SlideShare a Scribd company logo
PROFESSIONAL PRACTICE 1
QSB 60604
GROUP MEMBERS :
• TAN KAI XUAN (0325066)
• TAN SHEN SIN
(0324602)
• TEE WAN NEE (0325074)
• TEO CHIANG LOONG (0323762)
TUTORIAL QUESTION 7
PAM FORM OF CONTRACT 2006 (WITH QUANTITIES)
a) A Contractor is currently undertaking works on two construction projects adjoining to each other but under two separate contracts. Project “A” started a year
earlier than project “B”. The work on reinforced concrete framed building in Project “A” is 75% completed with only internal works remaining. Project “B”
consists of mainly infrastructure works such as earthworks, main drain and roadworks. The progress is about 30%. After heavy rain of five hours, both sites
were flooded for three days.
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
Delays due to reasons outside the control of both parties
exceptionally inclement
weather
CLAUSE 23.1
May apply for an
extension of time
CLAUSE
23.1(a)
CLAUSE
23.1(b)
If contractor failed to submit his final claims within the stated
time (28 days of the end of cause of delay), it shall be deemed
that such event will not delay the completion of work.
The contractor shall give written notice to the Architect his
intention to claim for such extension of time
The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the
contractor’s entitlement.
CLAUSE 23.8 (a) CLAUSE 23.8 (b)
Heavy rains for 5 hours are under Force Majeure
and it basically limits the contractors risk in
contract by removing his liability to pay
damages for late completion when Force
Majeure has occurred or frustration of contract
would occur.
As the contractor is claiming for EOT for the
similar reasons which are exceptionally
inclement of the weather, it would be referred to
the Clause 23.8 b which is the EOT for relevant
of time referred to exceptionally inclement
weather
.
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
CHECKING THE
WEATHER FORECAST
REPORT FROM THE
METHODOLOGY
The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the
contractor’s entitlement.
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
CLAUSE 23.2
The contractor shall send a copy of such written
notice & particulars to the Nominated Sub-
Contractor concerned.
CLAUSE 23.3
The architect shall inform the Contractor to
resubmit the particulars if it is insufficient for the
architect to decide on the application for extension
of time.
The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the
contractor’s entitlement.
CLAUSE 23.4
The Architect shall consider the Contractor's
submission and shall either reject the Contractor's
application or issue a Certification of Extension of
time within six (6) weeks from the receipt of
sufficient particulars.
CLAUSE 23.5
In assessing the extension of time, may take into
account the following
CLAUSE 23.5
(a)
CLAUSE 23.5
(b)
The Architect shall not fix a
Completion Date earlier than the
Completion stated in the appendix
Relevant Events which in the
Architect's opinion will have an effect
on Contractor's to an extension of
time
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the
contractor’s entitlement.
CLAUSE 23.6 CLAUSE 23.7
The Contractor shall prevent or reduce delay in
the progress of Works, and satisfy Architect's
requirements to prevent or reduce delay or further
delay in the completion of Works.
The Architect shall notify every Nominated Sub-
Contractor when fixing a later completion date
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the
contractor’s entitlement.
CONCLUSION
NIL because there are only internal works left and
the flood doesn’t goes into the internal work
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
PROJECT A WITH INTERNAL
WORKS LEFT
PROJECT B WITH
EARTHWORKS, MAIN DRAIN
AND ROADWORKS
Can be claimed because the flood does affect the
project works currently
b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the
issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and
defective works.
Certificate of
Practical
Completion
Contractor is no longer be
charged with liquidated
damages
IS ISSUED
Employer takes
over
responsibility
HANDS OVER
RESPONSIBLITY
THEN…
THE START OF THE
PERIOD OF:
I.) Final measurement
for the final account
(6months)
II.) First moiety of
retention fund is
released to contractor.
III.) Start of Defect
Liability period
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the
issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and
defective works.
When is Certificate of Practical Completion is issued ?
 Where architect considers the works are
complete, sufficient for the client to take
possession and use the building.
 Defects and minor works has still
needed to be executed by Contractor
and a notice has been given to the
Architect with reasonable time
specified.
CLAUSE 15.1(a)
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the
issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and
defective works.
PAM CONTRACT 2006 (WITH QUANTITIES) The issuance of the Certificate of Practical Completion
Practical
Completion
Clause15.1
Clause15.1(b)
Clause15.1 (a)
Works are practically
completed when: Clause15.2
When the whole of the
works are practically
completed, Contractor
shall forthwith give
written notice that effect
to Architects within 14
days
In architect’s opinion, employer can have full use of the works for their intended purpose, not withstanding that there may be works and
defects or minor nature still to be executed and the contractor has given to the Architect a written undertaking to make good and to
complete such works and defects with a reasonable time specified by architect; and
Others requirements expressly stated in Contract Documents as a pre-
requisite for the issuance of certificate of practical completion have been
complied with.
YES
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the
issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and
defective works.
PAM CONTRACT 2006 (WITH QUANTITIES) The issuance of the Certificate of Practical Completion
Clause15.2
Clause15.2(b)
Clause15.2 (a)
If the Architect is of the
opinion that the
Clause15.2(b)(i)
The date of receipt of the
Contractor’s written
undertaking to make
good and to complete
works and defects of a
minor nature; where
there are such works or
defects; or
Works are not practically completed under clause 15.1, the Architect shall
give written notice to the Contractor with copy extended to the
Nominated Sub-Contractor stating the reasons for his opinion; or
Works are practically completed under clause
15.1, the Architect shall issue the Certificated of
Practical Completion. The date of Practical
Completion shall be:
Clause15.2(b)(ii)
The date of receipt of the
Contractor’s written notice, where
there are no works and defects of
a minor nature.
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the
issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and
defective works.
PAM CONTRACT 2006 (WITH QUANTITIES) Contractor’s failure to comply with undertaking
Clause 15.3
Clause15.3 (a)
The contractor shall comply with his
undertaking to finish up the defects of
minor nature under clause 15.1a within
the time specified. If it is not being
done, the Employer may without
prejudice to any other rights and
remedies which he posses under the
Contract.
Clause15.3 (b)
Clause15.3 (c)
Grant the Contractor additional ex-gratia time to be
specified by the Architect to enable the Contractor to
comply with his said undertaking
Employ and pay the other person to execute
any work which may be necessary to give effect
to the Contractor’s said undertaking. All cost
incurred including any loss/expense shall be
set-off by the Employer under Clause 30.4, or
Accept to leave all or any such works and
defects of a minor nature in the Works subject
to an appropriate set-off under Clause 30.4
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
THE END
TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)

