Prioritisation
  Bob Andrew, Director
Custom Design Services (Financial)
            NCR Corporation
        bob.andrew@ncr.com


Custom Design Services (Financial) · NCR Confidential  2012
•   What I do…
                                                                           Agenda
•   ATMs – Department Store in a Box
•   Challenges
•   Product Lifecycle Management &
    Ideation
•   Business Planning Hierarchies
•   Prioritisation
•   Portfolio Management
•   Keeping it Simple - my 4 ‘Ps’




            Custom Design Services (Financial) · NCR Confidential  2012
CDS Organisation & Process                                                                           Discuss Requirement
                                                                                                                                          with Regional
                                                                                                                                          Deployment




Self-
Self-funded Engineering Team
  Part of Hardware Engineering and CTO Organisation
                                                                                                                                         Submit SCER
  Self-Funding

Delivery of Bespoke Financial ATM Solutions                                Process
 Unique customer requirement                                               Conceive how will the product meet the needs of the
 Expedite roadmap availability                                             end user, how much will it cost to manufacture, what       Secure LOB Approval


                                                                           should it look like, what does the customer want
Team Composition                                                           Innovate industrial designers and engineers propose
 Business Development Manager & Group Lead                                 alternative, viable strategies                             Create Statement of
 Snr. Programme Manager                                                    Inspire using CAD tools and prototypes to ratify, test
                                                                                                                                             Work
                                                                                                                                         & Project Plan
 Project Managers                                                          and demonstrate all aspects of the engineering concept
                                                                                                                                      ($5,000 Charge-out)


 Senior Design Consultant & Designers
                                                                           Realise dealing directly with the supply chain, ensuring
 Access to contract NCR Engineering Organisation                           production readiness and ongoing support.
 Access to contract external skills as required                                                                                           Go – No Go
 Product Management (for approval step)



                                                                                                                                       Start Development




                  Custom Design Services (Financial) · NCR Confidential  2012
ATMs & Department Stores
- Concessions




 31   33   32       34     34 DU      35       36         38




                Custom Design Services (Financial) · NCR Confidential  2012
• Multiple Stakeholders
                                                            Challenges
• Competing Product Managers
• Annual Planning Cycle vs. Rolling
  Portfolio Management
• Intuition vs. Analytics in Portfolio
  Management
• Matching resources & money to
  priorities
• Systems crush flexibility & innovation
    •Reporting not managing




             Custom Design Services (Financial) · NCR Confidential  2012
The PLM Ideation funnel
  Ideation & Portfolio Management - the key driver of innovation




Custom Design Services (Financial) · NCR Confidential  2012
Business Planning Hierarchy




Custom Design Services (Financial) · NCR Confidential  2012
Project Prioritization Model
                                              Category                           Criteria
                                  Weights
                                                                             Market Segment Size
                                                                           Market Segment Growth




             Attractiveness/Fit
                                        2x    Opportunity             Revenue Impact or Cost Reduction
                                             Attractiveness
                                                                            Potential Gross Margins
                                                                      NPV Potential (Funded Projects) or
                                                                    Investment (Unfunded Projects/Ideas)

                                                               Alignment with Strategic Initiative and Priorities
                                                                                Market Impact
                                      1.5x
                                              Strategic Fit                   Capability Leverage
                                                                           Competitive Advantage
                                                                             Proprietary Position


                                                                               Technical Change
                                        1x Probability of
             Composite Risk




                                                                             Program Complexity
                                               Technical
                                                                         Availability of Skills/Resources
                                                Success
                                                                           Platform/Product Leverage


                                                                            Business Model Change
                                        1x Probability of                       Market Maturity
                                              Commercial                     Competitive Intensity
                                                Success
                                                                           Commercial Assumptions




Custom Design Services (Financial) · NCR Confidential  2012
Optimized Portfolio Management
     Scoring and Prioritization                                Leadership decision-making




Custom Design Services (Financial) · NCR Confidential  2012
Portfolio Views/Lenses
          Portfolio View/Lens                                                                    Question(s)
                                                                             Strategic/Portfolio Question(s)
1. R&D Spend Breakdown                              Is our spending mix aligned with our strategic intent? Will it help us achieve
                                                    our near-term and long-term business strategies & goals?

2. Opportunity Attractiveness vs.                   Which projects provide us attractive opportunities that align with our strategic
   Strategic Fit                                    intent and capabilities?
3. Funnel Chart                                     How balanced is our development pipeline? Is there a concentration of
                                                    projects in specific phases? Are there phases with few or no projects?

