SlideShare a Scribd company logo
An- Najah National University
Rehabilitation of Nablus Electrical Network by adding a
new connection point
Submitted To :
Dr. Maher Khammash
Prepared By :
Ahmad HatemAbd-Albaqi
&
Ali Namrouti
2015-2016
1
Introduction
 Our project is to study the performance of Nablus
Network and to add a new connection point in the eastern
region of the city of Nablus at the village of " Huwwara
" with maximum capacity up to 20 MW.
 Analyzing and make a load flow study using ETAP
software and trying to achieve the optimum performance
for “Eastern Region” Network .
 Taking into consideration that there are 6 connection
points in the electrical network of the city of Nablus.
2
Objectives
 Collecting data for the new connection point including all parameters and
their specifications ( location, transmission lines , switchgear , load ).
 Designing the one line diagram in ETAP program for new condition by
adding the new supply bus .
 Improving the voltage level and reducing the losses and correcting of
power factor in the network .
 Making the system more protected by increasing reliability and stability .
 Analyzing the network under maximum load condition using load flow
analyses.
 To get economical benefit when improving the performance of network.
3
Why new connection point ?
 The main problem which faces Eastern Region Network is that the power
supplied by IEC ‫االسرائيلية‬ ‫القطرية‬ ‫الشركة‬) ) is not enough for the demand in the city,
especially in the summer season . And because the old connection point has a
capacity up to 20 MW which is not sufficient for the network demand because
the old connection point supplies more than one region, such as the industrial
area and “Al-Bathan” .
 To solve this problem , we add a new connection point with IEC in the eastern
region of the city of Nablus in the village of " Huwwara " through an over head
transmission line of 33 kV. The max demand is reached approximately to (20
MW) to cover the total demand .
4
Eastern Region Network
Before & After 5
Methodology
Collecting
data for
new C.P
and
elements
Plotting
one line
diagram
for new
network
Changing
the voltage
level to 11
kV instead
of 6.6 Kv
Analyzing
the
network
under max.
load case
Improve
p.f to
avoid
penalties
Making
Economical
study for
our project
6
 Plotting one-line diagram using ETAP
software for new Network
 We make a load flow study and analysis Network using ETAP
software .
 Components of the network :
1. Two sources (33 kV) .
2. ( 280 ) bus in this network .
3. ( 107 ) loads( residential, industrial, commercial).
4. Substation with ( 2 ) power transformer .
5. ( 108 ) Distribution transformers .
7
 Changing the Voltage Level from
6.6 to 11 kV
 In this case, each 6.6 kV low voltage side will be exchanged by 11 kV. The
same transformers are used because the transformers which are available
have two windings on the low voltage side of 6.6 kV and 11 kV.
 Distribution transformers of 11/0.4 and 6.6/0.4 kV will not be changed too .
So, no new transformers are needed .
 After raising the voltage to 11 kV , the voltage drop was decreased and a
slight improvement to the power factor was observed .
8
 The results of load flow in original
case
Operating Voltage(kV)Rated Voltage(kV)Bus
34.00034Bus 1
33.04333Bus 20
31.50333Bus 65
31.01633Bus 99
10.35511Bus 110
10.30211Bus 133
10.28011Bus 200
10.08711Bus 269
0.3650.4Bus 122
0.3620.4Bus 182
0.3560.4Bus 227
9
Some of under voltage buses : 10
Summary of results in original case
%PFMVAMVarMW
82.24 lag41.86423.81534.430Source (swing
bus)
--5.8762.700Apparent losses
11
 From the above results , there are many problems in the network .The P.F of the
swing bus = 82.24 Lagging , which causes high penalties and losses . So, we try to
increase the power factor of the busses and the voltage of the buses which is not
included in the acceptable range .
 Therefore ,we note that when we change the Voltage Level from 6.6 to 11 kV the
losses for network decrease from 8.9% to 7.8% .
Maximum load case
 The voltage should be within this range :
1.05 V nominal < V < 1.1 V nominal
 In first stage of the analysis of the network we have to take the
maximum load in daily load curve ,then applied it on ETAB .
