PROGRAM MANAGEMENT 2.0
RISK MANAGEMENT
Jeanne Bradford, John Carter, Scott Elliott
April, 2018
2
22
AGENDA
1 Schedule Prediction Accuracy
Exercise in creating diagram
2 Metrics for estimating progress at the engineering task levels
Exercise in creating a Task Burn- Down Chart
3 Monitoring Progress: Earned Value – Scope, Cost and Time
Exercise in managing Partner’s delay
4 Risk & Circle Dot Charts: What happens if there is a breakdown?
Exercise
5 Management Systems
Covered in this presentation
3
33
KEY LEARNING POINTS
Monitoring Project Performance for Internal and External Partners (TCGen’s Innovate Products Faster, Greene’s Head First PMP)
1 Metrics for estimating progress (at the engineering task levels)
2 Monitoring Progress (Earned Value – Scope, Cost and Time)
3 Risk Monitoring
4 Circle Dot Charts
5 Management Systems
Participants will understand how to create and update Schedule Prediction Accuracy charts and how to demonstrate program status
by showing scope, cost and time in one chart.
They will also gain skill in creating and using:
4
44
Risk Monitoring
5
55
ESSENTIAL PROCESSES FOR MANAGING RISKS
• Assess – Learn from the past, create checklist, review prior audits, go outside, generate list of potential risks
• Plan – Perform impact and probability analysis, prioritize, and make plans
• Monitor – Keep an active watch for trouble by monitoring predictive metrics
• React – Re-mediate if and when there is trouble
Assess Plan
Monitor &
React
6
66
RISK RESPONSE OPTIONS
Risk Response Description Examples/Notes
Avoidance
Avoiding the risk.
Changing the project plan to eliminate
the risk.
Changing the project plan to protect a
project objective from the impact.
Reducing the scope remove high-risk tasks.
Adding resources or time.
Adopting a proven approach rather than new one.
Removing a “problem” resource.
Acceptance
Accepting the consequences of the risk.
The project plan is not changed to deal
with the risk.
A better response strategy cannot be
identified.
Active acceptance.
Passive acceptance.
No action.
Contingency allowance (reserves).
Communication plan around possible major cost increases if
this risk occurs.
Monitor and prepare
Accepting the risk for now.
Closely monitor the risk and develop
alternate action plans proactively if the
event occurs.
Contingency plan.
Fallback plan.
Establish criteria that will trigger the implementation of the
response plans.
Source: Project Management, Absolute Beginner’s Guide, Gregory Horine Que Publishing, Indianapolis 2013
7
77
Risk Response Description Examples/Notes
Mitigation
Taking action to reduce the likelihood that
the risk will occur.
Taking action to reduce the impact of the
risk.
Reducing the probability is always more
effective than minimizing the
consequences.
Adopting less complex approaches.
Planning on more testing.
Adding resources or time to the schedule.
Assigning a team member to visit the seller’s facilities
frequently to learn about potential delivery problems as
early as possible.
Providing a less-experienced team member with additional
training.
Deciding to prototype a high-risk solution element.
Transference
Transferring ownership of the risk factor.
Shifting the consequence of a risk and the
ownership of the response to a third party.
Outsourcing difficult work to a more experienced company.
Fixed price contract.
Contract, insurance, warranties, guarantees, and so on.
Used most often for financial risk exposure.
Does not eliminate the risk.
RISK RESPONSE OPTIONS
Source: Project Management, Absolute Beginner’s Guide, Gregory Horine Que Publishing, Indianapolis 2013
8
88
ESSENTIAL PROCESSES FOR MANAGING RISKS
Which Business Problems Does the Tool Solve?
• Innovation brings with it additional risks which can still be managed by the team on its own
• Helps improve project execution because it can help the team anticipate, prevent, and mitigate risks
Benefits:
• You can identify risks before they occur
• There is a reduction of risk impact due to early detection
• Quantitative metrics that help clarify when to act on a risk item
• Action accelerates because of the clear thresholds and the agreement to follow a process
9
99
RISK MANAGEMENT MATRIX
Status Risk Impact Likelihood Metric Threshold
Current
Value
Date Action Plan
Global team does not communicate
frequently enough. Want to keep
weekly communication high.
4 7
Meetings per
week
2 2.5 Current
Invoke team’s elevation plan,
purchase videoconferencing
systems, change incentives.
Data captured on long forms from
online interaction sessions must not be
lost if user gets error message or
