PROJECT MANAGEMENT  Schedules Week 3 Propedeuse ICM 2011-2012 School of Communication & Media - INHOLLAND
Why do  projects   require  a time  schedule ? to organise activities http://www.west8.nl/projects/rotterdam_centraal_station/ http://www.rotterdam.nl/rotterdamcentraal   - to determine the duration and staffing costs of the project to monitor progress  to make adjustments along the way http://www.youtube.com/watch?v=Q4SD2m4NOVg
How do you decide which activities are required for your project? (Grit, p 81): Consider - come up with as many ideas as possible, always thinking of the end product Research - literature and other previous projects Consult - ask other project members, experienced project managers and/or the client Create a Work Breakdown Structure -containing a schematic overview of project activities
Name 3 professional planning techniques A. Gantt or Bar Chart  B. Network Plan/Diagram C. Script
BAR CHART (simple)
BAR CHART (complex)
The Gantt Chart includes Google A short description of phases and/or activities (left column) (Names of personnel responsible for activities) (second column from the left) General project information (top) Time scale (day, week, month, hour, etc.)  (below general information) Time bars and milestones (main area)
Gantt Chart terms: Time Bar estimated time of activity horizontal bars Milestones - important moments, deadlines or products circles, triangles or diamonds The Critical Path these activities must be completed by their deadline or the project deadline will be in jeopardy.  Critical path method - Wikipedia, the free encyclopedia vertical dotted line between bars and milestones
Gantt Chart terms: Dependant Activity: - can only be carried out after another activity is completed Critical Activity: - an activity whose duration affects the duration of the entire project (no  slack  time) Position Line: - shows a snap shot of the progress (i.e. today) ASAP ALAP  (e.g. spending money)
B. Network Planning Use a circle for: starting and finishing point Rectangles indicate: -milestones Arrows show: -dependencies and activities (duration is shown above the arrow)   Seen easily:  dependancy between activities Not clear: duration of activities
Step-By-Step Plan for drawing a Network Diagram  (Grit) Step 1:  Start from the table of activites Step 2:  Draw a rectangle for every activity Step 3:  Starting from the circle, draw an arrow to  each of the activities Step 4:  Draw rectangles for all other milestones  and connect them to the preceding activity  with an arrow
Step-By-Step Plan for drawing a Network Diagram  (Grit) Step 5:  Indicate the code (A, B, etc.) in all circles  and rectangles Step 6:  Indicate the duration of the activity above  the arrows (7 days, 1 month, etc.) Step 7:  Determine The Critical Path by checking  the duration of each paths.  The longest path =  The Critical Path
Step-By-Step Plan to derive a Bar Chart from a Network Diagram  (Grit) Step 1:  Draw a horizontal time scale (slightly  longer than actual duration  Step 2:  Draw “strips’’ or bars for each activity  along The Critical Path longer duration = longer strip The Critical Path = darker strips     = top left to bottom right  Step 3:  Add bars for the other activities, including  dependent activities  Step 4:  Indicate “slack’’ with dotted lines Step 5:  Indicate dependencies with vertical lines
Step-By-Step Plan for a Bar Chart  (Verhaar)  Step 1:  Determine the start and end date Step 2:  Divide into phases Step 3:  Find logical groupings of tasks Step 4:  Construct a preliminary overview of activities
What are the phases of a project?  Verhaar (events): Grit (general): Initiative Phase Concept Preparation Phase Definition Development Phase Design (Production Phase) Preparation Performance Phase Execution Evaluation Phase Aftercare
Step-By-Step Plan for a Bar Chart  (Verhaar)  Step 5:  Put an overview of activities in the plan (general, detailed, or a mix) Step 6:  Determine who will do what Step 7:  Determine the calendar scale Step 8:  Estimate time frame of each activity Step 9:  Mark milestones & deadlines
Step-By-Step Plan for a Bar Chart  (Verhaar)  Step 10:  Introduce relationships and determine….  The Critical Path Step 11:  Close the planning Step 12:  Make the plan definite Step 13:  Establish progress control
C. Script Use when: - activities become concrete - exact precision is required often part of the production or performance phase of a project
Read : Verhaar, Chapters 2,3,4, (10 & 11 recommended) Grit, Chapters 2,3 Write 2 questions with answers from each chapter, due week 5 Project group 1: Verhaar, Chapter 1,2,  Grit, Chapter 10, 11, 12 Project group 2: Verhaar, Chapter 3,4, 6 Grit, Chapter 8, 9 Project group 3: Verhaar, Chapter 7, 8, 9 Grit, Chapter 6, 7 Project group 4: Verhaar, Chapter 11, 12, 13 Grit, Chapter 4,5 For next week:
Read : Verhaar, Chapters 2,3,4, (10 & 11 recommended) Grit, Chapters 2,3 Write 2 questions with answers from each chapter, due week 5 Project group 1: Verhaar, Chapter 1, 2  Grit, Chapter 10, 11, 12 Project group 2: Verhaar, Chapter 3, 4,  Grit, Chapter 7, 8, 9 Project group 4: Verhaar, Chapter  6, 7, 8 Grit, Chapter 5, 6 For next week (IMEMB):
Read : Verhaar, Chapters 2,3,4, (10 & 11 recommended) Grit, Chapters 2,3 Write 2 questions with answers from each chapter, due week 5 Project group 5: Verhaar, Chapter 10, 11 Grit, Chapter 3, 4,  Project group 6: Verhaar, Chapter 12, 13 Grit, Chapter 1, 2 For next week:

