven_project_management
Ad

Portfolio Schedule Execution Metrics

  • 2. 2 Baseline Execution Index (BEI) Baseline Execution Index (BEI) measures the number of tasks competed as a ratio to those tasks that should have been completed to date (according to the original baseline). This index should be >=1.00. Average for July is 0.96 1.04 0.96 0.96 0.99 0.95 0.96 0.95 0.97 0.95 0.89 1.02 0.85 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 Project 1 Project 2 Project 3 Project 4 Project 5 Project 6 Project 7 Project 8 Project 9 Project 10 Project 11 Project 12 Baseline Execution Index (BEI)- index July avg: 0.96 2015 avg: 0.87 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 Baseline Execution Index (BEI) Improvement/Erosion BEI May BEI June BEI July Target
  • 3. 3 Critical Path Index (CPLI) Critical Path Length is the number of days from time now to the early finish date of the task or milestone representing program completion. The result is an index that measures the sufficiency of the total float available relative to the remaining duration of the critical path. CPLI also measures the relative efficiency required to complete the program's critical path on time. This index should be>= 1.00. Average for July is 0.97 1.00 1.07 0.70 1.00 1.00 0.98 1.17 0.81 0.89 1.01 1.02 1.00 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 Project 1 Project 2 Project 3 Project 4 Project 5 Project 6 Project 7 Project 8 Project 9 Project 10 Project 11 Project 12 Critical Path Lenght Index (CPLI)- index July avg: 0.97 2015 avg: 0.99 0.50 0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30 1.40 1.50 Critical Path Lenght Index (CPLI)-index Improvement/Erosion CPLI May CPLI June CPLI July Target
  • 4. 4 Total Float Consumption Index (TFCI) The focus of the TFCI is to provide a duration-based performance index calculating total float consumption as an efficiency factor. The TFCI can be used to assess the achievability of the project's completion date in any network schedule rather than just using the total float as a static indicator of projected completion. If the TFCI is below 1.0, then the program may not complete on-time without mitigation. Average for July is 0.98 1.00 1.04 0.90 1.00 1.00 0.99 1.01 0.93 0.79 1.01 1.01 1.00 0.00 0.50 1.00 1.50 Project 1 Project 2 Project 3 Project 4 Project 5 Project 6 Project 7 Project 8 Project 9 Project 10 Project 11 Project 12 Total Float Consumption Index (TFCI)-index 0.70 0.80 0.90 1.00 1.10 1.20 1.30 Total Float Consumption Index (TFCI)-index Improvement/Erosion TFCI May TFCI June TFCI July Target July avg 0.98 2015 avg: 0.99
  • 5. 5 % of Activities on the Critical Path This value represents the % of activities on the critical path, from the total number of activities on the schedule. Ideally, this number should be less than 15%. Average for July is 8.43% 2% 5% 10% 1% 6% 11% 4% 16% 23% 8% 21% 11% 0% 5% 10% 15% 20% 25% Project 1 Project 2 Project 3 Project 4 Project 5 Project 6 Project 7 Project 8 Project 9 Project 10 Project 11 Project 12 % of critical activities July avg: 8.43% 2015 avg: 10.59% 0% 5% 10% 15% 20% 25% 30% % of critical activities Improvement/Erosion % May % June % July Threshold
  • 6. 6 Trending Analysis – All Metrics 0.93 0.85 0.91 0.83 0.82 0.88 0.83 0.82 0.91 0.88 0.85 0.85 0.96 0.6 0.7 0.8 0.9 1 1.1 1.2 Baseline Execution Index (BEI) Monthly Portfolio Average Monthly avg Target 1.05 1.05 1.04 1.04 1 0.93 0.85 0.90 1.13 1.01 1.00 1.06 0.97 0.7 0.8 0.9 1 1.1 1.2 Critical Path Lenght Index (CPLI) Monthly Portfolio Average Monthly avg Threshold 1.05 1.02 1.06 1.04 0.99 0.98 0.98 0.98 1.02 1.01 0.99 1.00 0.98 0.8 0.9 1 1.1 1.2 Total Float Consumption Index (TFCI) Monthly Portfolio Average Monthly avg Threshold 6.0% 6.0% 10.0% 8.0% 10.0% 13.0%12.1%12.3% 9.2% 15.0% 9.0% 8.1%8.4% 0% 5% 10% 15% 20% 25% 30% % of critical activities (%) Monthly Portfolio Average Monthly avg Threshold