returns to screen.
6 6 % Data Lost 10% 25% Q3 FY 13
Design review current forms layout,
bring in Expert Co. consulting firm,
change staff balance.
Server must respond to users rapidly
under fairly high loads – expect page to
be updated way under a second.
7 7 Ms at 1000 Users 259 1000 Q2 FY 13
Add architect and create tiger team
with system optimization
experience.
Financial partner cooperation is critical
to this household finance program, and
we need to have a sufficient number at
launch
4 6 Institutions 1000 247 Q3 FY 13
Increases business development
staff, change incentive
compensation, add external business
development firm.
Mobile operating system support must
be in place at the same time as
launching the desktop version.
5 6 On Time Q4 FY 14 Q4 FY 14 Current
Track schedule prediction accuracy.
If slip then recruit internal team
from Vietnam (permission already
granted).
10
1010
Status Risk Impact Likelihood Metric Threshold
Current
Value
Date Action Plan
Global team does not communicate
frequently enough. Want to keep
weekly communication high.
4 7
Meetings per
week
2 2.5 Current
Invoke team’s elevation plan,
purchase videoconferencing
systems, change incentives.
Data captured on long forms from
online interaction sessions must not be
lost if user gets error message or
returns to screen.
6 6 % Data Lost 10% 25% Q3 FY 13
Design review current forms layout,
bring in Expert Co. consulting firm,
change staff balance.
Server must respond to users rapidly
under fairly high loads – expect page to
be updated way under a second.
7 7 Ms at 1000 Users 259 1000 Q2 FY 13
Add architect and create tiger team
with system optimization
experience.
Financial partner cooperation is critical
to this household finance program, and
we need to have a sufficient number at
launch
4 6 Institutions 1000 247 Q3 FY 13
Increases business development
staff, change incentive
compensation, add external business
development firm.
Mobile operating system support must
be in place at the same time as
launching the desktop version.
5 6 On Time Q4 FY 14 Q4 FY 14 Current
Track schedule prediction accuracy.
If slip then recruit internal team
from Vietnam (permission already
granted).
RISK MANAGEMENT MATRIX
Impact of Risk
1 = Low,10 = High
Likelihood
1 = Low,10 = High
Metric Value
triggering action
What to do if
Threshold reached
11
1111
CONTROLLING RISKS
• Tackle high risk tasks first
• Maximize resources on high-risk tasks
• Postpone low-risk tasks
• Use iterative, phased approaches
• Frequent, smaller deliverables reduce overall risk
• Change the way you design
• Create a better balance between theory and experimentation; lean more on experimentation to get fast answers
• Get to “no” more quickly on parallel paths
• QA the planning process
• Leverage independent QA audits
12
1212
MITIGATING RISKS: ALTERNATIVES
1 Soft Skills
2 Meetings
3 Dot Voting
4 Out of Bounds
5 Communication Paths
6 Fast Tracking and Crashing
Assess Plan
Monitor
&
React
These Tools are for the “Monitor and React” phase
13
1313
SOFT SKILLS: EXECUTING
A successful Program Manager has these critical soft skills
Is the leader of communications:
sets the tone and protocols for them
When there are breakdowns, emphasizes
the outcome the team is trying to produce
not who is to blame
14
1414
MANAGING YOUR TEAM & MEETINGS
• “Smooth” program management starts by running effective meetings
• Communicating effectively outside of team meetings is where the real work gets done however
• Focusing on the outcome rather than on blaming people
• Establishing clear priorities and sticking with them
• Tracking the status of each activity (sub-project) within the project
• Using metrics to see the big picture and to drive improvement
Necessary Conditions for “Execution: Managing Teams & Meetings”
Communication
Skills
Communication
Tools
Tracking Capability Metrics
• DOCUMENTS: Communication protocols, Metrics dashboard, Priority lists (These are suggested, not in place yet at D+M)
15
1515
FAST TRACKING & CRASHING TASKS
Source: Dynamics of Project Performance: System Dynamics and Project Management , Lyneis, MIT, 2003, p 16
Worry about taking shortcuts that only cause delay because of more rework
Traditional project
Overlap phases
Compress each phase
Reduce Rework
Planned
Duration
Actual
Phase 1
Rework
Phase 2
16
1616
EXERCISE: MONITORING RISK
Possibilities:
Build a Risk Management Matrix from a
project
Have a role-playing scenario where a risk
has crossed the threshold and Partner is
not responding well
17
17
TCGen Inc.
Menlo Park
CA, 94025
jcarter@tcgen.com
(650) 733-5310