 We started the study of this case after we applied the data
needed Like load factor and other data.
12
Load factor
 We have the average value of loads by using the load factor of
each load which we got from the real data of network and real
daily load curves from SCADA system
 The average demand load factor in our network is 75% that
means the average load to the maximum load ratio is 75% which
considered as a very good operating load factor .
13
Our goal is to improve the voltages within the range
by using the following steps :
 Tab changing in the transformers.
 Adding capacitors to produce reactive power.
 Changing and replacing transformer.
 Add another connection point .
The tap changer of the secondary side of the 2 power
transformers (33-11 kV) is raised to 10% , and tap change
in all distribution transformers by 5% .
14
Summary of results in maximum load
case
15
%PFMVAMVarMW
83.25 lag42.32023.44635.232Source (swing
bus)
--5.2422.415Apparent losses
 The losses in the network decrease . The losses before were = 2.700 MW,
but the losses after become =2.415 MW .
 For more improvement we add capacitor banks at the low voltage level and
this is a temporary solution but we need a major solution to cover the total
demand in the city. So , we choose to add a new connection point .
Add a new connection point
Comparing the voltages before and after adding the new connection point.
16
Voltage with two
connection point (kV)
Voltage with one
connection point (kV)
Bus
34.00034.000Bus 1
33.64933.043Bus 20
33.13431.503Bus 65
32.66631.016Bus 99
11.02410.355Bus 110
10.97310.302Bus 133
10.95210.280Bus 200
10.80610.087Bus 269
0.3900.365Bus 122
0.3870.362Bus 182
0.3830.356Bus 227
Some of under voltage buses : 17
Summary of results for new network 18
%PFMVAMVarMW
83.39 lag40.28822.23733.595Source (swing
bus)
--4.0971.168Apparent losses
 We note that when adding a new connection point the losses for
network decrease from 8.9% to 3.4% .
 The P.F of the swing bus = 83.39 lag , which is low and causes a lot of
penalties on both the company and consumers. So, we have to try to
increase the power factor of the busses .
Power Factor Improvement
 It is important to keep the P.F above 0.92 on the distribution transformer so as to
minimize the electrical losses and do not paying penalties.
 How to improve the P.F ??
19
We added shunt capacitor banks at the buses at both
transmission and distribution levels and loads with value :
( 300 , 400 , 1000 ) kVAR .
20
Summary of results after improvement the
network
%PFMVAMVarMW
92.09 lag36.51414.23333.626Source (swing
bus)
--3.6061.010Apparent losses
21
 After adding the capacitor banks the losses in the network decrease to 1.010 MW
 The P.F = 92.09% which it was achieved , since a P.F was lower than that , it would
lead to penalties on both the “NEDCO” and consumers .
Elements Of The Network
1- Sources :
Eastern Region are fed from 2 connection point by Israel Electrical
Company (IEC), at 33KV.
2- Transformers :
 Power Transformers :
This network consists of (2) power transformer (33/11) KV with ratings
10 MVA .
 Distribution transformers :
1. 41 distribution transformers (33/0.4)KV
2. 67 distribution transformers (11/0.4)KV
22
Number of
Transformers
Transformer
Ratings (KVA)
2 2000
1 1600
3 1000
43 630
34 400
16 250
8 160
1 100
108 Total
Elements Of The Network
3- Transmission Line & cable :
 Over Head Line:
The conductors used in the network are ACSR (Aluminum Conductor
Steel Reinforced)
 Under Ground Cable :
The underground cable used in the network are XLPE Cu .
4- Switch gear :
switchgears in substations are located on both the high and low
voltage sides of large power transformers .
Selection depends on : Voltage level ,Number of lines ,Location of
substation , Possibility of expansion
23
Elements Of The Network
 Switchgear contain of :
A. Circuit Breaker :
 How to choose CB :
• I C.B >= Ksafty * I max load .
• VC.B >= V system.
