The cumene production project analysis indicates economic feasibility with a pay-back period of approximately 7 years. Equipment sizes and cost estimations have been calculated, resulting in total capital costs of $2,300,612.13 and a profit of $1,110.00/hr, making the operation viable. Safety considerations are integrated into the design to minimize risks, including low-pressure steam use and strategic placement of equipment.