More Related Content

PDF
Program Management 2.0: Monitoring Performance
PDF
Program Management 2.0: Circle-Dot Charts and Communication
PDF
Program Management 2.0: Burndown Charts
PDF
Program Management 2.0: Schedule Prediction Accuracy
PDF
Program Management 2.0: Work Breakdown Structure
PDF
Program Management Tools and Techniques: Best Practices & Workshop for Progra...
PDF
SDPM - Lecture 7 - Project monitoring and control
PPTX
Software Project Scheduling Diagrams
Program Management 2.0: Monitoring Performance
Program Management 2.0: Circle-Dot Charts and Communication
Program Management 2.0: Burndown Charts
Program Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Work Breakdown Structure
Program Management Tools and Techniques: Best Practices & Workshop for Progra...
SDPM - Lecture 7 - Project monitoring and control
Software Project Scheduling Diagrams

What's hot (20)

PPTX
Project scheduling
PPTX
Project Monitoring and Control
PPT
Factors for Successful Projects
PPTX
MS Project Presentation
PPT
Chap 6 Developing A Project Plan
PPTX
00 Introduction of project scheduling
PPTX
Project Time Management
PDF
Project management milestones-webinar
PPSX
Project network scheduling and S-curve
PPTX
Project control. Management
PPT
Chap06 project time management
PPT
Project Time Management
PPTX
Building a-project-schedule
PDF
Assessing Enterprise Project Risk
PPT
Project time management
PDF
DCMA 14-Point Schedule Quality Check
PPTX
Work breakdown structure ppt
PPTX
Primavera presentation
PDF
Neil Varma - Stages of Project Management
PPT
Using Microsoft Project 2003
Project scheduling
Project Monitoring and Control
Factors for Successful Projects
MS Project Presentation
Chap 6 Developing A Project Plan
00 Introduction of project scheduling
Project Time Management
Project management milestones-webinar
Project network scheduling and S-curve
Project control. Management
Chap06 project time management
Project Time Management
Building a-project-schedule
Assessing Enterprise Project Risk
Project time management
DCMA 14-Point Schedule Quality Check
Work breakdown structure ppt
Primavera presentation
Neil Varma - Stages of Project Management
Using Microsoft Project 2003
Ad

Similar to Program Management 2.0: Risk Management (20)

PPTX
Risk Management in Project Management - PM Insiders
PPTX
Risk Management
PPTX
software project management risk control.pptx
PPTX
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
PPTX
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
PPTX
Risk Management
PPT
Software Risk Management updated.ppt
PDF
Risk management overview
PPT
Project Risk management
PPTX
Project risk management: Techniques and strategies
PPT
project_risk_mgmt_final 1.ppt
PPT
Ensuring Project Success Through Automated Risk Management
PPTX
Pm session10
PDF
Twelve Risks to Enterprise Software Projects-And What to Do About Them
PPTX
Project management (A Basic Approach)
PDF
Managing risk with deliverables planning
PDF
APM Thames Valley Network and The Charted Institute of Building: AI in the Pr...
PPTX
Risk Management
PDF
Risk Estimator PowerPoint Presentation Slides
PPT
project_risk_mgmt_final.ppt
Risk Management in Project Management - PM Insiders
Risk Management
software project management risk control.pptx
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
Risk Management
Software Risk Management updated.ppt
Risk management overview
Project Risk management
Project risk management: Techniques and strategies
project_risk_mgmt_final 1.ppt
Ensuring Project Success Through Automated Risk Management
Pm session10
Twelve Risks to Enterprise Software Projects-And What to Do About Them
Project management (A Basic Approach)
Managing risk with deliverables planning
APM Thames Valley Network and The Charted Institute of Building: AI in the Pr...
Risk Management
Risk Estimator PowerPoint Presentation Slides
project_risk_mgmt_final.ppt
Ad