More Related Content

PDF
Window Analysis @ 30-June-2012
PDF
10. Overall Implementation Programme
DOC
Rihan Height Project Execution Plan-Rev00
PDF
Monthly Progress Report - September 2014

What's hot (9)

PDF
PDF
Method statement of temporary office and fa
PPTX
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
PPTX
Delay analysis of raw water reservoir and pumping Station
DOCX
Method statement tank base concrete pouring
PDF
Causes of Delay in Construction of Bridge Girders
PPT
Contract adminstration and planning
PDF
Project management report of stadium
Method statement of temporary office and fa
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Delay analysis of raw water reservoir and pumping Station
Method statement tank base concrete pouring
Causes of Delay in Construction of Bridge Girders
Contract adminstration and planning
Project management report of stadium
Ad

Similar to Presentation 7-pp-final (20)

PDF
Assignment - Final Account
PDF
Pp2 assignment-final
PDF
Pp2 assignment-final
PPT
Claims in Contract - For FIDIC 1999 .ppt
PDF
Pp2 coursework 2
DOCX
PP2 - Assignment
DOCX
Professional Practice II
PPTX
Lecture 8-determination-of-own-employment-by
PDF
Assignmenr for pp2 final account
PPTX
A Claim submitted by the contractor during for slides.pptx
DOCX
Cl compilation
PDF
PP2 - Assignment
PDF
PP2 final report
PDF
Pp2 final report
PDF
Construction Law Assignment BQS Taylor's University
PPTX
Antara Dashboard-002.pptx
PDF
Seminar - Partial Possession by Employer
PPTX
PP2 presentation
PPTX
Pp2 p7
PDF
Pp2 coursework 2 201808
Assignment - Final Account
Pp2 assignment-final
Pp2 assignment-final
Claims in Contract - For FIDIC 1999 .ppt
Pp2 coursework 2
PP2 - Assignment
Professional Practice II
Lecture 8-determination-of-own-employment-by
Assignmenr for pp2 final account
A Claim submitted by the contractor during for slides.pptx
Cl compilation
PP2 - Assignment
PP2 final report
Pp2 final report
Construction Law Assignment BQS Taylor's University
Antara Dashboard-002.pptx
Seminar - Partial Possession by Employer
PP2 presentation
Pp2 p7
Pp2 coursework 2 201808
Ad

More from Wan Nee (20)