More Related Content

DOC
Critical Path Analysis
PPT
Ch08 pm2ndhalf
PDF
Derak project plan overview
PPTX
Critical Path Analysis
PPT
Critical Path Analysis
PPTX
Mba ii pmom_unit-4.3 scheduling-gantt chart a
PPTX
The Critical Path Method
PDF
Programme evaluation review technique
Critical Path Analysis
Ch08 pm2ndhalf
Derak project plan overview
Critical Path Analysis
Critical Path Analysis
Mba ii pmom_unit-4.3 scheduling-gantt chart a
The Critical Path Method
Programme evaluation review technique

What's hot (20)

PDF
05 critical path analysis
PPT
Gantt pert
PPTX
Apps4.Pro Planner Gantt chart (Chrome extension)
PDF
Critical path method(cpm)
DOCX
Pert Diagram & Gantt chart
PPT
Critical Path Analysis Notes
PPTX
Critical path method
PPTX
The Critical Path Method
PPTX
PPT
Gantt chart
PPTX
Seven Basic Steps to Build Realistic Schedule in Project 2010
PPTX
Lesson in fs cpm,cpa
PPT
Lecture5---Gantt Chart
PPT
Critical Path Method
PPTX
Critical path method
PPTX
Network Problem CPM & PERT
PPTX
Critical path method (cpm)
PPTX
Critical Path Method
PPT
Critical path method (cpm)
PPTX
Gantt chart & pert chart
05 critical path analysis
Gantt pert
Apps4.Pro Planner Gantt chart (Chrome extension)
Critical path method(cpm)
Pert Diagram & Gantt chart
Critical Path Analysis Notes
Critical path method
The Critical Path Method
Gantt chart
Seven Basic Steps to Build Realistic Schedule in Project 2010
Lesson in fs cpm,cpa
Lecture5---Gantt Chart
Critical Path Method
Critical path method
Network Problem CPM & PERT
Critical path method (cpm)
Critical Path Method
Critical path method (cpm)
Gantt chart & pert chart
Ad

Similar to Project management week 3 for students (20)