More from John Carter (17)

PDF
Product Roadmaps Done Right
PDF
Product Development Metrics: More Harm Than Good?
PDF
Innovation Sprint Readiness Scorecard
PDF
Never The Twain Shall Meet: Can Agile Work with a Waterfall Process?
PDF
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
PDF
Learning from the Trenches: Scrum for Hardware
PDF
Leadership and Product Strategy
PDF
Customer Collaboration & Product Innovation Using Social Networks
PDF
Strategy Leadership and Product Portfolio Management
PPTX
Agile: Not Just for Sofware
PDF
Agile Methods to Develop Tangible Products Quickly
PDF
Can Agile Work With a Waterfall Process?
PDF
Program and Change Management
PDF
Software Quality Dashboard Benchmarking Study
PDF
Smart Agile: An Elegant Recipe for Product Developers
PDF
Boundary Conditions - Who Needs Agile?
PDF
Software QA Metrics Dashboard Benchmarking
Product Roadmaps Done Right
Product Development Metrics: More Harm Than Good?
Innovation Sprint Readiness Scorecard
Never The Twain Shall Meet: Can Agile Work with a Waterfall Process?
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Learning from the Trenches: Scrum for Hardware
Leadership and Product Strategy
Customer Collaboration & Product Innovation Using Social Networks
Strategy Leadership and Product Portfolio Management
Agile: Not Just for Sofware
Agile Methods to Develop Tangible Products Quickly
Can Agile Work With a Waterfall Process?
Program and Change Management
Software Quality Dashboard Benchmarking Study
Smart Agile: An Elegant Recipe for Product Developers
Boundary Conditions - Who Needs Agile?
Software QA Metrics Dashboard Benchmarking

Recently uploaded (20)

PPTX
Organisational behaviour_ managerial applications of perception
PPTX
Human Resource Management | Introduction,Meaning and Definition
PPTX
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
PPTX
Course Overview of the Course Titled.pptx
PDF
CISSP - Domain 7: Security Operations - InfoSec Institute
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PDF
Organizational Effectiveness in companies
PPTX
BASIC H2S TRAINING for oil and gas industries
PPTX
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
PDF
Case study -Uber strategic plan and management
PPT
Project Management Change Management.ppt
PPTX
Chapter-3.pptx project life cycle presentation
PDF
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
PDF
Boost the power of design | Design Impulse
PPTX
Basics of Project Management for development of leadership skills in practice
PPTX
Self-Awareness and Values Development presentation
PPTX
Principles & Theories of Mgt-Master in PM.pptx
PPT
Project Management - Scope Management.ppt
PDF
Joshua Moll on Leadership & Mindset..pdf
PDF
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
Organisational behaviour_ managerial applications of perception
Human Resource Management | Introduction,Meaning and Definition
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
Course Overview of the Course Titled.pptx
CISSP - Domain 7: Security Operations - InfoSec Institute
_ISO_Presentation_ISO 9001 and 45001.pptx
Organizational Effectiveness in companies
BASIC H2S TRAINING for oil and gas industries
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
Case study -Uber strategic plan and management
Project Management Change Management.ppt
Chapter-3.pptx project life cycle presentation
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
Boost the power of design | Design Impulse
Basics of Project Management for development of leadership skills in practice
Self-Awareness and Values Development presentation
Principles & Theories of Mgt-Master in PM.pptx
Project Management - Scope Management.ppt
Joshua Moll on Leadership & Mindset..pdf
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf

Program Management 2.0: Risk Management

  • 1. 1 1 PROGRAM MANAGEMENT 2.0 RISK MANAGEMENT Jeanne Bradford, John Carter, Scott Elliott April, 2018
  • 2. 2 22 AGENDA 1 Schedule Prediction Accuracy Exercise in creating diagram 2 Metrics for estimating progress at the engineering task levels Exercise in creating a Task Burn- Down Chart 3 Monitoring Progress: Earned Value – Scope, Cost and Time Exercise in managing Partner’s delay 4 Risk & Circle Dot Charts: What happens if there is a breakdown? Exercise 5 Management Systems Covered in this presentation
  • 3. 3 33 KEY LEARNING POINTS Monitoring Project Performance for Internal and External Partners (TCGen’s Innovate Products Faster, Greene’s Head First PMP) 1 Metrics for estimating progress (at the engineering task levels) 2 Monitoring Progress (Earned Value – Scope, Cost and Time) 3 Risk Monitoring 4 Circle Dot Charts 5 Management Systems Participants will understand how to create and update Schedule Prediction Accuracy charts and how to demonstrate program status by showing scope, cost and time in one chart. They will also gain skill in creating and using:
  • 5. 5 55 ESSENTIAL PROCESSES FOR MANAGING RISKS • Assess – Learn from the past, create checklist, review prior audits, go outside, generate list of potential risks • Plan – Perform impact and probability analysis, prioritize, and make plans • Monitor – Keep an active watch for trouble by monitoring predictive metrics • React – Re-mediate if and when there is trouble Assess Plan Monitor & React
  • 6. 6 66 RISK RESPONSE OPTIONS Risk Response Description Examples/Notes Avoidance Avoiding the risk. Changing the project plan to eliminate the risk. Changing the project plan to protect a project objective from the impact. Reducing the scope remove high-risk tasks. Adding resources or time. Adopting a proven approach rather than new one. Removing a “problem” resource. Acceptance Accepting the consequences of the risk. The project plan is not changed to deal with the risk. A better response strategy cannot be identified. Active acceptance. Passive acceptance. No action. Contingency allowance (reserves). Communication plan around possible major cost increases if this risk occurs. Monitor and prepare Accepting the risk for now. Closely monitor the risk and develop alternate action plans proactively if the event occurs. Contingency plan. Fallback plan. Establish criteria that will trigger the implementation of the response plans. Source: Project Management, Absolute Beginner’s Guide, Gregory Horine Que Publishing, Indianapolis 2013
  • 7. 7 77 Risk Response Description Examples/Notes Mitigation Taking action to reduce the likelihood that the risk will occur. Taking action to reduce the impact of the risk. Reducing the probability is always more effective than minimizing the consequences. Adopting less complex approaches. Planning on more testing. Adding resources or time to the schedule. Assigning a team member to visit the seller’s facilities frequently to learn about potential delivery problems as early as possible. Providing a less-experienced team member with additional training. Deciding to prototype a high-risk solution element. Transference Transferring ownership of the risk factor. Shifting the consequence of a risk and the ownership of the response to a third party. Outsourcing difficult work to a more experienced company. Fixed price contract. Contract, insurance, warranties, guarantees, and so on. Used most often for financial risk exposure. Does not eliminate the risk. RISK RESPONSE OPTIONS Source: Project Management, Absolute Beginner’s Guide, Gregory Horine Que Publishing, Indianapolis 2013
  • 8. 8 88 ESSENTIAL PROCESSES FOR MANAGING RISKS Which Business Problems Does the Tool Solve? • Innovation brings with it additional risks which can still be managed by the team on its own • Helps improve project execution because it can help the team anticipate, prevent, and mitigate risks Benefits: • You can identify risks before they occur • There is a reduction of risk impact due to early detection • Quantitative metrics that help clarify when to act on a risk item • Action accelerates because of the clear thresholds and the agreement to follow a process