PDF
Professional practice-1-1-1-autosaved (1)
PDF
Structures final 20th june
PPTX
Eca presentation slide (group a)
PPTX
Estimating final
PDF
Seminar question
PPTX
Estimating presentation
PDF
Evaluation brief qsb2134 tender (1)
PDF
Estimating Assignment Brief
PDF
Estimating Assignment
PPTX
Supply Chain
PPTX
Supply chain
PDF
Supply chain
PPTX
Management Science
DOCX
Qsb 2413 group project august 2017
PPTX
BS 2 PRESENTATION
PDF
CT 3 Group Assignment Presentation Slide
DOCX
CT3 Group Assignment Report
PDF
Ct2 latest1-1 (3)
DOCX
SITE VISIT REPORT
PDF
INTEGRATED ASSIGNMENT - CT BM M
Professional practice-1-1-1-autosaved (1)
Structures final 20th june
Eca presentation slide (group a)
Estimating final
Seminar question
Estimating presentation
Evaluation brief qsb2134 tender (1)
Estimating Assignment Brief
Estimating Assignment
Supply Chain
Supply chain
Supply chain
Management Science
Qsb 2413 group project august 2017
BS 2 PRESENTATION
CT 3 Group Assignment Presentation Slide
CT3 Group Assignment Report
Ct2 latest1-1 (3)
SITE VISIT REPORT
INTEGRATED ASSIGNMENT - CT BM M

Recently uploaded (20)

PDF
01-Introduction-to-Information-Management.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
A systematic review of self-coping strategies used by university students to ...
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PDF
O7-L3 Supply Chain Operations - ICLT Program
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PPTX
GDM (1) (1).pptx small presentation for students
PDF
Computing-Curriculum for Schools in Ghana
PDF
RMMM.pdf make it easy to upload and study
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PPTX
Lesson notes of climatology university.
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
Anesthesia in Laparoscopic Surgery in India
PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
01-Introduction-to-Information-Management.pdf
Final Presentation General Medicine 03-08-2024.pptx
A systematic review of self-coping strategies used by university students to ...
human mycosis Human fungal infections are called human mycosis..pptx
Abdominal Access Techniques with Prof. Dr. R K Mishra
Chinmaya Tiranga quiz Grand Finale.pdf
2.FourierTransform-ShortQuestionswithAnswers.pdf
O7-L3 Supply Chain Operations - ICLT Program
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
GDM (1) (1).pptx small presentation for students
Computing-Curriculum for Schools in Ghana
RMMM.pdf make it easy to upload and study
Module 4: Burden of Disease Tutorial Slides S2 2025
Lesson notes of climatology university.
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Anesthesia in Laparoscopic Surgery in India
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
Chapter 2 Heredity, Prenatal Development, and Birth.pdf