• I breaking capacity >= 1.2 * I S.C
 The Specifications of the Circuit Breaker that
we have used are as follows:
• Ur = 36 kV, Up = 170 kV , Ud = 70kV ; 1 min
• Ir = 1250 A , Ik = 25 kA ; tk = 1sec , Ip = 62.5 kA
24
Elements Of The Network
B. Bus-Bar :
The Bus-Bar modules are either with single phase or three phase
enclosure. Three phase enclosures are compact and have lesser eddy
current losses.
C. Isolator Switch :
Isolating Switches are normally switched only when No Load .
D. Earth Switch :
Earth switch is used to discharge the voltage on the circuit to the earth for
safety , earth switch is mounted on the frame of the isolaters
25
Elements Of The Network
5 - Measurement in the medium voltage :
 Current Transformers
 Potential Transformers
6 - Supervisory Control & Data Acquisition (SCADA) :
SCADA is a system for remote monitoring and control that
operates with coded signals over communication channels.
26
Economical Study
In this project it is important to study the economical calculation to find if our work is suitable
or not .
 Saving in penalties :
P.F before imp. = 0.83
P.F after imp. = 0.92
Pav = L.F * Pmax
= 0.75 * 33.626 = 25.21 MW
Total energy per year = Pav * 8760= 220839.6 MWH.
Total cost per year = Total energy * cost (NIS/KWH) = 132503760 NIS/year.
Saving in penalties of P.F = 115278.27 NIS/year.
 Saving in losses :
Saving in losses = cost of losses before – cost of losses after
= 1064340 – 398142
= 666198 NIS/year.
27
Power Factor P.F Penalties
P.F ≥ 0.92 No Penalties.
0.92 > P.F ≥ 0.8 1% of total bill for each one under 0.92
0.8 > P.F ≥ 0.7 1.25% of total bill for each one under 0.92
P.F < 0.7 1.5% of total bill for each one under 0.92
Economical Study
 Simple Pay Back Period :
Total fixed capacitor banks using = 7.3 MVAR.
Cost of fixed capacitor = 18000 NIS / MVAR .
Total cost of capacitor banks = 7.3 * 18000 = 131400 NIS.
The cost of under ground cable XLPE (1*240 mm2) = 100 NIS / 1 meter
Total cost = 100 * 8000 = 800000 NIS .
The cost of Infrastructure (such as: excavations, power source, accessories) = 100 NIS/1meter
Total cost = 100 * 8000 = 800000 NIS .
The cost of ( Links , wages of workers , equipment , Towers , installation cost and maintenance ) = 300000 NIS
The cost of ( Internal equipment, construction, measurement device , SCADA system ) = 500000 NIS .
Total capital cost = 131400 + 800000 + 800000 + 300000 + 500000 = 2531400 NIS
Total saving = saving in losses + saving in penalties
= 666198 + 115278.27 = 781476.27 NIS
S.P.B.P = Investment / Saving = 2531400 / 781476.27 = 3.23 years
28
How our new connection point will affect on
Nablus network ?
29
RehabilitationoftheNabluselectricalnetwork
Rehabilitation of the Nablus electrical network
Conclusions
 After the analysis and adding a new connection point , drop voltage was decreased ,
apparent losses was reduced too .
 When adding a new connection point the losses for network decrease
from 8.9% to 3.4% .
 The power factor was improved to over 92% which will reduce any penalties paid to
"IEC" on both "NEDCO" Company and consumers as will, and this is duo to adding a new
connection point .
 The network at full load need to 34 MW , but the availability of current two connection
point is 40 MW . So, now we in the save side .
 The time needed to recover the cost for the project is about 3 year . And the new
network will be feed the new growth of load for the period from now to 2025 ,
depending on the annual increase of the loads to cover the demand in the city.