  • 9. 9 99 RISK MANAGEMENT MATRIX Status Risk Impact Likelihood Metric Threshold Current Value Date Action Plan Global team does not communicate frequently enough. Want to keep weekly communication high. 4 7 Meetings per week 2 2.5 Current Invoke team’s elevation plan, purchase videoconferencing systems, change incentives. Data captured on long forms from online interaction sessions must not be lost if user gets error message or returns to screen. 6 6 % Data Lost 10% 25% Q3 FY 13 Design review current forms layout, bring in Expert Co. consulting firm, change staff balance. Server must respond to users rapidly under fairly high loads – expect page to be updated way under a second. 7 7 Ms at 1000 Users 259 1000 Q2 FY 13 Add architect and create tiger team with system optimization experience. Financial partner cooperation is critical to this household finance program, and we need to have a sufficient number at launch 4 6 Institutions 1000 247 Q3 FY 13 Increases business development staff, change incentive compensation, add external business development firm. Mobile operating system support must be in place at the same time as launching the desktop version. 5 6 On Time Q4 FY 14 Q4 FY 14 Current Track schedule prediction accuracy. If slip then recruit internal team from Vietnam (permission already granted).
  • 10. 10 1010 Status Risk Impact Likelihood Metric Threshold Current Value Date Action Plan Global team does not communicate frequently enough. Want to keep weekly communication high. 4 7 Meetings per week 2 2.5 Current Invoke team’s elevation plan, purchase videoconferencing systems, change incentives. Data captured on long forms from online interaction sessions must not be lost if user gets error message or returns to screen. 6 6 % Data Lost 10% 25% Q3 FY 13 Design review current forms layout, bring in Expert Co. consulting firm, change staff balance. Server must respond to users rapidly under fairly high loads – expect page to be updated way under a second. 7 7 Ms at 1000 Users 259 1000 Q2 FY 13 Add architect and create tiger team with system optimization experience. Financial partner cooperation is critical to this household finance program, and we need to have a sufficient number at launch 4 6 Institutions 1000 247 Q3 FY 13 Increases business development staff, change incentive compensation, add external business development firm. Mobile operating system support must be in place at the same time as launching the desktop version. 5 6 On Time Q4 FY 14 Q4 FY 14 Current Track schedule prediction accuracy. If slip then recruit internal team from Vietnam (permission already granted). RISK MANAGEMENT MATRIX Impact of Risk 1 = Low,10 = High Likelihood 1 = Low,10 = High Metric Value triggering action What to do if Threshold reached
  • 11. 11 1111 CONTROLLING RISKS • Tackle high risk tasks first • Maximize resources on high-risk tasks • Postpone low-risk tasks • Use iterative, phased approaches • Frequent, smaller deliverables reduce overall risk • Change the way you design • Create a better balance between theory and experimentation; lean more on experimentation to get fast answers • Get to “no” more quickly on parallel paths • QA the planning process • Leverage independent QA audits
  • 12. 12 1212 MITIGATING RISKS: ALTERNATIVES 1 Soft Skills 2 Meetings 3 Dot Voting 4 Out of Bounds 5 Communication Paths 6 Fast Tracking and Crashing Assess Plan Monitor & React These Tools are for the “Monitor and React” phase
  • 13. 13 1313 SOFT SKILLS: EXECUTING A successful Program Manager has these critical soft skills Is the leader of communications: sets the tone and protocols for them When there are breakdowns, emphasizes the outcome the team is trying to produce not who is to blame
  • 14. 14 1414 MANAGING YOUR TEAM & MEETINGS • “Smooth” program management starts by running effective meetings • Communicating effectively outside of team meetings is where the real work gets done however • Focusing on the outcome rather than on blaming people • Establishing clear priorities and sticking with them • Tracking the status of each activity (sub-project) within the project • Using metrics to see the big picture and to drive improvement Necessary Conditions for “Execution: Managing Teams & Meetings” Communication Skills Communication Tools Tracking Capability Metrics • DOCUMENTS: Communication protocols, Metrics dashboard, Priority lists (These are suggested, not in place yet at D+M)
  • 15. 15 1515 FAST TRACKING & CRASHING TASKS Source: Dynamics of Project Performance: System Dynamics and Project Management , Lyneis, MIT, 2003, p 16 Worry about taking shortcuts that only cause delay because of more rework Traditional project Overlap phases Compress each phase Reduce Rework Planned Duration Actual Phase 1 Rework Phase 2
  • 16. 16 1616 EXERCISE: MONITORING RISK Possibilities: Build a Risk Management Matrix from a project Have a role-playing scenario where a risk has crossed the threshold and Partner is not responding well
  • 17. 17 17 TCGen Inc. Menlo Park CA, 94025 jcarter@tcgen.com (650) 733-5310