4. Gross Margin Forecast (risk-adjusted) Are we on target to achieve our gross margin targets? What is the magnitude
                                         and timing of any gaps?
5. Innovation Map                                   Do we have the right innovation mix to achieve our business goals? Are we
                                                    investing enough in future growth platforms?
6. New Product Revenue (% of sales) vs. Are we getting the right returns from our R&D spend?
   R&D Spend
7. Revenue Forecast (risk-adjusted)                 Are we on target to achieve our revenue and growth targets? What is the
                                                    magnitude and timing of any gaps?
8. Risk vs. Reward                                  Is the portfolio balanced from a risk vs. reward perspective? Are there any
                                                    projects with high risk but low reward? Are we taking too much risk or not
                                                    taking enough risk?
            Custom Design Services (Financial) · NCR Confidential  2012
R&D Spend Breakdown
                    R&D Spend Breakdown for FY2009 in USD ($'000)
                    Field Based
                   Development,
                   $6,000 , 15%                                      New Solution
                                                                     Development,
                                                                     $10,000 , 24%
                                                                                                    Is our spending mix aligned with our
                                                                                                    strategic intent?
Cost Reductions,
 $4,000 , 10%                                                                                       Will it help us achieve our near-term
                                                                                                    and long-term business strategies &
                                                                                                    goals?
                                                                                 Continuation
                                                                              Engineering, $3,000
                                                                                     , 7%




                             Solution
                          Enhancements,


                         Custom Design Services (Financial) · NCR Confidential  2012
Portfolio Dashboard




Custom Design Services (Financial) · NCR Confidential  2012
Keeping It Simple: 4 ‘P’s
Project                                                        Failure is Not An Option         Highly Important                Important

People (and Skills)
                                                               5 Project Maximum            10-20 Projects               10 Projects
Priority                                                       New projects added or        Ranked in priority
 ost-
Post-Its                                                       promoted

 – One per resource
 – Colour to indicate skillset                                 Fully Staffed at all times   Staffed fully from the top   Unstaffed or progressed
 – Column for priority                                         Dates & commitments                                       if small
                                                               100%
Test Criteria
1. Essential to stay in business (regulatory)
                                              Will take resource from                       Projects Lower on list       Promoted left or capacity
2. Projects already committed                 one of the other levels                       received resource when       frees up for them to be
3. To maintain market share                   immediately issues arise                      available                    progressed at slower rate
                                                                                                                         or when they have been
4. New Things (growth)                                                                                                   on this list too long

                  Custom Design Services (Financial) · NCR Confidential  2012
Custom Design Services (Financial) · NCR Confidential  2012

More Related Content

PDF
DfSS Webinar Part 1: An Introduction to DFSS
PDF
DfSS Webinar Part 2: Delivering better ROI on DFSS Projects
PDF
SmartConnect-CorpIntro
PDF
G2 It Services Overview 09.07.01
PDF
Req Pro - Andreas gschwind
PDF
APPROACH TO VALUE ENGINEERING USING PRO/ENGINEER
PDF
Corporate Presentation - Tech Connect
PPTX
Mind the 'business' while you 'analyze' - Mangesh Nadkarni
DfSS Webinar Part 1: An Introduction to DFSS
DfSS Webinar Part 2: Delivering better ROI on DFSS Projects
SmartConnect-CorpIntro
G2 It Services Overview 09.07.01
Req Pro - Andreas gschwind
APPROACH TO VALUE ENGINEERING USING PRO/ENGINEER
Corporate Presentation - Tech Connect
Mind the 'business' while you 'analyze' - Mangesh Nadkarni

What's hot (20)

PDF
Dbs overview atlppt
PDF
Corporate Positioning w Messaging Framework
PDF
PDF
SCG LONDON 2011 Brochure
PDF
Engineering Your Supply Chain for Exponential Growth
PDF
Through the looking glass
PDF
Conscientia How Winners Sell Outsourcing Services
PPTX
BA conf presentation 2010
PPT
Agility Matrix - Updated!
PDF
Avoiding the 11th Hour Sh*storm at SxSW
PDF
10 tips for chartering a project (v2)
PDF
Etops at a glance
PDF
Key Role of BA in Project Success
PDF
Project manager delivering project success
PPT
Vserv Capture Mgt Intro 7 9 09
PPTX
Solution Validation & Assessments - A practical Approach
PDF
Jijesoft Your Strategic Partner
PDF
Praxes Group Capabilities Overview
PDF
PBOPlus - About Us
PDF
SAP BPM Jump Start to Value Package
Dbs overview atlppt
Corporate Positioning w Messaging Framework
SCG LONDON 2011 Brochure
Engineering Your Supply Chain for Exponential Growth
Through the looking glass
Conscientia How Winners Sell Outsourcing Services
BA conf presentation 2010
Agility Matrix - Updated!
Avoiding the 11th Hour Sh*storm at SxSW
10 tips for chartering a project (v2)
Etops at a glance
Key Role of BA in Project Success
Project manager delivering project success
Vserv Capture Mgt Intro 7 9 09
Solution Validation & Assessments - A practical Approach
Jijesoft Your Strategic Partner
Praxes Group Capabilities Overview
PBOPlus - About Us
SAP BPM Jump Start to Value Package
Ad