30
Huwwara connection point 31
Rehabilitation of the Nablus electrical network
Askar substation 32
Rehabilitation of the Nablus electrical network
Switchgear in Askar substation 33
Rehabilitation of the Nablus electrical network
SCADA system 34
Rehabilitation of the Nablus electrical network
Recommendation
 Finally , we hope from NEDCO with which we have contributed in
gathering information and data about our project to take into
consideration our calculation and improvement of the electrical network
seriously . we also hope to see our project in Huwwara to be truly
applied on the ground of reality .
THANK YOU FOR YOUR ATTENTION
35
36

More Related Content

PDF
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
PPTX
Automatic Power Factor Improvement by Using PLC & SCADA
PDF
Micro-controller based Automatic Power Factor Correction System Report
PDF
Power Angle Control Scheme for Integration of UPQC In Grid Connected PV System
PDF
Power Quality Improvement of Grid Interconnection of renewable Energy Based D...
PPTX
automatic power factor correction
PDF
Minimizing Penalty in Industrial Power Consumption by Engaging APFC Unit : A ...
PDF
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Automatic Power Factor Improvement by Using PLC & SCADA
Micro-controller based Automatic Power Factor Correction System Report
Power Angle Control Scheme for Integration of UPQC In Grid Connected PV System
Power Quality Improvement of Grid Interconnection of renewable Energy Based D...
automatic power factor correction
Minimizing Penalty in Industrial Power Consumption by Engaging APFC Unit : A ...
“POWER FACTOR IMPROVEMENT BY SIMULATION AND IMPLEMENTATION OF FC-TCR”

What's hot (20)

PDF
Automatic Power Factor Corrector Using Arduino report
DOC
IEEE/NON-IEEE Projects For EEE branch
DOCX
main-project1
PDF
Ieee 2015 2014 power electronics project titles
PPTX
Automatic Power Factor Improvement.Pptx
PPTX
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
PPTX
power factor correction soham+niraj
PDF
Two area system
DOCX
Amit new report
PPTX
Automatic power factor correction
PDF
Application of Capacitors to Distribution System and Voltage Regulation
PDF
Automatic power factor_improvement_and_monitoring_by_using_plc[1]
PDF
Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...
PDF
Power factor correction
PPTX
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
PPT
Three phase power factor improvement using Vienna Rectifier
PDF
Power Factor
PDF
PSCAD Final Report
PDF
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmission
PPTX
Benifits of power factor improvement for industry
Automatic Power Factor Corrector Using Arduino report
IEEE/NON-IEEE Projects For EEE branch
main-project1
Ieee 2015 2014 power electronics project titles
Automatic Power Factor Improvement.Pptx
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
power factor correction soham+niraj
Two area system
Amit new report
Automatic power factor correction
Application of Capacitors to Distribution System and Voltage Regulation
Automatic power factor_improvement_and_monitoring_by_using_plc[1]
Design of a 3-phase FC-TCR Static Var Compensator for Power factor correction...
Power factor correction
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
Three phase power factor improvement using Vienna Rectifier
Power Factor
PSCAD Final Report
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmission
Benifits of power factor improvement for industry
Ad

Viewers also liked (6)

PDF
Leadership versus management 1
PPTX
From manager to leader
PPT
Leaders Or Managers
PPTX
Leadership
PPTX
Managers vs leaders
DOC
Summer internship project on hdfc
Leadership versus management 1
From manager to leader
Leaders Or Managers
Leadership
Managers vs leaders
Summer internship project on hdfc
Ad

Similar to Rehabilitation of nablus electrical network by adding a new connection point (20)

PPSX
ECNG 3015 - PU system and 3Phase Fault calculation
PPT
CH1.ppt
PDF
Novel technique in charactarizing a pv module using pulse width modulator
PDF
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
PDF
High Gain Non Isolated DC-DC Step-up Converters Integrated with Active and Pa...
PDF
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
PDF
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
PDF
Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...
PPT
Switched Capacitor Based Multilevel Inverter With Reduced Device Counts For E...
PDF
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
PPT
Islanding
PPTX
jeevan ppt 5.11.20.pptx
DOCX
uppcl training in moradabad report
PDF
Voltage Control Using Statcom in Dg Integrated With Distribution Network
PDF
I010616064
PDF
Analyses and monitoring of 132 k v grid using etap software
PDF
Design and Development of Power Electronic Controller for Grid-connected PV A...