DOCX
Project time
PPTX
Project Scheduling
PPTX
Software Project Scheduling Diagrams
PPTX
Project Management -WBS,Gantt Chart Presentation
PPTX
GANTT CHART nursing Management for Msc nursing
PPTX
programmed evaluation and review technique,
PDF
Gantt Chart
PPTX
1 Element Of a Netwok Construction .pptx
PPT
08. Project Time Management Upload
PPT
Training pm jan 11 part b
PPT
Project Time Management
PPT
Ch3 proj.mgt
PPTX
#@123ganttchart-240304175359-d9a26905.pptx
PPT
Project control tools by Samuel obino mokaya
PPTX
Pert and gantt chart
PPTX
concept of evaluation "Character insight"
PPTX
5. Management Project Planning 27.7.2025.pptx
PPTX
PMNM101 Lesson 2 2022.pptx
PPTX
Project scheduling and planning ppt for study
Project time
Project Scheduling
Software Project Scheduling Diagrams
Project Management -WBS,Gantt Chart Presentation
GANTT CHART nursing Management for Msc nursing
programmed evaluation and review technique,
Gantt Chart
1 Element Of a Netwok Construction .pptx
08. Project Time Management Upload
Training pm jan 11 part b
Project Time Management
Ch3 proj.mgt
#@123ganttchart-240304175359-d9a26905.pptx
Project control tools by Samuel obino mokaya
Pert and gantt chart
concept of evaluation "Character insight"
5. Management Project Planning 27.7.2025.pptx
PMNM101 Lesson 2 2022.pptx
Project scheduling and planning ppt for study
Ad

Recently uploaded (20)

PPTX
20th Century Theater, Methods, History.pptx
PDF
Trump Administration's workforce development strategy
DOCX
Cambridge-Practice-Tests-for-IELTS-12.docx
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PDF
Hazard Identification & Risk Assessment .pdf
PPTX
History, Philosophy and sociology of education (1).pptx
PPTX
Virtual and Augmented Reality in Current Scenario
PDF
Weekly quiz Compilation Jan -July 25.pdf
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PPTX
Introduction to pro and eukaryotes and differences.pptx
PDF
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PDF
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
Empowerment Technology for Senior High School Guide
20th Century Theater, Methods, History.pptx
Trump Administration's workforce development strategy
Cambridge-Practice-Tests-for-IELTS-12.docx
LDMMIA Reiki Yoga Finals Review Spring Summer
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
Hazard Identification & Risk Assessment .pdf
History, Philosophy and sociology of education (1).pptx
Virtual and Augmented Reality in Current Scenario
Weekly quiz Compilation Jan -July 25.pdf
B.Sc. DS Unit 2 Software Engineering.pptx
Introduction to pro and eukaryotes and differences.pptx
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
Share_Module_2_Power_conflict_and_negotiation.pptx
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
Empowerment Technology for Senior High School Guide