Similar to Prioritisation - Bob Andrew, NCR (20)

PDF
Configuration management
PDF
Visure Solutions Requirements Engineering_The word in a nutshell - Ulf Sandberg
PDF
Cyrius Company Profile En New
PDF
Zammarti Portafolios 2011 English
PDF
Selected Work Products
PDF
ex of my work for client: Corporate Back Office suite On Cloud
PPTX
David Pinches - Product Management - where do you start?
PDF
Ecm roadmap v2 0
PDF
ISSUE & WIKI based Integration of Project Management
PPTX
Architectural considerations
PDF
Business process strategies & organizational design
PDF
PDC global capability 03 13-13
PDF
ERP Implementation cycle
PDF
Product life cycle and design for total cost
PDF
Colin rudd-business-integration-and-value
PDF
Vijay kusurkar value chain stratagem
PDF
Sudip Julian Workshop Presentation 23 3 10
PDF
IBM Rational Software Conference 2009 Day 1 Keynote: Jamie Thomas
PDF
PLM-ERP Integration
PPTX
Business Process Improvement
Configuration management
Visure Solutions Requirements Engineering_The word in a nutshell - Ulf Sandberg
Cyrius Company Profile En New
Zammarti Portafolios 2011 English
Selected Work Products
ex of my work for client: Corporate Back Office suite On Cloud
David Pinches - Product Management - where do you start?
Ecm roadmap v2 0
ISSUE & WIKI based Integration of Project Management
Architectural considerations
Business process strategies & organizational design
PDC global capability 03 13-13
ERP Implementation cycle
Product life cycle and design for total cost
Colin rudd-business-integration-and-value
Vijay kusurkar value chain stratagem
Sudip Julian Workshop Presentation 23 3 10
IBM Rational Software Conference 2009 Day 1 Keynote: Jamie Thomas
PLM-ERP Integration
Business Process Improvement
Ad

Recently uploaded (20)

PPTX
Amazon (Business Studies) management studies
PPTX
HR Introduction Slide (1).pptx on hr intro
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PPT
Data mining for business intelligence ch04 sharda
PDF
Business model innovation report 2022.pdf
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
DOCX
Business Management - unit 1 and 2
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
Laughter Yoga Basic Learning Workshop Manual
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
How to Get Funding for Your Trucking Business
PDF
Unit 1 Cost Accounting - Cost sheet
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
Amazon (Business Studies) management studies
HR Introduction Slide (1).pptx on hr intro
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
Roadmap Map-digital Banking feature MB,IB,AB
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
WRN_Investor_Presentation_August 2025.pdf
Ôn tập tiếng anh trong kinh doanh nâng cao
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
Data mining for business intelligence ch04 sharda
Business model innovation report 2022.pdf
New Microsoft PowerPoint Presentation - Copy.pptx
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
Business Management - unit 1 and 2
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
Laughter Yoga Basic Learning Workshop Manual
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
How to Get Funding for Your Trucking Business
Unit 1 Cost Accounting - Cost sheet
DOC-20250806-WA0002._20250806_112011_0000.pdf