PPTX
Control of parallel dc dc converters in a dc microgrid
PDF
THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...
PDF
Load Flow and PV Curve Analysis of a 220kV Substation
ECNG 3015 - PU system and 3Phase Fault calculation
CH1.ppt
Novel technique in charactarizing a pv module using pulse width modulator
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
High Gain Non Isolated DC-DC Step-up Converters Integrated with Active and Pa...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
Real Time Implementation of Variable Step Size Based P&O MPPT for PV Systems ...
Switched Capacitor Based Multilevel Inverter With Reduced Device Counts For E...
IRJET- Design and Analysis of Typical Chemical Industry Electrical Distributi...
Islanding
jeevan ppt 5.11.20.pptx
uppcl training in moradabad report
Voltage Control Using Statcom in Dg Integrated With Distribution Network
I010616064
Analyses and monitoring of 132 k v grid using etap software
Design and Development of Power Electronic Controller for Grid-connected PV A...
Control of parallel dc dc converters in a dc microgrid
THREE-PHASE OF BI-DIRECTIONAL Z-SOURCE CONVERTERS FOR VEHICLE-TO-GRID APPLICA...
Load Flow and PV Curve Analysis of a 220kV Substation

More from slmnsvn (20)

PPTX
Analysis optimization and monitoring system
PDF
Analysis optimization and monitoring system
DOCX
Smart home
DOCX
Smart fuel theft detector
PPTX
Smart fuel theft detector
PPTX
Rfid attendace system
PPTX
Quad pod transformable vehicle
DOCX
Quad pod transformable vehicle
PPTX
Power factor correction
DOCX
Power factor correction
PPTX
Optimum performances of ramallah
DOCX
Optimum performances of ramallah
PPTX
Optimum performance of tulkarim governorate network
DOCX
Optimum performance of tulkarim governorate network
PPTX
Optimum performance for aqraba electrical network 2
DOCX
Optimum performance for aqraba electrical network 2
PPTX
Optimum performance for aqraba electrical network
PPTX
Multi tone test
DOCX
Multi tone test
PPTX
Mini scada system for monitoring pv and wind installation in meteorology stat...
Analysis optimization and monitoring system
Analysis optimization and monitoring system
Smart home
Smart fuel theft detector
Smart fuel theft detector
Rfid attendace system
Quad pod transformable vehicle
Quad pod transformable vehicle
Power factor correction
Power factor correction
Optimum performances of ramallah
Optimum performances of ramallah
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate network
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network
Multi tone test
Multi tone test
Mini scada system for monitoring pv and wind installation in meteorology stat...

Recently uploaded (20)

PDF
Visual Aids for Exploratory Data Analysis.pdf
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Information Storage and Retrieval Techniques Unit III
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
Fundamentals of Mechanical Engineering.pptx
PPTX
Current and future trends in Computer Vision.pptx
PPTX
introduction to high performance computing
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PDF
PPT on Performance Review to get promotions
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PPT
Occupational Health and Safety Management System
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PPT
Total quality management ppt for engineering students
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
Visual Aids for Exploratory Data Analysis.pdf
Fundamentals of safety and accident prevention -final (1).pptx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Information Storage and Retrieval Techniques Unit III
Safety Seminar civil to be ensured for safe working.
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Fundamentals of Mechanical Engineering.pptx
Current and future trends in Computer Vision.pptx
introduction to high performance computing
R24 SURVEYING LAB MANUAL for civil enggi
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PPT on Performance Review to get promotions
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Occupational Health and Safety Management System
Exploratory_Data_Analysis_Fundamentals.pdf
Total quality management ppt for engineering students
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...