Project management week 3 for students

  • 1. PROJECT MANAGEMENT Schedules Week 3 Propedeuse ICM 2011-2012 School of Communication & Media - INHOLLAND
  • 2. Why do projects require a time schedule ? to organise activities http://www.west8.nl/projects/rotterdam_centraal_station/ http://www.rotterdam.nl/rotterdamcentraal - to determine the duration and staffing costs of the project to monitor progress to make adjustments along the way http://www.youtube.com/watch?v=Q4SD2m4NOVg
  • 3. How do you decide which activities are required for your project? (Grit, p 81): Consider - come up with as many ideas as possible, always thinking of the end product Research - literature and other previous projects Consult - ask other project members, experienced project managers and/or the client Create a Work Breakdown Structure -containing a schematic overview of project activities
  • 4. Name 3 professional planning techniques A. Gantt or Bar Chart B. Network Plan/Diagram C. Script
  • 7. The Gantt Chart includes Google A short description of phases and/or activities (left column) (Names of personnel responsible for activities) (second column from the left) General project information (top) Time scale (day, week, month, hour, etc.) (below general information) Time bars and milestones (main area)
  • 8. Gantt Chart terms: Time Bar estimated time of activity horizontal bars Milestones - important moments, deadlines or products circles, triangles or diamonds The Critical Path these activities must be completed by their deadline or the project deadline will be in jeopardy. Critical path method - Wikipedia, the free encyclopedia vertical dotted line between bars and milestones
  • 9. Gantt Chart terms: Dependant Activity: - can only be carried out after another activity is completed Critical Activity: - an activity whose duration affects the duration of the entire project (no slack time) Position Line: - shows a snap shot of the progress (i.e. today) ASAP ALAP (e.g. spending money)
  • 10. B. Network Planning Use a circle for: starting and finishing point Rectangles indicate: -milestones Arrows show: -dependencies and activities (duration is shown above the arrow) Seen easily: dependancy between activities Not clear: duration of activities
  • 11. Step-By-Step Plan for drawing a Network Diagram (Grit) Step 1: Start from the table of activites Step 2: Draw a rectangle for every activity Step 3: Starting from the circle, draw an arrow to each of the activities Step 4: Draw rectangles for all other milestones and connect them to the preceding activity with an arrow
  • 12. Step-By-Step Plan for drawing a Network Diagram (Grit) Step 5: Indicate the code (A, B, etc.) in all circles and rectangles Step 6: Indicate the duration of the activity above the arrows (7 days, 1 month, etc.) Step 7: Determine The Critical Path by checking the duration of each paths. The longest path = The Critical Path
  • 13. Step-By-Step Plan to derive a Bar Chart from a Network Diagram (Grit) Step 1: Draw a horizontal time scale (slightly longer than actual duration Step 2: Draw “strips’’ or bars for each activity along The Critical Path longer duration = longer strip The Critical Path = darker strips = top left to bottom right Step 3: Add bars for the other activities, including dependent activities Step 4: Indicate “slack’’ with dotted lines Step 5: Indicate dependencies with vertical lines
  • 14. Step-By-Step Plan for a Bar Chart (Verhaar) Step 1: Determine the start and end date Step 2: Divide into phases Step 3: Find logical groupings of tasks Step 4: Construct a preliminary overview of activities
  • 15. What are the phases of a project? Verhaar (events): Grit (general): Initiative Phase Concept Preparation Phase Definition Development Phase Design (Production Phase) Preparation Performance Phase Execution Evaluation Phase Aftercare
  • 16. Step-By-Step Plan for a Bar Chart (Verhaar) Step 5: Put an overview of activities in the plan (general, detailed, or a mix) Step 6: Determine who will do what Step 7: Determine the calendar scale Step 8: Estimate time frame of each activity Step 9: Mark milestones & deadlines
  • 17. Step-By-Step Plan for a Bar Chart (Verhaar) Step 10: Introduce relationships and determine…. The Critical Path Step 11: Close the planning Step 12: Make the plan definite Step 13: Establish progress control
  • 18. C. Script Use when: - activities become concrete - exact precision is required often part of the production or performance phase of a project
  • 19. Read : Verhaar, Chapters 2,3,4, (10 & 11 recommended) Grit, Chapters 2,3 Write 2 questions with answers from each chapter, due week 5 Project group 1: Verhaar, Chapter 1,2, Grit, Chapter 10, 11, 12 Project group 2: Verhaar, Chapter 3,4, 6 Grit, Chapter 8, 9 Project group 3: Verhaar, Chapter 7, 8, 9 Grit, Chapter 6, 7 Project group 4: Verhaar, Chapter 11, 12, 13 Grit, Chapter 4,5 For next week:
  • 20. Read : Verhaar, Chapters 2,3,4, (10 & 11 recommended) Grit, Chapters 2,3 Write 2 questions with answers from each chapter, due week 5 Project group 1: Verhaar, Chapter 1, 2 Grit, Chapter 10, 11, 12 Project group 2: Verhaar, Chapter 3, 4, Grit, Chapter 7, 8, 9 Project group 4: Verhaar, Chapter 6, 7, 8 Grit, Chapter 5, 6 For next week (IMEMB):
  • 21. Read : Verhaar, Chapters 2,3,4, (10 & 11 recommended) Grit, Chapters 2,3 Write 2 questions with answers from each chapter, due week 5 Project group 5: Verhaar, Chapter 10, 11 Grit, Chapter 3, 4, Project group 6: Verhaar, Chapter 12, 13 Grit, Chapter 1, 2 For next week:

Editor's Notes

  • #6: What do you see here?
  • #7: What do you see here?
  • #8: Look at Figure 8.1 from Verhaar