Presentation 7-pp-final

  • 1. PROFESSIONAL PRACTICE 1 QSB 60604 GROUP MEMBERS : • TAN KAI XUAN (0325066) • TAN SHEN SIN (0324602) • TEE WAN NEE (0325074) • TEO CHIANG LOONG (0323762) TUTORIAL QUESTION 7 PAM FORM OF CONTRACT 2006 (WITH QUANTITIES)
  • 2. a) A Contractor is currently undertaking works on two construction projects adjoining to each other but under two separate contracts. Project “A” started a year earlier than project “B”. The work on reinforced concrete framed building in Project “A” is 75% completed with only internal works remaining. Project “B” consists of mainly infrastructure works such as earthworks, main drain and roadworks. The progress is about 30%. After heavy rain of five hours, both sites were flooded for three days. TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762) Delays due to reasons outside the control of both parties exceptionally inclement weather CLAUSE 23.1 May apply for an extension of time CLAUSE 23.1(a) CLAUSE 23.1(b) If contractor failed to submit his final claims within the stated time (28 days of the end of cause of delay), it shall be deemed that such event will not delay the completion of work. The contractor shall give written notice to the Architect his intention to claim for such extension of time
  • 3. The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the contractor’s entitlement. CLAUSE 23.8 (a) CLAUSE 23.8 (b) Heavy rains for 5 hours are under Force Majeure and it basically limits the contractors risk in contract by removing his liability to pay damages for late completion when Force Majeure has occurred or frustration of contract would occur. As the contractor is claiming for EOT for the similar reasons which are exceptionally inclement of the weather, it would be referred to the Clause 23.8 b which is the EOT for relevant of time referred to exceptionally inclement weather . TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762) CHECKING THE WEATHER FORECAST REPORT FROM THE METHODOLOGY
  • 4. The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the contractor’s entitlement. TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762) CLAUSE 23.2 The contractor shall send a copy of such written notice & particulars to the Nominated Sub- Contractor concerned. CLAUSE 23.3 The architect shall inform the Contractor to resubmit the particulars if it is insufficient for the architect to decide on the application for extension of time.
  • 5. The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the contractor’s entitlement. CLAUSE 23.4 The Architect shall consider the Contractor's submission and shall either reject the Contractor's application or issue a Certification of Extension of time within six (6) weeks from the receipt of sufficient particulars. CLAUSE 23.5 In assessing the extension of time, may take into account the following CLAUSE 23.5 (a) CLAUSE 23.5 (b) The Architect shall not fix a Completion Date earlier than the Completion stated in the appendix Relevant Events which in the Architect's opinion will have an effect on Contractor's to an extension of time TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
  • 6. The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the contractor’s entitlement. CLAUSE 23.6 CLAUSE 23.7 The Contractor shall prevent or reduce delay in the progress of Works, and satisfy Architect's requirements to prevent or reduce delay or further delay in the completion of Works. The Architect shall notify every Nominated Sub- Contractor when fixing a later completion date TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
  • 7. The Contractor is claiming for extension of time citing similar reasons, i.e. exceptionally inclement weather for both projects. Discuss and advise on the contractor’s entitlement. CONCLUSION NIL because there are only internal works left and the flood doesn’t goes into the internal work TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762) PROJECT A WITH INTERNAL WORKS LEFT PROJECT B WITH EARTHWORKS, MAIN DRAIN AND ROADWORKS Can be claimed because the flood does affect the project works currently
  • 8. b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and defective works. Certificate of Practical Completion Contractor is no longer be charged with liquidated damages IS ISSUED Employer takes over responsibility HANDS OVER RESPONSIBLITY THEN… THE START OF THE PERIOD OF: I.) Final measurement for the final account (6months) II.) First moiety of retention fund is released to contractor. III.) Start of Defect Liability period TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
  • 9. b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and defective works. When is Certificate of Practical Completion is issued ?  Where architect considers the works are complete, sufficient for the client to take possession and use the building.  Defects and minor works has still needed to be executed by Contractor and a notice has been given to the Architect with reasonable time specified. CLAUSE 15.1(a) TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
  • 10. b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and defective works. PAM CONTRACT 2006 (WITH QUANTITIES) The issuance of the Certificate of Practical Completion Practical Completion Clause15.1 Clause15.1(b) Clause15.1 (a) Works are practically completed when: Clause15.2 When the whole of the works are practically completed, Contractor shall forthwith give written notice that effect to Architects within 14 days In architect’s opinion, employer can have full use of the works for their intended purpose, not withstanding that there may be works and defects or minor nature still to be executed and the contractor has given to the Architect a written undertaking to make good and to complete such works and defects with a reasonable time specified by architect; and Others requirements expressly stated in Contract Documents as a pre- requisite for the issuance of certificate of practical completion have been complied with. YES TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
  • 11. b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and defective works. PAM CONTRACT 2006 (WITH QUANTITIES) The issuance of the Certificate of Practical Completion Clause15.2 Clause15.2(b) Clause15.2 (a) If the Architect is of the opinion that the Clause15.2(b)(i) The date of receipt of the Contractor’s written undertaking to make good and to complete works and defects of a minor nature; where there are such works or defects; or Works are not practically completed under clause 15.1, the Architect shall give written notice to the Contractor with copy extended to the Nominated Sub-Contractor stating the reasons for his opinion; or Works are practically completed under clause 15.1, the Architect shall issue the Certificated of Practical Completion. The date of Practical Completion shall be: Clause15.2(b)(ii) The date of receipt of the Contractor’s written notice, where there are no works and defects of a minor nature. TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
  • 12. b) In the PAM Form of Contract 2006 (With Quantities), advise the Employer the procedures involved in the issuance of the Certificate of Practical Completion, assuming even if there are minor outstanding and defective works. PAM CONTRACT 2006 (WITH QUANTITIES) Contractor’s failure to comply with undertaking Clause 15.3 Clause15.3 (a) The contractor shall comply with his undertaking to finish up the defects of minor nature under clause 15.1a within the time specified. If it is not being done, the Employer may without prejudice to any other rights and remedies which he posses under the Contract. Clause15.3 (b) Clause15.3 (c) Grant the Contractor additional ex-gratia time to be specified by the Architect to enable the Contractor to comply with his said undertaking Employ and pay the other person to execute any work which may be necessary to give effect to the Contractor’s said undertaking. All cost incurred including any loss/expense shall be set-off by the Employer under Clause 30.4, or Accept to leave all or any such works and defects of a minor nature in the Works subject to an appropriate set-off under Clause 30.4 TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)
  • 13. THE END TAN KAI XUAN(0325066)|TAN SHEN SIN(0324602)|TEE WAN NEE (0325074)|TEO CHIANG LOONG (0323762)