Rehabilitation of nablus electrical network by adding a new connection point

  • 1. An- Najah National University Rehabilitation of Nablus Electrical Network by adding a new connection point Submitted To : Dr. Maher Khammash Prepared By : Ahmad HatemAbd-Albaqi & Ali Namrouti 2015-2016 1
  • 2. Introduction  Our project is to study the performance of Nablus Network and to add a new connection point in the eastern region of the city of Nablus at the village of " Huwwara " with maximum capacity up to 20 MW.  Analyzing and make a load flow study using ETAP software and trying to achieve the optimum performance for “Eastern Region” Network .  Taking into consideration that there are 6 connection points in the electrical network of the city of Nablus. 2
  • 3. Objectives  Collecting data for the new connection point including all parameters and their specifications ( location, transmission lines , switchgear , load ).  Designing the one line diagram in ETAP program for new condition by adding the new supply bus .  Improving the voltage level and reducing the losses and correcting of power factor in the network .  Making the system more protected by increasing reliability and stability .  Analyzing the network under maximum load condition using load flow analyses.  To get economical benefit when improving the performance of network. 3
  • 4. Why new connection point ?  The main problem which faces Eastern Region Network is that the power supplied by IEC ‫االسرائيلية‬ ‫القطرية‬ ‫الشركة‬) ) is not enough for the demand in the city, especially in the summer season . And because the old connection point has a capacity up to 20 MW which is not sufficient for the network demand because the old connection point supplies more than one region, such as the industrial area and “Al-Bathan” .  To solve this problem , we add a new connection point with IEC in the eastern region of the city of Nablus in the village of " Huwwara " through an over head transmission line of 33 kV. The max demand is reached approximately to (20 MW) to cover the total demand . 4
  • 6. Methodology Collecting data for new C.P and elements Plotting one line diagram for new network Changing the voltage level to 11 kV instead of 6.6 Kv Analyzing the network under max. load case Improve p.f to avoid penalties Making Economical study for our project 6
  • 7.  Plotting one-line diagram using ETAP software for new Network  We make a load flow study and analysis Network using ETAP software .  Components of the network : 1. Two sources (33 kV) . 2. ( 280 ) bus in this network . 3. ( 107 ) loads( residential, industrial, commercial). 4. Substation with ( 2 ) power transformer . 5. ( 108 ) Distribution transformers . 7
  • 8.  Changing the Voltage Level from 6.6 to 11 kV  In this case, each 6.6 kV low voltage side will be exchanged by 11 kV. The same transformers are used because the transformers which are available have two windings on the low voltage side of 6.6 kV and 11 kV.  Distribution transformers of 11/0.4 and 6.6/0.4 kV will not be changed too . So, no new transformers are needed .  After raising the voltage to 11 kV , the voltage drop was decreased and a slight improvement to the power factor was observed . 8
  • 9.  The results of load flow in original case Operating Voltage(kV)Rated Voltage(kV)Bus 34.00034Bus 1 33.04333Bus 20 31.50333Bus 65 31.01633Bus 99 10.35511Bus 110 10.30211Bus 133 10.28011Bus 200 10.08711Bus 269 0.3650.4Bus 122 0.3620.4Bus 182 0.3560.4Bus 227 9
  • 10. Some of under voltage buses : 10
  • 11. Summary of results in original case %PFMVAMVarMW 82.24 lag41.86423.81534.430Source (swing bus) --5.8762.700Apparent losses 11  From the above results , there are many problems in the network .The P.F of the swing bus = 82.24 Lagging , which causes high penalties and losses . So, we try to increase the power factor of the busses and the voltage of the buses which is not included in the acceptable range .  Therefore ,we note that when we change the Voltage Level from 6.6 to 11 kV the losses for network decrease from 8.9% to 7.8% .