Prioritisation - Bob Andrew, NCR

  • 1. Prioritisation Bob Andrew, Director Custom Design Services (Financial) NCR Corporation bob.andrew@ncr.com Custom Design Services (Financial) · NCR Confidential  2012
  • 2. What I do… Agenda • ATMs – Department Store in a Box • Challenges • Product Lifecycle Management & Ideation • Business Planning Hierarchies • Prioritisation • Portfolio Management • Keeping it Simple - my 4 ‘Ps’ Custom Design Services (Financial) · NCR Confidential  2012
  • 3. CDS Organisation & Process Discuss Requirement with Regional Deployment Self- Self-funded Engineering Team Part of Hardware Engineering and CTO Organisation Submit SCER Self-Funding Delivery of Bespoke Financial ATM Solutions Process Unique customer requirement Conceive how will the product meet the needs of the Expedite roadmap availability end user, how much will it cost to manufacture, what Secure LOB Approval should it look like, what does the customer want Team Composition Innovate industrial designers and engineers propose Business Development Manager & Group Lead alternative, viable strategies Create Statement of Snr. Programme Manager Inspire using CAD tools and prototypes to ratify, test Work & Project Plan Project Managers and demonstrate all aspects of the engineering concept ($5,000 Charge-out) Senior Design Consultant & Designers Realise dealing directly with the supply chain, ensuring Access to contract NCR Engineering Organisation production readiness and ongoing support. Access to contract external skills as required Go – No Go Product Management (for approval step) Start Development Custom Design Services (Financial) · NCR Confidential  2012
  • 4. ATMs & Department Stores - Concessions 31 33 32 34 34 DU 35 36 38 Custom Design Services (Financial) · NCR Confidential  2012
  • 5. • Multiple Stakeholders Challenges • Competing Product Managers • Annual Planning Cycle vs. Rolling Portfolio Management • Intuition vs. Analytics in Portfolio Management • Matching resources & money to priorities • Systems crush flexibility & innovation •Reporting not managing Custom Design Services (Financial) · NCR Confidential  2012
  • 6. The PLM Ideation funnel Ideation & Portfolio Management - the key driver of innovation Custom Design Services (Financial) · NCR Confidential  2012
  • 7. Business Planning Hierarchy Custom Design Services (Financial) · NCR Confidential  2012
  • 8. Project Prioritization Model Category Criteria Weights Market Segment Size Market Segment Growth Attractiveness/Fit 2x Opportunity Revenue Impact or Cost Reduction Attractiveness Potential Gross Margins NPV Potential (Funded Projects) or Investment (Unfunded Projects/Ideas) Alignment with Strategic Initiative and Priorities Market Impact 1.5x Strategic Fit Capability Leverage Competitive Advantage Proprietary Position Technical Change 1x Probability of Composite Risk Program Complexity Technical Availability of Skills/Resources Success Platform/Product Leverage Business Model Change 1x Probability of Market Maturity Commercial Competitive Intensity Success Commercial Assumptions Custom Design Services (Financial) · NCR Confidential  2012
  • 9. Optimized Portfolio Management Scoring and Prioritization Leadership decision-making Custom Design Services (Financial) · NCR Confidential  2012
  • 10. Portfolio Views/Lenses Portfolio View/Lens Question(s) Strategic/Portfolio Question(s) 1. R&D Spend Breakdown Is our spending mix aligned with our strategic intent? Will it help us achieve our near-term and long-term business strategies & goals? 2. Opportunity Attractiveness vs. Which projects provide us attractive opportunities that align with our strategic Strategic Fit intent and capabilities? 3. Funnel Chart How balanced is our development pipeline? Is there a concentration of projects in specific phases? Are there phases with few or no projects? 4. Gross Margin Forecast (risk-adjusted) Are we on target to achieve our gross margin targets? What is the magnitude and timing of any gaps? 5. Innovation Map Do we have the right innovation mix to achieve our business goals? Are we investing enough in future growth platforms? 6. New Product Revenue (% of sales) vs. Are we getting the right returns from our R&D spend? R&D Spend 7. Revenue Forecast (risk-adjusted) Are we on target to achieve our revenue and growth targets? What is the magnitude and timing of any gaps? 8. Risk vs. Reward Is the portfolio balanced from a risk vs. reward perspective? Are there any projects with high risk but low reward? Are we taking too much risk or not taking enough risk? Custom Design Services (Financial) · NCR Confidential  2012
  • 11. R&D Spend Breakdown R&D Spend Breakdown for FY2009 in USD ($'000) Field Based Development, $6,000 , 15% New Solution Development, $10,000 , 24% Is our spending mix aligned with our strategic intent? Cost Reductions, $4,000 , 10% Will it help us achieve our near-term and long-term business strategies & goals? Continuation Engineering, $3,000 , 7% Solution Enhancements, Custom Design Services (Financial) · NCR Confidential  2012
  • 12. Portfolio Dashboard Custom Design Services (Financial) · NCR Confidential  2012
  • 13. Keeping It Simple: 4 ‘P’s Project Failure is Not An Option Highly Important Important People (and Skills) 5 Project Maximum 10-20 Projects 10 Projects Priority New projects added or Ranked in priority ost- Post-Its promoted – One per resource – Colour to indicate skillset Fully Staffed at all times Staffed fully from the top Unstaffed or progressed – Column for priority Dates & commitments if small 100% Test Criteria 1. Essential to stay in business (regulatory) Will take resource from Projects Lower on list Promoted left or capacity 2. Projects already committed one of the other levels received resource when frees up for them to be 3. To maintain market share immediately issues arise available progressed at slower rate or when they have been 4. New Things (growth) on this list too long Custom Design Services (Financial) · NCR Confidential  2012
  • 14. Custom Design Services (Financial) · NCR Confidential  2012