  • 12. Maximum load case  The voltage should be within this range : 1.05 V nominal < V < 1.1 V nominal  In first stage of the analysis of the network we have to take the maximum load in daily load curve ,then applied it on ETAB .  We started the study of this case after we applied the data needed Like load factor and other data. 12
  • 13. Load factor  We have the average value of loads by using the load factor of each load which we got from the real data of network and real daily load curves from SCADA system  The average demand load factor in our network is 75% that means the average load to the maximum load ratio is 75% which considered as a very good operating load factor . 13
  • 14. Our goal is to improve the voltages within the range by using the following steps :  Tab changing in the transformers.  Adding capacitors to produce reactive power.  Changing and replacing transformer.  Add another connection point . The tap changer of the secondary side of the 2 power transformers (33-11 kV) is raised to 10% , and tap change in all distribution transformers by 5% . 14
  • 15. Summary of results in maximum load case 15 %PFMVAMVarMW 83.25 lag42.32023.44635.232Source (swing bus) --5.2422.415Apparent losses  The losses in the network decrease . The losses before were = 2.700 MW, but the losses after become =2.415 MW .  For more improvement we add capacitor banks at the low voltage level and this is a temporary solution but we need a major solution to cover the total demand in the city. So , we choose to add a new connection point .
  • 16. Add a new connection point Comparing the voltages before and after adding the new connection point. 16 Voltage with two connection point (kV) Voltage with one connection point (kV) Bus 34.00034.000Bus 1 33.64933.043Bus 20 33.13431.503Bus 65 32.66631.016Bus 99 11.02410.355Bus 110 10.97310.302Bus 133 10.95210.280Bus 200 10.80610.087Bus 269 0.3900.365Bus 122 0.3870.362Bus 182 0.3830.356Bus 227
  • 17. Some of under voltage buses : 17
  • 18. Summary of results for new network 18 %PFMVAMVarMW 83.39 lag40.28822.23733.595Source (swing bus) --4.0971.168Apparent losses  We note that when adding a new connection point the losses for network decrease from 8.9% to 3.4% .  The P.F of the swing bus = 83.39 lag , which is low and causes a lot of penalties on both the company and consumers. So, we have to try to increase the power factor of the busses .
  • 19. Power Factor Improvement  It is important to keep the P.F above 0.92 on the distribution transformer so as to minimize the electrical losses and do not paying penalties.  How to improve the P.F ?? 19
  • 20. We added shunt capacitor banks at the buses at both transmission and distribution levels and loads with value : ( 300 , 400 , 1000 ) kVAR . 20
  • 21. Summary of results after improvement the network %PFMVAMVarMW 92.09 lag36.51414.23333.626Source (swing bus) --3.6061.010Apparent losses 21  After adding the capacitor banks the losses in the network decrease to 1.010 MW  The P.F = 92.09% which it was achieved , since a P.F was lower than that , it would lead to penalties on both the “NEDCO” and consumers .
  • 22. Elements Of The Network 1- Sources : Eastern Region are fed from 2 connection point by Israel Electrical Company (IEC), at 33KV. 2- Transformers :  Power Transformers : This network consists of (2) power transformer (33/11) KV with ratings 10 MVA .  Distribution transformers : 1. 41 distribution transformers (33/0.4)KV 2. 67 distribution transformers (11/0.4)KV 22 Number of Transformers Transformer Ratings (KVA) 2 2000 1 1600 3 1000 43 630 34 400 16 250 8 160 1 100 108 Total
  • 23. Elements Of The Network 3- Transmission Line & cable :  Over Head Line: The conductors used in the network are ACSR (Aluminum Conductor Steel Reinforced)  Under Ground Cable : The underground cable used in the network are XLPE Cu . 4- Switch gear : switchgears in substations are located on both the high and low voltage sides of large power transformers . Selection depends on : Voltage level ,Number of lines ,Location of substation , Possibility of expansion 23
  • 24. Elements Of The Network  Switchgear contain of : A. Circuit Breaker :  How to choose CB : • I C.B >= Ksafty * I max load . • VC.B >= V system. • I breaking capacity >= 1.2 * I S.C  The Specifications of the Circuit Breaker that we have used are as follows: • Ur = 36 kV, Up = 170 kV , Ud = 70kV ; 1 min • Ir = 1250 A , Ik = 25 kA ; tk = 1sec , Ip = 62.5 kA 24
  • 25. Elements Of The Network B. Bus-Bar : The Bus-Bar modules are either with single phase or three phase enclosure. Three phase enclosures are compact and have lesser eddy current losses. C. Isolator Switch : Isolating Switches are normally switched only when No Load . D. Earth Switch : Earth switch is used to discharge the voltage on the circuit to the earth for safety , earth switch is mounted on the frame of the isolaters 25
  • 26. Elements Of The Network 5 - Measurement in the medium voltage :  Current Transformers  Potential Transformers 6 - Supervisory Control & Data Acquisition (SCADA) : SCADA is a system for remote monitoring and control that operates with coded signals over communication channels. 26
  • 27. Economical Study In this project it is important to study the economical calculation to find if our work is suitable or not .  Saving in penalties : P.F before imp. = 0.83 P.F after imp. = 0.92 Pav = L.F * Pmax = 0.75 * 33.626 = 25.21 MW Total energy per year = Pav * 8760= 220839.6 MWH. Total cost per year = Total energy * cost (NIS/KWH) = 132503760 NIS/year. Saving in penalties of P.F = 115278.27 NIS/year.  Saving in losses : Saving in losses = cost of losses before – cost of losses after = 1064340 – 398142 = 666198 NIS/year. 27 Power Factor P.F Penalties P.F ≥ 0.92 No Penalties. 0.92 > P.F ≥ 0.8 1% of total bill for each one under 0.92 0.8 > P.F ≥ 0.7 1.25% of total bill for each one under 0.92 P.F < 0.7 1.5% of total bill for each one under 0.92
  • 28. Economical Study  Simple Pay Back Period : Total fixed capacitor banks using = 7.3 MVAR. Cost of fixed capacitor = 18000 NIS / MVAR . Total cost of capacitor banks = 7.3 * 18000 = 131400 NIS. The cost of under ground cable XLPE (1*240 mm2) = 100 NIS / 1 meter Total cost = 100 * 8000 = 800000 NIS . The cost of Infrastructure (such as: excavations, power source, accessories) = 100 NIS/1meter Total cost = 100 * 8000 = 800000 NIS . The cost of ( Links , wages of workers , equipment , Towers , installation cost and maintenance ) = 300000 NIS The cost of ( Internal equipment, construction, measurement device , SCADA system ) = 500000 NIS . Total capital cost = 131400 + 800000 + 800000 + 300000 + 500000 = 2531400 NIS Total saving = saving in losses + saving in penalties = 666198 + 115278.27 = 781476.27 NIS S.P.B.P = Investment / Saving = 2531400 / 781476.27 = 3.23 years 28
  • 29. How our new connection point will affect on Nablus network ? 29 RehabilitationoftheNabluselectricalnetwork Rehabilitation of the Nablus electrical network
  • 30. Conclusions  After the analysis and adding a new connection point , drop voltage was decreased , apparent losses was reduced too .  When adding a new connection point the losses for network decrease from 8.9% to 3.4% .  The power factor was improved to over 92% which will reduce any penalties paid to "IEC" on both "NEDCO" Company and consumers as will, and this is duo to adding a new connection point .  The network at full load need to 34 MW , but the availability of current two connection point is 40 MW . So, now we in the save side .  The time needed to recover the cost for the project is about 3 year . And the new network will be feed the new growth of load for the period from now to 2025 , depending on the annual increase of the loads to cover the demand in the city. 30
  • 31. Huwwara connection point 31 Rehabilitation of the Nablus electrical network
  • 32. Askar substation 32 Rehabilitation of the Nablus electrical network
  • 33. Switchgear in Askar substation 33 Rehabilitation of the Nablus electrical network
  • 34. SCADA system 34 Rehabilitation of the Nablus electrical network
  • 35. Recommendation  Finally , we hope from NEDCO with which we have contributed in gathering information and data about our project to take into consideration our calculation and improvement of the electrical network seriously . we also hope to see our project in Huwwara to be truly applied on the ground of reality . THANK YOU FOR YOUR ATTENTION 35
  • 36. 36